The Ottawa LRT Report (Part V)

This is the fifth part of my review of the Final Report of the Commission of Inquiry into the Ottawa LRT fiasco. This article covers the trial operation of the line up to the transition to revenue service and draws from chapter 12 of the Inquiry Report.

Some of the quotations here are extensive as I want there to be no doubt that the voice is that of the Inquiry Commissioner, not my paraphrase.

See also:

Continue reading

TTC Track Construction Update December 22, 2022

King-Queen-Queensway-Roncesvalles

Updated December 23, 2022: The City has issued an update stating that the work on Roncesvalles will not be finished until at least the end of February, and The Queensway will not be complete until Spring 2023.

  • Stage 3 work on Roncesvalles will be completed by the end of February 2023.
  • Work will continue after this period with the installation of TTC streetcar track platforms and overhead wiring, with only lane restrictions as necessary.

The final major piece of trackwork installation is underway. Once new paving is in place, the overhead can be restored and, at least in theory, streetcars can return to Roncesvalles Avenue. This is likely to be confined initially to carhouse moves to and from Howard Park until TTC schedules catch up. A service restoration date for 504 streetcars has not yet been announced, but the mid-February schedule change would be the first opportunity. (As I write this, the January changes have not yet been announced.)

With the revised completion dates announced by the City, the first schedule change that could restore streetcars to Roncesvalles would come at the end of March or early April. It is possible that bus service on Roncesvalles could be restored as work north of Queen reaches a point where some lanes can be opened.

Meanwhile, although road construction continues on The Queensway between Sunnyside and Parkside, only the span wires and hangers are up at Sunnyside Loop, but no contact wire. There is still no track between Glendale (St. Joseph’s Hospital stop) and Parkside (the first stop on the Queensway right-of-way). Paving of the new curb lane eastbound from Parkside to Roncesvalles was underway on December 22, and the new eastbound Glendale stop platform is now in place.

Dates for restoration of streetcar service to Sunnyside and to Long Branch have not been announced.

The City’s update puts completion of the road work in Spring 2023. Whether this will include restoration of track and overhead remains to be seen.

  • As part of work being completed on The Queensway (Parkside Drive to Roncesvalles Avenue), the contractor has uncovered conflicts with underground utilities that require modifications to the designs.
  • The Stage 2 work is now expected to be complete in Spring 2023. Upon completion, all travel lanes on The Queensway will be restored and northbound access to Sunnyside Avenue from The Queensway will be reinstated.  

Dundas Sinkhole

A major sinkhole on Dundas near Brock caused a service diversion of route 505 Dundas via College and Ossington. This ended in the early evening of December 19. The photo below, provided by reader Raymond Lee, shows the track restoration in progress on December 10.

Reinstalling track over Dundas sinkhole. Photo by Raymond Lee.

King & Shaw

Service was restored to King Street west of Bathurst on December 9, 2022. 504A Distillery cars run to Dufferin Loop. 504B Broadview Station cars run to Bathurst Street.

Adelaide Street

Work is expected to be complete to Charlotte Street by year-end. Work east from York Street to Victoria, and on York Street itself will be done as a separate project in 2023.

College Street

Most work on College Street is complete although 506 Carlton streetcar service remains on diversion. The TTC should be restoring the normal route soon, but has not announced a date yet. As of December 19, the 506C bus shuttle operates along College and Carlton streets rather than diverting along Harbord, Hoskin, Queen’s Park, University and Gerrard.

According to the City’s webpage for this project:

In spring 2023, the City’s contractor will return to complete work on the elevated cycle tracks between Manning Avenue and Spadina Avenue and upgrades to the existing bike lanes between Spadina Avenue and Bay Street.

Wellington Street

Updated: This original text has been removed because it proved to be out of date.

The current status is that undocumented underground conflicts still dog this project, which also was delayed to accommodate local festivals. Work on the north side of Wellington is expected to be largely completed in 2022, but the south side will be finished next Spring.

There is no word on when TTC will reinstall overhead so that 503 cars can return to the Church-Wellington-York loop.

King Street Travel Times: Fall 2022 Update

Updated December 20, 2022: Detailed charts have been added for the segments between Jarvis and Yonge, and between Yonge and University. Click here to jump to the new part of the article.

This article continues a series looking at the travel times on King Street in the “transit priority” segment between Bathurst and Jarvis Streets with data to the end of November 2022.

With the resumption of commercial and social activities, the comparative calm on King has disappeared, and the street can be very busy in the Entertainment District especially in the evening. The laissez-faire approach to traffic management and enforcement on King did not matter much during the pandemic shutdowns, but the benefits of the priority area are slowly being lost.

This echoes other aspects of the transit system where as a City we seem to have forgotten how to run things well under “normal” conditions either because of permanent funding cuts, or because we have forgotten the effort needed to deal with heavier demand on our services and infrastructure.

The first set of charts in the article takes the long view starting in 2016 to show the evolution from before the transit priority zone was created, then the effect of that zone, the arrival of the pandemic and the return to pre-pandemic activity.

There are two distinct sections of King Street. East of University is the business district, and it is less affected, at least from a transit travel time point of view, because activity there is still below “normal”, pre-pandemic conditions. However, interference from north-south traffic backlogs at intersections is starting to have an effect, mainly in the PM peak. West of University is the Entertainment District and its high density residential neighbourhood where one might ask “what pandemic?” from the number of pedestrians and motorists on the streets.

Later in the article, I will review changes in travel times over short segments between Jarvis and Bathurst.

The situation on King with deterioration of the transit priority area’s benefit was the subject of a recent item by the CBC: What’s Happened to the King Street Transit Corridor?

Continue reading

Service Analysis of 63 Ossington, November 2022

This article arose from complaints I saw on Twitter about the poor service on the 63 Ossington bus during November and early December. The common thread is that service is extremely erratic, a common problem on many routes.

In the case of the Ossington bus, most trips are comparatively short because it extends only from Eglinton West Station to Liberty Village, and many trips are to or from the subway at Bloor. This means that wait times can form a substantial part of a journey on the route, sometimes more than half. Moreover, they are unpredictable and riders must allow time for this whether they will need it or not. This is not a formula for attracting demand back to the system from those who have a choice of travel some other way.

The charts here are in a format familiar to readers of this site. To save repeating explanatory material, I urge those who are new to this type of analysis to read Understanding TTC Service Analysis Charts: A Primer. For details of how these charts are created, see Methodology For Analysis of TTC’s Vehicle Tracking Data.

Service on 63 Ossington during November 2022 operated with schedules that had been in place for some time. The weekday schedules had been in effect since March 2022, and the weekend schedules since November 2021.

During peak periods, half of the service short turns at St. Clair via Oakwood Loop, but at all other times, all buses run over the entire route.

During November 2022, there was an enlarged south end loop to avoid construction at King & Shaw, but no additional running time was provided in the schedule to compensate for this.

The route has frequent opportunities to regulate headways with layovers at the terminals and at Ossington Station Loop. Note that recovery times are particularly large during weekday peak periods and midday. This is intended to deal with congestion due to Line 5 Crosstown construction at Eglinton West Station. Recovery times are more commonly only one headway or less.

Continue reading

The Ottawa LRT Report (Part III)

This is the third part of my review of the Final Report of the Commission of Inquiry into the Ottawa LRT fiasco. This article covers mainly the vehicle and control system manufacturing, and corresponds to chapter 9 of the Inquiry Report.

See also:

Part IV will deal with the construction of the line, and Part V will deal with the transition to revenue service.

The entire process is a textbook example of what happens when “on time, on budget”, coupled with an unproven design, forces abandonment of well-established best practices for manufacturing and testing. Moreover, the lack of integration and communication across the project puts the lie to the idea that a private sector consortium will automatically be run like a well-oiled machine rather than a clanking contraption on the edge of collapse.

Updated Dec. 12/22 at 5:30 pm: The discussion of signalling systems used on various lines has been corrected to cite Bombardier’s Cityflo 650 system as the one used on Line 5 Eglinton.

Continue reading

TTC Board Meeting December 8, 2022

The inaugural meeting of the TTC Board for the new term of Council met on December 8. As is common for the first meeting, the agenda was light, and the event was more ceremonial than substantive.

Councillor John Burnside is the Board’s Chair, replacing Councillor Jaye Robinson who was not re-appointed.

Joanne De Laurentiis, who acted as Vice-Chair in the past term, was re-elected to the position. Note that terms of citizen members are not coterminous with the Council term, and so she remained on the Board through the recent election.

CEO’s Report

The Board received a presentation from staff as background to the CEO’s Report. A chunk of this was introductory giving some background on the TTC and its recent accomplishments. It included a short section on ridership and plans under the the title “Key Focus on Service and Customer Experience”.

CEO Rick Leary talked about the benefits of the move to Automatic Train Control on all of Line 1 and the implementation of One Person Train Operation. He cited a recent case where the TTC achieved a throughput of 32 trains/hour at Bloor Station between 8 and 9am, an increase over the typical pre-pandemic level of 24 to 26.

Note that this would have occurred after a gap with a backlog of trains, not as a routine level of service. The AM peak scheduled level sits at 21 trains/hour plus a few gap trains if needed. One advantage of ATC is that it provides a faster throughput of bunched trains after a delay at choke points like Bloor where platform dwell times are long.

Ridership continues to recover on the system, although only modest growth is expected for 2023 due to the effect of work-from-home. The bus network, which serves proportionately more trips that are not amenable to WFH, continues to show the best performance carrying 77% of pre-pandemic demand.

Weekday ridership sits at about 70%, while weekends do better at 80%.

Trips on the TTC occur for many reasons. Note that in the chart below, the percentages for October 2022 are on a ridership base about one third lower than the pre-covid values. The category “Professional and General Office Commutes” has not only fallen from a 28% to 22% share, but on a smaller base. Some percentages increase because their category is now measured against that base. For example, “Market Trips” went from 7% to 9%, but this still represents fewer trips.

This chart is important because it shows how many transit trips are not traditional office commutes, and that the wide variety of demands do not necessarily fit a system organized only to handle office workers.

Customer satisfaction is a softer metric than trip counts, but the general trend in 2022 has been downward, notably in October with the increased crowding levels associated with stronger ridership.

This is echoed by both crowding and wait time being two areas of dissatisfaction, especially wait time. TTC staff noted that customer pride ranks higher with frequent riders, while satisfaction ranks higher among infrequent riders.

Continue reading

The Ottawa LRT Report Part II

This is a continuation of my review of the Final Report of the Commission of Inquiry into the Ottawa LRT fiasco. This article picks up from the point where the contract is awarded to the successful P3 bidder, Rideau Transit Group, and reviews the contract and project structure.

See also: The Ottawa LRT Report Part I which contains introductory material and the story up to the contract award. In Part III I will turn to construction problems and testing before revenue service began, and Part IV will cover from that point to the present.

Contractual Agreement

On December 19, 2012, Rideau Transit Group (RTG) achieved the best score on their submission although, as I noted in the previous article, this was primarily on financial factors as the technical scores of the three bids were close to each other. Ottawa still clung to the 2010 budget estimate, and the project was approved at $2.13 billion. However, the P3 arrangement removed much of the City’s control over the project.

The actual structure of the project involved several entities, some of which were actually the same companies acting in different guises. This divided the project into subcontracts although ultimate responsibility rested at the top with RTG.

The Project Agreement accounted for the fact that, as is typical with this type of model, RTG would flow the bulk of its contractual obligations under the agreement down to subcontractors. […] The Project Agreement required RTG to ensure that its subcontractors complete the subcontracted scope of the OLRT1 project in the same manner and to the same extent as RTG is required to under the terms of the
Project Agreement.

Accordingly, the obligations for the works required by the Project Agreement were set out in RTG’s subcontracts with OLRT-C [the construction arm of the P3] and RTM [the mainenance arm], respectively. Under the subcontract with OLRT-C, OLRT-C took on the obligation to complete the design and construction as required under the Project Agreement as well as the risk and associated payments if the obligations were not met. Similarly, the subcontract with RTM flowed down RTG’s obligations to maintain the OLRT1 project as required under the Project Agreement, and RTM took on the risk and associated payments if the obligations were not met.

This structure allows RTG to be a small entity made up of only a handful of executives and support staff who would administer and oversee its contracts with its subcontractors. Any reporting from the subcontractors up to the City and back went through RTG. [p 148]

In this arrangement, management of the groups responsible for the work flows through the topmost level, RTG. In theory, this provides a single point of contact and responsibility, but it also creates a potential choke point in the City’s ability to manage work done on its behalf.

“Under the Project Agreement, RTG was responsible for the construction and maintenance of the OLRT, and the City would be the operator of the system. The Project Agreement, which was based on Infrastructure Ontario’s P3 template, gave the City limited control over the construction process or the subsequent maintenance of the system. Therefore, the City’s ability to direct the project was generally limited to enforcing specific financial remedies under the Project Agreement. In essence, the City was in a position where it had to rely on RTG to fulfill its contractual obligations and could only attempt to ensure compliance by withholding funds or otherwise enforcing contractual remedies.” [p 9]

Systems integration is an important part of any large technical project. One cannot simply buy components from various sources, plug them all in and expect them to work. With the management of suppliers happening a few levels removed from the City, an assumption is needed that this integration is actually happening. In fact, it was not, or at least not at a level needed to guarantee success.

“RTG’s project plan required the various engineering systems that went into the OLRT1 to be carefully integrated. However, the subcontractors operated in silos. These decentralized arrangements made it essential that the parties integrate their efforts and engage in near-constant communication. They failed to do so, OLRT-C [the construction arm of the P3] did not effectively coordinate their efforts, and the project suffered due to this lack of coordination.” [p 9]

On top of these issues, the vendors argued that the specifications were too “prescriptive” about how things should be achieved, as opposed to describing a system performance requirement and leaving it to the P3 to figure out how that should be met. This affected, in particular, the vehicle design.

An obvious question is why this was not addressed during the pre-award stage of commercially confidential discussions, or if the City and their consultants (who presumably were responsible for the specification) refused to change it.

“Regardless of the details of the project specifications required in the Project Agreement, by signing the Project Agreement, RTG agreed to be “responsible for the complete design, Construction, testing and commissioning and Maintenance of the complete Systems required for the safe and efficient operation of the LRT.” That is, RTG signed the Project Agreement with “eyes wide open.” [p 151]”

The contract contained provisions for various types of default including:

  • Failure to Maintain Schedule: The City could issue a notice to RTG which triggered a requirement for a plan to get the project back on time and achieve a Revenue Service Availability (RSA) date no later than mid-May 2019. Failure to deliver a plan would be deemed a default and entitle the City to terminate the contract.
  • Delays to Revenue Service Availability: Many preconditions determined whether RSA had been achieved including Substantial Completion of civil works, testing and safety requirements, and training of City staff for system operation. The RSA date was May 24, 2018, and five days after certification, RTG was entitled to a $200 million payment. If this date was not met, the agreement included provisions for rescheduling and a penalty payment (liquidated damages), but in any event if the date went beyond May 2019, this would be considered as a default.
  • The contract between RTG and OLRT-C also contained provisions for penalties up to about $145 million for delay damages.

Various types of events were provided for where RTG would be entitled to a schedule change and financial compensation. Typically these were external events including Acts of God, interference by other agencies or governments, labour actions, civil unrest, contamination of work sites, and archeological finds. Even if the event was beyond RTG’s control, they were required to reduce or eliminate its impact to the degree possible.

Despite this fairly exhaustive list, the agreement did not provide for any relief related to geotechnical risk. This was assumed completely by RTG with only the following exemption:

“The only partial exception to this is that the Project Agreement did create a Relief Event “with respect to Tunnel Work only” for “bursting or overflowing of water tanks, apparatus or pipes if such events are not attributable to the actions or omissions of Project Co [RTG] or any Project Co Parties and are not properly inferable, readily apparent or readily discoverable from the Background Information.” [p 159]

RTG, in effect, lost their bet on geotechnical risk thanks to a large sinkhole on Rideau Street. This event is covered later in the report.

Although the contract included a worst-case option that the P3 would be declared in default and the entire project would revert back to the City, this is obviously not a path to be followed except in the most dire circumstances. There is a strong incentive for the P3 to hit the mark on schedules, or at least claim that this will occur, and for the City to use financial threats to ensure projects stay on time. However, this creates an antagonistic relationship if anything goes substantially wrong on the project.

However, with the Mayor’s political credibility hanging on delivering a project “on time, on budget”, the likelihood that the P3 would be forced into default was minuscule. This created a situation where the project would “succeed” no matter what.

Continue reading

TTC Service Changes: Holiday Period 2022/23

As is usually the case, the TTC will implement modified schedules during the two-week holiday period which, because of the lie of the calendar, runs from December 25 to January 6 this year.

Several routes will revert to June 2022 summer schedules for the weekdays within this period. No changes are planned for Saturday and Sunday schedules. Many of the summer schedules have the same service frequency, but with fewer buses and shorter travel times reflecting reduced passenger and road traffic.

No school trippers are operated during the holiday period, and service is reduced on some routes serving post secondary campuses.

Late night New Year’s Eve service will operate until about 3am on most routes including all rapid transit lines.

Service will operate free of charge from 7pm on December 31 to 8am on January 1.

Details are in the spreadsheet linked below.

TTC Track Construction Update December 5, 2022

Here is a brief update on various construction projects in progress.

King/Queen/Queensway/Roncesvalles

Excavation continues on Roncesvalles at the north gate of the carhouse while the track panels for the new junction remain on trailers on King Street (see previous update).

Track installation has started south from Harvard Street toward the north gate.

The TTC has not yet announced a date for resumption of through service on Roncesvalles between Howard Park and The Queensway on route 504 King, nor for through streetcar service from downtown to Dundas West Station.

On The Queensway, the eastbound stop at Glendale has finally been taken out of service. Passengers are now directed to use westbound buses to access St. Joseph’s Hospital transferring at Roncesvalles or at Colborne Lodge Drive as appropriate.

The map below was tweeted by @ttchelps. As I write this, neither this map nor the diversion notice for the 504 bus service are linked to the route’s schedule page.

Construction continues on the new eastbound curb lane and the eastbound streetcar stop at Glendale. Work is also in progress on the track between Glendale and Parkside.

Overhead is still not in place at Sunnyside Loop although many span wires and hangers have appeared. The 501 Queen service cannot be extended from Dufferin to Sunnyside until this loop is available.

King & Shaw

According to a City of Toronto construction notice, this intersection will reopen on Friday, December 16. This would allow the 504 King and 63 Ossington services to resume normal operations here.

When the TTC announced their November service changes, this included a temporary option, once King & Shaw reopened, with half of the 504 service turning back at Exhibition Loop (the 504B Broadview cars) and half running through to Dufferin (the 504A Distillery cars). The 504C buses which loop at York Street would shift to a Bathurst turnback.

The TTC has not yet confirmed whether these arrangements will actually happen.

Adelaide Street

Construction has moved swiftly west on Adelaide and is now in the final stretch between Widmer and Charlotte Streets. The section east from York to Victoria will be rebuilt in 2023.

Wellington Street

New overhead has not yet been installed on Wellington Street. The 503 Kingston Road bus is looping via York, Richmond and University from King. Streetcar service should return in the Spring when pantograph-friendly overhead on the downtown loop and on Kingston Road has been installed.

Dundas at Brock Street

A large sinkhole appeared under the streetcar tracks on Dundas at Brock due to a burst 120-year old sewer. The City expects the street to be restored by the end of December, but the TTC will then have to restore the track and overhead. Until that work is finished, tentatively by the end of January 2023, the 505 Dundas service is diverting both ways east of Lansdowne via College and Ossington.

Media coverage is available from CBC and CITY, among other sources.

College Street

The diversion of 506 Carlton streetcars around the College Street reconstruction project is expected to finish by the end of 2022. Streetcars continue to operate both ways via Bay, Dundas and Ossington.