Drifting Timelines on Metrolinx Projects (Updated)

Updated June 23, 2020 at 1:50 pm: The table of projects has been updated to include anticipated events, notably “financial close” dates, that were included in various project announcements by Infrastructure Ontario. Also Union Station Platform Expansion was described in the original version of this article as closing sooner than originally projected. This has been corrected to show a delay of roughly nine months.

Infrastructure Ontario recently released its Spring 2020 Update for P3 projects under its control including several Metrolinx projects. To date there have been three of these updates:

These updates include information on the project status, the type of procurement model, and the expected progress of each project through the procurement process. This provides “one stop shopping” compared to Metrolinx’ own site. As a convenience to readers, I have consolidated the three updates as they relate to transit projects to allow easy comparison between versions.

Some projects have evolved since the first version, and in particular the delivery dates for a few projects have moved further into the future. The “financial close” dates for some projects, in effect the point at which a contract is signed and real work can begin, has moved beyond the date of the next Provincial election. Whatever government is in power after summer 2022 will have a final say on whether these projects go ahead.

Subway Projects

Ontario Line

The Ontario Line was previously reported as a single project with a price tag of over $10 billion. In the Fall 2019 update, the intent was to have the financial close in Winter/Spring 2022 ahead of the election. In the Winter 2020 update, this changed to Spring 2022.

In the Spring 2020 update, the project has been split into separate parts to reflect industry feedback about the original scope.

  1. GO Corridor from Don River to Gerrard
  2. South Tunnels, Civil Works and Stations CNE to Don River
  3. Rolling Stock, System Operations & Maintenance
  4. North Tunnels, Civil Works and Stations

The GO corridor work will be done as a conventional procurement by Metrolinx and will be bundled with upgrades to GO Transit trackage.

The financial close for items 2 and 3 above is now Fall 2022, and for item 4 it is Fall 2023.

This means that an actual sign-on-the-dotted-line commitment to the project will not be within the current government’s mandate. Even the so-called “early works” comprising the southern portion of the route from Exhibition to the Don River is not scheduled to close until Fall 2022. The northern portion, from Gerrard to Eglinton will close in Fall 2023. This contract is being held back pending results for the south contract to determine the industry’s appetite for the work.

The southern portion, with a long tunnel through downtown and stations in congested street locations would start first. However, the line cannot actually open without the northern portion because this provides the link to the maintenance facility which is included as part of item 3 above although the actual access connection would be built as part of item 4.

An issue linking all of these projects is the choice of technology which, in turn drives decisions such as tunnel and station sizes, power supply, signalling and maintenance facility design. When the Ontario Line was a single project, Metrolinx could say that this choice was up to the bidders, but now there must be some co-ordination to ensure that what is built can actually be used to operate the selected technology. It is hardly a secret that Metrolinx is promoting a SkyTrain like technology, although which propulsion scheme (LIM vs rotary motors) is not clear. There are well-known problems with LIMs and the power pickup technology used on the SRT, and this would also be a consideration for the outdoor portions of the Ontario Line.

Scarborough Subway Extension

Like the Ontario Line, the Scarborough Extension has been split into two pieces. The first will be the tunnel contract from Kennedy Station to McCowan. This is now in the  procurement phase, and financial close is projected for Spring 2021.

The remainder of the project previously had a projected closing date of “Winter/Spring 2023”, but this is now just “2023”. With the tunnel hived off into a separate contract, it is reasonable that the remainder would have a later start date because the tunnel is a key component that must be in place first.

Metrolinx recently published a Preliminary Business Case for this extension. It includes the following text:

Kennedy Station Pocket Track/Transition Section

The Kennedy transition section extends roughly 550 metres from the east side of the GO Transit Stouffville rail corridor to Commonwealth Avenue and will include special track work and a pocket track to enable every second subway train to short turn to suit ridership demand and minimize fleet requirements, as well as lower operating costs. [p 24]

This turnback has been an on-again, off-again part of the project but it is now clearly included as a cost saving measure. With only every second train running to Sheppard/McCowan, the fleet required (as well as storage) would be within the system’s current capacity. This ties in with the timing of the T1 fleet replacement on Line 2 as there are enough T1s to run alternate, but not full service to Sheppard. This would be similar to the arrangement now used on the TYSSE where only half of the AM peak service runs north of Glencairn Station to Vaughan.

Richmond Hill Subway Extension

The Ontario government recently signed an agreement with York Region for the extension of the Yonge line from Finch to Richmond Hill. The status of this project is unchanged with an RFQ to be issued in Fall 2021, an RFP in Spring 2022 and financial close in Fall 2023.

Sheppard East Subway Extension

This project remains in the planning phase.

Continue reading

TTC Board Meeting June 17, 2020

The TTC Board met on June 17, 2020 with several items on their agenda. Chief among these was recovery plan for the transit system as the effects of the Covid-19 lockdown recede and transit demand builds.

Updated June 18, 2020 at 1:30 pm: Charts from the service recovery presentation that were originally taken as screen captures from the meeting video have been replaced with higher resolution versions.

CEO’s Report

Many of the usual metrics for system performance are meaningless in the Covid-19 era because service and ridership are completely different from original budget forecasts. Even the “on time” statistics fail because the TTC reports this relative to scheduled times, not as a measure of service reliability. Detailed ridership tracking was reported separately under the Covid recovery report (below).

CEO Rick Leary reported that modifications to the operator’s area on buses are in development including extension of the plastic barrier forward to the windshield and altering airflow within the cab to be a “positive pressure” area where air is always pushing out rather than being drawn in from the main passenger area.

As reported elsewhere, the TTC is taking advantage of lower demand to accelerate capital and maintenance programs. The northern part of the Yonge subway (Line 1) will be closed for various periods during coming weeks including:

  • Sat/Sun June 20/21 all day: Sheppard-Yonge to St. Clair for Metrolinx construction at Eglinton and track repairs elsewhere.
  • Thu/Fri June 25/26 all day: Finch to Sheppard-Yonge for maintenance including ATC installation.
  • Sat/Sun June 27/28 all day: Finch to Lawrence for maintenance including asbestos removal and ATC installation.

The TTC has not announced whether completion dates for the ATC project will be moved forward thanks to the extra work.

The rebuild of streetcars to correct welding problems and other retrofits will also be accelerated with 19 more streetcars available for maintenance. This will allow the entire fleet to come up to standard 18 months sooner than originally planned.

Reliability of the streetcar fleet continues to improve. There are two measures of this with one based on contractual requirements (failures due to manufacturing issues) and one based on operational behaviour (including all failures). The contractual measure is running at over 70,000 km mean distance to failure on a monthly basis with the 12-month average sitting just over 40,000 and growing. The operational measure is running just under the 35,000 km target.

In the subway, vehicle reliability is mixed. On Line 2 BD, the T1 fleet is running far above the target level with MDBF values in the millions of vehicle kilometres compared to a target of 300,000. On Lines 1 and 4, the TR fleet is not faring as well. The 12-month rolling average is above the 600,000 target for this fleet (which is younger and therefore is expected to perform better), but numbers for both February and April 2020 were below the target, particularly in April.

The reliability of the electric bus fleet is improving although it is not yet at the 24,000 km MDBF target. The BYD fleet was still not in revenue service within the period of the report, and so no reliability stats for these vehicles are available.

The hybrid bus fleet is running at or above 30,000 km MDBF while the diesel bus fleet is at or above 20,000. It is not clear how much of the improvement is due to inherent reliability as opposed to the sidelining of problem vehicles in the fleet.

Covid Recovery / Bus Priority Lanes

Please see my previous article TTC Preps For Covid Recovery for a review of the main part of this report.

The Board considered this report together with a notice of motion regarding proposals for five bus transit priority corridors. Please see my article Transit Priority Lanes Can Help, But They Are No Panacea and other related articles for background analyses of the potential benefits and limitations of priority lanes as a way to improve bus service.

Covid Recovery

New information was added to the original report showing how demand is building across the TTC network.

Bus riding has been growing from its nadir in mid-April. Although 70,000 more boardings per day may not be much on the usual scale of TTC operations, it is a very large growth on a base of 288,000 (blue line in the chart below). Across the bus network, the TTC is now carrying on average 30% of its former load, a key point in the recovery where capacity and distancing requirements vie with each other. There is a growing problem with overcrowding relative to the current standard with 12% of trips now running about 15 passengers per standard sized bus, and 1.5% above 25 per bus. The system cannot handle more growth without a combination of additional service and social practices, mainly masking, that will improve safety on more crowded vehicles.

More service on Jane today than in Feb

The map below shows where the “hot spots” were in the bus network in mid-May when total boardings were at 25% of normal, and 7.6% of trips exceeded the 15/bus loading standard.

By June, this had evolved with over capacity conditions on several major routes. Many extra buses built into the May schedules were dispatched to supplement regular service, and on the key routes shown below, the scheduled service will be improved effective June 22. The TTC plans to have more service on 35 Jane in late June than it did in February, although this claim does not take into account the 935 Jane Express buses in the “before” service.

Eventually, the TTC will return to “100% service”, but this will be based on the count of vehicles, not simply a return to original schedules. Some routes still have weaker demand, and buses formerly assigned to them will be used to add service on the busy lines. The express bus routes serving the core where demand is weakest will remain suspended.

The TTC’s plan does not address the issue of using its considerable pool of spare buses to push service beyond the 100% level, nor of the degree to which the streetcar network can be fully operated with that mode once various construction projects are out of the way.

Although TTC management did not say this explicitly in the discussion, the move back to 100% service appears to be contingent on funding from the provincial or federal government that will insulate the City from the extra cost.

Bus Priority Lanes

According to TTC management, “significant” work has already been done with their City colleagues on the bus lanes which were proposed in the Five Year Service Plan last December. Eglinton East is the top priority, and there will be a report on it in July 2020. It is unclear just how quickly we will see detailed proposals for other corridors, especially with a desire by some affected Councillors to have public consultation, and the very real possibility that opposition to these lanes will block their implementation.

The TTC does not help its own argument on this point.

Staff advised that the Eglinton-Kingston-Morningside lane would save 7 buses overall for the routes operating in this corridor, and spoke first of this as a budgetary saving, not as an opportunity for improved service. This is exactly the same position staff took in the early days of the St. Clair proposal where residents and riders were dismayed that after so much upheaval there would be no improvement in service.

This position does not align with the statements by Commissioner Brad Bradford who spoke of “flooding the street” with buses taking advantage of the new transit priority, and while that may be a great sound bite, it does not reflect what the TTC is likely to do, or can do with limits on its fleet and staff constraining bus network growth. Moreover, a 7 bus saving is not a huge change at the scale of the full network. This is unsurprising given that the likely change in travel time is not going to bring as much saving as many think.

Bradford asked how the transit priority scheme would help in the Covid fight, and again staff’s response was lacklustre claiming that shorter travel times would reduce the time spent on board, rather than speaking to improved crowding conditions through additional service.

There is a stark disconnect between the hoped-for benefits of transit priority for riders and the manner in which the TTC appears poised to scoop any savings in the budget, not for better service.

Bradford spoke of the importance of the bus  network and the “underserved” neighbourhoods where bus lines run. It is odd for a TTC Commissioner to openly talk of “underserved” areas while the very Board and Council he sits on refuses to address the problem of bus route capacity.

The hoped-for September 1 implementation will be a stretch for anything beyond one corridor, and that with little more than paint and signs.

Commissioner/Councillor McKelvie proposed an amendment that the study of future corridors also include Lawrence East from Victoria Park to Rouge Hill. The report with this amendment passed unanimously.

Rider Attitude Survey

The Covid recovery report includes an extensive section on rider attitudes and the potential recovery of transit demand. I will deal with this in a separate article.

Streetcar Track Noise at King and Sumach

An ongoing issue at the intersection of King and Sumach has been streetcar noise and vibration ever since the Cherry Street branch began operation. Several issues contributed to this problem including wheel squeal on curves and noise from track switches tongues “slapping” in their castings as cars passed over them.

Various changes have been made to address components of the problem, but more work is pending.

  • With the removal of CLRVs from Cherry Street service, the noisiest cars were no longer making turns at King and Sumach.
  • A wheel lubricator was installed at Distillery Loop, although this is of no benefit for cars turning east to south off of King.
  • Wheel vibration dampening rings have been installed on 10 streetcars and these reduced noise on curves by 5-7 dBA. A further 60 cars will receive dampeners over 2020, and the rest of the fleet will be completed in 2021. Cars with these devices will be assigned to the 504A King route to the Distillery.
  • On board wheel lubricators are already installed on the first half of the fleet, and the TTC plans to add them to the remainder.
  • Curve track geometry has been adjusted, and will be further refined as part of the 2021 Capital Budget plan for track repairs.
  • Switch tongues that did not sit flush have been ground to reduce the slapping effect as cars pass over them.
  • A new design for flexible switch tongues is under review with plans to install one on the trailing eastbound switch where noise has been a problem. A trial installation is already in place at College & Lansdowne eastbound.

Although King & Sumach has been the focus of complaints and testing, many of these changes will benefit the streetcar system as a whole.

Waterfront LRT Design

The TTC Board approved a contract for $15 million for design work on the underground portion of the proposed Waterfront East LRT/streetcar extension. This work is being done jointly with Waterfront Toronto who are responsible for the surface portion of the route from a portal near Yonge Street to Cherry Street including a connection to the existing Distillery Loop.

This contract will take the design of the underground portion to 30% with a project cost estimate leading to a request for Council approval in the second quarter of 2022. Whether this project will actually proceed remains to be seen.

Part of the work will involve staging plans to determine whether and how the project can be built to stretch out spending based on the rate of growth of demand in the eastern waterfront. This statement was a bit puzzling considering the scale of changes required at Union and Queens Quay Stations including lowering the track elevation to provide more space for air circulation to meet modern fire code.

Eglinton West: An LRT Subway for Etobicoke?

On February 28, 2020, Metrolinx release a Preliminary Business Case for the Scarborough Subway Extension, and an Initial Business Case for the western extension of the Eglinton Crosstown LRT from Mount Dennis to Pearson Airport.

The Eglinton West Extension IBC is not as blatantly skewed as the Scarborough study in that it acknowledges the LRT plans and uses these as a starting point. The SSE study simply pretends that LRT does not exist and touts “benefits” of the subway versus a bus network.

The idea of a line along Eglinton West has been around for a long time.

  • 1972 ‘GO Urban’ and Rapid Transit Plan on Eglinton: Eglinton corridor was part of Province’s and TTC’s ‘Intermediate Capacity Transit System’ (ICTS) Network Plan (in which the present Scarborough RT was a part of)

  • 1985: ‘Network 2011’ and Eglinton West Plan: TTC Report identified Eglinton West as busway corridor as part of Metro Toronto’s rapid transit network plan (in which the present Sheppard subway was a part of)

  • 2007: ‘Transit City’ and Eglinton Crosstown Plan: Eglinton Crosstown LRT (spanning from Pearson in the west to Kennedy in the east) was part of the City of Toronto’s surface rapid transit expansion proposal

  • 2010: Crosstown LRT Project Approval: City of Toronto sought EA approval for surface LRT alignment from Kennedy to Pearson Airport Area boundary, one year after the City approved the full-length Eglinton Crosstown alignment

  • 2012: Eglinton West Segment Deferment: Metrolinx undertook Crosstown LRT construction, with Mount Dennis-Pearson Airport segment deferred due to funding constraint

  • 2016: Eglinton West LRT IBC: City of Toronto and Metrolinx co-published Eglinton West LRT’s first IBC and recommended surface LRT option, and the City approved funding for preliminary planning and design works

  • 2017: Grade Separation Review: City of Toronto approved arterial and midblock stops along Eglinton West and conducted grade separation study to address community concerns

  • 2019: Surface Option’s Affirmation: City of Toronto in its report maintained its preference for surface LRT based on fine-tuned benefit-cost analysis. [p 9]

As an historical note, a mid-1960s TTC plan to serve the airport with LRT linking southeast to the Bloor Subway and northeast to the Finch corridor was stillborn thanks to the 1972 GO Urban scheme.

We have arrived at a preferred subway option by provincial fiat:

In December 2017, the City of Toronto conducted further studies on additional grade-separated options based on inputs from the local community who are concerned with the at-grade LRT’s traffic impact. The number of options for the Toronto Segment were revised to four (featuring at-grade and below-grade alignments with frequent arterial and midblock stops, and a mostly below-grade alignment with either a single stop or multiple arterial stops) and re-evaluated using traffic model updates and additional metrics recommended by community representatives.

Nonetheless, the City of Toronto in early 2019 released a report re-confirming their preference for an at-grade LRT due to its cost-effectiveness in meeting all of the city’s project and policy objectives.

Subsequently, the Province’s 2019 Budget announcement included the extension of the Eglinton Crosstown LRT to Mississauga as one of the four budgeted rapid transit projects with an underground alignment. [p 27]

This is a second “Initial” study, but it is in the context of Premier Ford’s strong preference for subways. The usual caveats apply about the rough level of cost estimates and comparisons between options.

There is a fundamental conflict in the analysis in this study triggered both by the Premier’s distaste for “streetcars” and by Metrolinx methodology.

The surface option carries the greatest number of weekday riders, but one of the subway options carries the most “new” riders. In other words, the surface option does a better job of serving existing demand while not drawing as much new demand, while the subway option leaves some existing demand quite literally “out in the cold”, but (according to the modelling) shifts more people to transit from autos. The machinery of value assignment rewards the new riders more because they allegedly represent less auto use, and they tend to be longer-distance riders who save more travel time.

At no point does the study explain why carrying fewer total riders at much greater expense constitutes a valid planning outcome.

Continue reading

Eglinton Crosstown LRT Chronology (Updated)

Updated February 21, 2020 at 11:00 am:

This update includes a reply from Metrolinx detailing the nine-month contractor delay he cited in his announcement of the 2022 opening for the Crosstown, as well as additional information on delays to the project.

Metrolinx Metrolinx Media Relations provided additional information on the status of work at this point in an email on February 20, 2020.

Based on CTS’s original schedule, 30% design packages for the majority of stations (the first step in the final design process) were to have been completed and approved by December 2015/January 2016.

With the exception of Keelesdale station, none of that work was completed until March 2016 or later, and in the case of Eglinton station the 30% design was rejected due to design deficiencies.

It’s also important to note, that other key aspects of design, such systems design components, were also delayed significantly.

Despite the known delay at this point, this was not mentioned in public reports in following months.

While the update explains some of the issues CEO Phil Verster referenced in his announcement, it does not explain the reason why the in service date continued to be cited as September 2021 well after Metrolinx knew that this was not likely or possible. The opening date has been cited publicly and is included in TTC’s 2021 budget and bus fleet plan.

Internal Metrolinx status reports from September 2019 show that the problem at Eglinton Station was already a known issue as were problems with ground water at Avenue Station and a conflict with CPR at Mount Dennis, among other construction-related delays. The estimated substantial completion date was already in 2022, and it continued to move later in the year to at least May 2022. It is not clear whether “substantial completion” coincides with opening, or merely with the point where commissioning of the line can begin, a process that is several months long and during which other problems that could delay revenue service might arise.

Moreover, the claim by Minister Mulroney that proposed legislation would have accelerated this project by three years remains completely unsupported by the actual project chronology.

Updated February 21, 2020 at 7:00 pm: Metrolinx has confirmed that “substantial completion” includes commissioning so that revenue service can begin.

Original article:

On February 18, Transportation Minister Caroline Mulroney introduced the Building Transit Faster Act which is intended to speed up progress on the four key Ontario transit projects in the Toronto area: The Ontario Line, the Eglinton West LRT extension, the North Yonge subway extension to Richmond Hill, and the Scarborough Subway extension to Sheppard.

The day before, February 17, the Star’s Ben Spurr reported that the Crosstown line’s opening would be delayed until “well into 2022” according to Metrolinx CEO Phil Verster. This delay had been rumoured for some time, but was denied by Metrolinx until now.

Metrolinx published a statement on their website including photos showing unexpected conditions discovered on the Yonge Subway tunnel structure at Eglinton Station that were responsible for part of the delay.

The statement also includes a claim that the consortium building the project, Crosslinx Transit Solutions started work “nine months later than planned after contract award in July 2015”. This does not align with actual events as shown later in this article. I expect to receive a clarification from Metrolinx on this matter soon.

During her press conference, Minister Mulroney claimed that the Eglinton Crosstown project would have opened three years sooner had the provisions of the Act been in place. This claim is hard to believe considering the nature of the delays we know about, the types of delay addressed by the legislation, and the actual chronology of the project.

Eglinton and other projects have faced numerous hurdles, but these have overwhelmingly been political and financial.

To sort this out, I have assembled a history of the Eglinton Crosstown.

Continue reading

The Ford/Tory Subway Plan: Part II – Technical Appendices

In the first of two articles, A Big Announcement, or a Transit Three Card Monte?, I reviewed the proposed agreement between Ontario and Toronto whereby the Province would build four lines or extensions at no capital cost to the City, and ownership of the existing system would remain in City hands. This has been hailed as something of a “peace in our time” solution to the contentious relationship between Premier Ford and the City, but there are many outstanding issues that will not be resolved before the City signs on to the new deal.

In this article, I turn to three appendices to the City report, specifically:

Citations in this article are in the format [A3, p5] where “A3” is the attachment number and “p5” is the page number.

Reading through these documents, I was struck by how an essential section is buried right at the end of Attachment 4: the City/TTC evaluation of the Metrolinx Initial Business Case for the Ontario Line.

The main report is enthusiastic about the viability of the proposals and the contributions they will make to the City of Toronto. However, the attachments reveal the degree to which the scheme is far from complete or settled. There is a caveat that if the proposals change significantly, then the gushing support for the new plans could become only a trickle. But the political pressure is for the City to commit to the scheme, whatever it may become, in the rush to “get shovels in the ground”.

This is a long article intended to pull key points out of the technical discussion of proposed new lines in an attempt to highlight the major chunks without requiring readers to wade through every page (although the keen ones among you certainly will, I’m sure).

Timing of Market Calls for Procurement / Public Participation

The City/TTC have not received a detailed schedule from Metrolinx, however the Infrastructure Ontario Fall update includes the following timelines:

  • Ontario Line: RFQ Spring 2020, RFP Summer/Fall 2020
  • L2EE: RFQ Winter/Spring 2021, RFP Summer/Fall 2021
  • YSE: RFQ Fall 2021, RFP Spring 2022
  • EWLRT: To be determined [A3, p12]

This is aggressive for the OL and gives very little chance for substantive change before the RFP goes out. “Public participation” will be minimal in the best Metrolinx tradition.

The opportunity for feedback and input throughout a project’s development may differ given the anticipated P3 delivery model. Details regarding the Province’s proposed approach are provided as Attachment 11 to this report. City and TTC will continue to advocate for meaningful public consultation on provincial transit projects. [A3 p11]

There are conflicting priorities in completing work regarding the new design and changes to the Assessment with the desire for an expedited delivery process.

Q22: Has an assessment of construction-related impacts been undertaken as part of the preliminary planning and design? What about impacts on community, businesses, traffic congestion, noise, etc.? If not, when will this occur and be factored into decisions on build methodology, procurement, and a program for business and community supports?

A: The City/TTC expect that this will be undertaken as part of the updated environmental work for the TPAP(s).

Q23 Will the Province adhere to City permits and approvals, per the practice under the LRT Master Agreement?

A: The applicable Master agreement(s) for these projects are to be developed, and it will be the expectation that agreed upon service standards and timelines for applications, permits and approvals will be adhered to. The Province is seeking city commitment to explore opportunities to accelerate and expedite delivery including review of processes, and leveraging powers and authorities. [A3 p13]

Q29: Are you building the [Ontario] line to a budget of $10.9 B or are you building a line with a defined scope of work?

A: The project cost estimate is preliminary based on the current state of development. The scope in so far as length and areas served have been consistently stated. Future adjustments to scope, budget and schedule will be identified as part of subsequent phases of work. [A3 p15]

“Future adjustment” is a term that implies potential change, but how would this be handled with a P3 contract already in place? When do the requirements to deliver on time, on budget, supersede whatever objections or improvements might emerge from a review process?

Transit Oriented Development

One of the Province’s favourite terms now is “Transit Oriented Development” and the supposed ability to pay for transit with development charges and fares from new riders. There is a question, however, of whether the Province will seek higher density around stations to pay for its rapid transit plan even if this requires development at a scale beyond what the City has planned or the neighbourhood is expecting. What other costs will TOD bring for infrastructure, services, schools? The overdevelopment of Yonge & Eglinton, where the Province wants to see even more density, is a prime example.

Q13: With respect to “transit-oriented development” and seeking private sector investment, what assumptions are being made with respect to compliance with the City’s Official Plan policies and guidelines?

A: The Province has committed to work with the City to ensure that transit oriented developments advance a shared understanding for effective growth and high quality development of Toronto. The City and the Province are working through the details of an agreement on how they will work together to advance TOD opportunities. [A3, p10]

That is not the most reassuring of comments given the bull-headed nature of Provincial policy development. Doug Ford (and his brother before him) believes in the magic of the private sector somehow covering the cost of his dreams. This could have severe consequences for both the City and for the transit system if that dream is exploited to remove controls on high density development.

Getting There From Here

There is a problem throughout much rapid transit planning in Toronto that agencies only consider the end state after many projects have been built, new jobs and residences have been created, and magically we are transported to a future date and city where the models run.

Unfortunately, we have to get from 2019 to 2041, the year for all of the modelling cited in these reports, and there is no guarantee that the system can handle either the intermediate stages nor the “end state” if things do not occur as quickly as we hope.

Although GO expansion is part of the next decade’s work, there is nothing published to show how it will affect the TTC network for good or ill. Indeed, a major role for the Ontario Line now appears to be “relief” for congestion at Union Station almost to the point that relief of subway congestion is a secondary matter.

SmartTrack is a mythical “service” whose final configuration is still not known. Metrolinx has been quite evasive on this point, and the best we can hope for is a train every 15 minutes at “SmartTrack” stations along the Weston and Stouffville corridors. Two of the six ST stations may never be built because they physically conflict with, or lose projected ridership to, other services.

It may suit planners and politicians to talk of demand models for 2041, but what will the 2020s and 2030s look like on Toronto’s and the wider region’s transit system as we await the arrival of new services? This is a major shortfall in the City reports because they do not address the “how do we get from here to there” problem complete with associated operational and financial headaches. A scheme for the province to pay the entire cost of four new lines is wonderful, but there is much more to the transit system’s future than Premier Doug Ford’s map.

Continue reading

A Big Announcement, or a Transit Three Card Monte?

On October 16, the governments at Queen’s Park and Toronto City Hall announced a deal to sort out competing transit plans for the city. The current provincial priority projects are the Ontario Line (Don Mills/Eglinton to Exhibition), Scarborough Subway extension from Kennedy Station to Sheppard, Yonge Subway extension from Finch to Richmond Hill, and the Eglinton West LRT extension from Mount Dennis to Renforth.

The main City of Toronto report will be discussed at Executive Committee on October 23, and then at Council on October 29-30.

This article reviews that report with reference to a few parts of its many attachments. I will turn to the technical attachments in a second article. To focus material on each subject for readers, I have grouped related items together or re-sequenced things for emphasis. There are extensive quotations of key material so that readers hear not just my “voice” but that of the report’s authors.

Despite the importance politicians at both levels place on the proposals, the fundamental problem remains that many of the details are cloudy, to be kind. Specifically:

  • The City of Toronto retains ownership of the existing transit system avoiding a complex realignment of responsibilities and governance, but with this comes total responsibility for funding the ongoing state of good repair.
  • A large gap remains between the amount of funding needed to maintain and expand Toronto’s transit system relative to the amounts actually available and committed in budgets at various levels of government.
  • Ontario will build four key projects substantially with its own money, but continued support for transit beyond this is uncertain.
  • Toronto will redirect funding originally earmarked for its share of the key projects to other priorities, notably the TTC’s repair backlog. However, much of that “funding” does not exist as allocations in existing budgets and new money is required from Toronto to pay its share.
  • Cost estimates for the key projects are based on preliminary estimates that could change substantially as the design process unfolds. These estimates are in 2019 dollars and make no provision for inflation. The reports are silent on how the proportion of total spending by each contributor might change over the decade or more of construction.
  • A substantial total of project costs will be born by private sector partners through a “P3” financing mechanism. These arrangement will require future payments for what will be, in effect, a capital lease, but the mechanism for funding this from three levels of government is unclear. The reports are silent on the split between short term borrowing to pay for construction as opposed to long term payments to the P3 financier.
  • Project details as they are known today will change in response to design work and the need to keep costs within the projected level. This will affect alignments and stations, and what we think we are buying could be quite different from what we actually get.

The challenge in all of this is, as always, the question of money. We can watch the hands of politicians and managers at all levels as they shuffle cards on the table. We hope to “find the Queen”, to win in the subway sweeps rather than being taken for suckers who will cheer any plan, but lose every game. It is far from clear whether the proposal is a “good deal” for Toronto, and there are huge future transit costs that are barely addressed.

The whole exercise is a political deal to bring peace, comparatively speaking, to the transit file which was needlessly fouled by Doug Ford’s insistence that he knows more about transit in Toronto than anyone else. Does Toronto take this as its last best chance to preserve some semblance of control over its transit future, or do we keep fighting for a better deal?

There are a lot of holes in this plan and severe implications both for the City’s finances and the future of Toronto’s transit system. Many questions need to be asked and answered, even if the result will be a whole new plan after provincial and municipal elections in 2022.

Continue reading

Ontario’s Transit Plans: Details Emerge in City Report

When Premier Doug Ford announced his new transit plan in April as part of his first budget, there was plenty of hype about provincial transit investment, but few details about what would be built or how far design had progressed beyond doodles on bar napkins. Four projects comprise the Ford plan:

  • The “Ontario Line” from the Science Centre at Don Mills & Eglinton to Ontario Place replacing Toronto plans for the Relief Line
  • The Richmond Hill extension of Line 1 Yonge
  • The Scarborough Line 2 Danforth extension to Sheppard & McCowan with at least three stops rather than the one in the current Toronto plan
  • A modified plan for the Eglinton West LRT extension with underground construction for part of the route east of Martin Grove
  • Extension of the Sheppard subway east to McCowan to meet the northern end of Line 2

Information about these proposals came more from rumours than from specifics, notably from Metrolinx, the agency charged with planning and delivery of the scheme.

Staff from the City of Toronto and the TTC have been meeting with their provincial counterparts, and details begin to emerge in a staff report to Toronto’s Executive Committee.

The Ontario Line concept proposed by the Province is at an early stage of design. [p 5]

This is not a “shovel ready” project, nor is the revised Scarborough subway, in spite of claims that the Ontario line can be open by 2027. That is very much a political date based on the need to have relief capacity in place before new demand is added to the Line 1 Yonge route from the Richmond Hill extension. The government, knowing the votes available in York Region, needs to show progress on that extension, but actually operating it would totally overload the subway system without substantial diversion of ridership to a relief line.

Previous studies by Metrolinx foresaw a drop in ridership at the Bloor/Yonge choke point provided that a new line went at least to Eglinton rather than stopping at Danforth. This is not news, but the political change lies in recognition that a line to Eglinton is not some future, “Phase 2” option, but an essential part of reducing demand on Line 1. Whether the construction timing and possible opening dates for the Ontario and Richmond Hill lines can be achieved is quite another matter. In a political context, the important date is 2022, the next Provincial election. By that time, visible “progress” will be needed to shore up support for the government, but the target dates will be far enough off that the inevitable slippage will not yet be evident.

Public Consultation

In parallel with the technical work on provincial plans, the City of Toronto has launched a public participation campaign about the shift in responsibilities for transit between the municipal and provincial governments. This is all a bit vague at present because the details of what Queen’s Park actually intends remain rather vague. The government has given itself the power to take over projects completely or in part, and to seize Toronto assets with or without compensation. However, the financial details are murky including the problem of expected contribution to capital projects by other governments and the as-yet unaddressed question of cost sharing for day-to-day transit operations which includes a substantial component of running maintenance, not just driving the trains.

The City will bring a wider range of issues than a few new lines before the public for comment. Four public meetings are planned over the coming month:

Thursday, June 13, 6:30 to 8:30 p.m.
Father Serra Catholic School
111 Sun Row Drive, Etobicoke

Thursday, June 20, 6:30 to 8:30 p.m.
North York Memorial Community Hall
5110 Yonge Street, North York

Saturday, June 22, 10:30 a.m. to 12:30 p.m.
Scarborough Civic Centre
150 Borough Drive, Scarborough

Thursday, June 27, 6:30 to 8:30 p.m.
City Hall, Council Chamber
100 Queen Street West, Toronto

Although one might despair that the Ford government cares about or will listen to concerns by Toronto citizens, this consultation will be important if only to gauge overall public feeling. The challenge will be to conduct real consultation without having sessions hijacked by Ford Nation supporters.

Continue reading

Ontario’s 2019 Budget: Transit Effects in Toronto

The Ontario Government introduced its 2019 budget on April 11. The section on transit and transportation begins with the usual statements about the cost of congestion, and the economic benefit of transit and highways. Transit specifics focus on the recent Toronto subway announcement. Metrolinx/GO continues on its expansion path, but with more emphasis on what has been done than what is to come.

The Subway “Upload”

Ontario reiterated its intention to take ownership of the Toronto subway network, but it is now clear that this will be done in two parts. First will come responsibility for system expansion as announced on April 10 with the existing system assets to follow in 2020. This puts the more complex problem off nominally for a year, but that debate is really underway now with negotiations between the City of Toronto, TTC and province.

By separating the upload into two distinctive parts, the Province can begin building subway extensions and new lines immediately while giving proper due diligence to the state of repair of the existing assets and fulfilling its commitments to consultation under the Terms of Reference.

The Province remains steadfastly committed to the full upload of the TTC subway network. [p. 64]

That “due diligence” is the nub of any transfer. Past provincial statements imply that the cost of life cycle maintenance (major repairs and replacement, items found in the TTC’s capital budget) would shift to the province leaving day-to-day costs to the City of Toronto. The problem lies in the inevitable tug-of-war between transit expansion and state of good repair. Provincial Treasurer Vic Fedeli, speaking on CBC’s Metro Morning, claims that the investment in new transit lines more than offsets gas tax revenue promised by the former Liberal government. However, this leaves a major hole in planned funding for system upgrades.

Gas Tax Transfer

Fedeli claimed that the Gas Tax can only be used for specific type of spending, but this is not true. The money today goes partly to subsidize day-to-day operations and partly to capital for state-of-good-repair (SOGR). Across the province, few cities are building rapid transit expansions, and their gas tax allocation goes to operation and maintenance of existing systems. Fedeli, in parliamentary language, is “badly briefed”.

The gas tax transfer from Ontario to Toronto for 2018-2019 will be $185 million, and this was expected to double in stages over the next four years. This increase has been cancelled in the new Ontario budget.

Beginning in 2019, Ontario will gradually increase the municipal share of gas tax funds up to a total of four cents per litre in 2021-22. Based on the averages from the past 10 years, gas tax funding is estimated to be about $642 million in 2021-22. There will not be any increase in the tax that people in Ontario pay on gasoline.

Year                            2018-19 2019-20 2020-21 2021-22

Municipal share (cents/litre)   2.0     2.5     3.0     4.0
Estimated funding (millions)    $321    $401.3  $481.5  $642

Source: Enhanced Gas Tax Program, Ontario Government Backgrounder, January 27, 2017

Note that the dollar funding above is for all of Ontario, not just for Toronto, although it gets the lion’s share due to its size.

The Province will not move forward with the previous government’s proposed changes to the municipal share of gas tax funding. The Province will continue to support municipalities through the existing Gas Tax program and ensure it continues to meet the needs of the people of Ontario in alignment with provincial priorities.

Over the next few months, the government will consult with municipalities to review the program parameters and identify opportunities for improvement. This review will be informed by the goals of responsible planning and a more sustainable government to ensure taxpayer dollars are being spent as effectively as possible. [p. 75]

Toronto allocates almost half, $91.6 million, to the TTC Operating Budget, leaving $93.4 million for capital in 2018-2019.

Planned spending based on federal and provincial gas tax transfers is summarized in the city’s 2019 budget papers. This document details the allocation of federal and provincial transfers planned over 2019-2028 with $1.358 billion broken out by TTC budget line. Note that this is less than the total that would have been expected over ten years because the “out years” of the TTC’c capital plan is constrained by city financing plans. Many projects are “below the line” in the budget, especially in the outer five years, and the rise in gas tax funding could have helped to bring some of these projects to approved, above the line status.

About 70% of planned provincial gas tax spending by Toronto is for assets that are subway related. If Ontario transfers responsibility for all of this to the provincial level, then this would offset the loss of expected gas tax. However, that depends on just what budget lines Ontario chooses to take on. When capital subsidies began under the Davis government, there was something of a shell game between Toronto and Queen’s Park over the classification of expenses because “capital” received at least a 50% subsidy while “operations” only got 16%. This sort of thing will bedevil negotiations between the two governments on funding of the uploaded subway system’s SOGR projects.

The table below summarizes the categories listed in the city’s budget and splits them between subway and surface networks. The breakdown is based on my experience in reviewing TTC budgets. Although some adjustment of percentages might be argued, the overall balance will not change much.

Continue reading

Toronto’s Omnibus Transit Report: Part III

This is the third and final part of my review of the transit reports that will be before Toronto’s Executive Committee on April 9, 2019, and at Council a week later.

In part one, I reviewed the financial issues presented in the reports together with the Scarborough Subway Extension, now known as the Line 2 East Extension (L2EE).

In part two, I turned to SmartTrack, the Relief Line and the Bloor-Yonge station expansion project.

This article reviews the streetcar/LRT projects as presented in the current set of reports.

Relevant documents include:

  • Main report: Toronto’s Transit Expansion Program – Update and Next Steps
  • Attachment 1: A status update on all projects
  • Attachment 3: Waterfront Transit Network – Union Station-Queens Quay Link and East Bayfront Light Rail Transit. [Note: The properties of this attachment were incorrectly set by the authors. Although it really is Attachment 3, it appears on browser tabs as if it were Attachment 2 for the Scarborough Extension.]
  • Attachment 4: Eglinton East LRT
  • Attachment 5: Eglinton West LRT

Much of the LRT network still at some stage of design or construction is a remnant of the Transit City plan announced in 2007. Pieces have have fallen off of that network proposal, notably in Scarborough, but also a few key links that would have knitted the network together allowing sharing of carhouse and maintenance facilities. Confusion about the planning, ownership and funding scheme for parts of the network complicates the situation further.

Although the province has announced that it wishes to take over “the subway”, the boundary is unclear because a previous government decided to take over at least part of the Transit City LRT network, notably the Eglinton/Crosstown and Finch West routes. The Ford government prefers to put as much transit underground as possible, but if Toronto wants to extend an existing route (for example on Eglinton East), the city’s preference will be for surface construction to keep cost within its ability to fund projects.

Continue reading

Premier Doug Plays With Toronto’s Train Set

In the continuing circus which is the Ford Family Transit Plan, the provincial government has advised Toronto and the TTC of its priorities for rapid transit construction. The Province is quite firm that since it will be paying for these lines, it will call the shots.

This information broke in two letters dated March 22 and 26, 2019 from Michael Lindsay, Special Advisor to the Cabinet – Transit Upload, and Shelley Tapp, Deputy Minister of Transportation, together with a report from the Toronto City Manager, Chris Murray, dated March 26.

The Province has four priority projects, although some of the information about them is vague:

  • A three-stop Scarborough Subway Extension [SSE]
  • A Downtown Relief Line [DRL] of indefinite scope
  • The Richmond Hill Extension of the Yonge Subway [YNE]
  • Construction of the Eglinton West Crosstown LRT primarily underground rather than at grade

These are the only projects mentioned in the letters. By implication anything else is off of the table as far as provincial funding is concerned except for whatever the subway “upload” still under discussion might entail. More about that later.

The Province refers to “incongruencies between the province and city/TTC with respect to the design and delivery of priority projects”. Most of this should be no surprise given previous statements both by Doug Ford as a candidate, and rumblings from his supporters.

The March 22 letter arose from a March 8 meeting between Provincial, City and TTC representatives. Two things are clear:

  • The Province was not paying attention to, or chose to ignore, information it received or should have been able to access easily through public channels.
  • The City/TTC should have had some idea of what was coming down the pipe over two weeks ago, but there was no public hint of what was in store even with the subway upload on the Executive Committee and Council agendas. This is a classic case of “who knew what and when”, and a troubling question of whether the direction of provincial plans was withheld from public view for political expediency.

The March 22 letter makes statements that were revised on March 26, and which have provoked considerable comment as this story broke. Most astounding among these was:

Per our meeting of March 8, we were informed that the City’s preliminary cost estimates for both the Relief Line South and the Scarborough Subway Extension have significantly increased to nearly double or greater the figures released publicly.

On March 26, the Province wrote:

We acknowledge, in light of the helpful clarification you provided at our Steering Committee meeting [of March 25], that the city’s/TTC’s revised project cost estimates for the Relief Line South and Scarborough Subway Extension projects represent estimates in anticipation of formal work that will reflect greater specificity in design. We accept that the actual budget figures remain to be determined …

This bizarre pair of statements suggests that either:

  • the Province was not really paying attention in the meeting of March 8 which led to the March 22 letter, or
  • they really were, but that their first statement was guaranteed to blow every transit plan to smithereens if it were not retracted.

On March 26, they do not say they were wrong, merely that they were dealing with preliminary estimates.

That is a strange position considering that the SSE is on the verge of reaching a firm design number and budget to be reported in early April to Toronto Executive Committee and Council. The agenda publication date is April 2, and it is hard to believe that a firm estimate for the SSE does not already exist. As for the DRL South, that is in a more preliminary state, but if anything the numbers already published have been rather high.

The Scarborough Subway Extension

For the SSE, there are two conflicting proposals:

  • City: One stop extension terminating at Scarborough Town Centre
  • Province: Three stop extension “with the same terminus point”.

There is no reference to any potential connection with a Sheppard Subway extension. However, the March 26 letter contains this statement:

… we recognize that the city/TTC and province share the intention for a station to be located at Scarborough Centre. However, under the province’s preferred three-stop extension of Line 2, the project would proceed northward from the station at Scarborough Centre.

Given that the TTC’s alignment for STC station is itself on a north-south axis, it is unclear just what this remark refers to especially if STC is to be the terminus of the provincial project.

As I wrote recently in another article, there is an issue of equipment and storage required to allow the SSE to open with full service to STC. One potential source of “additional” cost could well be that works such as a new Line 2 yard at Kipling plus the rebuilding and/or replacement/expansion of the fleet are now counted as part of the overall project cost. This is precisely the sort of hidden cost I warned the Province would face when they started to understand the full scope of the TTC’s infrastructure requirements.

Whether this is the case remains to be seen, but with the Province taking responsibility for delivery of this project and planning to assume the cost of maintenance and expansion of the existing subway, they (or anyone else looking at funding the SSE) will be facing these costs as “add ons”.

One other concern is that there is no mention of capacity expansion for Line 2 either by way of station expansion at critical junction points nor of fleet expansion to allow more service once the line has Automatic Train Control [ATC].

Crosstown LRT Westward Extension

  • City: A substantially at-grade extension from Mount Dennis westward, although there are references from recent public participation to the possibility of some grade separations.
  • Province: A “significant portion of this extension” would be underground, an option “which has not been considered in a material way” as part of the current design.

The March 26 letter revised the characterization of the City’s work to date:

… we recognize that tunnelling options for the project have been considered as part of previous assessment, but that these options are not preferred by the city/TTC.

Again, one must wonder just what the province was doing at the March 8 meeting to have so botched their understanding of the work to date. The work already done is documented on the project’s website. I cannot help wondering how much the original provincial position was a product of political posturing by Etobicoke politicians. Such a gaffe does no credit to Michael Lindsay and his team.

It is no secret that there is strong political pressure from politicians in Etobicoke for the LRT line to be buried as much as possible, and it is no surprise that the Province would embrace this.

Missing, however, is any reference to the portion of the line west of the Toronto-Mississauga boundary and specifically the link into Pearson Airport. Will this be part of the Provincial project?

Relief Line South

The text in this section has provoked speculation in various fora, both the mainstream and social media.

Planning work undertaken by the TTC contemplates utilizing existing technology … the province would propose … a truly unique transit artery spanning the city that is not beholden to the requirements of the technologically-outdated Line 2.

On March 26, the Province changed their tune, a bit:

… we recognize that the city/TTC is contemplating a different technology for the project than that currently deployed for Line 2.

It is hilarious to see Line 2 described as “technologically outdated” when it is this line that the Province plans to extend to STC. At the risk of peering into a murky crystal ball, I will venture an interpretation of what is being said here.

The “outdated technology” is the current fleet of T1 trains which do not have ATC installed. Moreover, TTC plans would not see ATC operation on Line 2 for at least a decade unless the existing fleet is retrofitted.

The TTC has always intended that the DRL would use modern technology, and again I cannot help wonder whether the Provincial reps were paying attention at their March 8 meeting with the TTC. This information is not difficult to obtain. They could even read my blog if they don’t want to spend time wading through official documents, but possibly it is simpler just to slag the municipal agency in a time-honoured Queen’s Park tradition.

The Province wants the DRL to be completely free-standing in that it would not depend on Line 2 and the existing yard at Greenwood, but would be built completely separate from the existing subway network. Moreover, “alternate delivery methods” would be used for this project, a clear indication that this would be a privately designed, built, financed and operated line much as the Crosstown was intended to be before a deal was worked out to let the TTC drive the trains, at least for a time.

The reference to a “transit artery spanning the city” implies something much more extensive than the DRL South from Pape to Osgoode Station, but what exactly this might be is anyone’s guess. It could be a truly different technology, something like Skytrain in Vancouver (which itself has two separate technologies). The construction technique could be changed from the proposed double bore to a single bore line, especially if the vehicle cross-section were smaller. The alignment and station locations could be changed. Any of these and more is possible, but we don’t know. As this is to be an AFP project, a blanket of confidentiality hides everything.

Yonge Northern Extension to Richmond Hill

The primary provincial interest here is in getting the line built as quickly as possible with planning and design work for the YNE and DRL to progress in parallel so that “the in-service date for the extension is fast tracked to the greatest extent possible”.

There is no mention of capacity issues on the existing Line 1 including the need for more trains, nor of the expansion needed at key stations to handle larger volumes of passengers.

Jumping the Gun on Uploading?

The March 26 letter clearly attempts to correct misapprehensions from the March 22 missive. These were presumably communicated privately at or before the March 25 meeting.

The Province is supposed to be engaged, in good faith, in discussions with the City and TTC about how or if it would take control of subway assets and what that control, and associated responsibility for ongoing costs, would entail. One might easily read the March 22 letter as showing that the Province has made up their mind, and all that remains is to “drop the other shoe” with respect to everything beyond the “priority projects”.

On March 26, the Province talks at length about “our priority transit expansion projects”. This has always been the political red meat in that new lines translate into votes, or so the Ford faction hopes. The myriad of details in looking after the existing system do not lend themselves to coverage in a two-page letter, let alone simplistic posturings by politicians eager to show the wisdom of their plans.

The March 26 letter does not discuss any aspect of the existing system including asset transfers or financial commitments. That’s not to say the Province has not considered this, but no details are public yet. That will be a critical issue for Toronto because the degree to which the Province actually plans to pay for the existing subway system will affect future City budgets.

There is a myth that fare revenues will cover off the City’s share, but we don’t actually know which aspects of subway “maintenance” will remain in the City/TTC hands. There are two separate budgets, capital and operating, but there has been no statement of how these will be divided. Although there could be a one-time payment for the capital value of the system, this begs two questions. First, who benefits from appreciation of property value as subway lands are repurposed/redeveloped. Second, what does the City do when the nest egg from selling the subway, assuming they even have anything left over after discharging subway-related debt, is used up.

Another issue to be decided is how the split in ownership and financial responsibility will affect gas tax funding that now flows from both the Provincial and Federal governments, over $300 million in 2018. How much of this will Toronto lose, and what will be offset by costs the Province will assume?

Further System Expansion

The correspondence from the Province is silent on many projects including:

  • Eglinton East LRT
  • Waterfront LRT
  • Finch LRT extension to Pearson Airport
  • Sheppard Subway extension to STC
  • SmartTrack and GO Transit Service Expansion

Eglinton East and Waterfront would, assuming a City/Province divide on surface/subway projects, lie clearly in the City’s court, while any extension of Line 4 Sheppard would be a Provincial project. Oddly, Eglinton East would be a “City” extension of a provincially-owned line, the Crosstown.

The Finch LRT occupies an odd place as a surface line that for historical reasons is being delivered by the Province. Moreover, an airport extension would lie partly outside of Toronto. Who knows what the fate of this will be.

To Be Continued …

The provincial letters have dropped into the Council meeting planned for March 27, and we can expect a great deal of debate, if not clarity, in coming days.

At a minimum, the Province owes Toronto a better explanation of just what they intend with their view of projects. This information should not be “confidential” because we are simply asking “what exactly do you want to do”. This is particularly critical for the Downtown Relief Line whatever the “unique transit artery” it might become.

SmartTrack and GO are important components because they will add to the “local” network within Toronto and could be part of the “relief” efforts that will span multiple projects. SmartTrack is a City project, and we are about to learn just how much it will cost Toronto to put a handful of John Tory branded stations on GO’s Kitchener and Stouffville corridors. SmartTrack also takes us into the tangled net of fare “integration” and the degree to which Toronto riders will pay more so that riders from beyond the City can have cheaper fares.

Finally, there is the question of operating costs. The Ford mythology includes a claim that subways break even, and in the uploading schemes mooted to date, there is an assumption that Toronto will still operate the subway network and pay for its day-to-day costs out of farebox revenue. Even if that were true today, much of the proposed network expansion will not gain revenue to cover its operating cost, and Toronto will face increased outlay. There is still no proposal, let alone an agreement, about the operating costs of the Crosstown and Finch LRT lines from which we might guess at how the combination of three new lines/extensions will affect the subsidy call against Toronto’s tax base.

With clear errors in the March 22 letter, the Province showed that it cannot be trusted to propose policy based on fair and accurate characterization of Toronto’s transit system. One would hope that a “Special Advisor” backed by the boffins at Metrolinx and the Ministry of Transportation might be able to avoid screw-ups. When the Province puts forward a scheme to take over part of the TTC, their rationale should be based on transparent and accurate information. Alas, recent experience in other portfolios shows that this will not happen, and dogma will trump common sense.