TTC 2019 Fleet and Capacity Plans Part III: The TTC Responds

In the first two installments of this series, I reviewed plans for the subway system and the surface bus and streetcar networks. These reviews triggered many questions which I sent off to the TTC.

We have all been a little pre-occupied with other matters recently, and it took a while for the TTC to reply. Thanks to Stuart Green and the staff at TTC who pulled this together.

Each question is formatted with two or three sections:

  • My original question
  • The TTC’s reply
  • My observations on the reply, if any

The text has been lightly edited for formatting purposes.

Apologies to readers seeing this post with no background. It is based on information in two previous articles as well as a general review of the TTC’s Capital Budget detailed briefing books, known as the “Blue Books”. This article covers a variety of issues some of more interest to general readers than others. If you need clarification, please leave a comment.

Continue reading

61 Questions And Counting (Updated)

Update: Council’s action on this report has been added at the end of the article.

As I write this article on April 17, 2019, it has been three weeks since Toronto learned that Premier Doug Ford’s love for rewriting transit plans would turn Toronto’s future upside down. Ford’s special advisor Michael Lindsay wrote to Toronto’s City Manager Chris Murray first on March 22, and then in an attempt to paper over obvious problems with the provincial position, on March 25.

Just over two weeks later, Ford announced his transit plan for Toronto, and this was followed by the 2019 provincial budget.

A hallmark of the process has been a distinct lack of details about design issues, funding and the future responsibility for an “uploaded” subway system. In parallel with these events, city and TTC staff have met from time to time with Lindsay and his team to flesh out details and to explain to provincial planners the scope of TTC’s needs, the complex planning and considerable financial resources required just to keep the trains running.

On April 9, Toronto’s Executive Committee directed Murray to report directly to Council on the effect of provincial announcements, but his report did not arrive on Councillors’ desks until early afternoon April 16 with the Council meeting already underway.

The report reveals a gaping hole in the city’s knowledge of provincial plans with a “preliminary” list of 61 technical questions for the province. So much for the idea that discussions to date have yielded much information. Click on any image below to open this as a gallery.

 

To these I would add a critical factor that always affects provincial projects: cost inflation. It is rare to see a provincial project with an “as spent” estimate of costs. Instead, an estimate is quoted for some base year (often omitted from announcements) with a possible, although not ironclad, “commitment” to pay actual costs as the work progresses. This puts Ontario politicians of all parties in the enviable position of promising something based on a low, current or even past-year dollar estimate, while insulating themselves from overruns which can be dismissed as “inflation”. The City of Toronto, by contrast, must quote projects including inflation because it is the actual spending that must be financed, not a hypothetical, years out of date estimate from the project approval stage.

That problem is particularly knotty when governments will change, and “commitments” can evaporate at the whim of a new Premier. If the city is expected to help pay for these projects, will the demand on their funds be capped (as often happens when the federal or provincial governments fund municipal projects), or will the city face an open-ended demand for its share with no control over project spending?

Unlike the city, the province has many ways to compel its “partner” to pay up by the simple expedient of clawing back contributions to other programs, or by making support of one project be a pre-requisite for funding many others. Presto was forced on Toronto by the threat to withdraw provincial funding for other transit programs if the city did not comply. Resistance was and is futile.

How widely will answers to these questions be known? The province imposed a gag order on discussions with the city claiming that information about the subway plans and upload were “confidential”. Even if answers are provided at the staff level, there is no guarantee the public will ever know the details.

At Council on April 16, the City Manager advised that there would be a technical briefing by the province on the “Ontario Line” (the rebranded Downtown Relief Line) within the next week. That may check some questions off of the list, or simply raise a whole new batch of issues depending on the quality of paper and crayons used so far in producing the provincial plan. It is simply not credible that there is a fully worked-out plan with design taken to the level normally expected of major projects, and if one does exist, how has it been produced in secret entirely without consultation? The province claims it wants to be “transparent”, but to date they are far away from that principle.

The Question of Throwaway Costs

Toronto has already spent close to $200 million on design work, primarily for the Line 2 East Extension (formerly known as the Scarborough Subway Extension, or SSE). The province claims that much of this work will be recycled into their revised design, and this was echoed by TTC management at a media briefing. However, with changes in both alignment, scope and technology looming, it is hard to believe that this work will all be directly applicable to the province’s schemes.

The city plans to continue work on these lines at an ongoing cost of $11-14 million per month, but will concentrate on elements that are likely to be required for either the city’s original plan or for the provincial version. The need to reconcile plans has been clear for some time:

In order to minimize throw-away costs associated with the Line 2 East Extension and the Relief Line South, the City and TTC will be seeking the Province’s support to undertake an expedited assessment of the implications of a change at this stage in the project lifecycle. The City and TTC have been requesting the Province to provide further details on their proposals since last year, including more recently through ongoing correspondence and meetings under the Terms of Reference for the Realignment of Transit Responsibilities. [p 4]

The city/TTC may have asked “since last year”, but Queen’s Park chose not to answer.

The city would like to be reimbursed for monies spent, but this is complicated by the fact that some of that design was funded by others.

Provincial Gas Tax

As an example of the mechanisms available to the province to ensure city co-operation, the Ford government will not proceed with the planned doubling of gas tax transfers to municipalities. This has an immediate effect of removing $585 million in allocated funding in the next decade from projects in the TTC’s capital program, and a further $515 million from potential projects in the 15 year Capital Investment Plan.

At issue for Toronto, as flagged in the questions above, is the degree to which this lost revenue will be offset by the province taking responsibility for capital maintenance in the upload process. Over half of the planned and potential capital projects relate to existing subway infrastructure, but it is not clear whether the province understands the level of spending they must undertake to support their ownership of the subway lines.

Public Transit Infrastructure Fund (PTIF)

City management recommends that Council commit much of the $4.897 billion in pending federal infrastructure subsidies from PTIF phase 2 to provincial projects:

  • $0.660 billion for the Province’s proposed three-stop Line 2 East Extension project instead of the one-stop Line 2 East Extension project; and
  • $3.151 billion for the Province’s proposed ‘Ontario Line’ as described in the 2019 Ontario Budget, instead of the Relief Line South. [p 3]

This is subject to an assessment of just what is supposed to happen both with proposed new rapid transit lines and the existing system in the provincial scheme.

Mayor Tory has proposed an amendment to the report’s recommendations to clarify the trigger for the city’s agreeing to allocation of its PTIF funds to the provincial plan, so that “endorsing” the plan is changed to “consider endorsing”. Reports would come back from the City Manager to Council on the budget changes and uploading process for approval that could lead to the city releasing its PTIF funds to the province.

The Status of SmartTrack

Part of the city’s PTIF funding, $585 million, is earmarked for the six new stations to be built on the Weston, Lake Shore East and Stouffville corridors. The future of these stations is cloudy for various reasons:

  • The Finch East station on the Stouffville corridor is in a residential neighbourhood where there is considerable opposition to its establishment, and grade separation, let alone a station structure, will be quite intrusive.
  • The Lawrence East station on the Stouffville corridor would be of dubious value if the L2EE includes a station at McCowan and Lawrence. Indeed, that station was removed from the city plans specifically to avoid drawing demand away from SmartTrack.
  • There is no plan for a TTC level fare on GO Transit/SmartTrack, and the discount now offered is available only to riders who pay single fares (the equivalent of tokens) via Presto, not to riders who have monthly passes.
  • Provincial plans for service at SmartTrack stations is unclear. Originally, and as still claimed in city reports, SmartTrack stations would see 6-10 trains/hour. However, in February 2018, Metrolinx announced a new service design for its GO expansion program using a mix of local and express trains. This would reduce the local stops, including most SmartTrack locations, to 3 or 4 trains/hour. I sought clarification of the conflict between the two plans from Metrolinx most recently on April 3, 2019 and they are still “working on my request” two weeks later.

Some of the SmartTrack stations will be very costly because of the constrained space on corridors where they will be built. The impetus for Council to spend on stations would be substantially reduced if train service will be infrequent, and the cost to ride will be much higher than simply transferring to and from TTC routes. Both the Mayor and the province owe Council an explanation of just what they would be buying into, although that could be difficult as cancelling or scaling back the SmartTrack stations project would eliminate the last vestige of John Tory’s signature transit policy.

The Line 2 East Extension

The City Manager reports that the alignment of the provincial version of the three-stop subway is not yet confirmed, nor are the location of planned stations. Shifting the terminus north to Sheppard and McCowan and possibly shifting the station at Scarborough Town Centre will completely invalidate the existing design work for STC. This is an example of potential throwaway work costs the city faces.

The design at Sheppard/McCowan will depend on whether the intent is to through-route service from Line 2 onto Line 4, or to provide an interchange station where both lines would terminate. The L2EE would have to operate as a terminal station for a time, in any event, because provincial plans call for the Line 4 extension to follow the L2EE’s completion.

An amended Transit Project Assessment (TPAP) will be needed for the L2EE, and this cannot even begin without more details of the proposed design.

The Ontario Line

Although this line is expected to follow the already approved route of the Relief Line between Pape and Osgoode Stations, the map in the provincial budget is vague about the stations showing different names and possibly a different alignment. This could be a case of bad map-making, or it could represent a real change from city/TTC plans to the provincial version.

A TPAP will definitely be required for the extended portions of the line west of Osgoode and north of Pape. A pending technical briefing may answer some issues raised by the city/TTC including details of just where the line would go and what technology will be used, but the degree of secrecy to date on this proposal does not bode well for a fully worked-out plan.

Council Decision

The item was approved at Council with several amendments whose effects overall were:

  • The City Manager and TTC CEO are to work with the province:
    • to determine the effects of the provincial announcement,
    • to negotiate principles for cost sharing including ongoing maintenance and funding arrangements, and
    • to seek replacement of funding that had been anticipated through increased gas tax transfers to the city.
  • The city will consider dedication of its PTIF funding for the Line 2 extension and for the Relief Line to Ontario’s projects subject to this review.
  • The city requests “confirmation that the provincial transit plans will not result in an unreasonable delay” to various transit projects including the Relief line, the one-stop L2EE, SmartTrack Stations, Eglinton and Waterfront LRT lines.
  • Discussions with the province should also include:
    • those lines that were not in the provincial announcement,
    • compensation for sunk design costs,
    • phasing options to bring priority segments of the Relief Line in-service as early as possible,
    • city policy objectives such as development at stations, and
    • public participation on the provincial plans.
  • The City Manager is to investigate the acceleration of preliminary design and engineering on the Waterfront and Eglinton East LRT using city monies saved from costs assumed by the province.
  • The City Manager is to report back to Council at its June 2019 meeting.

Former TTC Chair Mike Colle moved:

That City Council direct that, if there are any Provincial transit costs passed on to the City of Toronto as a result of the 17.3 billion dollar gap in the Province’s transit expansion plans, these costs should be itemized on any future property tax bills as “The Provincial Transit Plan Tax Levy”.

This was passed by a margin of 18 to 8 with Mayor Tory in support.

Planning for Line 1 (YUS) Growth

At its meeting of April 11, the TTC Board considered several reports that bear on the question of future demand and capacity on Line 1 Yonge-University-Spadina.

Also discussed were the planned subway closures in 2019 which I covered in a previous article, and a contract amendment to the ATC signalling consultant to cover extending the implementation period for the Line 1 project.

This segment of the meeting contained far more technical material than we usually see at the TTC Board, but it was long overdue, especially with a large contingent of new Board members in 2019. Too many Board debates touch only the surface of issues without an appreciation for what is “under the covers” within this large organization, the largest single entity within the City of Toronto and its agencies.

Who Watches the Watchers?

A troubling aspect surfaced regarding the status of the Automatic Train Control (ATC) project and the question of why its delivery date will be so much later than originally planned. Some of this gets murky because of discussions earlier in the day in a private session, but there were two clear outcomes:

  • There is a clear implication that information about the status of the ATC project was withheld from the Board who have only recently come into knowledge of what is actually happening.
  • The Board wants an oversight/audit function to ensure that what management tells the Board about projects is actually credible.

On the second point, Commissioner Ron Lalonde moved, and the Board approved.

That the CEO of the TTC implement a function independent of the project management that would review major project implementation and report quarterly to the CEO and to the TTC Board on the status of major projects and on their compliance with TTC project management policies.

This is an astounding motion in that it effectively says nobody in management can be trusted to do their jobs and report accurately to the Board. One might reasonably ask why the CEO himself is not subject to such oversight, considering that the situation from which this motion arises clearly was the product of the previous CEO’s term. That “Transit System of the Year” award would be rather tarnished if the organization were provably misrepresenting its accomplishments.

The complaint, as raised by Vice Chair Alan Heisey, was that the Board had been told repeatedly that the ATC project was on time and on budget, only to find that it was not. He cited a November 2017 status chart from the CEO’s Report showing “green” status for the project. In fact, this status continued into the March 2018 report which was the last one published in that format. The set from November 2016 to March 2018 appears below (click on any item to open as a gallery).

Throughout the six versions of this dashboard, the ATC project remains at an estimated cost of $563 million and a completion date of Q4 2019. Only the to-date expenditure and percent completion rise (from $266m to $381m, 47% to 68%), albeit with an anomalous lack of progress between November 2016 and March 2017 which show the same values. Note that the percentages are of spending versus final cost and they do not necessarily reflect the proportion of the work that is finished. For example, as I write this, only 40% of Line 1 is under ATC control (Vaughan to Dupont) with a further extension south (to St. Patrick) pending in May.

Reports on the status of major projects vanished from the CEO’s Report after March 2018, and these were eventually replaced as part of a quarterly report from the Chief Financial Officer. The first of these reports, in January 2019, flagged a schedule and budget problem with the ATC project.

Schedule reassessment: An operational review concluded that the required closures for Phase 3, the significantly longest continuous phase, were overly disruptive to customers. The multiple closures required would have shut down all subway service from St. Clair to St. Clair West stations. To mitigate this impact on our customers, a revised plan divides the area into three sub-Phases 3A, 3B and 3C. The project team is reviewing the schedule with the contractor to develop a mitigation plan.

For operational reasons it was necessary to advance Phase 6 (Wilson Yard) and implement it prior to both Phases 1 and 3. This Phase was extremely complex, requiring it be divided into 3 manageable sub-Phases which had schedule impact. These changes will delay the project scheduled completion date to 2021. [pp 16-17]

The idea of subdividing phase 3 was already being discussed for exactly the reasons stated above before 2018, and this was hardly news. Other extensions to the completion date arise from timing on competing projects (about which more later in this article). The need to reschedule Phase 6 was obvious from the moment the TYSSE to Vaughan opened and operations at Wilson Yard became a choke point on loading and unloading service from the line.

By the April CFO’s report, there was a further source of delay:

An operational review concluded the implementation of Automatic Train Protection (ATP) on maintenance workcars and Line 4 TR trains is required for efficient travel speeds in ATC areas to work zones and maintenance facilities.

The project team has reviewed the impact of these changes and performed a schedule reassessment. The revised project in-service completion date is 2022. [pp 18-19]

A consultant’s review of the ATC project by Transit Systems Engineering found that the ATC project itself was well-run, but that a combination of focus on getting the line ready for TYSSE opening in late 2017 together with a failure to fully appreciate other works that ATC and the planned capacity increase would trigger push out the completion date for the project. TSE did not criticize management of the ATC project itself, and indeed recommended that this team remain intact because of their knowledge and experience. It is ironic that a report dated January 13, 2019 makes this recommendation a month after the former ATC Project Director left the TTC to join Andy Byford in New York City.

The TSE report states:

… the installation of the ATC system would appear to be on-schedule and on-budget to meet the revised delivery date of Q3 2021 at an overall cost of $663M. [p 6]

This is different from the 2022 schedule now presented to the Board, and the changes noted in the April CFO’s report must have been “discovered” after the TSE review. I put that in quotation marks because a project to make the maintenance fleet ATC-compatible already existed in the 2017 Capital Budget, and the project remains in the 2019 version.

On the subject of keeping the Board informed, I really cannot avoid mentioning the management decision taken during the election interregnum in 2018 to rebuild rather than replace the T1 trains now used on Line 2 Bloor-Danforth. This has pervasive effects on other project schedules including:

  • delay of ATC implementation on Line 2 and the service improvements this could bring,
  • the future of Greenwood Yard and its availability for the Relief Line,
  • the timing of Kipling Yard (the Obico property) and
  • the choice of signalling on the Scarborough extension.

None of this was brought to the Board’s attention, and it was “approved” as one of many items buried within the Capital Budget with no explicit analysis or “heads up” for the Board.

Continue reading

TTC Board Meeting April 11, 2019

The TTC Board met on April 11 with a full agenda. Among the items discussed were:

  • The joint City/TTC “omnibus” transit report and the implications of the provincial intent to “upload” the subway system
  • Public Deputations at Board Meetings
  • Presto limited use tickets and the TTC/Presto contract generally
  • The Junction Area Study and proposed route changes
  • Subway Closures for 2019

The Board also discussed Line 1 (YUS) Capacity Requirements, State of Good Repair and Automatic Train Control. This is a complex enough issue to warrant an article in its own right, and I wil publish that separately.

Results of the King Street Pilot

The King Street Pilot report that was presented to Toronto’s Executive Committee on April 9 came before the TTC Board on April 11. There was a short discussion of the possibility of extension of the project further west. This review will be rolled into the surface transit network plan to come to the board in December 2019.

One item that may further complicate the taxi exemption for King Street was a proposal that Wheel Trans contracted vehicles be allowed to operate just like a transit vehicle when carrying Wheel Trans clients. This will come to Council when they debate the issue at their meeting of April 16.

The Board endorsed the report’s recommendations.

In future articles, I will update information about travel times, headways and line capacity on King street with data to the end of March 2019.

Continue reading

Ontario’s 2019 Budget: Transit Effects in Toronto

The Ontario Government introduced its 2019 budget on April 11. The section on transit and transportation begins with the usual statements about the cost of congestion, and the economic benefit of transit and highways. Transit specifics focus on the recent Toronto subway announcement. Metrolinx/GO continues on its expansion path, but with more emphasis on what has been done than what is to come.

The Subway “Upload”

Ontario reiterated its intention to take ownership of the Toronto subway network, but it is now clear that this will be done in two parts. First will come responsibility for system expansion as announced on April 10 with the existing system assets to follow in 2020. This puts the more complex problem off nominally for a year, but that debate is really underway now with negotiations between the City of Toronto, TTC and province.

By separating the upload into two distinctive parts, the Province can begin building subway extensions and new lines immediately while giving proper due diligence to the state of repair of the existing assets and fulfilling its commitments to consultation under the Terms of Reference.

The Province remains steadfastly committed to the full upload of the TTC subway network. [p. 64]

That “due diligence” is the nub of any transfer. Past provincial statements imply that the cost of life cycle maintenance (major repairs and replacement, items found in the TTC’s capital budget) would shift to the province leaving day-to-day costs to the City of Toronto. The problem lies in the inevitable tug-of-war between transit expansion and state of good repair. Provincial Treasurer Vic Fedeli, speaking on CBC’s Metro Morning, claims that the investment in new transit lines more than offsets gas tax revenue promised by the former Liberal government. However, this leaves a major hole in planned funding for system upgrades.

Gas Tax Transfer

Fedeli claimed that the Gas Tax can only be used for specific type of spending, but this is not true. The money today goes partly to subsidize day-to-day operations and partly to capital for state-of-good-repair (SOGR). Across the province, few cities are building rapid transit expansions, and their gas tax allocation goes to operation and maintenance of existing systems. Fedeli, in parliamentary language, is “badly briefed”.

The gas tax transfer from Ontario to Toronto for 2018-2019 will be $185 million, and this was expected to double in stages over the next four years. This increase has been cancelled in the new Ontario budget.

Beginning in 2019, Ontario will gradually increase the municipal share of gas tax funds up to a total of four cents per litre in 2021-22. Based on the averages from the past 10 years, gas tax funding is estimated to be about $642 million in 2021-22. There will not be any increase in the tax that people in Ontario pay on gasoline.

Year                            2018-19 2019-20 2020-21 2021-22

Municipal share (cents/litre)   2.0     2.5     3.0     4.0
Estimated funding (millions)    $321    $401.3  $481.5  $642

Source: Enhanced Gas Tax Program, Ontario Government Backgrounder, January 27, 2017

Note that the dollar funding above is for all of Ontario, not just for Toronto, although it gets the lion’s share due to its size.

The Province will not move forward with the previous government’s proposed changes to the municipal share of gas tax funding. The Province will continue to support municipalities through the existing Gas Tax program and ensure it continues to meet the needs of the people of Ontario in alignment with provincial priorities.

Over the next few months, the government will consult with municipalities to review the program parameters and identify opportunities for improvement. This review will be informed by the goals of responsible planning and a more sustainable government to ensure taxpayer dollars are being spent as effectively as possible. [p. 75]

Toronto allocates almost half, $91.6 million, to the TTC Operating Budget, leaving $93.4 million for capital in 2018-2019.

Planned spending based on federal and provincial gas tax transfers is summarized in the city’s 2019 budget papers. This document details the allocation of federal and provincial transfers planned over 2019-2028 with $1.358 billion broken out by TTC budget line. Note that this is less than the total that would have been expected over ten years because the “out years” of the TTC’c capital plan is constrained by city financing plans. Many projects are “below the line” in the budget, especially in the outer five years, and the rise in gas tax funding could have helped to bring some of these projects to approved, above the line status.

About 70% of planned provincial gas tax spending by Toronto is for assets that are subway related. If Ontario transfers responsibility for all of this to the provincial level, then this would offset the loss of expected gas tax. However, that depends on just what budget lines Ontario chooses to take on. When capital subsidies began under the Davis government, there was something of a shell game between Toronto and Queen’s Park over the classification of expenses because “capital” received at least a 50% subsidy while “operations” only got 16%. This sort of thing will bedevil negotiations between the two governments on funding of the uploaded subway system’s SOGR projects.

The table below summarizes the categories listed in the city’s budget and splits them between subway and surface networks. The breakdown is based on my experience in reviewing TTC budgets. Although some adjustment of percentages might be argued, the overall balance will not change much.

Continue reading

Ontario Announces Toronto Subway Plan

On April 10, 2019, Premier Doug Ford announced his government’s intentions to expand transit in Toronto. The plan includes:

  • The “Ontario Line”, a rebranded and extended version of the Relief Line, will run from Don Mills and Eglinton to Ontario Place.
  • The Yonge North Extension from Finch Station to Richmond Hill Centre
  • The three-stop version of the Scarborough Subway Extension from Kennedy Station to Sheppard with stops at Lawrence East and Scarborough Town Centre
  • Extension of the Sheppard Subway east from Don Mills Station to connect with the SSE at McCowan and Sheppard
  • Extension of the Eglinton Crosstown west from Mount Dennis to Pearson Airport

Continue reading

Toronto’s Omnibus Transit Report: Part II

On April 9, Toronto’s Executive Committee will consider a massive set of reports on the many transit projects at various stages of design and construction in Toronto.

In Part I of this series, I reviewed the financing scheme for four major projects as well as details of the Scarborough Subway Extension, aka the Line 2 East Extension. In this article, I will review the Relief Line, SmartTrack and the Bloor-Yonge Station Expansion project.

The reports applicable to this article are:

  • Main Report: Toronto’s Transit Expansion Program – Update and Next Steps
  • Attachment 1: A status update on all projects

There are related reports about signalling and capacity expansion of Line 1 Yonge-University-Spadina in the TTC Board’s agenda for their April 11 meeting. I will deal with these in a separate article.

After decades in which the focus of transit planning looked outward to the 905 beyond the bounds of Toronto, there is now a political realization that capacity into the core is a major issue for the region’s economy. Politicians and planners may show optimistic studies of suburban centres and growth, but the development industry, a bastion of free enterprise thinking, persists in building downtown because that’s where they can sell at the greatest profit.

The Relief Line, SmartTrack, Automatic Train Control, subway station expansions and even surface transit projects like the King Street Pilot all attempt to address the demand for travel to and through the core area. Looking beyond the city boundaries, there are subway and GO Transit extensions and service improvements. Some of these schemes are more successful than others, and some have very long lead times before any benefit will be seen. Political attention has shifted from the fights over which one project will be built each decade to the recognition that many projects must occur in parallel so that capacity can catch up with latent and growing demand.

Continue reading

Toronto’s Omnibus Transit Report: Part I

Planning for many transit projects in Toronto has been underway for years, but the public face of this work took a long holiday in 2018 thanks to elections at both the provincial and municipal levels.

In coming weeks, Toronto’s Executive Committee and then Council will consider an omnibus report that provides updates on many transit projects and recommends a path forward.

Today, that path is murky given uncertainty about provincial intentions and the degree to which consultation between the city and province is actually in good faith. Premier Ford’s approach on other portfolios, coupled with the breezy confidence of his Transportation Minister (seen recently on TVO’s The Agenda), do not bode well. With the arrival of Doug Ford at Queen’s Park, the provincial goal on transit is more about settling old scores with Toronto Council and proving that Ford’s transit vision is correct than it is about good planning. Recent correspondence between the province’s special advisor on a proposed subway takeover revealed just how much the province does not know, or chooses to ignore. This was not a good start and the province wounded its credibility on basic technical points, never mind the political context.

But for a moment, let us consider Toronto’s future from the point of view of what the city hopes to do, if only they have the control and the money to pull this off.

The report is long, and to break this article into digestible pieces, I will focus on groups of issues. This article covers overall financing of the transit expansion project and specific details for the Scarborough Subway Extension (SSE), now known as the Line 2 East Extension (L2EE). I will turn to other components of the plan in further articles.

Many reports are available on the City’s website (scroll down to the end for all of the links). The principal reports are:

Financing Transit Expansion

The most challenging part of any transit project, let alone a complex program, is to obtain funding from governments whose priorities do not necessarily align and which may talk at least as much about the sanctity of “taxpayer dollars” as they do about investment in public infrastructure.

In a media briefing, city staff were quite clear that no project can proceed to the stage of contract tendering and awards unless the contribution agreements underpinning a project are in place.

At the federal level, the primary funding source will be the Public Transit Infrastructure Fund (PTIF) which has two phases. An initial phase was time-limited, and was used in Toronto mainly to fund the purchase of hundreds of new buses. The second, longer-lived phase of PTIF will be used for transit construction projects. There is some urgency to nail down PTIF contributions given the fall 2019 election and uncertainty about this program under a new government.

Note that this entire discussion relates only to projects that would be funded in part through PTIF, not to many others such as the Eglinton LRT extensions or the Waterfront LRT.

Federal funding of $4.897 billion will be allocated by the city, assuming government approval, as below [Main Report, p. 2]:

  • $0.660 billion for the Line 2 East Extension project
  • $0.585 billion for the SmartTrack Stations Program
  • $3.151 billion for the Relief Line South
  • $0.500 billion for the Bloor-Yonge Capacity Improvement project

Negotiations with Ontario are ongoing, and the status of projects and associated $4.04 billion in provincial funding is unclear. This could be clarified in the provincial budget to be announced on April 11, 2019. Provincial interest in and plans for the Scarborough extension and the Relief Line will affect both of these projects.

City funding comes from a variety of sources:

  • Development charges
  • The Scarborough Subway levy
  • The City Building Fund levy
  • Interest on accumulated reserves from the levies

Financial projections are also affected by factors that have changed since projections made in past years:

  • Higher growth rates in development
  • Lower interest rates

PTIF2 has an assumed split of 40-33-27% for the federal, provincial and municipal governments respectively. This creates a breakdown of responsibilities as shown below.

The provincial share is supposed to be “new funding” and the amount here does not include prior commitments to Scarborough transit which originally were for the proposed LRT line, later for a subway. Exactly how much Ontario will contribute remains to be seen given discussions about ownership and the scope of the Scarborough subway project. I will return to this in more detail later.

Within the city share, $2.42 billion is unfunded (no revenue sources have been committed to fund/finance the expense), and only $885 million of the SmartTrack Stations Program has city funding. The report recommends that the city’s CFO and Treasurer report prior to the 2020 budget process on strategies for addressing the shortfall.

The project cost estimates for these are broken down below. In the chart, the acronyms are:

  • LTD: Life To Date
  • PDE: Preliminary Design & Engineering

The possible funding arrangements vary for each project, and these are complicated both by past history and by the uncertainty of early “class 5” estimates. A tentative breakdown is shown below, but this must be taken with a grain (or more) of salt due to technical and political uncertainties. For example, the assumed provincial contribution to the Line 2 Scarborough project is based on inflation of a commitment made in 2010 dollars where the city and province do not agree on the appropriate inflation factor.

Two separate numbers have been used for the Relief Line cost estimate: $6.8 billion in Table 2 above, and $7.2 billion in Table 3 below. In the media briefing, TTC staff explained that the change was due to an alignment revision (Carlaw vs Pape) and changes in construction techniques (mining vs cut-and-cover) at some locations. That may be so, but to have two different numbers for the same project so close together within a report makes one wonder about the care taken in other aspects. On top of that is almost $2 billion as a “provision” for the Relief Line to guard against potential cost increase as the estimate is refined from class 5 to class 3.

This sort of uncertainty is not unusual, but the constant variation in quoted “estimates” makes for no end of problems. The converse is seen with the Scarborough project where the “estimate” for the subway’s cost has remained fixed since 2014 despite major changes in project scope.

The report explains the difference between initial class 5 estimates and the class 3 estimates to be used in setting project budgets:

As a project moves through the three phases, project definition becomes more refined and the information used as the basis for developing a cost estimate is more mature.

  • A Class 5 cost estimate is typical when starting the initiation and development phase, where the project is conceptual (0-2% design level). This an order of magnitude estimate to inform the decision of whether or not to continue to study an option.
  • A Class 3 cost estimate is based on PDE work (10-40% design level), and is the estimate class recommended when establishing a project budget for procurement and construction. A Class 3 estimate should be used to inform full funding commitment decisions. [p. 16]

Note that the term “order of magnitude” has considerable leeway, and a change from one order to the next is a factor of 10. Saying that costs “A” and “B” are in “the same order of magnitude” gives huge scope which on projects of this nature is measured in billions of dollars. Too much past debate has assumed that minor swings in estimates might occur as designs are refined, but this is more wishful thinking and the political hope that a project will not get out of hand even before shovels hit the ground.

Overall Project Status

The map below shows the location of all projects in the transit network plan.

Projects will advance from stage to stage on their own timetables which are summarized in the chart below.

Line 2 East Extension (aka Scarborough Subway Extension)

This section reviews the status of the Scarborough extension as it is presented in the city reports. Obviously this is subject to major change given provincial announcements of support for taking ownership of the extension and for building a three-stop subway.

Continue reading

Premier Doug Plays With Toronto’s Train Set

In the continuing circus which is the Ford Family Transit Plan, the provincial government has advised Toronto and the TTC of its priorities for rapid transit construction. The Province is quite firm that since it will be paying for these lines, it will call the shots.

This information broke in two letters dated March 22 and 26, 2019 from Michael Lindsay, Special Advisor to the Cabinet – Transit Upload, and Shelley Tapp, Deputy Minister of Transportation, together with a report from the Toronto City Manager, Chris Murray, dated March 26.

The Province has four priority projects, although some of the information about them is vague:

  • A three-stop Scarborough Subway Extension [SSE]
  • A Downtown Relief Line [DRL] of indefinite scope
  • The Richmond Hill Extension of the Yonge Subway [YNE]
  • Construction of the Eglinton West Crosstown LRT primarily underground rather than at grade

These are the only projects mentioned in the letters. By implication anything else is off of the table as far as provincial funding is concerned except for whatever the subway “upload” still under discussion might entail. More about that later.

The Province refers to “incongruencies between the province and city/TTC with respect to the design and delivery of priority projects”. Most of this should be no surprise given previous statements both by Doug Ford as a candidate, and rumblings from his supporters.

The March 22 letter arose from a March 8 meeting between Provincial, City and TTC representatives. Two things are clear:

  • The Province was not paying attention to, or chose to ignore, information it received or should have been able to access easily through public channels.
  • The City/TTC should have had some idea of what was coming down the pipe over two weeks ago, but there was no public hint of what was in store even with the subway upload on the Executive Committee and Council agendas. This is a classic case of “who knew what and when”, and a troubling question of whether the direction of provincial plans was withheld from public view for political expediency.

The March 22 letter makes statements that were revised on March 26, and which have provoked considerable comment as this story broke. Most astounding among these was:

Per our meeting of March 8, we were informed that the City’s preliminary cost estimates for both the Relief Line South and the Scarborough Subway Extension have significantly increased to nearly double or greater the figures released publicly.

On March 26, the Province wrote:

We acknowledge, in light of the helpful clarification you provided at our Steering Committee meeting [of March 25], that the city’s/TTC’s revised project cost estimates for the Relief Line South and Scarborough Subway Extension projects represent estimates in anticipation of formal work that will reflect greater specificity in design. We accept that the actual budget figures remain to be determined …

This bizarre pair of statements suggests that either:

  • the Province was not really paying attention in the meeting of March 8 which led to the March 22 letter, or
  • they really were, but that their first statement was guaranteed to blow every transit plan to smithereens if it were not retracted.

On March 26, they do not say they were wrong, merely that they were dealing with preliminary estimates.

That is a strange position considering that the SSE is on the verge of reaching a firm design number and budget to be reported in early April to Toronto Executive Committee and Council. The agenda publication date is April 2, and it is hard to believe that a firm estimate for the SSE does not already exist. As for the DRL South, that is in a more preliminary state, but if anything the numbers already published have been rather high.

The Scarborough Subway Extension

For the SSE, there are two conflicting proposals:

  • City: One stop extension terminating at Scarborough Town Centre
  • Province: Three stop extension “with the same terminus point”.

There is no reference to any potential connection with a Sheppard Subway extension. However, the March 26 letter contains this statement:

… we recognize that the city/TTC and province share the intention for a station to be located at Scarborough Centre. However, under the province’s preferred three-stop extension of Line 2, the project would proceed northward from the station at Scarborough Centre.

Given that the TTC’s alignment for STC station is itself on a north-south axis, it is unclear just what this remark refers to especially if STC is to be the terminus of the provincial project.

As I wrote recently in another article, there is an issue of equipment and storage required to allow the SSE to open with full service to STC. One potential source of “additional” cost could well be that works such as a new Line 2 yard at Kipling plus the rebuilding and/or replacement/expansion of the fleet are now counted as part of the overall project cost. This is precisely the sort of hidden cost I warned the Province would face when they started to understand the full scope of the TTC’s infrastructure requirements.

Whether this is the case remains to be seen, but with the Province taking responsibility for delivery of this project and planning to assume the cost of maintenance and expansion of the existing subway, they (or anyone else looking at funding the SSE) will be facing these costs as “add ons”.

One other concern is that there is no mention of capacity expansion for Line 2 either by way of station expansion at critical junction points nor of fleet expansion to allow more service once the line has Automatic Train Control [ATC].

Crosstown LRT Westward Extension

  • City: A substantially at-grade extension from Mount Dennis westward, although there are references from recent public participation to the possibility of some grade separations.
  • Province: A “significant portion of this extension” would be underground, an option “which has not been considered in a material way” as part of the current design.

The March 26 letter revised the characterization of the City’s work to date:

… we recognize that tunnelling options for the project have been considered as part of previous assessment, but that these options are not preferred by the city/TTC.

Again, one must wonder just what the province was doing at the March 8 meeting to have so botched their understanding of the work to date. The work already done is documented on the project’s website. I cannot help wondering how much the original provincial position was a product of political posturing by Etobicoke politicians. Such a gaffe does no credit to Michael Lindsay and his team.

It is no secret that there is strong political pressure from politicians in Etobicoke for the LRT line to be buried as much as possible, and it is no surprise that the Province would embrace this.

Missing, however, is any reference to the portion of the line west of the Toronto-Mississauga boundary and specifically the link into Pearson Airport. Will this be part of the Provincial project?

Relief Line South

The text in this section has provoked speculation in various fora, both the mainstream and social media.

Planning work undertaken by the TTC contemplates utilizing existing technology … the province would propose … a truly unique transit artery spanning the city that is not beholden to the requirements of the technologically-outdated Line 2.

On March 26, the Province changed their tune, a bit:

… we recognize that the city/TTC is contemplating a different technology for the project than that currently deployed for Line 2.

It is hilarious to see Line 2 described as “technologically outdated” when it is this line that the Province plans to extend to STC. At the risk of peering into a murky crystal ball, I will venture an interpretation of what is being said here.

The “outdated technology” is the current fleet of T1 trains which do not have ATC installed. Moreover, TTC plans would not see ATC operation on Line 2 for at least a decade unless the existing fleet is retrofitted.

The TTC has always intended that the DRL would use modern technology, and again I cannot help wonder whether the Provincial reps were paying attention at their March 8 meeting with the TTC. This information is not difficult to obtain. They could even read my blog if they don’t want to spend time wading through official documents, but possibly it is simpler just to slag the municipal agency in a time-honoured Queen’s Park tradition.

The Province wants the DRL to be completely free-standing in that it would not depend on Line 2 and the existing yard at Greenwood, but would be built completely separate from the existing subway network. Moreover, “alternate delivery methods” would be used for this project, a clear indication that this would be a privately designed, built, financed and operated line much as the Crosstown was intended to be before a deal was worked out to let the TTC drive the trains, at least for a time.

The reference to a “transit artery spanning the city” implies something much more extensive than the DRL South from Pape to Osgoode Station, but what exactly this might be is anyone’s guess. It could be a truly different technology, something like Skytrain in Vancouver (which itself has two separate technologies). The construction technique could be changed from the proposed double bore to a single bore line, especially if the vehicle cross-section were smaller. The alignment and station locations could be changed. Any of these and more is possible, but we don’t know. As this is to be an AFP project, a blanket of confidentiality hides everything.

Yonge Northern Extension to Richmond Hill

The primary provincial interest here is in getting the line built as quickly as possible with planning and design work for the YNE and DRL to progress in parallel so that “the in-service date for the extension is fast tracked to the greatest extent possible”.

There is no mention of capacity issues on the existing Line 1 including the need for more trains, nor of the expansion needed at key stations to handle larger volumes of passengers.

Jumping the Gun on Uploading?

The March 26 letter clearly attempts to correct misapprehensions from the March 22 missive. These were presumably communicated privately at or before the March 25 meeting.

The Province is supposed to be engaged, in good faith, in discussions with the City and TTC about how or if it would take control of subway assets and what that control, and associated responsibility for ongoing costs, would entail. One might easily read the March 22 letter as showing that the Province has made up their mind, and all that remains is to “drop the other shoe” with respect to everything beyond the “priority projects”.

On March 26, the Province talks at length about “our priority transit expansion projects”. This has always been the political red meat in that new lines translate into votes, or so the Ford faction hopes. The myriad of details in looking after the existing system do not lend themselves to coverage in a two-page letter, let alone simplistic posturings by politicians eager to show the wisdom of their plans.

The March 26 letter does not discuss any aspect of the existing system including asset transfers or financial commitments. That’s not to say the Province has not considered this, but no details are public yet. That will be a critical issue for Toronto because the degree to which the Province actually plans to pay for the existing subway system will affect future City budgets.

There is a myth that fare revenues will cover off the City’s share, but we don’t actually know which aspects of subway “maintenance” will remain in the City/TTC hands. There are two separate budgets, capital and operating, but there has been no statement of how these will be divided. Although there could be a one-time payment for the capital value of the system, this begs two questions. First, who benefits from appreciation of property value as subway lands are repurposed/redeveloped. Second, what does the City do when the nest egg from selling the subway, assuming they even have anything left over after discharging subway-related debt, is used up.

Another issue to be decided is how the split in ownership and financial responsibility will affect gas tax funding that now flows from both the Provincial and Federal governments, over $300 million in 2018. How much of this will Toronto lose, and what will be offset by costs the Province will assume?

Further System Expansion

The correspondence from the Province is silent on many projects including:

  • Eglinton East LRT
  • Waterfront LRT
  • Finch LRT extension to Pearson Airport
  • Sheppard Subway extension to STC
  • SmartTrack and GO Transit Service Expansion

Eglinton East and Waterfront would, assuming a City/Province divide on surface/subway projects, lie clearly in the City’s court, while any extension of Line 4 Sheppard would be a Provincial project. Oddly, Eglinton East would be a “City” extension of a provincially-owned line, the Crosstown.

The Finch LRT occupies an odd place as a surface line that for historical reasons is being delivered by the Province. Moreover, an airport extension would lie partly outside of Toronto. Who knows what the fate of this will be.

To Be Continued …

The provincial letters have dropped into the Council meeting planned for March 27, and we can expect a great deal of debate, if not clarity, in coming days.

At a minimum, the Province owes Toronto a better explanation of just what they intend with their view of projects. This information should not be “confidential” because we are simply asking “what exactly do you want to do”. This is particularly critical for the Downtown Relief Line whatever the “unique transit artery” it might become.

SmartTrack and GO are important components because they will add to the “local” network within Toronto and could be part of the “relief” efforts that will span multiple projects. SmartTrack is a City project, and we are about to learn just how much it will cost Toronto to put a handful of John Tory branded stations on GO’s Kitchener and Stouffville corridors. SmartTrack also takes us into the tangled net of fare “integration” and the degree to which Toronto riders will pay more so that riders from beyond the City can have cheaper fares.

Finally, there is the question of operating costs. The Ford mythology includes a claim that subways break even, and in the uploading schemes mooted to date, there is an assumption that Toronto will still operate the subway network and pay for its day-to-day costs out of farebox revenue. Even if that were true today, much of the proposed network expansion will not gain revenue to cover its operating cost, and Toronto will face increased outlay. There is still no proposal, let alone an agreement, about the operating costs of the Crosstown and Finch LRT lines from which we might guess at how the combination of three new lines/extensions will affect the subsidy call against Toronto’s tax base.

With clear errors in the March 22 letter, the Province showed that it cannot be trusted to propose policy based on fair and accurate characterization of Toronto’s transit system. One would hope that a “Special Advisor” backed by the boffins at Metrolinx and the Ministry of Transportation might be able to avoid screw-ups. When the Province puts forward a scheme to take over part of the TTC, their rationale should be based on transparent and accurate information. Alas, recent experience in other portfolios shows that this will not happen, and dogma will trump common sense.

The Hidden Cost of Subway Capacity Relief

Two studies are underway for the so-called Relief Line:

The alignment for the southern segment has been settled for some time, but the northern segment is still in the exploratory phase of deciding the best route. Planning for the northern segment is under Metrolinx, and all publicly visible work on this stopped for the provincial election in 2018.

Every time either of these lines comes up, the inevitable reaction is “sticker shock” from the very high cost of building a new subway into downtown.

What is missing from the debate is the high cost of retrofitting the existing subway to handle more riders.

When the TTC first advanced its ATC (Automatic Train Control) project, it was to be the solution to all problems. There have been a lot of bumps along the road including:

  • Failure to include ATC signals in the design for the Vaughan subway extension.
  • An unworkable plan to run a mixture of ATC (Toronto Rocket) and non-ATC trains (the T1s now on the BD line) on Line 1.
  • Piecemeal contracts for new signal systems resulting in overlapping and incompatible work.

This was all sorted out, more or less, a few years ago as one of Andy Byford’s big successes as TTC CEO. For a history of the signalling contracts, please read my article here.

However, there is much more to providing added capacity on the subway system, as the TTC gradually discovered and acknowledged through additions to its Capital Budget. Several projects, many of which are not funded, now sit as proposals in TTC plans.

  • Additional trains for Line 1 (for more frequent service and for the Richmond Hill extension)
  • Additional storage for more trains
  • Platform Edge Doors (PEDs)
  • Expansion of Bloor-Yonge Station
  • Expansion of busy stations to provide better circulation for increased volumes of riders to and from trains

Additional Trains and Storage

The subway fleet plan, which I reviewed in detail in another article, includes a provision for more trains to increase the level of service and capacity on Line 1 Yonge-University-Spadina.

Current peak service requires 65 trains of which 4 are “gap trains” used to fill in where a delay would otherwise create a gap in service. The 61 regular trains provide AM peak service every 141 seconds (2’21”) with half of the trains short-turning at Glencairn. According to the plan, by 2029 there will be 79 trains of which 2 will be gap trains. The 77 regular trains represent an increase of about 26% and would bring headways down to roughly 112 seconds (1’52”). Allowing for some trimming of running time expected with ATC, this would result in Line 1 operating a 1’50” headway which is considered the minimum possible given physical constraints at terminals and the effects of dwell times at very busy stations.

However, the fleet of 76 TR trains will only get the TTC through part of this improvement, and there will be a deficit of 9 trains by 2028 as shown above. A 68 train service (70 trains total less 2 gap trains) corresponds to a headway of about 126 seconds (2’06”), an improvement of about 11.4%, and this is the limit of what is possible without more trains.

The plan shows trains under the headings of “capacity” and “ridership growth”. However, only part of the proposed procurement (the 18 “capacity” trains) is necessary to get to the 79 train service shown in 2029. The remaining 26 trains, some of which are spares, would not physically fit on the line without extension of all service on the Spadina leg to Vaughan. Whether the north end of the Spadina leg would actually require a 110 second headway is another matter.

With the price of a subway train sitting at about $36.5 million (mid 2020s), the 44 new trains proposed here would be worth about $1.6 billion plus the cost of future operation. This project is not funded.

A project to expand storage at Wilson Yard is part of the budget, but there is a limit to how many trains will fit there. As the chart above shows, the TTC would run out of storage for trains before all of the proposed new trains are delivered. Future storage depends on a new yard that is part of the North Yonge extension to hold them.

There is a catch-22 here in that some might argue for advancing the Richmond Hill project so that its yard would be available sooner. However, this would also advance the point at which more capacity on both the existing Line 1 and the proposed Relief Line would be needed.

Station Capacity

Much of the TTC’s focus for capacity has been on the signal system and on trains needed to provide more service. However, more service means more riders, and specifically a larger rate for passengers arriving at and leaving stations, and for transfers between lines 1 and 2. There are already problems at some locations with the crush of passengers. Bloor Station is best known, but St. George also has difficulties, and some stations south of Bloor encounter problems with backlogs of passengers trying to leave the platform before the next train arrives. This is particularly severe at locations with limited platform access which can include escalators that are not always in service.

There are three projects in the Capital Budget to address these problems.

Bloor-Yonge Station

The expansion of Bloor-Yonge Station includes the addition of a second platform to Yonge Station on the Bloor line much like the second platform recently added at Union. This would split demand for eastbound and westbound trains between two platforms. The project also includes additional circulation space on the upper (Bloor Station) level for the connections to the new platform. While this addresses some station capacity issues, it will do nothing to increase service and capacity on Line 2 to carry passengers away from Yonge Station even though increased service on Line 1 will deliver them at a higher rate.

This project has a $1 billion price tag, and is budgeted for the first half of the 2020s with completion in 2025. This project is not funded.

There is currently no proposal to expand the capacity of St. George Station, and this location is hemmed in by buildings.

The project summary for the project is below.

Platform Edge Doors

Platform Edge Doors (PEDs) have been proposed for both Lines 1 and 2 for various reasons:

  • suicide prevention,
  • allowing trains to operate through stations without slowing to avoid passengers on crowded platforms, and
  • elimination of litter at track level which causes fire-related delays.

In various public statements, the TTC has been inconsistent about which of these goals is most important, and of course a decision to equip all stations, or only some, depends on what one is trying to achieve. Each is a noble cause in its own right, especially with respect to suicides, but the TTC needs to project a more consistent message on this.

Litter at track level varies with the station usage, and is worst at the very busy stations. Recently, a potato, or maybe it was a lemon, became notorious as it spent over a week wedged under the eastbound track at Yonge Station. Whatever it was, this was only part of an accumulation of debris that had built up over a month putting the lie to the TTC’s claim that it cleans stations frequently specifically to avoid the buildup of material which could cause “smoke at track level” incidents. Some problems do not require multi-million dollar solutions.

A more recent problem with passengers going to track level to retrieve lost objects, or possibly just as a stunt, is quite another matter.

Automatic Train Control (ATC) is an integral part of a PED roll out to provide precision stopping. For Line 1 YUS, the budgeted cost is $610 million with the project spanning the mid 2020s following the full cut over to ATC. In turn, the TTC argues that it will be difficult to achieve the planned 110 second headways with the expected crowding level at major stations unless trains are not slowed on their approach out of concern for hitting waiting passengers.

The cost of PEDs is budgeted at $651 million for Line 2 BD as a post-2028 project assuming that ATC will be in place by that time.

The PED projects are not funded.

The project description from the Capital Budget for the work on Line 1 is below. The Line 2 version is almost identical.

Proposed project schedule. In this chart “BTL” refers to “Below The Line”, that is to say, not included in the funded part of the budget.

Other Station Improvements

Big as many of the subway projects might be, the TTC now includes in its plans a $5.5 billion – yes, that’s billion – unfunded project for enhancement of its station capacity on Line 1. The timing of the proposed work is:

  • 2019: Preliminary strategic implementation plan, solutions and recommendations; business case and Class 5 cost estimate.
  • 2020: Program management plan and preliminary design.

The bulk of the spending for this project is shown in years 2023-2027, although some work might begin sooner depending on the timing of design, project approval and tendering.

The project description includes this warning:

Failure to identify and eliminate key element constraints to achieve target capacity at required horizons will result in increased overcrowding and congestion on Line 1 forgoing TTC’s ability to meet demand needs beyond our current capacity. [Capital Budget Blue Books, p. 584]

There is no indication of the scale of the problem of the locations to be tackled, but the price shows the cost of reworking station capacity in a busy and very constrained set of downtown stations.

And, no I am not making up the $5.5 billion estimated cost. Here is the page showing projected funding and cash flow. To put this in context, this one project is almost as big as the entire funded TTC Capital Budget for State of Good Repair. And of course, that $5.5 billion is unfunded.

Summary

The cost of providing more capacity on Line 1 Yonge-University-Spadina is far more than Toronto has been told in the past. When this all started, it was simply a matter of a new signal system, but that was only the first of many parts in this story. How much of the projected cost here can be trimmed is difficult to say, and that in turn would be affected by the capacity the TTC seeks to operate on Yonge Street. Moving to a full 37k/hour peak demand may not be practical, or could be quite challenging.

Meanwhile, the Relief Line project has, until comparatively recently in TTC history, been treated as something the city only needs as a last ditch effort, something to address a long-future problem, not a pressing need today.

Toronto has been ill-served by the attitude that the Relief Line is a project for another day, not to mention its characterization by some politicians that it is only a project for coddled downtowners. Tell that to people who cannot get on the Yonge Subway, many of whom live far north of Bloor Street.

The division of the RL planning into a south-of-Danforth segment separate from the northern extension means that the substantial benefit of intercepting riders east of Yonge well north of Bloor-Danforth is many years in the future.

The TTC owes Council a thorough discussion of capacity issues on the subway network including all of the interrelated projects needed to deal with present and future demand. For far too long, many projects have been discussed in isolation from each other, or simply have been ignored.

This is an issue for politicians at both Toronto and Queen’s Park who downplay the cost and complexity of a provincial takeover of responsibility for the subway and its funding. Even if the subway remains in Toronto’s hands, there are huge costs facing the TTC and its “funding partners”.

Nothing less than the credibility of transit as an engine for the city’s growth is at stake.