TTC Plans For a Zero-Emission Bus Fleet

Updated June 13, 2018: Discussion and motions from the TTC Board Meeting added.

At its meeting on June 12, 2018, the TTC board will consider a staff report which sets out in some detail the first stages of Toronto’s migration from diesel and diesel/hybrid buses to a zero-emission fleet.

The TTC’s abrupt shift from diesel to zero-emission followed a July 2017 motion adopting the TransformTO climate change plan which included a reduction target of 80% by 2050. After continued defense of “clean diesel” technology on the basis of cost and reliability, ongoing problems with Hybrid buses, and a view that new technologies were not yet mature enough for system-wide use, the TTC has reversed course and embraced a move to buying only zero-emission vehicles by the mid-2020s. As older vehicles reach end of life, the diesel and hybrid fleets would gradually disappear.

In September 2017 at an unusual Board meeting a vendor, BYD, was given the opportunity to make an extended product pitch as a “deputation”. This led to a more general interest in zero-emission vehicles from two other vendors (New Flyer and Proterra), as well as natural gas alternatives thanks to lobbying by Enbridge Gas.

In November, the Board approved a 30-bus trial with ten vehicles from each of the three vendors, as well as a less definitive study of the role of gaseous fuels.

A major problem through the entire process is that much of this is new technology, and there are many competing claims for its suitability that are not yet substantiated by real world experience. A recent article in the Los Angeles Times details problems with their battery buses and the gap between promises and actual performance.

Toronto is just beginning to learn the cost of moving to a greener fleet and the escalation not only in vehicle costs but in related infrastructure. $50 million has been allocated for those first 30 buses, and a further $88 million is on the table for another 30 plus associated infrastructure. The report is deliberately vague about specific prices for vehicles because negotiations with vendors are still underway.

Without extra investment by other governments, the technology change simply would not happen. In a November 2017 report, TTC staff noted that battery buses were “significantly less expensive” than other options based on the availability of PTIF funding.

Indeed, the current plan is structured to burn through as much of the Federal government’s Public Transit Infrastructure Fund Phase I money as possible. When PTIF was announced, all projects to be part of the first phase were required to be finished by March 2019. This is partly a political date given the election next year, and partly an accounting requirement so that spending occurs within a few fiscal years (government fiscal years start on April 1). The PTIF deadline was extended from 2019 to 2020 when it became obvious that actually spending the new money would not be possible for many cities.

Toronto found itself without projects either in the City or Transit budgets that could soak up the available money in only a few years, and initially the focus was on a massive replacement of the bus fleet to retire the worst of the older buses and, at the same time, shift from an 18-year to a 12-year replacement cycle.

In this context – a subsidy windfall plus an unusually large, multi-year bus order – the opportunity for a fast change in technology presented itself both to the politicians and to the would-be vendors. Whether this will work out remains to be seen, but the TTC is moving cautiously with a trial program that will determine whether the new technologies are credible replacements for what we have today. Meanwhile, the TTC will shift back to Hybrids from Clean Diesel on the premise that Hybrid technology has improved since the less-than-reliable generation of buses they are about to retire.

Recommended Action

The staff report recommends that:

  1. The quantity of electric buses will be increased from 30 to 60 with all vehicles to be delivered by March 31, 2020, and the TTC will work with Toronto Hydro on the design and installation of charging and energy storage systems; the project cost is increased from $50 to $120 million.
  2. The TTC will work with Toronto Hydro to modify one bus garage to accommodate up to 300 buses through the supply of a substation and backup generator at an estimated cost of $18 million.
  3. Staff will provide a project update in first quarter 2019 to the new TTC Board following the Council election in the fall of 2018.
  4. Staff will conduct a feasibility study of all garages and report in the fourth quarter of 2019 on “preliminary estimates for the total costs, benefits, and potential funding opportunities associated with the green bus plan”.

Separately from these reports, staff will present a plan in July 2018 feeding into the 2019 budget process with updated capital plans and tradeoffs necessary to free up money for the new bus infrastructure.

Continue reading

TTC 2018 Capital Budget: (1) Fleet Plans

The TTC’s detailed version of the Capital Budget is known as the “Blue Books” because they are issued in two large blue binders. They are not available online. Over coming weeks, I will post highlights from this material beginning with the fleet plans.

These plans were drawn up in late 2017 as the budget was finalized, and there have actually been changes since that are not reflected here. I will note these where appropriate.

For starters, a review of how all of these capital projects are paid for.

Financing and Funding the Capital Budget

The TTC’s budget process at times looks like a game of Three Card Monte where one is certain that one card is the Queen of Diamonds, but never quite sure where she is. This shows up in various ways:

  • There is a “base program” consisting of projects that have Council approval for inclusion in the ten-year plan. The estimated cost of this program is $9.240 billion, but there is funding shortfall of $2.702 billion.
  • There is an “unfunded list” of projects making up the shortfall. These will migrate to funded status as and when money becomes available.
  • The City requires that the TTC make provision for “capacity to spend” reductions in its projects based on the premise that all of the money in the budgets will not actually be used. This offsets $427 million of the shortfall, although one can argue that this is a polite fiction meant to convey the idea that the funding hole is not quite as deep as it seems. The premise is that not all projects will be spent to their full budgets, and an across-the-board provision will soak up the underspending. In practice, some of this “shortfall” is a question of timing – project slippage that shifts spending to other years – not a question of budgeting too high.
  • Some projects have their own, dedicated funding streams and appear separately from the base program. At present, these are the subway extensions to Vaughan and to Scarborough.
  • Some projects in the base program have funding directed specifically to them. The provincial 1/3 share of the new streetcars is an example. This is separate from provincial money that flows to Toronto from the gas tax.
  • Some projects have timelines associated with the structure of funding programs. Ottawa’s Public Transit Infrastructure Fund (PTIF) Phase 1 requires that projects be completed by March 31, 2019 so that the subsidy is expensed, federally, by the end of the 2018-19 fiscal year. PTIF phase 2 has not yet been announced either as to amount or to the timeframe in which spending will occur. These constraints prevent many projects from receiving PTIF money because they do not fit within the prescribed window for spending.
  • Metrolinx projects do not appear on the TTC’s books, but in some cases they can trigger payments from the TTC and/or the City of Toronto. Examples are Presto and SmartTrack.
  • Some transit proposals are not even in the base program, but wait in readiness as “nice to haves”.

“Funding” is the process of paying for projects, while “Financing” is the mechanism by which that money is raised. A “funded” project is associated with revenue from “financing” sources that the City can depend on such as property taxes and committed monies from other governments. Where there is a shortfall, someone has to step up with new money, however they might raise it, or something must be removed (or at least reduced in scope) from the list of funded projects.

City of Toronto contributions to capital come primarily from current taxes (“capital from current” and development charges) and from borrowing. The amount of borrowing available to the TTC each year is dictated by the City’s self-imposed 15% cap on the ratio of debt service costs to property tax revenue. A few major projects in the near future, notably the Gardiner Expressway rebuild, are crowding the debt ceiling, and there are years when little new debt will be issued on the TTC’s behalf. In turn, this affects spending plans at the TTC, and projects are shifted into future years with more borrowing room to get around this.

Other constraints can arise from a program like PTIF which, because it has a sunset date, requires that spending that might otherwise occur some years in the future must actually happen sooner than planned. This, in turn, requires matching funds from the City in years where they might otherwise have been spent on other projects.

Continue reading

Toronto’s Transit Capacity Crisis

In recent days, Mayor Tory has announced, twice, a ten point program to address crowding on the TTC. The effectiveness of this program is limited by years of bad political decisions, and the hole Toronto has dug itself into is not one from which it will quickly escape.

This article is a compendium of information about the three major portions of the “conventional” (non-Wheel-Trans) system: subway, bus and streetcar. Some of this material has appeared in other articles, but the intent here is to pull current information for the entire system together.

Amendment February 15, 2018 at 5:30 pm: This article has been modified in respect to SmartTrack costs to reflect the fact that over half of the cost shown as “SmartTrack” in the City Manager’s budget presentation is actually due to the Eglinton West LRT extension which replaced the proposed ST service to the commercial district south of the airport. A report on SmartTrack station costs will come to City Council in April 2018. Eglinton LRT costs will take a bit longer because Council has asked staff to look at other options for this route, notably undergrounding some or all of it.

Continue reading

TTC Board Meeting February 15, 2018

The TTC Board will meet on February 15, 2018. Among the items on the agenda are:

Scarborough Subway Extension (SSE)

The SSE itself is not on the agenda, but it has been the subject of much recent debate over when the projected cost and schedule for the extension will be released.

In the November 2017 CEO’s Report, the project scorecard included a schedule showing that 30% design would be complete in the second quarter of 2018, and an RFP [Request for Proposals] would be issued in the third quarter. Even when this report came out, former CEO Andy Byford was hedging his bets about a spring 2018 date saying that more work would be needed to verify and finalize the figures. A key note in this scorecard states:

EFC [Estimated Final Cost] was approved in 2013 based on 0% design. With the alignment/bus terminal now confirmed by City Council, the project budget and schedule will be confirmed as design is developed to the 30% stage, factoring in delivery strategy and risk. The performance scorecard will continue to report relative to the project’s original scope, budget and schedule, as approved by Council in 2013, until the project is rebaselined at the 30% stage in late 2018.

In other words, neither the schedule nor the projected cost reflected the evolving and expanding design of this project.

Jennifer Pagliaro in the Star wrote about the result of a Freedom of Information Request that revealed a briefing to Mayor Tory in September 2017. That briefing included a statement that the cost estimate for a Stage 3, 30% design, would be available in September 2018.

Because Council will not meet until 2019, numbers that might have been available before the election would not be released until after the new Council takes office. After the story appeared, City staff replied:

The cost information referenced in page 9 of the October TTC briefing deck refers to the planned timing for initial cost inputs from TTC engineering staff. These are not the full cost estimates necessary for consideration by Council. Further work will be required to appropriately account for financing, procurement model, market assessment and other critical factors. The final cost estimate, subject to the variability ranges noted below, will include these inputs.

This additional work will be undertaken by various TTC staff as well as city officials from corporate finance, financial planning, city planning and other divisions. [Tweet from Jennifer Pagliaro, February 7, 2018]

I wrote to the TTC’s Brad Ross about this conflicting information, and particularly about the question of how an RFP could be issued in 3Q18 when Council would not be approving that the project pass beyond “stage gate 3” until 2019. He replied:

No RFP will be issued until after Council approval. You will note in the Key Issues and Risks section of the scorecard from November reads, “The performance scorecard will continue to report relative to the project’s original scope, budget and schedule, as approved by Council in 2013, until the project is rebaselined at the 30% stage in late 2018.”

To be consistent with the report to Council in March 2017, only the revenue service date was revised in the scorecard (from Q4 2023 to Q2 2026). The TTC recognizes and acknowledges that this has led to confusion. The TTC will be taking steps to ensure greater clarity in its next CEO Report in March 2018. [Email of February 9, 2018]

The February CEO’s report states:

Work continues to progress design towards Stage Gate 3, expected in fall of 2018. At this time, the project will provide initial cost inputs from the TTC team (includes detailed costs for the Scarborough Centre station, tunnel, Kennedy station, systems, property and utilities). Further work is underway by the new Chief Project Manager with key stakeholders within TTC and the City to define the activities, approval process and timelines to arrive at the final Class 3 Cost Estimate, Level 3 Project Schedule, and associated Risk Analysis.

As requested by City Council, a report will be presented at the first opportunity to the Executive Committee, TTC Board and City Council, which is expected to be Q1 of 2019. [pp 15-16]

The debate, as it now stands, is about releasing whatever material will be available in September 2018 so that it can inform the election debates. Additional costs as cited by the city would sit on top of the September numbers, but at least voters and politicians would know whether the SSE’s cost has gone up just for the basic construction, let alone factors related to financing and procurement that would be added later.

Meanwhile, SSE promoter Councillor Glenn De Baeremaeker speaking on CBC’s Metro Morning said:

I don’t think it matters what the costs are.

This has been taken to read that money is no object, and that well may be the political reality in Scarborough – there is no way the many politicians who have so deeply committed to the subway project can back out. De Baeremaeker continued:

Whether the costs go up or the costs go down, people who have tried to sabotage the subway and stop the subway, will continue to try to sabotage it, they’ll continue to try to stop it, and they will never vote for it. So I would challenge the Councillors who say “I want to see the cost”. My response is and if it’s a reasonable cost, will you support the subway? Well, no. [At 3:26 in the linked clip]

What De Baeremaeker does not address is whether he has an upper limit beyond which even his enthusiasm might be dimmed. Also, on the question of a “reasonable cost”, what has been lost here is the fact that the subway “deal” was sold on the basis that the $3.5 billion included the Eglinton LRT extension to UTSC Campus. What had been a $2 billion-plus subway when it was approved as a compromise by Council, quickly grew to $3 billion-plus, and the LRT extension is left to find alternate funding. One could reasonably ask whether the LRT was ever really part of the deal, or was simply there as a sweetener that pulled in wavering supporters who now see just how gullible they were.

A related issue that has not yet surfaced is the question of whether building the SSE for a 2026 opening will require concurrent changes in timing and/or scope for the planned renewal of the Bloor-Danforth subway including a new signalling system and fleet. A report on the renewal is expected in April 2018, although this date has changed a few times over past months. The TTC/City capital budget and ten year plan do not reflect this project, at least with respect to timing, and probably with respect to total cost.

Continue reading

TTC Board Meeting October 16, 2017 (Updated)

The TTC Board will meet on October 16. Among items of interest on the agenda are:

Continue reading

Is A TTC Bus Technology Gerrymander In The Works?

At its September 5, 2017, Board Meeting, the TTC considered a report recommending the purchase of 440 “clean diesel” buses from Nova Bus, a division of Volvo. This sort of thing would normally sail through because the Board has considered and approved future bus plans at previous meetings. In this particular case, one important aspect of the order is that 325 of the vehicles would be delivered before the deadline for federal PTIF (Public Transit Infrastructure Fund) grants that end on March 31, 2019. A further 115 buses would be procured with the “standard” arrangement for TTC capital financing, but no federal contribution.

This procurement went through a common pattern with an RFI (Request for Information) in October 2016 and an RFP (Request for Proposal) in April 2017. Two proposals were received, one from Nova and the other from Flyer Industries, and both met the technical requirements. The decision to award to Nova Bus was based on pricing (Nova’s bid was $300.5 million while Flyer’s was $345.0 million).

In an unusual move, the Board entertained a last-minute addition to the deputations list, two representatives of a builder of battery buses, BYD. This is a Chinese manufacturer with an office in Los Angeles and, more recently, representatives in Canada. BYD did not bid on this RFP because it specified clean diesel technology which they do not supply.

Their presentation and associated Q&A went on at some length, far moreso than public deputations are normally allowed, and it was quite clear that this was a sales pitch for their product. In any other Board meeting, this would have been stopped as an abuse of process, but this situation was under the charmed support of Deputy Mayor Minnan-Wong who is a member of the TTC Board.

Many claims were made for BYD technology and for the scope of the battery bus industry that went largely unchallenged.

In response, TTC management advised that they would be issuing an RFI for alternative technology buses to four supplies, including Nova and Flyer, later in the week, and that they planned to bring back an overview report to the Board in November.

The situation became more interesting with a motion proposed by Minnan-Wong and eventually approved by the Board with only two votes against that would reduce the contract award to Nova to 325 vehicles and pursue the remaining 115 as a potential for a different propulsion technology.

Another wrinkle was added by Chair Colle (one of the two “no” votes on Minnan-Wong’s proposal). The PTIF funds allocated to Toronto were split between the TTC and the City, and the TTC has found projects that can qualify for this funding. However, the City is unable to spend all of its available funding and is looking for projects that could soak up the shortfall. Colle proposes that TTC management report on what projects might be brought forward for this purpose.

During the discussion, there were comments pro and con the TTC’s becoming embroiled in yet another new transit technology. They have already been burned by the Hybrid Bus fiasco, ironically a scheme they were forced into by a combination of environmental enthusiasm at Council and federal subsidies that were only available for “green” technology. A good deal of that federal money went not to additional buses, but to paying the extra cost of the hybrid vehicles. The BYD reps proposed exactly the same thing for their products – yes, they were more expensive than regular buses, but the feds would pay and the TTC could save money in the long run on operating costs. Of course this approach would negate the ability to buy more transit infrastructure with the federal funding, and of course would not apply to any buses bought outside of the PTIF envelope.

TTC management including CEO Andy Byford made the point strongly that it is staff’s job to get service out onto the road, and the 440 bus order was to allow retirement of the oldest and least reliable vehicles. Battery bus technology is evolving quickly, but beyond some large fleets in China, cannot be said to be well-established in North America or Europe.

It is quite clear that there has been lobbying behind the scenes, primarily to the Deputy Mayor, for several months. Below are snapshots from the City of Toronto’s Lobbyist Registry. (Click to enlarge.)

The lobbyist company, Earnscliffe, is well-known. The initial contact by them corresponds to the point at which the TTC issued its RFP for diesel buses in April 2017.

Any company is free to lobby, but it is quite unusual for this to result in a direct presentation to a Board meeting where a contract award is up for approval. We have learned recently how political meddling has influenced advice and decisions at both Metrolinx and the City of Toronto, and this continues a disturbing trend.

Worst of all, the TTC staff report on alternative technology buses will now be under a cloud. Will it be a technically honest report, or will it be spun to suit the position of a well-connected member of the Board? By giving credibility to BYD’s presentation, has the Board placed TTC staff in the unenviable position of debunking claims made by one would-be vendor? Will there be another round of vendor presentations attacking whatever staff brings forward?

Members of the TTC Board just love to think of themselves as progressive, forward thinkers who will embrace potential transit improvements. One Board member, Councillor De Baeaemaeker, even launched into an attack on “clean diesel” by reference to all of the pollution created by exploration, extraction and refining, while carefully avoiding the fact that a great deal of Ontario’s base electrical load comes from nuclear power. That is where overnight charging would come from, but this delicate point was not part of his thesis.

If the TTC invests in electric buses, regardless of the manufacturer, this will require a garage with very different capabilities from any they now own. A substantial power supply will be needed for all of the overnight charging, and repair facilities will have to be attuned to electric, not diesel, vehicles. The TTC does not have any increase in garage capacity in the pipeline beyond McNicoll Garage, already under construction, and it will easily be the early 2020s before there is a garage where a new fleet could be based, assuming that it is a net addition and not simply a replacement for existing buses. (McNicoll, although a new garage, will simply take the pressure off all of the existing garages which are badly overcrowded.)

The irony here is not lost on those of us who followed the TTC through its abandonment of electric buses a few decades ago when beautiful, clean compressed natural gas was a panacea to solve both our diesel woes and TTC management’s distaste for trolley buses.

Battery buses may well have a future in Toronto and in world transit generally, but the way this has been introduced at the TTC leaves a foul taste, a sense that the fix is already in. Toronto’s transit technology choices have been gerrymandered more than once in the past to suit politicians and businesses looking to cash in on new technology. We have had enough of this, thank you.

A Slow Trip to Express Buses (Updated)

Updated June 19, 2017 at 3:30 pm: The TTC has clarified that the hourly costs shown for various routes are net costs, not gross costs, and this addresses my concern that some of these values were understated. The text of this article has been updated where appropriate.

Updated June 20, 2017 at 10:30 am: A section has been added on gross operating costs (the TTC study includes only net costs) to illustrate how these vary from route to route.

The TTC Board recently approved an Express Bus Network Study that proposes several new and enhanced express routes in Toronto. The premise of the study – improving the bus network’s attractiveness and convenience to riders – is a good one addressing the basic function of any transit system. However, thanks to the TTC’s severe constraints on capital and operating funding, the actual implementation of these proposals drags out for the better part of a decade. Bus planning in Toronto is converging with new subways for a lengthy gestation period.

There are three types of “express” route in Toronto:

  • The (mainly) peak period services usually signified by an “E” suffix on the route number. Typically, buses will run express over part of a route stopping only at major transfer points or destinations, and will continue as local service on the outer part of the route. These services are useful for riders who would otherwise face a long stop-and-go trip on a local bus for their entire journey. By carrying the long-distance riders express for part of the trip, the cost of route operations is reduced from that of an all-local service and provides a more attractive service overall.
  • The Rocket services (route numbers in the 18x-19x series) operate for most of the day on weekdays and weekends, and provide a more limited stop service, end-to-end, than the “E” branches. Some are designed around major endpoints such as the 192 Airport Rocket from Kipling Station to Pearson Airport, while others more closely resemble the stopping pattern of “E” services. Unlike the “E” branches, the Rockets do not necessarily duplicate the route of a local service.
  • The five Downtown Premium Express services (route numbers 14x) charge an extra fare for the privilege of avoiding the crowded Yonge subway and the 501 Queen car.

The TTC proposes an interim classification of the first two of these as Tier 1 (Rockets) and Tier 2 (“E” branches) with the intent of coming up with some sort of branding that could be used to market them. Some cities have special bus services with their own names such as Hamilton’s B Line Express and Vancouver’s 99 B-Line. Given that there already is an established name for Tier 1 with a strong Toronto reference, it is hard to understand why a new brand is required. As for the Tier 2 services, riders are well acquainted with the “E” convention (broken in rare cases such as 60F Steeles West).

The first recommendation of this study is that a marketing effort is required to brand these services. That says a lot about where the TTC’s focus has been in recent years – selling the “pizzazz”, to quote a former TTC Chair, while the system gradually declines thanks to penny-pinching by two successive City administrations.

Summary

This is a long article. Here are the highlights:

  • Growth of express services is limited as much by the political question of transit funding as it is by planning and resource constraints within the TTC.
  • The TTC’s bus fleet plan should be thoroughly reviewed to determine how more buses can be made available for service sooner than 2019/20 when McNicoll Garage opens.
  • TTC budgets should reflect a return to full streetcar service on the streetcar lines in 2018 and the redeployment of replacement buses back to the bus network.
  • Express bus routes that were added in 2016 have performed better than expected showing that these are popular services and should be expanded as soon as possible.
  • New Rocket and express routes are proposed in two waves, one for 2019-21 and the second with a tentative date of 2026.
  • Costs and revenues allocated to existing and proposed routes should be verified.
    • Update (text deleted): The costs shown for some routes appear to be in error if the methodology for costing used by the TTC is to be believed. (This issue has been referred to the TTC for comment.)
    • Revenue allocation in a flat fare system can distort the benefit of a route, and the measure of value should be based on usage not on a misleading allocation of fare revenue.
  • Express buses provide a means of carrying riders on a route with a mix of short and long haul demand more efficiently and attractively than an all-local service.
    • Riders on express services travel further than on local services taking advantage of the faster trip between major points on the route. There are fewer riders per bus kilometre because there is less turnover of the passenger load on express services.
    • Express buses cost more per ride than local buses because of their lower turnover (i.e. more riders), but the overall route cost is lower with a mix of services.
    • A proposal by one member of the TTC Board to charge extra for express routes would be counterproductive.
  • The Premium Express buses to downtown operate at a very high cost per passenger, although this needs to be verified in light of the issue with cost calculations. Demand on these routes is relatively light, and they contribute only trivially to reducing demand on parallel services. The TTC proposes to leave them in place at least until 2021, but this should be reviewed even though removing the services will be politically challenging.
  • Transit Signal Priority is not just an issue for an Express network, but for transit in general. It should be pursued on major routes whether or not they include express operations.
  • Route supervision will be essential to maintaining reliable service not just on express routes, but on the transit system overall.
  • The staff proposal to “brand” services continues the TTC’s focus on marketing when what is needed is service. The “Rocket” name is already well-established as a service type in Toronto, as are the “E” express branches of various routes. In a few cases, the “wrong” name is associated with a service (some “rockets” are really just “E” services in terms of their service patterns), but this does not justify a complete rebranding exercise.

Continue reading

The Fords’ Fascination With Streetcars

At a recent meeting of Toronto’s Public Works and Infrastructure Committee (PWIC), a motion was approved asking for reports on the comparative cost of streetcar and bus operations on Queen Street. The author of this was Councillor Michael Ford, although it was actually placed by his colleague, Councillor Holyday because Ford is not a member of PWIC.

1.  City Council request the Toronto Transit Commission, upon completion of the construction projects that have resulted in the removal of the 501 Queen Streetcar route from service for Summer 2017, to defer reintroduction of streetcar service for a period of two weeks, to permit the collection of data for the comparison study.

2.  City Council request the General Manager, Transportation Services, in consultation with the Toronto Police Service and the Toronto Transit Commission, to conduct a comparison study of the efficacy of streetcar service versus bus service on Queen Street, specifically looking at:

a. Schedule reliability of transit vehicles
b. Delays to other users of the road
c. Collisions at transit stops involving transit vehicles and cars, pedestrians, or cyclists
d. Collisions at transit stops between cars, pedestrians and cyclists not including transit vehicles
e. Ridership satisfaction
f. Fleet maintenance costs
g. Fleet operator and operation costs
h. Incidences of driver assault
i. Incidences of passenger disputes
j. Traffic volumes in peak period and off-peak periods

using bus data collected during the two week delayed streetcar re-implementation period, followed by the subsequent two weeks once they have been re-implemented, in order to get a clear and direct comparison during non-construction periods, and report back to the Public Works and Infrastructure Committee in the first quarter of 2018.

The request received little debate coming as it did as an add-on motion to a Friday meeting. Nobody from the TTC was present, nor were there any interventions by downtown Councillors or members of the public. PWIC, although it deals with many issues affecting downtown, contains no members from that area thanks to the gerrymandering of committees by Mayor Tory.

An amendment to this motion by Councillor Lee asked the Deputy City Manager to report to Council with additional information such as the cost and feasibility of such a study.

The package passed on a 3-2 vote and the request goes to the July 2017 Council meeting for approval.

My recent series of articles on bus vs streetcar operations on Queen was already “in the works” when this motion was approved, although this request triggered somewhat more urgency to producing them than I had planned.

Part I: A comparison of travel times for streetcars in April vs buses in May 2017
Part II: An historical review of travel times September 2013 to May 2017
Part III: Capacity of service scheduled and operated
Part IV: Comparative operating speeds in May 2017

One important point flowing through these article is that “comparison” can be challenging when the underlying conditions vary. From the analysis I have published, it is already clear that buses tend to fare better than streetcars where traffic is light and demand is low, but they lose this advantage in busy areas. A further problem is that TTC operating practices for each vehicle type differ and buses tend to be driven more aggressively. Streetcars could be too, but in an attempt to manage service, various practices have resulted in streetcars being forced to drive more slowly than actual road conditions dictate. The longer this goes on, the more it is assumed to be an inherent part of streetcar operations, while those of us who have ridden the TTC for some years know what streetcars can actually do given the chance.

The motion proposes that buses stay in operation for two weeks beyond the point that streetcars would have returned (Labour Day weekend) and that data be collected to compare operations. To be fair to the buses, this may not be an ideal period because early September sees much traffic displaced from King to Queen thanks to TIFF. Other planned construction work will disrupt the street: in September, track will be replaced at Queen & Coxwell, and in October/November at Queen & McCaul. Coxwell, at least, is well out of the core an work there will not affect streetcar service (a bus shuttle will run to Neville). There is also the question of whether the TTC will have enough buses to spare for Queen once the summer service cutbacks end in September.

One issue raised by the motion and by some media reports is that riders feel they are getting a faster trip with buses. My analysis shows that for some times and parts of the route this is true, but not for the most congested areas. Moreover, as already noted, we are seeing buses unconstrained by a “go slow” operating policy compared with streetcars that limp along the route to avoid running early. This is not an apples-to-apples comparison.

We have been down this road before when former Councillor Rob Ford, later Mayor, posed a series of questions to the TTC in 2010. My thanks to Councillor Kristyn Wong-Tam for providing the exchange. For the purposes of this article, I have divided up the material so that I can comment on each section, and reordered the sections to provide a better thread in the current context.

It is no secret that I support the retention and expansion of the streetcar network. Although new suburban lines such as 5 Crosstown and 7 Finch West will use the “Metrolinx” Toronto car, whatever it might be, new lines in the waterfront west to Humber Bay and east to the Port Lands will be part of the “legacy” network. Waterfront plans depend on the capacity that an LRT  link to Union Station can bring.

The question of articulated buses as a streetcar replacement comes up from time to time. My response is that there are suburban routes where these are appropriate, but that in the congested core area, streetcars are the best vehicles for traffic conditions and they have the ability to operate underground where needed. Buses might be made to work, but only if Toronto is prepared to devote much more road space and time to transit vehicles. They are not a panacea for suburban motorists fighting their way through traffic in an oversized SUV.

Continue reading

TTC Board Meeting April 20, 2017 (Updated)

The TTC Board will meet on April 20, 2017. Items of interest on the agenda include:

  • The monthly CEO’s Report
  • Repair of SRT Vehicles
  • Disposition of Bay Street Bus Terminal

This article has been updated with a commentary on subway and surface route performance statistics presented at the Board meeting. (Scroll down to the end of the CEO’s Report.)

Continue reading