SmartTrack Reduced to a Handful of GO Stations

The ongoing saga of SmartTrack, once billed by then-candidate John Tory as the saviour of Toronto’s transit, took another hit with the publication of an update on the SmartTrackStations project.

As originally proposed, SmartTrack looked like this. The line ran from Unionville to the Airport Corporate Centre with 22 stations, mostly new.

It was supposed to open this year (2021). That has been pushed back to 2026, and even that could be a soft date if GO’s expansion plans are delayed.

It would have worked hand-in-glove with GO Transit’s Regional Express Rail concept as former Metrolinx Chair Rob Prichard enthused in the project’s promotional literature:

The project contemplates making the GO train corridors virtual “surface subways” with service so frequent and fast that the trains became an irresistible substitute for driving, thus significantly mitigating traffic congestion. Imagine going to the GO station confident that the next train will be along soon, just like when we go to a subway station.

Robert Prichard: Transforming the Way We Move. Address to the Empire Club April 23, 2014. Cited in Surface Subways for Toronto from John Tory’s election website [since removed].

Many parts fell off of this plan including:

  • The proposed Eglinton West branch to the Airport would have required a mainline rail corridor from Mount Dennis to the Airport. This was not technically practical, and plans for this area reverted to the western extension of the Crosstown LRT.
  • Instead of being a dedicated service with its own fare structure, SmartTrack stations will now be served as part of the GO network using whatever fare arrangements are in place by the time service begins.
  • The City’s plan now includes only four stations on the Weston-Scarborough corridor, plus one on the Barrie corridor that had previously been part of GO’s plans.
    • The most recently deleted stations were at Lawrence East and at Gerrard as these locations will be served by the Scarborough Subway Extension and the Ontario Line respectively. Bloor-Lansdowne has become a “City” station while Spadina-Front remains a “GO” station.

Park Lawn and Woodbine, also shown in the map below, are “GO” stations that are not part of the SmartTrack plan.

Of the stations that remain in the project, their viability deserves reconsideration:

  • Three of the stations (Finch-Kennedy, St. Clair-Old Weston and Bloor-Lansdowne) are projected to have little walk-in trade.
  • Transfer traffic at two stations (Finch-Kennedy and Bloor-Lansdowne) may be limited by competing nearby services including the Scarborough Subway terminal at Sheppard-McCowan and the subway-GO connection at Dundas West.

The original SmartTrack plan projected very high all-day demand:

The SmartTrack line will have a conservatively estimated ridership of 200,000 per day. This is the equivalent of about half the daily ridership of the existing Bloor-Danforth line.

Source: The SmartTrack Line from John Tory’s election website [since removed].

To put this in context, this is about two-thirds of the entire GO Transit network, pre-pandemic. That is simply not possible with trains running every 15 minutes that must also carry riders from other GO stops.

The demand projection depended on a level of service and fare structure that will not be part of whatever “SmartTrack” is by the time service finally operates to the new stations. When SmartTrack was “sold” to Council, a different service level, station count and fare structure were cited than now appears to be likely.

Indeed, Metrolinx had already change its future service plans and announced their miraculous discovery (a mix of local and express trains) at a Toronto Region Board of Trade event. Frequent service at SmartTrack stations would not be possible if the express trains did not stop there.

The report makes clear a change in service planned for the SmartTrack stations that Metrolinx watchers had suspected for years, namely that the frequent “subway like” service touted for SmartTrack had been replaced with much less frequent GO service.

From the main report:

2018 Version2021 Version
Service ConceptProgram service levels will be 6-10 minutes during peak periods and 15 minutes during off-peak periods.Program service levels will be the same as the planned GO Expansion-level service for the corridors in which the Stations reside, with a minimum service level of two-way, 15-minute frequency commencing upon full implementation of GO Expansion service, with more frequent service to be determined on a market-led basis and subject to ridership demand.

As for fares, the whole idea that somehow riders on trains in GO corridors could pay via two different tariffs with free transfers to/from TTC service was always hard to believe. It is now clear that a “TTC” fare will be achieved by forcing everything, including local TTC service, into a regionally integrated system that, judging by Metrolinx’ long-held preferences, will be based on distance travelled.

Council and Torontonians were misled as they have been on more than one transit project.

A related problem, considering the size of the investment, is that the lion’s share of ST riders will not be net-new to transit, but rather will be diverted onto ST trains by the lure of a faster, and possibly less-crowded journey.

In total, the five stations are projected to attract a combined 24,000 boardings and alightings during the average weekday peak hour. Taken together, the five new stations are projected to attract 3,400 new daily riders to Toronto’s transit system by 2041 every weekday. Ridership would likely be higher with full fare integration between the TTC and GO Transit.

Source: Technical Update, p. 3

Note that by counting both boardings and alightings, these figures double the number of trips because anyone who “boards” must eventually “alight” somewhere. This will count everyone who makes a trip on GO twice for the network as a whole.

Time savings were illustrated by a “SmartTracker” website (still active as of January 20, 2021 at 3:00 pm) to demonstrate how one might make a faster journey with ST in place. The calculated ST travel times did not include any wait time for the train because service was assumed to be very frequent.

Projected values are in the Technical Update for each station, but they do not show the network as a whole. “Person Minutes Saved” are calculated by multiplying the riders for a station by the extra time they would have required to make the same trip if the ST station did not exist. For a station that is off of the beaten path like East Harbour, this translates into a large total saving.

It is not clear which lines were in the “base network” without the ST stations, and in the particular case of East Harbour, whether the Ontario Line was there or not. In other words, what is the extra riding and time saving due to SmartTrack as opposed to the Ontario Line? We don’t know because this information is not in the report. Another key missing piece of information is the service level assumed in the model.

StationPeak Hour Boardings & AlightingsPerson Minutes SavedNotes
Finch-Kennedy4,600 (*)> 250,000Demand primarily from bus transfers
East Harbour13,000> 1 millionMajor development node and transfer point with Ontario Line
King-Liberty3,200> 175,000Major residential neighbourhood
St. Clair-Old Weston300Limited demand, but some development possible. Project will include road reconfiguration between Keele and Old Weston Road.
Bloor-Lansdowne2,900Connection to subway poor
Source: Technical Update / (*) The Finch-Kennedy value is not in the report, but is derived from 24K total cited above less published values for other stations.

How Much Will “SmartTrack” Cost?

The City’s original budget for SmartTrack was $1.463 billion of which $585 million would be from the pool of Federal infrastructure funding. The project is now smaller because there is, net, one fewer station and some elements originally included have been deferred to a “phase 2” (and a separate budget line). However, the total is unchanged probably due to inclusion of other options in the design such as the City-initiated Keele-St. Clair project.

Cost estimates for specific stations have not been released yet, only the totals: $1.195b is for base station infra and $268 is for city initiated station requirements. That’s a cost/station of over $200 million, rather substantial for a line that is not underground.

Metrolinx will carry the operating and maintenance cost of the stations which they will own, and they will get to dictate the service level. Fare revenue will flow to Metrolinx who will set the tariff.

How this would interact with City policies on reduced fares for low-income riders is difficult to say, but the higher GO fares could work against any benefit for low-income areas the new stations might otherwise provide.

Continue reading

GO / UP Express Off-Peak Service Cuts Effective January 23, 2021

In response to the steep decline in demand on their rail services, Metrolinx announced substantial changes to off-peak services on January 14.

Union-Pearson Express

Service now begins at 4:55 am every day and continues until 1:00 am every half-hour. This will change:

  • On weekends, the first train will leave Union at 6:00 am.
  • The last train will leave Union at 10:00 pm every day.
  • Half-hourly service will be provided only during these periods:
    • Weekdays 5:30 to 9:00 am, and 3:00 to 8:00 pm
    • Weekends 9:00 am to 7:00 pm
  • Hourly service will operate at other times.

GO Transit

All weekend and evening train service on the Kitchener, Barrie and Stouffville corridors will be replaced by buses operating from the new Union Station bus terminal. The changeover will begin on Friday, January 22 for Stouffville trains in the evening due to planned construction on the line that weekend.

The Effect of Covid-19 on GO/UPX Ridership

In recent years, Metrolinx has been proud to show strong growth on its network, and was starting to think in terms beyond peak-period, peak-direction commuting to downtown Toronto. With the work-from-home shift in the business core, this demand has collapsed.

The map below shows the growth in ridership for the period April-December 2019 compared with the 2018 figures. The size of the dot at each station is scaled to the change in demand. (Click on the images below for larger versions.)

Covid-19 changed everything, and ridership in April-September 2020 is only a fraction of former levels.

PDF versions of these files are available here:

The decline in demand has been severe, and no corridor is carrying even 10 per cent of its former demand. This is much worse than the situation on the TTC network where demand, although down from 2019, ranges up to 50 per cent of former levels thanks to continued strong ridership by essential workers and by those for whom car travel is not an option.

At a corridor level, the best performance is on Lakeshore East at 9.4 per cent of former demand, while Richmond Hill brings up the rear at 1.5 per cent, or 87 riders per day.

At a station level, the best performance is at Oshawa at 11.6 per cent of former demand, or 418 riders per day. Some stations are below 10 per day.

A tabular version of the station-by-station values is available here:

Weekday train service to Niagara Falls was suspended earlier in GO Transit’s covid-era schedules, and the weekend service was dropped on Saturday, January 9. GO hopes to resume weekend service in spring 2021.

Longer term, the challenge for Metrolinx will be the pace of demand recovery on its network given its strong commuter orientation. The program to expand GO capacity and, eventually, to electrify parts of the network now depends on assumptions about future levels of service and demand including when or if these will be achieved.

As on the TTC, it would be easy for budget hawks to claim that big spending on transit is a waste, but this is entirely the wrong time to make such a call. We do not know what the situation will be even a year from now, let alone further out, and what course the pandemic era will follow. This is not the moment to give up on transit much as road-building advocates might prefer to kick the competition while it is down.

There is a more subtle, but important point about GO Transit’s situation. If their service and policy focus shifted away from downtown commuting to all-day, everywhere service, this could bring a truly “regional” outlook.

Governments of both the Conservative and Liberal stripe at Queen’s Park have no interest in “local” transit service beyond funding provided to municipalities via the gas tax. The tax amounts just announced are for the fiscal year 2020-21 and are already baked into local budgets, and are separate from any covid-specific relief. They are not “new money”.

Ontario suffers from a combination of limited local transit and even less intercity service thanks to the disappearance of private sector carriers. A few new services have appeared, but there is no sense of a network approach let alone provincial funding to build ridership. With the core GO Transit network at historically low ridership, an expanded role for GO buses is the last thing on anyone’s mind. The problem is compounded by a political orthodoxy that somehow the private sector will fill the gap, ideally without any public funding.

Metrolinx and Queen’s Park are happy to focus on transit megaprojects, but the benefits are confined to specific corridors, some at great cost, and are years in the future. Meanwhile, we wait and hope for transit demand to recover and restore GO Transit’s relevance.

Eglinton East & Waterfront LRT Updates

Toronto’s Executive Committee considered a report on the current status of the Eglinton East LRT and Waterfront East LRT projects at its meeting on December 10, 2020.

The primary function of this report is to authorize continued study, not to set priorities nor to discuss funding schemes. As such, its recommendations passed easily because it preserves the convenient fiction of progress without actual commitment. The real battles come when there are $30 billion worth of transit projects and less than $10 billion to pay for them.

In a beautifully ironic touch, the same morning brought news from the Toronto Star’s Jennifer Pagliaro that the Scarborough RT would not last long enough to avoid a shutdown well before the Scarborough Subway could be completed. That announcement raises a raft of questions about Toronto’s transit future that go well beyond Scarborough itself, and I will turn to those issues in a separate article.

Continue reading

The Siren Song of Regional Fare Integration

The Toronto Region Board of Trade recently published a discussion paper on the subject of regional transit integration focused on fare structure and the barriers it creates to regional travel.

See: Erasing the Invisible Line: Integrating the Toronto Region’s Transit Networks

This is to be the first of four papers with others to follow on subjects such as increasing utilization of the regional rail network and improving service on the local bus networks around the GTHA. No publication dates have been announced for the remainder of this series.

The absence of those papers leaves the first one on fare integration out on its own missing some of the context that drives choices of what might make an appropriate “solution”. In particular the key roles of both GO Transit and local transit systems, or at least as the Board of Trade might see them, inform the proposal of a new fare structure, but more as background. Are these assumptions valid and does a new tariff based on them actually stand up to scrutiny?

Schemes to unify the regional fare structure have floated around the GTA for years. Lots of ink was spilled on reports, models and consultation. Nothing much has actually happened, or at least that’s the impression one might get, in part because different players have different goals.

Metrolinx is absolutely wedded to a zone fare system because that is how their fare collection technology works. They speak of it as “fare by distance”, but their zonal structure contains many inequities because it evolved piecemeal along with their network. Long trips are cheaper than short ones, measured in cost/km, both to discourage short-haul riding and to give greater incentives to long-haul commuters to switch from their cars to GO’s trains. Relatively recently, GO introduced reduced short-haul fares so that it could attract more short trips, but the tariff as a whole remains a patchwork.

When Metrolinx first proposed a distance-based regional fare strategy, it had an added wrinkle with a premium fare for “rapid transit” which meant anything on rails on its own right-of-way including the subway. Any trip longer than 10km (slightly above the average trip length on the TTC) would cost more than it does today, and drawing 10km circles around various centres easily shows who would pay more to travel. This had the effect of preserving GO Transit’s revenue stream, while raising the cost of subway travel for longer-than-average journeys.

This was in aid of a “zero sum” solution where the cost of lower fares for riders crossing the 905-416 boundary would be recouped from higher fares within Toronto. Metrolinx showed only a few sample fares to illustrate changes, but neglected to present a thorough review of the effect on TTC riders who are by far the majority of transit users in the GTHA.

In time, Metrolinx, or at least some members of its Board, came to realize that this was not a viable solution, and that any new fare structure would require added subsidy to avoid penalizing one group of riders to reduce fares for others. Alas, nothing official ever came of this.

The regional transit agencies were not sitting still, however, and the now-universal fare model is based not on distance travelled, but on the elapsed time for one or more trips, in effect a limited duration pass. Not only is this scheme easy to understand and administer, it removes a long-standing penalty against riders who took multiple short trips, typically to run errands or stop off in a longer journey just as one would do as a motorist.

Even Toronto, after much foot-dragging, embraced the two-hour transfer when it became politically beneficial. What was once portrayed as an unaffordable fare giveaway morphed into a modest-cost change that greatly simplified fares and improved system convenience. The only remaining gap in this arrangement is the lack of reciprocity across the 416-905 boundary so that a two hour fare can buy rides inside and outside of Toronto.

The odd man out remains GO Transit, a regional, long-haul carrier, an operator of fast trains where two hours would take a rider a far greater distance than on a bus, streetcar or subway. There will always be a conflict between seeing GO as a “rapid transit” line serving local demand as opposed to “commuter rail”. Just to complicate things, GO buses fall somewhere in between because they operate limited stop service with much more comfortable accommodation than, say, the Dufferin bus.

GO faces an additional problem with a penny-pinching master at Queen’s Park for whom spending more money on transit operations (as opposed to capital construction) is not a priority. Even the GO-TTC co-fare was eliminated although it remains in place for GO-905 travel. It is ludicrous that a “first mile” trip in the 905 gets a co-fare subsidy, but not one in Toronto.

Continue reading

Plans for GO Expansion Omit Key Features

Metrolinx has launched another round of consultation for various projects that make up the GO Transit Expansion Plan. Information on these is scattered through various pages on their site.

The consultation runs until December 11, 2020.

There is an interactive map of locations where changes are proposed, although it can be tedious to navigate because the default map does not have street names. (You can change this by selecting a different base map from the options in the upper right of the display.)

This map shows roughly the location of the Ontario Line corridor, but gives no detail about extra space, although the map is not to be taken as definitive. Nothing is shown of potential stations for the OL, and there is no information at all in the map for the several proposed SmartTrack stations.

This means that the scope of the project review and the combined effect GO Expansion will have with other projects is not known. Moreover, it would be foolish to approve a project based on a spec that did not include two major additions that are somewhere in the Metrolinx pipeline.

Stations, be they for the Ontario Line or for GO/SmartTrack require platforms and circulation elements (stairs, elevators, roads) but there is no hint of the space these will take.

Continue reading

Expanding Bloor-Yonge Station (Updated)

Updated October 25, 2020 at 9:30 pm: Illustrations have been added or replaced to provide higher resolution versions that were issued as part of the TTC Board Meeting presentation.

Plans for the expansion of Bloor-Yonge Station have reached another milestone with revelation that the project will have some effect on the buildings above and around the subway structure. This was not really a surprise, and some of the structural challenges have been acknowledged in past reports.

For this iteration, however, the need for more platform and circulation space triggered negotiation with affected property owners who may view this as an opportunity to reconfigure their buildings.

To put everything in context, here is a bird’s eye view of Bloor and Yonge showing the existing subway structure. North is at the top.

Yonge Station lies on a diagonal between, roughly, Bloor Street East and Park Road (the east end of the Hudson’s Bay building) and the northern half of the block on Yonge between Bloor and Cumberland. The building at 2 Bloor Street East (northeast corner) actually sits on an underground bridge because of local ground water conditions and a nearby stream that continues to appear from time-to-time within the station.

1877 Map of Yorkville by Silias James from the Toronto Public Library

The original Yonge line is east of Yonge Street and its alignment is easy to spot from the surface by a succession of parks and parking lots above the subway where once there were buildings.

Source: Google Maps

Before the Bloor-Danforth line opened in 1966, there was a fare-paid transfer station in the middle of Bloor Street where passengers switched between the subway and extremely frequent streetcar service. The problem of moving people between the Yonge and Bloor routes has been with us for a very long time.

Photo from Transit Toronto

A painting of the proposed Yonge Station by Sigmund Serafin from 1957 shows how the then-new Yonge Line would relate to the proposed station on the Bloor Line. Note the red Gloucester cars on the Bloor line. That’s what everyone thought of as a subway train in those days.

[Many decades ago, I rescued this painting and others from a TTC housecleaning binge. It is now in the collection of the City of Toronto Archives Fonds 16, Series 2449, Item 1]

The connections to the streetcar platforms are now walled off, but they were behind a row of fluted aluminum columns about a third of the way down the platform.

The platforms on the Bloor Station (Line 1) level were expanded decades ago to double their width over much of their length, and the east and west concourses were also expanded to provide more circulation space. However, problem remain on the Yonge Station (Line 2) level where a single centre platform is shared by both directions. It is often crowded and can be dangerous when service is suspended.

The map below shows the site and the degree to which the structure will be expanded. Most of the new construction will be under Bloor Street but some will be under existing buildings on the northeast corner of the Bloor-Yonge intersection. Exactly how this will affect the buildings is unknown because details of the property agreements are in a confidential appendix to the report.

The important point about this land is that it is still owned by the City and is leased. The expanded station will require changes in the lease arrangements.

On Line 2, a new platform will be added south of the existing structure. This will separate eastbound and westbound passengers. The new platform will have its own connections to the upper level into expanded concourse areas, as well as a link to the exit onto Yonge Street at the west end of the station.

Also shown in the diagrams below are new fan plants (red). These are required to improve emergency ventilation at the station and bring it to current fire code.

Updated October 25, 2020: A second version of the plan has been added below (the “Concept Design”) from the presentation to the TTC Board. It is at higher resolution and gives a better site context. Figure 3 from the original report has been left here because it contains notes that are not in the presentation version.

At the north end of Bloor Station, the circulation space will be considerably increased and there also be new elevators linking the east and west concourse areas to the two Yonge Station platforms below.

Not shown in either the report nor the presentation materials is the layout for the fare control area one level up from Bloor Station. This will necessarily be affected both by the relocation of stairs, escalators and elevators, as well as by whatever changes might occur in the mall outside of the station itself.

This project is fully funded with contributions from Toronto’s City Building Fund, as well as the Provincial and Federal governments at a total cost of $1.5 billion. Design is expected to reach the 30 per cent level in mid-2021 for project approval. Final design would be completed in 2023 with an aim for the construction contract award in 2024. The completion date of 2029, before the Richmond Hill extension opens, drives the overall schedule for this project.

TTC Proposes Massive Fleet Plan

At its meeting on October 22, the TTC Board will consider a report setting out plans to purchase new buses, streetcars, subway trains and Wheel-Trans vans in coming years.

TTC Fleet Procurement Strategy and Plan

In an important departure from typical practice, the City is setting out its position including what can be achieved with already-committed City funding without waiting for confirmation of contributions from other governments. Both the provincial and federal governments will face voters sometime in the next few years, and this, in effect says “come to the table”.

The plan has many strong points although some important details are missing. Key to this plan is that it is a system plan, not a scheme for one tiny chunk of the network nor a flavour-of-the-day announcement from one politician.

Overview

The TTC proposes acquisition of hundreds of new and replacement vehicles over the coming years:

  • From 13 to 60 new streetcars from Bombardier to be delivered between 2023 and 2025.
  • Approximately 300 hybrid-electric buses for one or both of the two qualified suppliers to be delivered between 2022 and 2023.
  • Pending outcome of technical evaluation and product comparison work now underway, approximately 300 all-electric long-range buses in 2023 to 2025.
  • 70 Wheel-Trans buses for delivery in 2022 and 2023.
  • 80 subway trains to replace the existing fleet now used on Line 2 and to provide for future service improvement with ATC (automatic train control).

That list is only part of a larger scheme shown in the table below.

The “ask” for funding on these projects is based on the full quantity of vehicles (column 2 above) as opposed to what the TTC can achieve with only the City’s contribution (column 3).

A political problem for the TTC is that they are seeking funding for the ten year plan within the next few years even though some of the spending is in the latter part of the decade.

For example, the buses are unlikely to be contracted on one big purchase that would lock in a single supplier, and a new contract would be tendered two or three times during the decade. Similarly, the quantity of Wheel-Trans buses represents far more than one fleet replacement (as of June 30 there were about 280 WT buses). Part of this funding would not be required until late in the decade when the next purchases would be at end-of-life.

Commitments that far off are unlikely to be made by either the provincial or federal governments both of which would face at least one if not more elections in the meantime.

A further issue is that there are many more projects in the TTC’s long-range capital plan than the ones listed here, and there is no sense of relative priority for things like ongoing infrastructure maintenance. If the vehicles program soaks up all available funding, other projects could find that the cupboard is bare.

Missing from this report is an overview of the cash flow requirements for each project and the point at which money for each component must be secured. Projects with long timelines such as ATC installation need early commitment even though they would not finish until late in this decade or possibly longer. The same does not apply to the cyclic renewal of the bus fleets and some of the associated infrastructure.

TTC footnote 1: Estimated vehicle procurement quantities are based on Class 4 cost estimates. Given the need exceeds the funding currently available, TTC will seek to maximize the final number of vehicles to be procured through negotiation of contract unit pricing.

To support the electric vehicle purchases, the TTC together with Toronto Hydro and Ontario Power Generation (OPG) are working on plans for the charging infrastructure that will be required to move to a zero emissions fleet by 2040 in regular buses, Wheel-Trans and non-revenue vehicles.

The subway train order will likely grow because Metrolinx would piggy-back the needs of the Yonge North extension to Richmond Hill and the Scarborough extension to Sheppard for economies of scale and consistency of fleets on the two major rapid transit lines. However, the cost will be on Metrolinx’ account because these are now provincial projects. There is a danger that if future provincial funding is constrained, the provincial projects could elbow aside requests for local projects.

The committed and required funding amounts are set out below.

TTC footnotes:
1: Number of Vehicles reflects the current fleet plan as described under the Comments section of the report.
2: Estimated Total Costs includes the following: (1) vendor contract payments for vehicle design, production, delivery and commissioning of vehicles; and (2) delivery costs including procurement, project management, engineering, quality assurance, and project contingency
3. Total Estimated Cost has been revised from $5.84 billion (Class 5) to $6.17 billion (Class 4).

The City’s share is provided by the City Building Fund, a supplementary property tax introduced in the 2020 budget, together with funding that had been allocated to a planned rejuvenation of the Line 2 subway fleet for an additional decade of service. Now that those trains will be replaced, the money set aside to refresh the old fleet is available for this project.

City Building Fund Project$ millions
Bloor-Yonge Station Expansion$500
Line 1 Capacity Enhancement$1,490
Line 2 Capacity Enhancement$817
Line 2 Automatic Train Control $623
Other Critical Subway State of Good Repair (Note 1)$160
New Vehicles and eBus Charging Systems$1,140
Total City Building Fund$4,730
Note 1: These values do not exactly match numbers cited in the TTC report due to rounding.

The vehicle procurements are funded on the City side by a combination of CBF monies (see above) and the previous allocation for renovation of the Line 2 fleet of T1 trains.

Project$ millions
80 New Subway Trains$ 623
T1 Overhaul and Maintenance to 2030$ 74
Procurement of Buses$ 686
eBus Charging Infrastructure$ 64
Wheel-Trans Buses$ 22
New Streetcars$ 140
Total$1,609
Existing Approved Funding (T1 Life Extension)$ 474
City Building Fund$1,140
Total$1,614

Combining the $1.61 billion above with the Line 2 ATC funding brings the City’s total to about $2.2 billion. The TTC and City invite their partners at the provincial and federal levels to make up the difference of just under $4 billion between City allocations and the total required for this portion of the overall capital plan.

The City’s strategy is to start spending its $2.2 billion and hope that the other governments will come in for their share. There are elections at both levels that could provide some leverage, but there are also problems with Toronto’s appetite for capital compared to other parts of Ontario and Canada.

Continue reading

Toronto Council Pursues Details of Metrolinx Projects

An ongoing problem for anyone attempting to work with Metrolinx on their projects is the lack of transparency, the fog through which details emerge, if at all, on what they actually propose to do.

Distrust of Metrolinx to deal fairly and honestly with communities and their political representatives led to widely-supported motions when Council considered two reports regarding Metrolinx projects on October 1, 2020:

Included here are Council motions regarding:

Also included are recent replies to queries from me about the Ontario Line.

Continue reading

Drifting Timelines on Metrolinx Projects (Fall 2020 Update) (Revised)

Back in June 2020, I wrote about the gradual drift in the planned dates for various Metrolinx projects as reported by Infrastructure Ontario [IO for short].

See: Drifting Timelines on Metrolinx Projects

The September 2020 Market Update has been issued by IO and it shows changes in some projects from the June update.

Sept 26, 2020: Revised to include the change in financing method for the OnCorr GO Corridor project.

Is The P3 Model Falling Apart?

Two revisions in the large GO project procurement model involve a change from private sector financing to traditional government borrowing.

This suggests that the market willingness to finance projects on behalf of the government, or at least to do so at rates competitive with direct government borrowing, may be on the wane. That implies that the “P3” model may be coming unglued.

At its heart, this was always seen as an accounting mechanism to shift debt off of the government’s books, and without this shell game, a major argument for P3s could vanish.

The Future of Electrification

The change in financing model could shift any decision on propulsion technology back to the government.

Metrolinx had pushed this off its plate by saying that the bidders who were going to design and operate a future GO network would make that choice. This punted the knotty political problem of hydrogen trains touted former Premier McGuinty out of Metrolinx itself.

Will Ontario be willing to finance the large up-front capital costs of electrification itself with so many other pressures on financial resources, or is electrification about to fall out of consideration while spending focuses on service expansion?

Ontario Line

The project is in three sections of which the last will be the “Northern Civil, Stations and Tunnel” which includes the portion of the line east of the Don River and north to Eglinton, but not the Maintenance Facility which is included with the “South Civil” portion as it is needed relatively early in the project.

Some of the work on the North section between the Don River and Gerrard Station might be undertaken as part of the GO Corridor improvements, but exactly what this might entail has not been made public.

Since the last update, there are three changes for the North section:

  • The date for RFQ (Request for Qualifications) issue has been changed from Winter to Spring 2022.
  • The RFP (Request for Proposals) issue has been changed from Spring 2022 to Fall 2022.
  • The Financial Close (in effect, the contract signing) has been changed from Fall 2023 to Spring 2024.

The remaining portions of the line are on the same timeline as before.

The timelines for this project, with financial close for the first two portions in fall 2022 and for the third in spring 2024 puts this beyond the next provincial election expected in mid 2022, the four-year anniversary of the Ford government’s election. Who will be in place to make final decisions, and what the government’s financial position will be by then, remain to be seen.

Line 2 East Extension (Scarborough Subway)

This project is now shown with two portions: one for the tunnel, and the other for the stations, railway and systems.

There is no change in the tunnel portion of the project, but the remaining portion has reverted to the dates shown for the overall project in the Winter 2020 update.

GO Expansion Lakeshore West Corridor

The financial close for this project has been changed from Winter 2021 to Spring 2021.

GO Expansion Lakeshore East-West Corridor

This was originally to have been a “Build-Finance” project, but it is now “Design-Bid-Build”, a change that was made in August 2020 according to the IO report.

GO OnCorr Projects

[Added to this article on September 26, 2020]

This is a very large project including future operation of GO Transit and possible changes in the propulsion technology.

The procurement model has been changed from “DBOFM” (Design-Build-Operate-Finance-Maintain) to “DBOM”. The proponent will no longer finance the project which has a projected value of over $10 billion.

All other projects are unchanged. A summary of the Metrolinx projects tracking their changing status is available in this spreadsheet (revised version).