Toronto’s Board of Trade Contemplates Transportation

Prologue: When I started to write this story, John Tory was still Mayor of Toronto and the dynamics of City-Province relations assumed he was in charge. The context for these discussions was soon to change.

The Toronto Region Board of Trade holds a yearly “transportation summit”, and on February 8, 2023, this focused on the Greater Toronto Area’s transit, plans for the future, and the aftermath of the covid pandemic.

The TRBoT is no wild-eyed radical institution. The regional economy and businesses are at the heart of causes it advocates.

Both in the introductory remarks and in comments by speakers sprinkled through the day, the economic effect of traffic congestion was a mantra. This sets the framework for the importance of both transit and road projects, depending on who is speaking. The latest factoid describing Toronto’s problems is that we have the third worst congestion in North America and the seventh worst in the world.

CBC: Toronto ranks 3rd most congested city in North America. Here are the city’s worst traffic spots

A problem with this hand-wringing is that there is little acknowledgement that some particularly bad locations are related to major infrastructure projects such as the Gardiner Expressway rebuild and various rapid transit lines. Moreover, goods movement has severe problems in areas that historically have poor transit and show little chance of seeing any in the near future. No single project will solve the problem of many-to-many trips patterns that now depend almost totally on roads and private vehicles.

Continue reading

Infrastructure Ontario’s April 2021 Update

Infrastructure Ontario issues quarterly updates about the projects it is managing for P3 procurement, and I have been tracking the transportation items on this site. Their April 2021 Market Update came out on April 8, but I have been waiting for clarification of some issues before posting here.

Here is a spreadsheet tracking changes in project status since these updates began.

Items highlighted in yellow have changed since the last update.

Note that this report only covers the procurement portions of Metrolinx projects that are undertaken through Infrastructure Ontario. Contracts that are in construction, or are directly tendered and managed through Metrolinx outside of the P3 model, do not appear here.

Ontario Line, Line 1 North Extension (Richmond Hill Subway), Line 4 Sheppard East Subway

There are no changes to these projects in this update.

Line 2 East Extension (Scarborough Subway)

As previously announced, the tunneling contract gets underway this spring. The contract for the remainder of the project (stations etc.) enters the Request for Qualifications (RFQ) stage this spring/summer, but contract execution is not expected until spring 2023.

Note that vehicles for the extension will be procured as part of a TTC order for fleet expansion and renewal that does not show up in the IO updates.

Line 5 Eglinton West Extension

As previously announced, the tunneling contract gets underway this spring. There is no date yet for the remainder of the project to enter the RFQ stage.

GO Expansion Projects

Metrolinx came up with a new term for procurement, the “alliance” model where more responsibility for the project is shifted back onto Metrolinx as owner rather than expecting bidders to take on a substantial project risk. This showed up in the Union Station platform expansion project early in 2020.

In this round of updates, things appear to have gone a step further. Three projects (Lake Shore East and West Corridors, and the Milton Corridor) are reduced in dollar value. I asked Infrastructure Ontario about this, and they replied:

Since the previous Market Update (Dec 2020), there have been some changes in scope of work for these projects. Items which have been descoped may be carried out by Metrolinx in the future under separate, traditionally-procured contracts. The intent is to better manage risks and costs with respect to the GO Expansion program.

As these projects remain in procurement, we will provide further updates this spring/summer.

Email from Ian McConachie, IO Media Relations, April 9, 2021

Specific changes by corridor:

CorridorChange (per Infrastructure Ontario)Previous CostUpdated Cost
Lakeshore WestDescoping of Exhibition Station in-corridor enhancement works and track improvements, Clarkson Station and Bronte Station in-corridor enhancement works.$500M-$1B$200-500M
Lakeshore East-Central Descoping of Scarboro Golf Club Works and 2.5km of grading (previously part of LSE-E) and deferral of Highland Creek Expansion $200-499M$100-200M
Milton Descoping of Station Operations West Facility and replacing the pedestrian tunnel with a pedestrian bridge. $100-199M< $100M

The project formerly called “Milton Corridor” is now called “Milton Station”.

A separate project line, Lakeshore East-West Corridor, dropped off of the IO Update in mid-2020. The project was transferred to Metrolinx for delivery as a non-P3 contract.

The comment about “better manage risks and costs” is telling here, and it implies that the P3 model has not worked out as favourably as hoped for all of Metrolinx’ work. In some cases it is simpler and cheaper to just go out and buy/build something yourself than to set up elaborate machinery for others to do this for you.

Notably the $10B GO “ON-Corr” project which entails a complete restructuring of GO including future operation, maintenance and electrification has not changed status in a year. With GO’s ridership uncertain in the near term, projecting just what Metrolinx might ask a P3 to undertake, let alone contracting for it, is like peering into a very cloudy crystal ball.

Toronto Council Pursues Details of Metrolinx Projects

An ongoing problem for anyone attempting to work with Metrolinx on their projects is the lack of transparency, the fog through which details emerge, if at all, on what they actually propose to do.

Distrust of Metrolinx to deal fairly and honestly with communities and their political representatives led to widely-supported motions when Council considered two reports regarding Metrolinx projects on October 1, 2020:

Included here are Council motions regarding:

Also included are recent replies to queries from me about the Ontario Line.

Continue reading

Metrolinx Board Meeting: November 22, 2019

The Metrolinx Board met on November 22, 2019 with its usual mixed agenda of private session and public items. This article deals with the following public reports and mainly with the Kitchener and Niagara Falls business cases.

Continue reading

Comfirm or Deny: Big Changes Coming to GO Bus Service

Over the past weekend, a post appeared briefly on Facebook describing proposed changes to GO Transit bus service that were presented to ATU Local 1587 members on Wednesday, July 17. Normally I would take info like this with a grain of salt based on decades of hearing various half-baked stories about TTC plans that pop up from railfan speculation and internal TTC rumours. However, this was too detailed a list and from a first-hand source, and it cannot be ignored.

Updated July 23, 2019 at 8:55 am: The following email was sent to me by ATU 1587 who represent the GO Transit Workers:

A.T.U. Local 1587 was not aware of a posting on social media of service cuts produced by Metrolinx. It was brought to our attention from you, Steve. Thank you.

Metrolinx has however, brought to the union, approx. a month ago, of service cuts in bus that affected Beaverton, Oshawa, Waterloo, Bolton, Cambridge.

Metrolinx is trying to reduce bus service, and force passengers onto trains, which means less local access for our passengers. If there is local transit, then they will have to take that system and  transfer once they are close to a GO station, if not then they will have to use their personal vehicle.

Our members provide an excellent service overall. We don’t however, create the schedules of where we go or don’t go. Our members have voiced their disbelief about the cuts to trips not only for our seniors that use our service for appointments, but our university students as well. Everyone who uses GO Transit/Metrolinx is using us for a reason. Our members are proud of what they do, helping those with disabilities, seniors, children, etc. The pride does not stop at our drivers. Everyone from plant maintenance to station attendants, to our coach tech’s (mechanics), transit safety officers, OFPT. We are all proud of the job we do for the public, our passengers.

Thank you,

Christine Broeze
President/Business Agent
A.T.U. Local 1587

Updated 4:44 pm July 22: Metrolinx claims that the information posted on Facebook is not true.

The rumours are not accurate.

Buses form a vital connection between trains and communities not connected to train service or with limited train service.

Buses will always be an important part of our regional transportation plan. In fact, we are actively recruiting bus drivers to join our team.

We currently have a fleet of 532 buses and approximately 420 are used for service. We have more buses on the road today than we ever have and every year since our existence they have increased.

We are always monitoring our services to ensure we are making the best use of our resources.

We are embarking on the largest expansion of rail service in our history.

At times, when new train service is introduced it makes sense to redeploy bus services to other communities. Trains can carry far more passengers and shorten the trip.

It is difficult for us to comment on the presentation made to union members as we were not there. [Email from Fannie Sunshine 4:35 pm, July 22]

Original post below:

Continue reading

Metrolinx Board Meeting: February 7, 2019 (Updated)

Updated February 10, 2019 at 9:00 am: Notes from the Board meeting have been added at the beginning of this article.

Relief Line Business Case

When the agenda was released, the Relief Line report created quite a stir with an apparent shift in Metrolinx’ position on the staging of subway expansion projects. Where “relief” taking precedence over the Yonge north extension only referred to the southern section (Pape to Osgoode), Metrolinx now shows a shortfall in capacity if the northern section (Danforth to Sheppard) is missing from the network.

This prompted a letter from Frank Scarpitti, Mayor of Markham and Chair of the York Region Rapid Transit Corporation Board. The heart of Scarpitti’s objection is that the Metrolinx report uses a mixture of demand models and assumptions to arrive at its conclusion, and that this is out of step with previous studies and approvals.

The Relief Line Business Case Development presentation paints a flawed picture of the ridership modelling work being undertaken by Metrolinx, in conjunction with York Region and City of Toronto staff. The vague and contradictory information being used to update the public on slide 7 regarding Line 1: Ridership Demand and Network Effects has, once again, pitted two critically needed infrastructure projects against one another, namely the Relief Line against the Yonge Subway Extension. This positioning is not supported by the ridership modelling analysis and is at odds with the advice and information presented by Metrolinx at a recent meeting.

On June 25, 2015, Metrolinx released the results of the Yonge Relief Network Study to the Board. Supported by a Stakeholder Advisory Committee and a Peer Review Panel, the Board endorsed the finding that “With the Yonge North Extension, the Yonge Subway will still be under capacity.”

The Relief Line Update uses a blend of data and methodologies to make broad assumptions about future ridership. Each subsequent ridership model claims to have better information, more detail and more sophisticated analysis. Some models include independent findings and more recently, to our objection, some have been relying heavily on market driven employment and population data, contrary to the required obligation of all municipalities to follow the Provincially-mandated “Growth Plan” numbers.

The Relief Line Update being presented to the Metrolinx Board on February 7, 2019 has, according to Metrolinx staff, blended the findings of at least three different models and does not accurately represent any of the individual modelling analyses. Slide 7 suggests that, in 2041, Line 1 will be below capacity and then over capacity when the Yonge Subway Extension is added. This is completely inaccurate – current Metrolinx modelling shared as recent as January 21, 2019 demonstrates that the Yonge Subway Extension adds a relatively minor number of riders to the peak demand location and, in no case, is it the cause of Line 1 becoming over capacity.

The facts are that only 20% of the new riders on an extension of the Yonge Subway line would be headed south of Bloor. Ridership growth on Line 1 is directly related to population and employment growth in Toronto. In fact, models show that ridership on Line 1 will exceed capacity regardless of whether the Yonge Subway Extension is constructed. We believe that by promoting the shift of as little as 10% of people from peak hour travel from the Extension to the Richmond Hill GO Line, and by using fare structure and level of service incentives, that substantial relief on Line 1 can be achieved while the Yonge Subway Extension is being constructed.

Modelling also shows that the majority of riders (80%) on the Yonge Subway Extension are headed to Toronto’s uptown employment centres north of Bloor, including St. Clair, Eglinton and York Mills. Furthermore, the Yonge Subway Extension will also serve a large number of Toronto residents that work in York Region Other initiatives are underway, or should be underway, to alleviate Line 1 capacity problems. Metrolinx’s 2015 study concluded that a number of planned and funded initiatives such as Automatic Train Control, more Rocket Trains, GO Expansion, and the opening of the Line 1 extension to Vaughan Metropolitan Centre will add capacity and offload the Line 1 demand.

These are serious challenges to the professional quality of work presented by Metrolinx planners.

The June 2015 report cited here was the Yonge Relief Network Study and it contains the quotation about the subway remaining under capacity even with the Yonge North extension. However, this depends on a number of factors:

  • The model year is 2031
  • Then-current projections for population and jobs
  • Assumed diversion levels for ridership to TYSSE and GO RER, net of demand added by new projects especially the Crosstown LRT at Eglinton

The reported projected that the volume/capacity ratio would have been 96% (2031) over the peak hour meaning that the super-peak would be above the line. The claim that the subway would still have capacity is “true” only on average and with no headroom for growth. Metrolinx planners should have known better to make that statement in 2015.

Metrolinx staff pointed out:

  • They are modelling for 2041, ten years later
  • The 2016 Census shows that core area employment is growing faster than predicted
  • Modelling now includes factors for latent demand and safety considerations at stations and platforms
  • If there is no alternate relief in place by 2041, the Relief Line North will be required

Staff also reported that although the Relief Line South approved concept (Pape to Osgoode via Carlaw and Queen) has a positive Business Case, the value is only slightly above 1.0. All six of the options were close to 1 and so the distinction between them is not as strong as the simple over/under status in the report might imply. With only a small positive margin, factors such as cost control and encouragement of Transit Oriented Development along the line will be important to maintain the supposed benefit.

CEO Phil Verster argued strongly that building the Relief Line does not preclude building other projects. His concern is to build more transit and build faster. Metrolinx is looking at (unspecified) new technology and innovation from industry to speed up the process. More than one line could be built concurrently, but the critical point is to open them in a sequence that causes the desired redistribution of demand.

Verster admitted that Metrolinx has not done enough to look at the Richmond Hill GO corridor for its potential contribution to relief.

A Board member asked whether the staff have identified a “tipping point” in safety for their studies. There is not a single value, but rather a variation from one location to another depending on local demand, station geometry and passenger flows.

Unspoken through all of this was the years of delay in admitting that a problem even exists, let alone of doing something about it. GO’s ability to provide relief has been downplayed for various reasons including the need to regrade the south end of the line to make it flood-proof, the winding valley route’s limitation of travel speed, and operational conflicts with CN’s freight traffic that limit GO capacity to Richmond Hill. Meanwhile, candidate John Tory’s SmartTrack campaign claimed that his scheme would eliminate the need for a Relief Line, and TTC projections did not raise alarms about capacity and safety issues until the situation at Bloor-Yonge could not be ignored.

“Relief” will not come from any one line or project, but from the contributions of several.

Financing and deliverability studies will be reported in spring 2019 for the Relief Line South, and a preliminary business case for the Relief Line North will be available by year-end.

This entire exchange shows the problems brought on by oversimplified presentation decks for the Board. In their oral remarks, Metrolinx staff displayed a more extensive grasp of the issues and details than contained in the Powerpoint deck.

Continue reading

A Few Questions For Metrolinx (II) (Updated)

Updated April 15, 2018 at 6:00 pm: Comments about projected demand at Park Lawn Station have been added at the end of this article.

In a previous article, I reviewed the Metrolinx technical report on the performance of proposed new GO and SmartTrack stations as part of their overall network. At the time, there was some debate about the validity of the report’s analysis.

Metrolinx has now produced a backgrounder to this report which gives greater details about their methodology and results.

This information is interesting not just in its own right as part of GO’s planning, but also in its implications for the City of Toronto’s expectations for GO/SmartTrack service. The service levels listed in the City’s report date from a Metrolinx plan approved by their board in June 2016. The levels shown in the backgrounder are different, and reflect the change to a mix of local and express trains in the GO corridors. The backgrounder takes pains to emphasize that the service plan is not definitive, but the express/local mix of trains is an essential part of GO’s strategy as approved at a recent Board meeting.

The report begins with an introduction common to such documents laying the basic process for “business analysis” of new proposals. This is summarized in the following diagram. The model focuses on a few key factors:

  • The degree to which riders are lost from GO because the addition of stops reduces the competitiveness of GO travel versus driving.
  • The degree to which riders shift to a new station thereby reducing their travel time.
  • The number of new riders who previously drove and are enticed onto transit by the new station.

This scheme underpins recent changes in the planning for services notably through the benefits conferred by a combination of express services (avoided delays from new stations) and level boarding (reduced station dwell times generally). The technical details of “level boarding” have yet to be revealed, but the analysis assumes a benefit through the elimination of the step between platforms and the interior of trains.

The benefits of electrification in reducing overall travel times and allowing for more closely spaced stops are not mentioned at all, and travel time comparisons are based on an electrified service as a starting point. Metrolinx has effectively discarded one of the arguments they used in advocating electrification in the first place.

Continue reading

Who Will Pay For SmartTrack?

Toronto’s Executive Committee will consider a series of reports on the proposed SmartTrack project and related matters at its meeting on Tuesday, April 17, 2018.

These reports set in motion several aspects of the GO/RER/ST program, although the primary focus is the funding the the new SmartTrack stations which is a city responsibility. This article deals with the main report and the first two attachments.

Attachment 3 is a compilation of the information on the proposed new stations that has already been discussed in my previous articles on the public meetings.

Attachment 4 explains the link between SmartTrack and plans for significant changes to the road network in the St. Clair, Keele, Old Weston Road area including widening of St. Clair through the railway underpass and extensions of various roads to fill gaps and provide additional paths for traffic flow. The new station at St. Clair and Old Weston/Keele would be constructed based on the new layout, and work on these projects will be co-ordinated.

Attachment 5 was prepared by Metrolinx. It sets out the status of the many changes to various rail corridors that are within the City of Toronto.

Attachment 6 illustrates the planned new south platforms and concourse at Union Station, an expansion project separate from the renovation of the existing station now underway. Of note in the design is the replacement of four tracks by two making room for a pair of much wider platforms than in the older part of the station. From a service design point of view, these tracks and platforms will likely be the new home for the Lakeshore services as this will allow them to operate along the south side of the rail corridors free of interference with traffic from the more northerly corridors like Milton/Kitchener/Barrie to the west and Richmond Hill/Stouffville to the east.

(Metrolinx has already talked about the need to consolidate trackage and platforms in the old part of the station to improve capacity both for train service and for passengers, but that is beyond the scope of the city reports.)

The current report deals only with the SmartTrack stations. Specifically it does not address:

  • The Eglinton West LRT which, having replaced a part of the original SmartTrack scheme, is still bound up with ST as part of the total budget number for this project.
  • Operating and maintenance costs for GO/ST service.
  • The cost to the city of “fare integration” or even exactly what this will mean.

A further problem, as I discussed in a recent article, is that recent changes in the Metrolinx/GO service design for various corridors has changed the mix of local and express trains on which the SmartTrack scheme rests. Metrolinx has still not explained how they will operate the number of trains the city report claims will stop at all of the “local” SmartTrack stations, and they are quite testy on the matter when pressed. For its part, the city assumes a service level (and hence attractiveness of service) greater than what Metrolinx has, so far, committed to operating.

The works that are included in the report are:

  • Six new GO/SmartTrack stations at Finch, Lawrence East, Gerrard/Carlaw, East Harbour, Liberty Village and St. Clair/Old Weston.
  • Additional city requirements for station facilities that are not strictly required for operation of the transit service.

Continue reading

A Few Questions For Metrolinx

The recent publication of updates to the New Stations review together with information at two public SmartTrack station meetings raises several questions about Metrolinx plans and their methodology in evaluation of the worth of new facilities.

In attempting to dig through the contradictions, I asked Metrolinx for the detailed background reports for their updated “business cases” for new stations, and was advised that there are no reports beyond the technical paper that is part of the board’s agenda for their March 8, 2018 meeting.

This is not a credible statement.

The evaluation of new stations depends heavily on the projected demand at each location. This demand depends on several factors:

  • The frequency and capacity of service provided at the station
  • The travel time to destinations for trips served by the station
  • The cost of a trip
  • Feeder services for riders including connecting transit routes and parking lots

Land use patterns around the station are also a factor, but they are secondary in two senses. First, demand projections are generally run against a fixed land use model while changing other factors such as service frequency and cost. Second, land use is not under the direct control of a transit agency while service and fare factors are, and they can have a much more immediate effect on demand.

The newly modelled demand for stations follows on from the Initial Business Cases (IBCs) of 2016:

The overall methodology and approach to modelling used in carrying out the business case analysis is consistent with the approach used in undertaking the 2016 IBC’s and has been independently peer-reviewed and validated. In particular, the current business case analysis measures and captures the same key benefits (e.g. new station users benefit from the station) and impacts (e.g. delays to upstream riders due to the station). The current business case analysis for new stations take advantage of updated input information, including GO rail service assumptions, land use, connecting rapid transit infrastructure, and a refined approach to ridership forecasting and modelling.

The economic and financial cases for each new station depend on forecasts of how travellers will respond to the presence of a new station. Stations can support increased system ridership by providing a new access opportunity that may be closer to household locations and employment, school, or other travel destinations. Individuals who use the new station benefit by saving time relative to their previous travel option – travelling farther to another GO station, or using a different transport mode such as subway, bus, or auto. Existing GO passengers that do not use the station, on the other hand, can be delayed if they travel on a train that now stops at the new station. Examining travel time savings, delays, and modal shifts is the focal point of the business case analysis. [p 7]

Metrolinx is all about “transparency”, and in that spirit here are several questions about their models and plans.

Continue reading

New SmartTrack/GO Station Designs

In two recent articles, I wrote about new stations that are proposed on some of the GO corridors, and their recently updated evaluations and designs:

The reports did not include any illustrations of the proposed designs, but these are starting to appear through the SmartTrack station consultation meetings. As they become available, I will post excerpts in this article.

The March 1 meeting dealt with four stations on the west side of the old City of Toronto. The presentation materials are not yet online, but I have included excerpts from them here.

Among the issues discussed in an earlier round of meetings were:

  • Noise during the construction period, and later from trains including the bells which sound as they enter and leave stations.
  • The service plan – what will be the frequency of service through and at each station?
  • Fare integration – what will the fare be for a combined TTC/GO trip?

A Metrolinx representative was somewhat evasive on the issue of noise on two counts. First, there is the question of how long it will be before the majority of service will be electrified. If one believes the original electrification plan (cited by the Metrolinx rep), some trains will always be diesel on some lines because they will run into territory owned by other railways where electrification will not occur. Conversely, if one believes the optimistic claims of the hydrogen train study, all GO trains will convert to hydrogen-electric operation, although on exactly what timetable is unclear.

The noise of the bells raises two concerns. First is the question of whether there can be an exemption so that neighbours are not constantly annoyed by the bells of passing trains. The other is the methodology by which an “environmental assessment” treats transient noises like this. Past EAs have dismissed transient noises because they average out with lots of quiet time between trains, but this does not address the problem of occasional noises such as roaring engines or ringing bells. Moreover, with the planned increases in service levels, these noises will be present more frequently.

SmartTrack was described broadly in the following slide:

A pressing issue for most stations is the recently revised service plan that Metrolinx announced in its updated stations report.

Express (non-stop) and tiered service patterns typically have trains serving outer stations. They typically run non-stop past inner stations which are served for by other trains. Such tiered service patterns impact business case assessment in the following key ways:

  • Reduces the number of upstream riders that need to travel through the station. Upstream users that are travelling through may now choose to use a faster express train to reach their destination. This reduces upstream delays and the number of riders that switch to other modes. This will have a positive impact on station performance.
  • Reduced train frequency at stations without express service (i.e. trains that previously stopped at the station can now skip some stations). Riders may also divert to stations with express services resulting in a negative impact on station performance.

As the GO RER service plan is still evolving, a conceptual service plan has been developed for modelling purposes only, which considers the following express or tiered inner/outer service concepts on the Lakeshore West, Barrie and Stouffville corridors.

  • Lakeshore West corridor: Alternating trains with bi-directional 15 minutes service on the corridor with stops at Mimico and Park Lawn stations. Mimico and Park Lawn stations would therefore receive 30 minutes service inbound and outbound all day.
  • Barrie corridor: Outer service stopping at all stations between Allandale Waterfront and Aurora; trains will also stop at Downsview Park and Spadina stations, otherwise, express to Union Station. Inner services will serve all stations between Union Station and Aurora.
  • Stouffville corridor: All-stop peak direction outer service between Lincolnville and Unionville stations; trains will also stop at Kennedy and East Harbour stations, otherwise, express to Union Station. “Inner” services will stop at all stations between Unionville and Union Station.

This does not match the service plan adopted for RER in June 2016 where all trains would serve all stations, although that appears to be the plan staff at the March 1 meeting were working from.

The claim of “all-day two-way service, with more frequent trains during peak periods and every 15 minutes during off-peak periods” can be read to mean quarter-hourly service all day with even better peak service, or it can be read as “better service than you have today” during peak periods, but not necessarily every 15 minutes, let alone 10 minutes or below. As things now stand, the difference between Metrolinx’ updated service plan and the claims of SmartTrack service levels border on misrepresentation.

Continue reading