How Slow Is My Streetcar: Part I

At its November 2023 meeting, Council passed a motion proposed by Councillor Chris Moise whose ward covers the east side of downtown, and who also sits on the TTC Board:

1. City Council direct the General Manager, Transportation Services, in consultation with the Toronto Transit Commission, the Toronto Police Service, and the City Solicitor to review and report back to the Executive Committee in the second quarter of 2024, including:
a. an update on streetcar performance over the last five years;
b. suggested improvements to the public realm along King Street until the permanent capital project can be delivered; and
c. the feasibility of implementing automated traffic enforcement on the King Street Transit Priority Corridor, including details on what legislative amendments would be required to provincial legislation including, but not limited to, the Ontario Highway Traffic Act.

This article addresses point “a” with a review of streetcar lines over the past five years. It is important to go back to 2019 before the pandemic fundamentally shifted traffic and transit patterns downtown as a point of reference.

From time to time, there are calls to expand a “King Street” redesign to other parts of the network, but there are two “cart before the horse” issues to address first:

  • Figure out how to make King Street operate as it was intended and return at least to its pre-pandemic behaviour, if not better, as a model.
  • Understand how other streets operate including where and when problems for transit performance exist.

An update on transit priority will come to Council in February 2024, although this will look more widely at the city, not just downtown. In previous articles I have reviewed the growing problem of transit travel times as traffic builds on the proposed RapidTO corridors, some of which exceeded pre-pandemic levels some time ago. In future articles I will refresh these analyses with data through to the end of 2023.

An important distinction between most RapidTO bus corridors and the downtown streetcar system is the design of suburban vs downtown streets. In the suburbs, the streets are mostly wide, have relatively few points of access (e.g. driveways) or pedestrian oriented uses (e.g. shops), and travel distances tend to be longer. In the core, streets are narrow, mostly four lanes with no possibility of widening, access points are more frequent, there is a strong pedestrian orientation, and trips tend to be short. Even if buses were running, express operations would be almost impossible and would save very little time on the downtown routes.

There are exceptions such as some older parts of the inner suburbs that bring physical challenges for transit priority, but also the political challenge that the transit share of road use is lower as one moves outward from the core. King Street is a very different place from Steeles, and Dufferin is somewhere in between depending on which section one considers.

An important message in all of this is that “congestion” (put in quotes because it is so often cited as a get-out-of-jail-free excuse for all transit woes) varies from place to place and time to time. Simply putting transit priority everywhere will not solve all problems and could even be overkill (even assuming that it is true “priority” and not a sham to keep transit vehicles out of motorists’ way). It is simple to colour a bunch of key routes end-to-end on a map, but much harder to identify changes that will actually make a difference. Meanwhile, a focus on “priority” could divert attention from badly-needed improvements in headway reliability and more reliable wait times.

This article begins with a comparison of scheduled travel speed on each route, and then turns to actual travel speeds by route segment. In the interest of length, I will leave a discussion of headway reliability to future articles. This is an important component of total travel time, especially for short trips or trip segments.

I have also included tables showing the constant change in route configurations on the four major east-west corridors thanks to a never-ending procession of track and water main work, rapid transit construction, and overhead changes for pantograph operation. Some of this work was accelerated to take advantage of lighter traffic conditions during the pandemic, and some to bring forward work to keep staff employed.

However, the rate of route changes persisted well beyond the heart of the pandemic and threatens the credibility of transit service on major corridors leaving riders constantly wondering where their streetcar or replacement bus might be. Some changes occurred without the planned work actually taking place, or work started and ended later than announced (sometimes much later as in the never-ending KQQR project).

An important change over recent years, separate from the pandemic, has been the move to larger streetcars on wider headways. What might have been a tolerable unevenness in service when streetcars arrived every 4 or 5 minutes simply does not work for scheduled headways of 10 minutes with much wider swings. Bunching when it occurs leaves much bigger gaps between vehicles. A laissez faire attitude to route management, and especially the assumption that routes under construction cannot be managed, has led both to unreliable service and basic questions of how or if the TTC can recover the quality riders expect.

For all the talk of project co-ordination, the last people who seem to count are the riders. Simply studying raw travel times be they scheduled or actual does not capture the frustration, delay and despair from the ever-changing and unreliable services, be they by streetcar or bus.

Continue reading

TTC Subway & Streetcar Infrastructure Projects 2023-24 (Updated)

The TTC has published its planned schedule for various streetcar infrastructure inspection and repair projects for 2023, and a look-ahead to 2024.

See: Subway Closure and Streetcar Diversions – 2022 Review and 2023/2024 Forecast

This article was updated on January 19, 2023 at 8:45 pm with additional illustrations from a staff presentation to the TTC Board.

See: Board Report Briefing Subway Closure & Streetcar Diversions – 2022 Review and 2023/2024 Forecast

Subway

The full list of closures begins on p 13 of the report. There is a variety of full weekend, early closing and late opening events (check the legend to the chart).

There are fewer Line 1 closures in 2023 due to ATC (Automatic Train Control) than in 2022 because the main work is complete. However, there is a follow-up phase that will require some weekend closures for testing and implementation. Other work affecting Line 1 includes repair of station finishes on the University subway, elevator installation at Lawrence, various track replacements, and preliminary work at Finch for the Yonge North Subway Extension.

On Line 2, there will be work at Kipling to add a new storage track, preparatory work at Kennedy for Scarborough Subway Extension, preparatory work on the east end of the line for ATC installation, and some track replacement work. As usual there will be several late openings of service on Sundays for beam replacement on the Prince Edward Viaduct.

Many closures involve only an early shutdown of subway service to give a longer overnight maintenance window than would be possible with normal hours of service.

Streetcar

There is a long list of events for the streetcar system, but many of them are short interruptions of overnight/weekend work for inspections or minor repairs.

The major trackwork planned in 2023 is listed both in the report (starting on p 19) and on the TOInview map of City construction projects. The schedule implies that a good chunk of the streetcar system will be shut down at various times during the year. The Ontario Line contributes some of this to the Queen car, but the long-suffering riders on King do not get a break either after years of work at King-Queen-Roncesvalles. Note that Adelaide from York to Victoria is a Metrolinx project and so does not appear in this list.

Some of the dates in the TTC list do not align with info on TOInview. This is very common.

Parts of the schedule simply do not make sense. Some projects have far more time reserved than they should take based on past experience. Some projects will block the routes from carhouses in the east end to the rest of the network either via Queen Street or via Coxwell and Gerrard Streets, and times for these overlap.

Update: The TTC confirms that planned work on Gerrard Street will not occur at the same time as projects on Queen will block access to Leslie Barns and Russell Carhouse. See the map at the end of this section for a graphic view of the planned work.

Details of the Broadview Station Loop expansion are not yet available, nor is it confirmed whether this will actually occur.

I hope to get clarification of what is going on from the TTC.

  • Feb 27-Mar 26: King Street West from Close to Strachan
  • Mar 10-Oct 29: Dufferin Loop
  • Mar 24-Nov 28: Queen Street East from Carlaw to Leslie & Leslie to Greenwood
  • Mar 31-Apr 7: Intersection of King & Church
  • May 1-Nov 29: York from Queen to Adelaide (Ontario Line diversion)
  • May 6-July 8: Intersection of Lower Gerrard & Coxwell
  • May 6-Nov 21: Russell Yard
  • May 14-Nov 8: Broadview from Gerrard to Broadview Station
  • June 18-July 29: Intersection of King & Parliament
  • July 30-Nov 18: Metrolinx work at Queen/Degrassi overpass
  • Sept 3-Oct 2: Broadview Station Loop
  • Sept 7-Oct 29: Queen from Parliament to River & Davies to Broadview
  • Oct 8-Dec 16: Oakwood Loop
  • Oct 16-Feb12: St. Clair West Station Loop

The report does not list specifics for 2024, but info already appears on the TOInview map. It is not clear how some of this work will interact with Metrolinx Ontario Line construction at King & Bathurst. There is a proposed track and lane realignment at Bathurst & Fleet, but it is not clear whether this will actually occur, or if the planned work is simply replacement of existing special work as is. Details of the Spadina Station streetcar loop expansion are not yet available.

  • St. Clair & Yonge
  • St. Clair & Bathurst
  • Queen St. W from O’Hara to Triller
  • King St. W from Strachan to Spadina
  • King & Queen (Don Bridge)
  • Bathurst St. from Queen to Front
  • Bathurst & Queen
  • Bathurst & Fleet
  • College St. from Bay to Yonge
  • Main & Gerrard
  • Russell Yard (continuing from 2023)
  • Expansion of the streetcar platform at Spadina Station Loop

Update: The following map was included in the staff presentation to the Board on January 19, 2023.

This map contains several geographic errors:

  • The project labelled Queen & Yonge points at King & Spadina.
  • The project for St. Clair & Bathurst is shown east of St. Clair West Station rather than west of it.
  • The project for St. Clair & Earlscourt is shown well west of Lansdowne rather than east of it.
  • Carstops on Queen East at Wineva and at Waverley are shown as west of Kingston Road rather than east of it.
  • The project for Queen & Jarvis is shown well west of Yonge.
  • The project for Fleet Loop actually points to Exhibition Loop.

There are a few more, but my point in cataloguing them is that this is sloppy work and it speaks to the quality of information presented to the Board by management.

Pantograph Conversion

Gradually, and several years behind the original target date, the TTC has converted overhead wiring designed for trolley poles first to a hybrid pole/pantograph configuration, and then to pure pantograph style. A map of the current status was included in the staff presentation.

There are some problems with this map which is based off of a track plan that is itself out of date. “Wrong way” track has been removed from the one-way streets downtown, although it still appears here. Also, some work is underway on King West even this is not shown with the orange “in progress” colour. The intersection of King & Shaw had already been converted to Hybrid format when I visited it a month ago. (There are other errors in the map, but please don’t bother commenting with fixes.)

One amusing relic is the legend “Hillsdale Ave” on Lake Shore Blvd West. This was the site of a long-removed wye, the last in the system, and the street is called “Hillside Ave”. “Hillsdale” is in North Toronto.

Again, this is an unfortunate example of how the “official” records of the system are out of sync with actual conditions in the field.

TTC Service Changes January 8, 2023

The TTC will modify many routes on January 8, 2023, although most of the changes are small tweaks rather than a significant overhaul of service. Current changes are achieved mainly by reallocation of vehicles, modification of running times and headway adjustments.

Updated January 3, 2023 at 4:35pm: A table showing the number of replacement buses on streetcar routes has been added.

In the January schedule period, the planned weekly service is down from November 2022 levels. That is the appropriate comparison because the “December” schedules only cover the holiday period when service is reduced. All of these reductions have been reversed in the January schedules, and some school trips have been added beyond the November level.

Service in the latter part of 2022 ran below budget because riding had not rebounded as quickly as originally hoped across the system. January 2023 continues at a similar level, and a service budget has not yet been published, let alone approved.

Hours/WeekRegular ServiceConstruction ServiceTotal
Nov 2022 Budget182,0164,492186,508
Nov 2022 Planned173,2494,187177,436
Dec 2022 Planned170,7083,779174,387
Jan 2023 Planned171,8025,175176,977
Source: TTC Service Change Memos for November/December 2022 and January 2023

Subway Service

There is no change in subway service for January 2023.

Streetcar Service

506 Carlton will return to its normal route over its entire length after an extended sojourn on Dundas Street. The 306 night service will return to streetcar operation. Construction of streetscape changes on College Street is not yet complete, but this will not require a diversion in 2023.

Some streetcar routes will have new schedules:

  • 509 Harbourfront and 510 Spadina will be modified to reduce layover conflicts at Union and Spadina Stations.
  • Service on 509 Harbourfront will be reduced to match demand in some periods.
  • Sunday early evening service on 510 Spadina will be changed so that all cars operate as 510A to Union rather than a split service with 510B turning back at Queens Quay. This matches the Saturday service pattern.
  • 512 St. Clair service will be reduced to match demand during some periods.

The allocation of routes to carhouses will change slightly to balance resources. The table below includes a long absent route “507 Long Branch” and the temporarily suspended “508 Lake Shore”, but not the “502 Downtowner”. Make of that what you will.

The number of buses operating on streetcar routes for construction projects is shown in the table below.

Bus Service

Routing Changes

29/329 Dufferin

Due to construction for the Ontario Line’s Exhibition Station, the 29 and 329 Dufferin services will be rerouted as shown in the maps below.

43B Kennedy and 985A Sheppard STC Services

These routes will be modified to access Scarborough Town Centre via a different path in order to provide connecting stops with the temporary GO bus terminal.

95C York Mills and 996 Wilson Express Service to Ellesmere Station

The 95C York Mils branch will be dropped, and in its place the 996 Wilson Express will be extended east to Ellesmere Station.

The levels of service in the “before” and “after” configurations are compared below.

Buses/HourAM Pk PreAM Pk PostMidday PreMidday PostPM Pk PrePM Pk Post
95A Pt Union7.563.365.56
95C Ellesmere Stn7.53.35.5
995 UTSC5.553.83.85.55
996 Ellesmere Stn6.74.86
Total to Ellesmere Stn20.517.710.414.616.517
Total to UTSC13117.110.81111

Other affected bus routes

  • 600 Run As Directed: The number of scheduled RAD buses is deeply reduced with only 6 weekday crews and none on weekends. Divisions will assign buses locally depending on operator availability.
  • 19 Bay: An AM peak tripper to handle demand to the waterfront will be created by diverting one 503 Kingston Road bus to run eastbound as a Bay bus to Dockside Drive and Queens Quay, then deadhead to Broadview and Queen to resume service on the 503.
  • 20 Cliffside and 113 Danforth: Headways will be standardized so that an evenly blended service can operate from Main Station on these overlapped routes.
  • 25 Don Mills: The split branch structure north and south of Don Mills Station will be extended into the early evening on weekdays.
  • 925 Don Mills Express: Trips added during peak periods to match demand.
  • 939 Finch Express: Midday and PM peak service improved, evening service reduced.
  • 41 Keele: Service reduced to match demand.
  • 44/944 Kipling South: Some early express trips will be replaced with local buses. Two school trips from 44 Kipling South will interline with 76 Royal York South school trips.
  • 945 Kipling Express: AM peak service improved.
  • 48 Rathburn and 112 West Mall: PM school trips serving Michael Power Saint Joseph HS will be changed to match dismissal times.
  • 52 Lawrence West: A new trip will be added from Westwood Mall at 6:52am to accommodate demand. A new trip will be added between Lawrence and Lawrence West Stations in the early PM peak. This is a hook-up with an existing school trip.
  • 57 Midland: Service reductions to match demand.
  • 60C/960 Steeles West: Service between Pioneer Village Station and Kipling on the 60C branch will be reduced in peak periods to match demand. This will be offset by improvement to the express service.
  • 960 Steeles West Express: Early evening service reduced.
  • 63 Ossington: Service modified for resiliency and to match demand (mainly reductions).
  • 68/968 Warden: Schedules adjusted for reliability with less frequent service during many periods.
  • 79 Scarlett Road: Service reduction weekdays in peak and midday periods.
  • 86 Scarborough: Zoo shuttle will operate only on Saturday to serve Terra Lumina. Sunday service dropped.
  • 95/995 York Mills an 96/996 Wilson: 996 Express service extended to Ellesmere Station replacing the 95C local service (see map above). Service changes during many periods to improve reliability with a mix of frequency changes.
  • 102/902 Markham Road: New trips to serve school demand to R.H. King Academy and Centennial College.
  • 116 Morningside: New PM school trips from Morningside & Ellesmere to serve Jack Milner PS and Sir Wilfrid Laurier CI.
  • 122 Graydon Hall: All trips will now enter service eastbound at Don Mills.
  • 130 Middlefield: New school trips to serve Henry Kelsey Senior PS.
  • 165 Weston Road: Service reliability changes primarily through longer running times and additional buses.
  • 168 Symington: Service reduced to match demand.

Peak bus service

The Details

Details of these changes are in the spreadsheet linked below.

TTC Service Changes 2023.01.08 (Revised)

Construction Projects

TTC Service Changes Effective September 4, 2022

Updated:

  • The spreadsheet detailing all of the changes has been added at the end of this post.
  • The number of the Mimico GO shuttle has been corrected to 176.
  • Transfer arrangements at Queen & Dufferin for the 501 bus and streetcar services have been clarified.
  • Transfer arrangements at Queen & Roncesvalles for the 501 and 504 bus services have been added.

Updated September 5, 2022:

  • The spreadsheet listing all of the changes has been corrected for route 504 King. The original version included a description of the route carried over from the August version. This has been changed to reflect the September arrangements.

The TTC will make many changes to its scheduled service on September 4, 2022 with restorations of previous service levels on many routes. This will not get the system back to 100% of pre-pandemic levels.

An important distinction is between three values:

  • The amount of service scheduled before Spring 2020
  • The amount of service budgeted for 2022
  • The amount of service scheduled for 2022

The TTC plans to be back to 97% of budgeted service for bus, 84% for streetcar and 92% for subway. The overall numbers are compared below.

Hours/WeekRegularConstructionTotal
January 2020 Scheduled185,8257,068192,893
September 2022 Budgeted186,3796,398192,777
September 2022 Scheduled177,9304,965182,895

In the original 2022 service budget, the TTC planned to be back to roughly the same level of service as in January 2020 by September 2022. However, slower ridership recovery coupled with staffing constraints produced a lower scheduled service expressed as hours/week.

There are further caveats:

  • The distribution of hours by time of day might not be the same in 2022 as in 2020 because of changing demand patterns.
  • Changes in running times to deal with congestion or service reliability can mean that the same service hours are stretched over wider headways. Not all vehicle hours are created equal.

All that said, there are many changes in service levels, and with the bus network being back to 97%, the schedules for September 2022 are often based on old versions before service cuts were implemented. Another change for this month is the reintroduction of school trips on many routes.

Continue reading

TTC Service Changes: May 8, 2022

Several of the service cuts implemented in November 2021 will be restored with the May 2022 schedules. This includes express service on several routes. Although planned service will be 6.2% lower than the original budget for this period, the TTC intends to resume restoration of full service through the fall to the end of the year.

Information in this article is taken from the May 8, 2022 Scheduled Service Summary and from a copy of the detailed memo on service changes which was provided by a source. Normally the TTC sends these to various people in advance, but for some unknown reason, the document has not officially been sent to the normal external recipients.

There are some conflicts between information in the two documents and I have tried to reconcile these with my own judgement about which is correct because it is not unusual for there to be discrepancies in descriptions of service changes.

Rapid Transit Services

There are no changes in rapid transit services.

Streetcar Services

  • The 501H/501L Queen replacement buses for service on the west end of the route will be shortened to turn back downtown via University Avenue, Adelaide Street and York Street rather than operating to Broadview & Gerrard or Broadview Station.
    • Eastbound buses will operate as 501U.
    • Bus service will be provided from Birchmount, Queensway and Eglinton divisions.
    • There is no change to the existing 501 Queen streetcar service between Neville Loop and Bathurst Street (Wolseley Loop), nor to the 301 Blue Night Bus operation.
  • Headways on 505 Dundas and 506 Carlton will be blended to allow for the shared terminal at High Park Loop.
    • The 505 Dundas routing change to High Park Loop will be officially recognized in the schedules.
    • Service will be reduced during most periods on both routes as a seasonal change.
  • 306 Carlton Blue Night will operate with buses to Dundas West Station.
  • 509 Harbourfront: Seasonal service increase evenings and weekends.
  • 512 St. Clair: Service increase on weekdays.

Bus Services

Routes With Express Service Changes/Restorations

  • 29/929 Dufferin:
    • Local service improved during most periods on weekdays.
    • Weekend service rescheduled for articulated buses.
    • Weekend express service restored using artics.
  • 939 Finch East Express:
    • Weekend service restored.
  • 41/941 Keele:
    • Local service changed from articulated to standard buses on weekdays with improved frequency of service.
    • Midday express service restored.
    • Express operation changed to articulated buses.
  • 43/943 Kennedy:
    • Minor service reallocation on weekday local service.
    • Peak period express service restored.
  • 52/952 Lawrence West:
    • Service reliability adjustments weekdays
    • Express peak period service improvements
  • 60/960 Steeles West:
    • Seasonal service reductions
    • Reliability changes
  • 68/968 Warden:
    • Reliability changes and some weekend service improvements.
    • Peak period express service restored.
  • 85/985 Sheppard East:
    • All 85 local service on weekends will now operate with standard sized buses rather than with artics.
    • Weekend 985 express service restored.

Diversions

Note: These diversions are described in the service memo, but are not reflected in the scheduled service summary.

  • 31 Greenwood:
    • Effective approximately May 18, service will be diverted to Coxwell Station while the loop at Greenwood Station is closed for Easier Access construction. This work will last about one year.
  • 57 Midland
    • Service reliability adjustments.
    • Northern terminus shifted to the Redlea cul-de-sac via Steeles and Redlea.

Other Changes

  • 365 Parliament Blue Night Bus:
    • Weekend service that was removed in error in fall 2021 will be restored.
  • 73 Royal York and 76 Royal York South:
    • Service reliability improvements
    • During some periods, the 73B Eglinton service will interline with the 76B Queensway service.
  • 83 Jones
    • Recovery time reallocated to the south end of the route to reduce conflicts near Donlands Station.
  • 95 York Mills:
    • Stops added on Durnford Road and Rylander Blvd for the 95A Port Union extension. These will be reviewed in advance of the September 2022 schedule changes.
  • Service reallocation affecting some periods on the following routes:
    • 16 McCowan (peak periods)
    • 17 Birchmount (peak periods)
    • 36B Finch West (am peak and early evening)
    • 81 Thorncliffe Park (peak periods)
  • Service reliability changes which generally widen headways during most or all periods:
    • 30 High Park
    • 31 Greenwood
    • 57 Midland
    • 62 Mortimer
    • 77 Swansea
    • 93 Parkview Hills
  • Service reliability changes rebalancing driving/recovery time with no change in service level:
    • 33 Forest Hill
    • 101 Downsview
  • Service improvements:
    • 31 Greenwood (peak periods)
    • 33 Forest Hill (peak and weekday midday)
    • 83 Jones PM (peak periods)
    • 86 Scarborough early evening Zoo shuttle (restored, seasonal)
    • 92 Woodbine South (weekends, seasonal)
    • 996 Wilson Express (weekday midday and pm peak)
    • 175 Bluffer’s Park (restored, seasonal)
  • Service reductions:
    • 75 Sherbourne: AM peak and midday (seasonal)
    • 600 Run As Directed: The number of crews/buses assigned to RAD service will be reduced by about one third as full scheduled service returns.

With the restructuring of bus service in the waterfront and the creation of the 121 Esplanade-River route, there is no existing route to provide seasonal service to Cherry Beach or Ontario Place. Two new routes, 172 Cherry Beach and 174 Ontario Place-Exhibition will operate instead.

172 Cherry links Union Station to Cherry Beach. It will operate from Eglinton Division.

174 Ontario Place links Exhibition Loop to Ontario Place. It will operate from Mount Dennis Division.

Details of the changes are in the spreadsheet linked below.

TTC Service Changes Sunday, February 14, 2021

There will be few service changes in February 2021 in anticipation of the reassignment of bus services with the opening of McNicoll Garage at the end of March.

Weekday service will be trimmed in response to passenger demand on the following routes:

  • 2 Bloor-Danforth
  • 509 Harbourfront
  • 510 Spadina
  • 512 St. Clair

The 9 Bellamy and 913 Progress Express routes will be changed to operate via Progress Avenue. Bellamy buses will no longer serve stops on McCowan Road, Corporate Drive and Consilium Place (these are served by other routes).

The service changes are summarized in the table linked below.

2021.02.14 Service Changes (ver 3)

The project list has been updated to reflect construction on various parts of the streetcar system as announced by the TTC. This includes:

  • Overhead and station construction work on the east end of 506 Carlton.
  • Overhead reconstruction on various parts of 501 Queen.
  • The King-Queen-Queensway-Roncesvalles project.
  • Reconstruction of Dundas West Station Loop including expansion of streetcar platforms.

Between the construction projects and the reduced streetcar service, the peak scheduled streetcars now number only 126 (AM) and 127 (PM). Out of a fleet of 204 cars, this leaves a lot of room for “maintenance spares”. We must hope that when the TTC puts the entire network back together again late in 2021 that they will have enough working cars to operate it.

In spite of the considerable surplus of streetcars, there are still bus trippers scheduled on 505 Dundas and 506 Carlton.

The bus fleet will operate at less than capacity with a scheduled peak service of 1,520 vehicles compared to the garage capacity of 1,675 and a fleet size of over 2,000. Run-as-directed (RAD) buses are not included in this total, although there are fewer of them now that “regular” service levels have been restored on many routes.

The project list also includes some items for 2022 from the City of Toronto’s map of planned construction work, TOInview. This includes:

  • Completion of the KQQR project from Queen to Dundas (stop modifications).
  • Reconstruction of Broadview Station Loop. The status of a proposed expansion of streetcar platforms is not yet known.
  • Track construction on College from Yonge to Bathurst, and at the intersection of Church & Carlton. Whether the TTC will add curves in the southeast quadrant here to simplify diversions is not yet known. In a previous project at Broadview & Gerrard, the “institutional memory” forgot that there were plans to add a north-to-west curve, and a once in 25 year opportunity was missed.
  • Replacement of the intersection of King & Shaw.
  • Reconstruction of Adelaide Street from Charlotte to Yonge. It is not yet clear whether this will only involve the removal of long-inactive track or the restoration of Adelaide as an eastbound bypass for King and Queen service between Spadina and Church.

TTC Service Changes January 3, 2021 Part I: Streetcars (Updated)

Updated January 7, 2021: Maps showing the revised operation of 501/301 Queen, 504/304 King and 506/306 Carlton have been added from the TTC’s Route Diversion pages.

Updated December 23, 2020: The operating schedules (in GTFS format used by various trip planning apps) for the January-February period have now been issued on the City of Toronto’s Open Data Portal. These confirm two outstanding issues with the service as it was described in the change memo:

  • The 304C King West night shuttle will operate on a 20′ headway, while the main part of the 304 King streetcar route between Dufferin and Broadview Station will operate on a 30′ headway. This means that timed connections between the two services will not be reliably possible for each trip.
  • The 310 Spadina night service appears to have escaped the cutback from a 15′ to a 30′ headway. The January schedules show service every 15′.

The TTC memo detailing service changes for January is a long one, and in the interest of breaking this up into more digestible chunks, I will deal with the streetcar and bus networks separately.

The usual summary of schedule changes (for the streetcars only) is linked here:

Some routes will see major changes beginning in January and continuing, with modifications as the year goes on.

In addition to various construction projects, the TTC plans to accelerate the retrofit of its Flexity fleet with various fixes and the major repairs to the early cars with frame integrity problems. The intent is to substantially complete this work by September 2021 by which time ridership recovery in the territory served by streetcars will be recovering from the pandemic ‘s effects.

The total scheduled cars in peak periods will be 145 out of a total fleet of 204. As I reported in a recent article about the 2021 Service Plan, the TTC aims to field 168 cars in peak once they have the fleet back at a normal 20 per cent maintenance ratio.

Queen Street will take the brunt of construction work for the early part of 2021 with a shutdown of streetcar service west of McCaul Loop. This will allow conversion of the overhead system for pantograph operation and, when construction weather allows, the complete replacement of the King-Queen-Queensway-Roncesvalles intersection. See:

That project will also affect the King service west of Dufferin Street.

Streetcars will return to Bathurst and to part of the Carlton route.

Blue Night Service (Updated)

The overnight service on four routes (501 Queen, 504 King, 506 Carlton and 510 Spadina) was increased due to congestion at the carhouses when most of the fleet, including many still-active CLRVs, was “in for the night”. Service on all but Carlton operated every 15 minutes, while Carlton ran every 20, even when it was a bus operation.

The night service reverts to half-hourly headways in January, except for 310 Spadina which remains at quarter-hourly. Also, the 304C King bus between Dundas West and Shaw will operate every 20′ while the main 304 streetcar route will operate half-hourly.

501 Queen

The 501 Queen route will be split with streetcars running between Neville Loop and McCaul Loop, and buses between Long Branch Loop and Jarvis Street. The 301 Blue Night service will also be split, but the streetcar portion will loop via Church, Richmond and York to avoid causing noise from wheel squeal at McCaul Loop.

The western portion of the route will include a short turn with half of the buses terminating at Park Lawn during most periods of service. Buses will loop downtown via Jarvis, Richmond and Church Streets. The buses will be supplied by Mount Dennis and Birchmount garages.

Routings in the area of Humber Loop will vary depending on the branch:

  • Westbound 501L and 301L: From the Queensway, south on Windermere Avenue, west on Lake Shore Boulevard West to Long Branch Loop.
  • Eastbound 501L and 301L: East on Lake Shore Boulevard west, north on Windermere Avenue, east on the Queensway.
  • Westbound 501P: From the Queensway, south on Park Lawn Road, south on Marine Parade Drive to Park Lawn Loop.
  • Eastbound 501P: From Park Lawn Loop via north on Marine Parade Drive, north on Park Lawn Road, east on the Queensway.

501 Queen will operate from Russell Carhouse and will continue to use trolley poles as the east end of the route has not yet been converted for pantographs (that project is planned for fall 2021).

502 Downtowner

This route is still suspended and all streetcar service on Kingston Road is provided by route 503.

503 Kingston Road

The 503 Kingston Road streetcar will continue to operate to Charlotte Loop at Spadina. The City has just awarded the contract for reconstruction of Wellington and Church Streets from Yonge to King, and that will occur in the spring. This will complete the Wellington Street project which has been delayed by other utility projects in the same area.

503 Kingston Road will operate from Leslie Barns and, like 501 Queen, will continue to use trolley poles.

504 King

The 504 King route will be split with streetcars running east of Dufferin Street and a bus service operating from Shaw to Dundas West Station. Both the 504A Distillery and 504B Broadview Station services will terminate at Dufferin Loop.

To reduce congestion at Dufferin Loop, all service on 29/929 Dufferin will be extended to the Princes’ Gate Loop.

The 504A Distillery service will operate from Russell Carhouse, and the 504B Broadview Station service will operate from Leslie Barns. The route will continue to operate with trolley poles.

The west end bus service 504C and 304C Blue Night will loop via south and east on Douro Street, north on Shaw Street to King Street West. Buses will be provided by Mount Dennis Garage. Because service on the 304 streetcar and the 304C bus will operate at different headways, regular connections between them will not be possible.

The operator relief point for the 504B service will be shifted from Queen & Broadview to Broadview Station to avoid service delays on other routes caused by late arrivals of operators for shift changes.

505 Dundas

The cutback of 505 Dundas service to Lansdowne has already ended (on Dec 9) and all cars now run through to Dundas West Station. This change becomes part of the scheduled service in January. Headways will be widened slightly during most periods to operate the same number of cars over a longer journey.

Operation of this route will be split between Leslie Barns and Roncesvalles Carhouse, and that will continue until spring 2022. Cars running to and from Roncesvalles will operate with trolley poles and will change to pantographs at Dundas West Station. Cars from Leslie already run on pantograph on their dead head trips.

The eight AM peak bus trippers will be interlined with buses from other routes. In the west, four trips will originate at Lansdowne from trippers on the 47 Lansdowne route. In the east, four trips will originate at Broadview Station from trippers on the 100 Flemingdon Park route.

506 Carlton

The 506 Carlton route will be split with streetcars returning between Broadview and High Park Loop, and buses operating between Parliament and Main Station. Overhead conversion for pantographs is not completed yet on the east end of the route, and reconstruction of the bus roadway at Main Station is planned to start in March.

506 streetcars will loop in the east via Broadview, Dundas and Parliament. 506C Buses will loop via River, Dundas and Sherbourne Streets.

For the overnight service, the 306 streetcars will run to Broadview Station and will use the bay normally occupied by 505 Dundas which has no overnight service.

The looping shown for the 506B/306B buses is different from the version show in the service change memo. The TTC has confirmed that the map is the correct version.

All 506 Carlton cars will operate from Roncesvalles Carhouse. They will enter and leave service using trolley poles, but once on Howard Park Avenue will switch to pantographs as the west and central portions of the route have been converted. The 506 buses will operate from Eglinton and Malvern garages.

508 Lake Shore

This route remains suspended pending recovery of demand to the business district downtown.

509 Harbourfront

This route reverts to the February 2020 schedules. Extra service that was added to compensate for the absence of 511 Bathurst cars will be removed.

510 Spadina

This route reverts to the February 2020 schedules with minor changes in service levels.

511 Bathurst

Streetcars return to 511 Bathurst using the February 2020 schedules. If construction work on the Bathurst Street Bridge is not completed by January 3, streetcars will divert via King, Spadina and Queens Quay until the bridge reopens.

512 St. Clair

The 512 St. Clair route continues with the November 2020 schedules and a covid-era reduction in service.

Routes 509 through 512 will all operate from Leslie Barns and will enter service using pantographs from the barns to route via Queen and King Streets.

The allocation of streetcars to carhouses by route is shown in the table below.