The Ford/Tory Subway Plan: Part II – Technical Appendices

In the first of two articles, A Big Announcement, or a Transit Three Card Monte?, I reviewed the proposed agreement between Ontario and Toronto whereby the Province would build four lines or extensions at no capital cost to the City, and ownership of the existing system would remain in City hands. This has been hailed as something of a “peace in our time” solution to the contentious relationship between Premier Ford and the City, but there are many outstanding issues that will not be resolved before the City signs on to the new deal.

In this article, I turn to three appendices to the City report, specifically:

Citations in this article are in the format [A3, p5] where “A3” is the attachment number and “p5” is the page number.

Reading through these documents, I was struck by how an essential section is buried right at the end of Attachment 4: the City/TTC evaluation of the Metrolinx Initial Business Case for the Ontario Line.

The main report is enthusiastic about the viability of the proposals and the contributions they will make to the City of Toronto. However, the attachments reveal the degree to which the scheme is far from complete or settled. There is a caveat that if the proposals change significantly, then the gushing support for the new plans could become only a trickle. But the political pressure is for the City to commit to the scheme, whatever it may become, in the rush to “get shovels in the ground”.

This is a long article intended to pull key points out of the technical discussion of proposed new lines in an attempt to highlight the major chunks without requiring readers to wade through every page (although the keen ones among you certainly will, I’m sure).

Timing of Market Calls for Procurement / Public Participation

The City/TTC have not received a detailed schedule from Metrolinx, however the Infrastructure Ontario Fall update includes the following timelines:

  • Ontario Line: RFQ Spring 2020, RFP Summer/Fall 2020
  • L2EE: RFQ Winter/Spring 2021, RFP Summer/Fall 2021
  • YSE: RFQ Fall 2021, RFP Spring 2022
  • EWLRT: To be determined [A3, p12]

This is aggressive for the OL and gives very little chance for substantive change before the RFP goes out. “Public participation” will be minimal in the best Metrolinx tradition.

The opportunity for feedback and input throughout a project’s development may differ given the anticipated P3 delivery model. Details regarding the Province’s proposed approach are provided as Attachment 11 to this report. City and TTC will continue to advocate for meaningful public consultation on provincial transit projects. [A3 p11]

There are conflicting priorities in completing work regarding the new design and changes to the Assessment with the desire for an expedited delivery process.

Q22: Has an assessment of construction-related impacts been undertaken as part of the preliminary planning and design? What about impacts on community, businesses, traffic congestion, noise, etc.? If not, when will this occur and be factored into decisions on build methodology, procurement, and a program for business and community supports?

A: The City/TTC expect that this will be undertaken as part of the updated environmental work for the TPAP(s).

Q23 Will the Province adhere to City permits and approvals, per the practice under the LRT Master Agreement?

A: The applicable Master agreement(s) for these projects are to be developed, and it will be the expectation that agreed upon service standards and timelines for applications, permits and approvals will be adhered to. The Province is seeking city commitment to explore opportunities to accelerate and expedite delivery including review of processes, and leveraging powers and authorities. [A3 p13]

Q29: Are you building the [Ontario] line to a budget of $10.9 B or are you building a line with a defined scope of work?

A: The project cost estimate is preliminary based on the current state of development. The scope in so far as length and areas served have been consistently stated. Future adjustments to scope, budget and schedule will be identified as part of subsequent phases of work. [A3 p15]

“Future adjustment” is a term that implies potential change, but how would this be handled with a P3 contract already in place? When do the requirements to deliver on time, on budget, supersede whatever objections or improvements might emerge from a review process?

Transit Oriented Development

One of the Province’s favourite terms now is “Transit Oriented Development” and the supposed ability to pay for transit with development charges and fares from new riders. There is a question, however, of whether the Province will seek higher density around stations to pay for its rapid transit plan even if this requires development at a scale beyond what the City has planned or the neighbourhood is expecting. What other costs will TOD bring for infrastructure, services, schools? The overdevelopment of Yonge & Eglinton, where the Province wants to see even more density, is a prime example.

Q13: With respect to “transit-oriented development” and seeking private sector investment, what assumptions are being made with respect to compliance with the City’s Official Plan policies and guidelines?

A: The Province has committed to work with the City to ensure that transit oriented developments advance a shared understanding for effective growth and high quality development of Toronto. The City and the Province are working through the details of an agreement on how they will work together to advance TOD opportunities. [A3, p10]

That is not the most reassuring of comments given the bull-headed nature of Provincial policy development. Doug Ford (and his brother before him) believes in the magic of the private sector somehow covering the cost of his dreams. This could have severe consequences for both the City and for the transit system if that dream is exploited to remove controls on high density development.

Getting There From Here

There is a problem throughout much rapid transit planning in Toronto that agencies only consider the end state after many projects have been built, new jobs and residences have been created, and magically we are transported to a future date and city where the models run.

Unfortunately, we have to get from 2019 to 2041, the year for all of the modelling cited in these reports, and there is no guarantee that the system can handle either the intermediate stages nor the “end state” if things do not occur as quickly as we hope.

Although GO expansion is part of the next decade’s work, there is nothing published to show how it will affect the TTC network for good or ill. Indeed, a major role for the Ontario Line now appears to be “relief” for congestion at Union Station almost to the point that relief of subway congestion is a secondary matter.

SmartTrack is a mythical “service” whose final configuration is still not known. Metrolinx has been quite evasive on this point, and the best we can hope for is a train every 15 minutes at “SmartTrack” stations along the Weston and Stouffville corridors. Two of the six ST stations may never be built because they physically conflict with, or lose projected ridership to, other services.

It may suit planners and politicians to talk of demand models for 2041, but what will the 2020s and 2030s look like on Toronto’s and the wider region’s transit system as we await the arrival of new services? This is a major shortfall in the City reports because they do not address the “how do we get from here to there” problem complete with associated operational and financial headaches. A scheme for the province to pay the entire cost of four new lines is wonderful, but there is much more to the transit system’s future than Premier Doug Ford’s map.

Continue reading

A Big Announcement, or a Transit Three Card Monte?

On October 16, the governments at Queen’s Park and Toronto City Hall announced a deal to sort out competing transit plans for the city. The current provincial priority projects are the Ontario Line (Don Mills/Eglinton to Exhibition), Scarborough Subway extension from Kennedy Station to Sheppard, Yonge Subway extension from Finch to Richmond Hill, and the Eglinton West LRT extension from Mount Dennis to Renforth.

The main City of Toronto report will be discussed at Executive Committee on October 23, and then at Council on October 29-30.

This article reviews that report with reference to a few parts of its many attachments. I will turn to the technical attachments in a second article. To focus material on each subject for readers, I have grouped related items together or re-sequenced things for emphasis. There are extensive quotations of key material so that readers hear not just my “voice” but that of the report’s authors.

Despite the importance politicians at both levels place on the proposals, the fundamental problem remains that many of the details are cloudy, to be kind. Specifically:

  • The City of Toronto retains ownership of the existing transit system avoiding a complex realignment of responsibilities and governance, but with this comes total responsibility for funding the ongoing state of good repair.
  • A large gap remains between the amount of funding needed to maintain and expand Toronto’s transit system relative to the amounts actually available and committed in budgets at various levels of government.
  • Ontario will build four key projects substantially with its own money, but continued support for transit beyond this is uncertain.
  • Toronto will redirect funding originally earmarked for its share of the key projects to other priorities, notably the TTC’s repair backlog. However, much of that “funding” does not exist as allocations in existing budgets and new money is required from Toronto to pay its share.
  • Cost estimates for the key projects are based on preliminary estimates that could change substantially as the design process unfolds. These estimates are in 2019 dollars and make no provision for inflation. The reports are silent on how the proportion of total spending by each contributor might change over the decade or more of construction.
  • A substantial total of project costs will be born by private sector partners through a “P3” financing mechanism. These arrangement will require future payments for what will be, in effect, a capital lease, but the mechanism for funding this from three levels of government is unclear. The reports are silent on the split between short term borrowing to pay for construction as opposed to long term payments to the P3 financier.
  • Project details as they are known today will change in response to design work and the need to keep costs within the projected level. This will affect alignments and stations, and what we think we are buying could be quite different from what we actually get.

The challenge in all of this is, as always, the question of money. We can watch the hands of politicians and managers at all levels as they shuffle cards on the table. We hope to “find the Queen”, to win in the subway sweeps rather than being taken for suckers who will cheer any plan, but lose every game. It is far from clear whether the proposal is a “good deal” for Toronto, and there are huge future transit costs that are barely addressed.

The whole exercise is a political deal to bring peace, comparatively speaking, to the transit file which was needlessly fouled by Doug Ford’s insistence that he knows more about transit in Toronto than anyone else. Does Toronto take this as its last best chance to preserve some semblance of control over its transit future, or do we keep fighting for a better deal?

There are a lot of holes in this plan and severe implications both for the City’s finances and the future of Toronto’s transit system. Many questions need to be asked and answered, even if the result will be a whole new plan after provincial and municipal elections in 2022.

Continue reading

Ontario’s Transit Plans: Details Emerge in City Report

When Premier Doug Ford announced his new transit plan in April as part of his first budget, there was plenty of hype about provincial transit investment, but few details about what would be built or how far design had progressed beyond doodles on bar napkins. Four projects comprise the Ford plan:

  • The “Ontario Line” from the Science Centre at Don Mills & Eglinton to Ontario Place replacing Toronto plans for the Relief Line
  • The Richmond Hill extension of Line 1 Yonge
  • The Scarborough Line 2 Danforth extension to Sheppard & McCowan with at least three stops rather than the one in the current Toronto plan
  • A modified plan for the Eglinton West LRT extension with underground construction for part of the route east of Martin Grove
  • Extension of the Sheppard subway east to McCowan to meet the northern end of Line 2

Information about these proposals came more from rumours than from specifics, notably from Metrolinx, the agency charged with planning and delivery of the scheme.

Staff from the City of Toronto and the TTC have been meeting with their provincial counterparts, and details begin to emerge in a staff report to Toronto’s Executive Committee.

The Ontario Line concept proposed by the Province is at an early stage of design. [p 5]

This is not a “shovel ready” project, nor is the revised Scarborough subway, in spite of claims that the Ontario line can be open by 2027. That is very much a political date based on the need to have relief capacity in place before new demand is added to the Line 1 Yonge route from the Richmond Hill extension. The government, knowing the votes available in York Region, needs to show progress on that extension, but actually operating it would totally overload the subway system without substantial diversion of ridership to a relief line.

Previous studies by Metrolinx foresaw a drop in ridership at the Bloor/Yonge choke point provided that a new line went at least to Eglinton rather than stopping at Danforth. This is not news, but the political change lies in recognition that a line to Eglinton is not some future, “Phase 2” option, but an essential part of reducing demand on Line 1. Whether the construction timing and possible opening dates for the Ontario and Richmond Hill lines can be achieved is quite another matter. In a political context, the important date is 2022, the next Provincial election. By that time, visible “progress” will be needed to shore up support for the government, but the target dates will be far enough off that the inevitable slippage will not yet be evident.

Public Consultation

In parallel with the technical work on provincial plans, the City of Toronto has launched a public participation campaign about the shift in responsibilities for transit between the municipal and provincial governments. This is all a bit vague at present because the details of what Queen’s Park actually intends remain rather vague. The government has given itself the power to take over projects completely or in part, and to seize Toronto assets with or without compensation. However, the financial details are murky including the problem of expected contribution to capital projects by other governments and the as-yet unaddressed question of cost sharing for day-to-day transit operations which includes a substantial component of running maintenance, not just driving the trains.

The City will bring a wider range of issues than a few new lines before the public for comment. Four public meetings are planned over the coming month:

Thursday, June 13, 6:30 to 8:30 p.m.
Father Serra Catholic School
111 Sun Row Drive, Etobicoke

Thursday, June 20, 6:30 to 8:30 p.m.
North York Memorial Community Hall
5110 Yonge Street, North York

Saturday, June 22, 10:30 a.m. to 12:30 p.m.
Scarborough Civic Centre
150 Borough Drive, Scarborough

Thursday, June 27, 6:30 to 8:30 p.m.
City Hall, Council Chamber
100 Queen Street West, Toronto

Although one might despair that the Ford government cares about or will listen to concerns by Toronto citizens, this consultation will be important if only to gauge overall public feeling. The challenge will be to conduct real consultation without having sessions hijacked by Ford Nation supporters.

Continue reading

Ontario’s 2019 Budget: Transit Effects in Toronto

The Ontario Government introduced its 2019 budget on April 11. The section on transit and transportation begins with the usual statements about the cost of congestion, and the economic benefit of transit and highways. Transit specifics focus on the recent Toronto subway announcement. Metrolinx/GO continues on its expansion path, but with more emphasis on what has been done than what is to come.

The Subway “Upload”

Ontario reiterated its intention to take ownership of the Toronto subway network, but it is now clear that this will be done in two parts. First will come responsibility for system expansion as announced on April 10 with the existing system assets to follow in 2020. This puts the more complex problem off nominally for a year, but that debate is really underway now with negotiations between the City of Toronto, TTC and province.

By separating the upload into two distinctive parts, the Province can begin building subway extensions and new lines immediately while giving proper due diligence to the state of repair of the existing assets and fulfilling its commitments to consultation under the Terms of Reference.

The Province remains steadfastly committed to the full upload of the TTC subway network. [p. 64]

That “due diligence” is the nub of any transfer. Past provincial statements imply that the cost of life cycle maintenance (major repairs and replacement, items found in the TTC’s capital budget) would shift to the province leaving day-to-day costs to the City of Toronto. The problem lies in the inevitable tug-of-war between transit expansion and state of good repair. Provincial Treasurer Vic Fedeli, speaking on CBC’s Metro Morning, claims that the investment in new transit lines more than offsets gas tax revenue promised by the former Liberal government. However, this leaves a major hole in planned funding for system upgrades.

Gas Tax Transfer

Fedeli claimed that the Gas Tax can only be used for specific type of spending, but this is not true. The money today goes partly to subsidize day-to-day operations and partly to capital for state-of-good-repair (SOGR). Across the province, few cities are building rapid transit expansions, and their gas tax allocation goes to operation and maintenance of existing systems. Fedeli, in parliamentary language, is “badly briefed”.

The gas tax transfer from Ontario to Toronto for 2018-2019 will be $185 million, and this was expected to double in stages over the next four years. This increase has been cancelled in the new Ontario budget.

Beginning in 2019, Ontario will gradually increase the municipal share of gas tax funds up to a total of four cents per litre in 2021-22. Based on the averages from the past 10 years, gas tax funding is estimated to be about $642 million in 2021-22. There will not be any increase in the tax that people in Ontario pay on gasoline.

Year                            2018-19 2019-20 2020-21 2021-22

Municipal share (cents/litre)   2.0     2.5     3.0     4.0
Estimated funding (millions)    $321    $401.3  $481.5  $642

Source: Enhanced Gas Tax Program, Ontario Government Backgrounder, January 27, 2017

Note that the dollar funding above is for all of Ontario, not just for Toronto, although it gets the lion’s share due to its size.

The Province will not move forward with the previous government’s proposed changes to the municipal share of gas tax funding. The Province will continue to support municipalities through the existing Gas Tax program and ensure it continues to meet the needs of the people of Ontario in alignment with provincial priorities.

Over the next few months, the government will consult with municipalities to review the program parameters and identify opportunities for improvement. This review will be informed by the goals of responsible planning and a more sustainable government to ensure taxpayer dollars are being spent as effectively as possible. [p. 75]

Toronto allocates almost half, $91.6 million, to the TTC Operating Budget, leaving $93.4 million for capital in 2018-2019.

Planned spending based on federal and provincial gas tax transfers is summarized in the city’s 2019 budget papers. This document details the allocation of federal and provincial transfers planned over 2019-2028 with $1.358 billion broken out by TTC budget line. Note that this is less than the total that would have been expected over ten years because the “out years” of the TTC’c capital plan is constrained by city financing plans. Many projects are “below the line” in the budget, especially in the outer five years, and the rise in gas tax funding could have helped to bring some of these projects to approved, above the line status.

About 70% of planned provincial gas tax spending by Toronto is for assets that are subway related. If Ontario transfers responsibility for all of this to the provincial level, then this would offset the loss of expected gas tax. However, that depends on just what budget lines Ontario chooses to take on. When capital subsidies began under the Davis government, there was something of a shell game between Toronto and Queen’s Park over the classification of expenses because “capital” received at least a 50% subsidy while “operations” only got 16%. This sort of thing will bedevil negotiations between the two governments on funding of the uploaded subway system’s SOGR projects.

The table below summarizes the categories listed in the city’s budget and splits them between subway and surface networks. The breakdown is based on my experience in reviewing TTC budgets. Although some adjustment of percentages might be argued, the overall balance will not change much.

Continue reading

Toronto’s Omnibus Transit Report: Part III

This is the third and final part of my review of the transit reports that will be before Toronto’s Executive Committee on April 9, 2019, and at Council a week later.

In part one, I reviewed the financial issues presented in the reports together with the Scarborough Subway Extension, now known as the Line 2 East Extension (L2EE).

In part two, I turned to SmartTrack, the Relief Line and the Bloor-Yonge station expansion project.

This article reviews the streetcar/LRT projects as presented in the current set of reports.

Relevant documents include:

  • Main report: Toronto’s Transit Expansion Program – Update and Next Steps
  • Attachment 1: A status update on all projects
  • Attachment 3: Waterfront Transit Network – Union Station-Queens Quay Link and East Bayfront Light Rail Transit. [Note: The properties of this attachment were incorrectly set by the authors. Although it really is Attachment 3, it appears on browser tabs as if it were Attachment 2 for the Scarborough Extension.]
  • Attachment 4: Eglinton East LRT
  • Attachment 5: Eglinton West LRT

Much of the LRT network still at some stage of design or construction is a remnant of the Transit City plan announced in 2007. Pieces have have fallen off of that network proposal, notably in Scarborough, but also a few key links that would have knitted the network together allowing sharing of carhouse and maintenance facilities. Confusion about the planning, ownership and funding scheme for parts of the network complicates the situation further.

Although the province has announced that it wishes to take over “the subway”, the boundary is unclear because a previous government decided to take over at least part of the Transit City LRT network, notably the Eglinton/Crosstown and Finch West routes. The Ford government prefers to put as much transit underground as possible, but if Toronto wants to extend an existing route (for example on Eglinton East), the city’s preference will be for surface construction to keep cost within its ability to fund projects.

Continue reading

Premier Doug Plays With Toronto’s Train Set

In the continuing circus which is the Ford Family Transit Plan, the provincial government has advised Toronto and the TTC of its priorities for rapid transit construction. The Province is quite firm that since it will be paying for these lines, it will call the shots.

This information broke in two letters dated March 22 and 26, 2019 from Michael Lindsay, Special Advisor to the Cabinet – Transit Upload, and Shelley Tapp, Deputy Minister of Transportation, together with a report from the Toronto City Manager, Chris Murray, dated March 26.

The Province has four priority projects, although some of the information about them is vague:

  • A three-stop Scarborough Subway Extension [SSE]
  • A Downtown Relief Line [DRL] of indefinite scope
  • The Richmond Hill Extension of the Yonge Subway [YNE]
  • Construction of the Eglinton West Crosstown LRT primarily underground rather than at grade

These are the only projects mentioned in the letters. By implication anything else is off of the table as far as provincial funding is concerned except for whatever the subway “upload” still under discussion might entail. More about that later.

The Province refers to “incongruencies between the province and city/TTC with respect to the design and delivery of priority projects”. Most of this should be no surprise given previous statements both by Doug Ford as a candidate, and rumblings from his supporters.

The March 22 letter arose from a March 8 meeting between Provincial, City and TTC representatives. Two things are clear:

  • The Province was not paying attention to, or chose to ignore, information it received or should have been able to access easily through public channels.
  • The City/TTC should have had some idea of what was coming down the pipe over two weeks ago, but there was no public hint of what was in store even with the subway upload on the Executive Committee and Council agendas. This is a classic case of “who knew what and when”, and a troubling question of whether the direction of provincial plans was withheld from public view for political expediency.

The March 22 letter makes statements that were revised on March 26, and which have provoked considerable comment as this story broke. Most astounding among these was:

Per our meeting of March 8, we were informed that the City’s preliminary cost estimates for both the Relief Line South and the Scarborough Subway Extension have significantly increased to nearly double or greater the figures released publicly.

On March 26, the Province wrote:

We acknowledge, in light of the helpful clarification you provided at our Steering Committee meeting [of March 25], that the city’s/TTC’s revised project cost estimates for the Relief Line South and Scarborough Subway Extension projects represent estimates in anticipation of formal work that will reflect greater specificity in design. We accept that the actual budget figures remain to be determined …

This bizarre pair of statements suggests that either:

  • the Province was not really paying attention in the meeting of March 8 which led to the March 22 letter, or
  • they really were, but that their first statement was guaranteed to blow every transit plan to smithereens if it were not retracted.

On March 26, they do not say they were wrong, merely that they were dealing with preliminary estimates.

That is a strange position considering that the SSE is on the verge of reaching a firm design number and budget to be reported in early April to Toronto Executive Committee and Council. The agenda publication date is April 2, and it is hard to believe that a firm estimate for the SSE does not already exist. As for the DRL South, that is in a more preliminary state, but if anything the numbers already published have been rather high.

The Scarborough Subway Extension

For the SSE, there are two conflicting proposals:

  • City: One stop extension terminating at Scarborough Town Centre
  • Province: Three stop extension “with the same terminus point”.

There is no reference to any potential connection with a Sheppard Subway extension. However, the March 26 letter contains this statement:

… we recognize that the city/TTC and province share the intention for a station to be located at Scarborough Centre. However, under the province’s preferred three-stop extension of Line 2, the project would proceed northward from the station at Scarborough Centre.

Given that the TTC’s alignment for STC station is itself on a north-south axis, it is unclear just what this remark refers to especially if STC is to be the terminus of the provincial project.

As I wrote recently in another article, there is an issue of equipment and storage required to allow the SSE to open with full service to STC. One potential source of “additional” cost could well be that works such as a new Line 2 yard at Kipling plus the rebuilding and/or replacement/expansion of the fleet are now counted as part of the overall project cost. This is precisely the sort of hidden cost I warned the Province would face when they started to understand the full scope of the TTC’s infrastructure requirements.

Whether this is the case remains to be seen, but with the Province taking responsibility for delivery of this project and planning to assume the cost of maintenance and expansion of the existing subway, they (or anyone else looking at funding the SSE) will be facing these costs as “add ons”.

One other concern is that there is no mention of capacity expansion for Line 2 either by way of station expansion at critical junction points nor of fleet expansion to allow more service once the line has Automatic Train Control [ATC].

Crosstown LRT Westward Extension

  • City: A substantially at-grade extension from Mount Dennis westward, although there are references from recent public participation to the possibility of some grade separations.
  • Province: A “significant portion of this extension” would be underground, an option “which has not been considered in a material way” as part of the current design.

The March 26 letter revised the characterization of the City’s work to date:

… we recognize that tunnelling options for the project have been considered as part of previous assessment, but that these options are not preferred by the city/TTC.

Again, one must wonder just what the province was doing at the March 8 meeting to have so botched their understanding of the work to date. The work already done is documented on the project’s website. I cannot help wondering how much the original provincial position was a product of political posturing by Etobicoke politicians. Such a gaffe does no credit to Michael Lindsay and his team.

It is no secret that there is strong political pressure from politicians in Etobicoke for the LRT line to be buried as much as possible, and it is no surprise that the Province would embrace this.

Missing, however, is any reference to the portion of the line west of the Toronto-Mississauga boundary and specifically the link into Pearson Airport. Will this be part of the Provincial project?

Relief Line South

The text in this section has provoked speculation in various fora, both the mainstream and social media.

Planning work undertaken by the TTC contemplates utilizing existing technology … the province would propose … a truly unique transit artery spanning the city that is not beholden to the requirements of the technologically-outdated Line 2.

On March 26, the Province changed their tune, a bit:

… we recognize that the city/TTC is contemplating a different technology for the project than that currently deployed for Line 2.

It is hilarious to see Line 2 described as “technologically outdated” when it is this line that the Province plans to extend to STC. At the risk of peering into a murky crystal ball, I will venture an interpretation of what is being said here.

The “outdated technology” is the current fleet of T1 trains which do not have ATC installed. Moreover, TTC plans would not see ATC operation on Line 2 for at least a decade unless the existing fleet is retrofitted.

The TTC has always intended that the DRL would use modern technology, and again I cannot help wonder whether the Provincial reps were paying attention at their March 8 meeting with the TTC. This information is not difficult to obtain. They could even read my blog if they don’t want to spend time wading through official documents, but possibly it is simpler just to slag the municipal agency in a time-honoured Queen’s Park tradition.

The Province wants the DRL to be completely free-standing in that it would not depend on Line 2 and the existing yard at Greenwood, but would be built completely separate from the existing subway network. Moreover, “alternate delivery methods” would be used for this project, a clear indication that this would be a privately designed, built, financed and operated line much as the Crosstown was intended to be before a deal was worked out to let the TTC drive the trains, at least for a time.

The reference to a “transit artery spanning the city” implies something much more extensive than the DRL South from Pape to Osgoode Station, but what exactly this might be is anyone’s guess. It could be a truly different technology, something like Skytrain in Vancouver (which itself has two separate technologies). The construction technique could be changed from the proposed double bore to a single bore line, especially if the vehicle cross-section were smaller. The alignment and station locations could be changed. Any of these and more is possible, but we don’t know. As this is to be an AFP project, a blanket of confidentiality hides everything.

Yonge Northern Extension to Richmond Hill

The primary provincial interest here is in getting the line built as quickly as possible with planning and design work for the YNE and DRL to progress in parallel so that “the in-service date for the extension is fast tracked to the greatest extent possible”.

There is no mention of capacity issues on the existing Line 1 including the need for more trains, nor of the expansion needed at key stations to handle larger volumes of passengers.

Jumping the Gun on Uploading?

The March 26 letter clearly attempts to correct misapprehensions from the March 22 missive. These were presumably communicated privately at or before the March 25 meeting.

The Province is supposed to be engaged, in good faith, in discussions with the City and TTC about how or if it would take control of subway assets and what that control, and associated responsibility for ongoing costs, would entail. One might easily read the March 22 letter as showing that the Province has made up their mind, and all that remains is to “drop the other shoe” with respect to everything beyond the “priority projects”.

On March 26, the Province talks at length about “our priority transit expansion projects”. This has always been the political red meat in that new lines translate into votes, or so the Ford faction hopes. The myriad of details in looking after the existing system do not lend themselves to coverage in a two-page letter, let alone simplistic posturings by politicians eager to show the wisdom of their plans.

The March 26 letter does not discuss any aspect of the existing system including asset transfers or financial commitments. That’s not to say the Province has not considered this, but no details are public yet. That will be a critical issue for Toronto because the degree to which the Province actually plans to pay for the existing subway system will affect future City budgets.

There is a myth that fare revenues will cover off the City’s share, but we don’t actually know which aspects of subway “maintenance” will remain in the City/TTC hands. There are two separate budgets, capital and operating, but there has been no statement of how these will be divided. Although there could be a one-time payment for the capital value of the system, this begs two questions. First, who benefits from appreciation of property value as subway lands are repurposed/redeveloped. Second, what does the City do when the nest egg from selling the subway, assuming they even have anything left over after discharging subway-related debt, is used up.

Another issue to be decided is how the split in ownership and financial responsibility will affect gas tax funding that now flows from both the Provincial and Federal governments, over $300 million in 2018. How much of this will Toronto lose, and what will be offset by costs the Province will assume?

Further System Expansion

The correspondence from the Province is silent on many projects including:

  • Eglinton East LRT
  • Waterfront LRT
  • Finch LRT extension to Pearson Airport
  • Sheppard Subway extension to STC
  • SmartTrack and GO Transit Service Expansion

Eglinton East and Waterfront would, assuming a City/Province divide on surface/subway projects, lie clearly in the City’s court, while any extension of Line 4 Sheppard would be a Provincial project. Oddly, Eglinton East would be a “City” extension of a provincially-owned line, the Crosstown.

The Finch LRT occupies an odd place as a surface line that for historical reasons is being delivered by the Province. Moreover, an airport extension would lie partly outside of Toronto. Who knows what the fate of this will be.

To Be Continued …

The provincial letters have dropped into the Council meeting planned for March 27, and we can expect a great deal of debate, if not clarity, in coming days.

At a minimum, the Province owes Toronto a better explanation of just what they intend with their view of projects. This information should not be “confidential” because we are simply asking “what exactly do you want to do”. This is particularly critical for the Downtown Relief Line whatever the “unique transit artery” it might become.

SmartTrack and GO are important components because they will add to the “local” network within Toronto and could be part of the “relief” efforts that will span multiple projects. SmartTrack is a City project, and we are about to learn just how much it will cost Toronto to put a handful of John Tory branded stations on GO’s Kitchener and Stouffville corridors. SmartTrack also takes us into the tangled net of fare “integration” and the degree to which Toronto riders will pay more so that riders from beyond the City can have cheaper fares.

Finally, there is the question of operating costs. The Ford mythology includes a claim that subways break even, and in the uploading schemes mooted to date, there is an assumption that Toronto will still operate the subway network and pay for its day-to-day costs out of farebox revenue. Even if that were true today, much of the proposed network expansion will not gain revenue to cover its operating cost, and Toronto will face increased outlay. There is still no proposal, let alone an agreement, about the operating costs of the Crosstown and Finch LRT lines from which we might guess at how the combination of three new lines/extensions will affect the subsidy call against Toronto’s tax base.

With clear errors in the March 22 letter, the Province showed that it cannot be trusted to propose policy based on fair and accurate characterization of Toronto’s transit system. One would hope that a “Special Advisor” backed by the boffins at Metrolinx and the Ministry of Transportation might be able to avoid screw-ups. When the Province puts forward a scheme to take over part of the TTC, their rationale should be based on transparent and accurate information. Alas, recent experience in other portfolios shows that this will not happen, and dogma will trump common sense.

Metrolinx to Buy LRVs from Alstom

The Globe and Mail reports that Metrolinx has entered into a deal with Alstom, who are already building the LRV fleet for Ottawa, to produce cars for at least some of the Metrolinx projects in the GTHA. In effect, Metrolinx is looking to cut its ties to Bombardier whose car deliveries are long overdue, although the actual mechanics of this will depend on contract negotiations and whether Bombardier actually does manage to produce cars in time for the Eglinton Crosstown line’s opening.

The Alstom cars will go to Eglinton, unless Bombardier comes through, in which case they will be repurposed for the Finch and Hurontario lines. Given the opening dates planned for those lines, a decision to extend the Alstom order would come well before opening day unless the current target dates for Finch and Hurontario were changed.

Metrolinx and Bombardier still must go through a dispute resolution process, but is it clear that Metrolinx feels that they are on solid enough ground to make this move.

Metrolinx press release (May 12, 2017):

METROLINX STATEMENT ON ALSTOM / BOMBARDIER

TORONTO: May 12, 2017 – Metrolinx is taking a major step forward to ensure that the Eglinton Crosstown LRT opens on time, and that our other LRT projects are on track.

We are making great progress on the Eglinton Crosstown and are well on our way to launching this outstanding new service as scheduled in 2021.

Now, we are pleased to be able to say we have certainty that there will be trains to run on this line.  That is because we are entering into an agreement with Alstom as an alternative supplier of light rail vehicles.  Alstom will build 17 vehicles for the Finch West LRT project and, if necessary, 44 for Eglinton Crosstown. If Alstom vehicles are not needed for Eglinton Crosstown, they will be reassigned to the Hurontario LRT project.

We know for sure that Alstom’s light rail vehicles work.  They are currently producing quality vehicles on-time for Ottawa’s Confederation Line LRT project.

We are going through a dispute resolution process with Bombardier, but that could take 8-12 months, and we can’t wait that long to determine whether Bombardier will be able to deliver.

We are hopeful that Bombardier can get its program on track.   However, the steps we are taking give us a safety net if it turns out Bombardier is unable to fulfil its contract.

Our end goal remains opening our LRT projects on time with high-quality vehicles that will provide excellent service to the people of this region.  This new contract with Alstom provides flexibility to ensure that happens.

John Jensen

President & CEO, Metrolinx

Bombardier Statement (May 12, 2017)

From Marc-André Lefebvre, Head of Communications and Public Relations, Canada

Bombardier is ready, able, and willing to deliver these vehicles to the people of Toronto on time. As the Minister and Metrolinx are well aware, these vehicles can be ready ahead of schedule and well before a single track has even been laid on the Eglinton Crosstown.

In fact, the Metrolinx pilot vehicle is ready, undergoing qualification testing, and Bombardier is right now producing vehicles for the Region of Waterloo that are identical to those that will be used on the Eglinton Crosstown. All 14 of those vehicles will be delivered to Waterloo by the end of this year.

We believe what’s best for the people of Toronto and Ontario is that we work together to ensure taxpayers are not on the hook for another cancelled contract. We’ve met each and every major LRV delivery milestone in the last eight months and the proof will be in the performance of these vehicles in Waterloo and on Eglinton. We have addressed the issues raised in the past and we are confident this will be upheld in the dispute resolution process.

We are committed to working with Metrolinx to find a clear path forward; one that ensures the transit riding public has the most efficient, comfortable and reliable transit system in the world.

I will update this article as more information becomes available.

Minister of Transportation’s statement (May 12, 2017)

Youtube video of Alstom Citadis cars for Ottawa

Alstom product page for Citadis Spirit

Alstom press release (May 12, 2017)

Toronto Star article

Just think, this could have been Scarborough. While Toronto has utterly cocked up its transit planning, with substantial help from Queen’s Park, Ottawa has built and is about to open the first phase of their line.

An Invitation to Dinner

At the recent meeting of the TTC Board, Vice-Chair Alan Heisey proposed that the TTC and Metrolinx Boards should meet regularly to discuss issues of mutual interest. Such a meeting took place a year ago, but despite the best intentions at the time, nothing further came out of this. As Heisey said “It’s not as if we don’t have things to talk about” citing fare integration, Presto, the Crosstown project and SmartTrack. Using fare integration as an example, with some discussion already afoot about just what this entails, it will be better to have these discussions earlier rather than later, said Heisey. The TTC should be in front of discussions on how an integrated system will be structured in Toronto.

Heisey went on to mention that at a recent meeting of the Toronto Railway Club, of which he is a member, he learned things about the Crosstown contract he did not know such as that the operation of the Mount Dennis yard will not be done by the TTC, and that although the TTC is supposed to be operating the line, the company delivering the project would really like to do this work. This is the sort of information Heisey hopes would come out in a joint meeting, and he proposes that the TTC host the event (as Metrolinx did in 2016).

It is no secret that far more information is available outside of formal Board meetings at both TTC and Metrolinx than one ever hears on the record. Those of us who attend Metrolinx meetings regularly know that “information” is thin on the ground at these events where the primary function appears to be telling the staff how wonderful they are and luxuriating in the ongoing success of everything Metrolinx, and by extension the Government of Ontario, touches. “Seldom is heard a discouraging word” could be the Metrolinx motto.

Indeed the TTC has become infected with a similar problem recently where whatever new award(s) they manage to win take pride of place at meetings while serious discussion about ridership and service quality await reports that never quite seem to appear. Budgets do not offer options conflicting with Mayor Tory’s insistence on modest tax increases. Getting an award for the “We Move You” marketing campaign is cold comfort to people who cannot even get on a bus or train because there is no room.

Oddly enough, when TTC Chair Josh Colle contacted his opposite number at Metrolinx, Rob Prichard, the word back was that such a meeting might have to await the appointment of a new CEO. The position is now held on an acting basis with the departure of Bruce McCuaig to greener pastures in Ottawa. That is a rather odd position to take. Is Metrolinx policy and strategy so beyond discussion that without a CEO, they cannot have a meeting? How is the organization managing to push trains out the door, let along host an almost endless stream of photo ops for their Minister?

Commissioner De Laurentiis agreed that there are many issues, and warmed to the idea, but suggested an information sharing/exchange session as opposed to a formal meeting. She concurred that the type of information Heisey is gathering “accidentally” should come the Board’s way formally.

Vice-Chair Heisey noted that he was told he could not see the Crosstown’s Operating Agreement because it was confidential. For what they’re worth, here are a few handy links:

These do not include the operating agreement for the line because, I believe, it does not yet exist beyond a draft format and the intention is not to formalize it until a few years before the line opens in 2021. However, aspects of the proposed agreement are certainly known to TTC staff. Whether their interpretation matches Metrolinx’ intent is quite another issue.

Other topics for a joint meeting suggested by Commissioner Byers included Accessibility, and the working relationship between Metrolinx and Infrastructure Ontario including the topic of risk transfer.

For those who have trouble sleeping, the Crosstown agreement makes interesting, if tedious, reading. One section deals for pages on end with the contractual arrangements between Metrolinx who will procure and provide the fleet, and the project provider who must test, accept and operate (or at least maintain) the cars. This is a perfect example of the complexity introduced by multi-party agreements with the 3P model. Each party must define at length its roles and responsibilities where a consolidated organization would deal with the whole thing in house. Of course some would argue that this simply shows how keeping parts of the overall procurement within Metrolinx adds layers of complexity that a turnkey solution might avoid. That’s a debate for another day, but an important part of any future project design.

Chair Colle observed that just because you invite someone over to your house, they don’t necessarily accept, and the TTC could find itself without a dance partner. Heisey replied that we should invite Metrolinx to dinner and tell them what the menu will be. Dinner invitations are often accepted. Colle observed that any one or two of the suggested items could “keep us well nourished”.

Mihevc added to the list by suggesting both the Finch and Sheppard LRT projects. That should be an amusing discussion considering that Metrolinx and City Planning have gone out of their way to be agnostic on the subject of Sheppard East’s technology considering that there are Councillors and (Liberal) MPPs who would love to see a subway extension there, not LRT. Both Boards, not to mention their respective management teams, would go to great lengths to avoid implying any sort of commitment beyond the next announcement of another GO parking lot or a long-anticipated subway extension’s opening date.

The biggest problem with the Metrolinx-TTC relationship is the province’s heavy-handed approach whereby any move away from the “official” way of doing things will be met with a cut in subsidy. Indeed, despite increasing outlays from Queen’s Park on transit, they keep finding more ways to charge Toronto for their services. The City gets more money on paper for transit, but spends some of it to buy provincial services in a monopoly market. Even if Metrolinx invites Toronto to dinner, they will expect the City to foot the bill.

As a public service, if only to forestall imminent starvation of the TTC Board, the balance of this article explores some of the issues raised by Commissioners.

The video record of the TTC debate is available online.

[For readers in the 905, please note that this is a Toronto-centric article because it deals with issues between the TTC and Metrolinx. Municipalities outside of Toronto have their own problems with the provincial agency, not least of which is its undue focus on moving people to and from Union Station.]

Continue reading

Has John Tory Discovered Life After SmartTrack?

With all the flurry of transit funding and construction announcements lately, Mayor John Tory added his own contribution with a media statement at that busiest of stations, Bloor-Yonge. What prompted such a high-profile event? Rumour has it that Queen’s Park plans to fund the Richmond Hill subway extension in its coming budget, and Tory wants to be sure he defends the existing downtown system against overloading from the north.

(See coverage in The Star and The Globe & Mail)

Specifically, Tory wants to ensure that funding will be available for:

Building new transit lines including the Eglinton East LRT, waterfront transit and the downtown relief line

This is brave stuff, our Mayor rallying his city to the barricades [cue inspirational and very-hummable anthem here] were it not that Tory himself is responsible for much of the confusion and misdirection in transit plans today. His election campaign promoted “SmartTrack”, a single city-wide project that would solve every problem and magically be funded through taxes on new development the line would bring. A “surface subway” would speed riders from Markham to Mississauga via downtown with frequent service at TTC fares. Nothing else (except for a politically unavoidable subway in Scarborough) was needed, certainly not better bus and streetcar service to fill all those spaces in between major routes.

Things didn’t quite work out as planned. SmartTrack has dwindled to a handful of new GO stations to be built on the City’s dime, some of which Metrolinx might have built anyhow, and a few in locations of dubious merit beyond their soothing effect on local politicians. With the demise of a scheme to run GO trains along Eglinton from Mount Dennis to the Airport district, the Eglinton West LRT extension is also on the table, but it stops short of its necessary end, the airport, because Toronto lopped off the outside-416 segment to reduce the cost. Whether Mississauga and/or the airport authority itself will contribute to the LRT remains to be seen.

Tory discovered that surface routes suffered under his predecessor, and vowed more money for buses. Toronto bought the buses, but money to actually operate many of them is harder to come by. The only thing that saved the TTC from widespread service cuts in 2017 was a last minute City budget fiddle to bump the expected revenue from Land Transfer Tax.

Meanwhile in Scarborough, SmartTrack and the Scarborough Subway Extension vie for the same pool of riders, and it is only the comparatively infrequent GO service that preserves any credibility for the subway extension. Planners who once argued that an east-west line through the Town Centre precinct would better serve future development now compliantly endorse the supposed benefit of a single new north-south station between McCowan and the shopping mall.

Mayor Tory might now think of both ST and the SSE as “done deals”, although there’s a lot of ground to cover before the final cost projections and approvals by Council. Those extra GO stations and the express subway might still cost more than the preliminary estimates shown to Council, but there’s no more money coming from Queen’s Park. Indeed, the two governments cannot agree on how to calculate inflation in the provincial “commitment”, and Toronto thinks more money is on the table than is likely to be available. After all, Tory is in no position to tell a funding government how much they will pay out. Even those numbers are subject to change if the Liberals lose control of Queen’s Park to the Tories, as seems very likely in 2018.

Then there’s Ottawa and Trudeau’s huge infrastructure program, just the thing a politician who is desperate to make everything seem affordable could wish for. Except, of course, that the infrastructure pot isn’t bottomless. Once it is divvied up across the country, Toronto’s share is well below the level John Tory hoped to spend with his shiny new Liberal red credit card. Holding press conferences about the need for projects won’t change the amount of money available, and the federal program requires that municipalities, even big irresponsible ones, must set priorities. Tory’s plans also require Queen’s Park to come in with funding equal to the Fed’s contribution at a time when provincial budgets are tapped out, and Toronto’s ongoing game of holding down taxes rather than pay for its own services and infrastructure plays poorly beyond the 416.

What does the Mayor do? John Tory, the man who had a one-line plan to solve everything, now looks to a world beyond SmartTrack.

Continue reading

SmartTrack’s Next Steps

After a day-long debate, Toronto Council has approved continuing along the path set by Mayor John Tory to study and possibly to build the transit lines branded as “SmartTrack”. Although this proposal is now much different from the scheme that was Tory’s campaign centrepiece, the idea of SmartTrack continues to receive broad support among Councillors.

The debate covered a lot of ground with two related threads: how would Toronto actually pay for SmartTrack, and how much of the larger transit network many hope to see will actually be built.

Council has yet to consider a long-term financing strategy and possible “revenue tools” (new taxes in plain English) to deal with the combined capital and operating budget demands of the would-be network. Although there was much talk of the lost decades of underinvestment in transit, Council has yet to show that it really is ready to spend Toronto dollars (as opposed to  money from any other source) at the level that will be needed. City staff will present a report on financing options in a few weeks, and the reaction to this will be telling.

What Did Council Approve?

Below is a consolidation of the staff recommendations and amendments adopted by Council arranged to keep related issues together. For full information, please refer to the detailed record of the item.

Note that in all cases where approvals relate to “SmartTrack” this includes both the six new GO stations and the Eglinton West LRT extension unless otherwise noted.

Process:

  • (1) Adopt the “Summary Term Sheet and Stage Gate Process” which includes details of the many parts of the proposed agreements and (2) authorize the City Manager to negotiate and execute agreements with the province to implement this.
  • (3) Request staff to report at Stage Gate 5 for final approval of full funding for SmartTrack. A report on more definitive costing and the financing funding strategy has been requested for an earlier step in this process. See (18) below.
  • (4) Approve the confidential staff recommendation regarding settlement of the Georgetown corridor funding issue. See also recommendation 15.

Technical and Planning:

  • (5) Proceed with planning and design for the six SmartTrack GO stations, report back to Council, and launch the Transit Project Assessment Process (TPAP). This was amended by two further requests that the work include improvement of:
    • the placement and access points of the Liberty Village Smart Track Station to maximize connectivity, and
    • pedestrian connections to the existing Exhibition Place Station for both Liberty Village and Exhibition Place.
  • (6) Confirmation of city support for transit supportive land use plans for areas around the SmartTrack and GO RER stations. Amendments related to this included:
    • Amending the development strategy for public lands at stations, including air rights, to create ongoing operating revenue streams from development resulting from that strategy.
    • Directing the Chief Planner to report in January 2017 with options to develop a comprehensive plan for managing development and growth related to transit expansion.
    • Confirming that the Official Plan as well as other plans, bylaws and policies, are not changed by this decision on this item. The intent of this is to forestall any claim for additional density by would-be developers in advance of the passing of updated plans for area affected by transit projects.
  • (7) Proceed with planning and analysis of the Eglinton West LRT extension up to Stage Gate 3 including finalization of stops and grade separations, provide a scope for this project up to the Renforth Gateway, and provide a class 4/5 estimate of the project’s cost, and conduct the TPAP. Note that this is a more restrictive approval seeking more detail than in the case of the ST/GO stations in (5) above.
  • (8) Request a financial contribution from Mississauga and Pearson Airport to the outside-416 portion of the Eglinton West extension.
  • (9) Ensure that the proposed new station design at St. Clair and Keele includes improved road operations and is co-ordinated with the St. Clair West Transportation Master Plan. A significant part of this would be the widening of the underpass east of Keele Street to remove the existing choke point.
  • (10) Request Metrolinx to consider grade separations at Progress and at Danforth on the Stouffville corridor, with the proviso that any option closing existing roads would not be considered. This was amended at Council to add requests for grade separations at Passmore, McNicoll, Huntingwood and Havendale.

At Council, there was an attempt to have items (7) and (8) deferred until after the Waterfront Transit Reset report is considered by Council in 2Q17, effectively putting both of the proposed Etobicoke LRT proposals on the same approval timeframe. The deferral motions did not pass.

Finance:

  • (13) Approve $71m for preliminary planning and design on SmartTrack (the 6 new stations plus the Eglinton West LRT)
  • (14) Include $2b in net capital requirements for SmartTrack (stations plus LRT) in the city’s 10 year capital projections.
  • (15) Approve $95m for settlement of the Georgetown South issue with the province.
  • (16) Approve $62m for Toronto’s share of 5 grade separation projects.
  • (17) Approve $60m for GO capital expansion (2 stations at Bloor/Lansdowne and at Spadina on the Barrie corridor). This was amended to ask that staff work with Metrolinx on including the study and design of the Railpath along the Barrie line between Bloor and Dundas West.
  • (18) Request staff to develop the financing and funding strategy, and report back when a class 3 cost estimate is available for a definitive Council commitment to the SmartTrack project.

Two additional amendments ask for:

  • strong TTC in developing procurement options, and
  • negotiations with the province for resumption of operating subsidies.

Commitment to the full cost of the new stations and the Eglinton West LRT will not occur until much more detailed cost estimates come back to Council over the next year (or possibly more). In the event that Council opts not to proceed with any component for which Metrolinx has spent money on development prior to the point of final approval, Council will be responsible to reimburse Metrolinx for its costs.

With respect to the additional grade separation studies requested for the Stouffville line, it is unclear how work on this would be funded, although one might expect Metrolinx to respond with a request for some up-front payment and guaranteed participation in funding if any of these goes ahead.

The Status of Other Major Transit Proposals and Projects

Planning and building any part of SmartTrack should be seen in the wider context of other transit needs and schemes, let alone wider demands on the city’s operating and capital budgets.

  • The Spadina Subway extension to Vaughan (TYSSE) is scheduled to open at the end of 2017, although startup costs will affect the TTC’s operating budget before any passengers are carried. For 2018, the current estimate of the annual operating cost to Toronto is $30 million including whatever marginal fare revenue the extension will bring in. This line’s capital was covered roughly one third by each level of government, with about 60% of the municipal share falling to Toronto based on the proportion of the route within its boundaries.
  • The Scarborough Subway from Kennedy Station to Scarborough Town Centre remains the subject of much debate. Although its capital cost is already covered by money from all three levels of government, the proportions are unequal, and any increase to the overall Scarborough transit scheme will be on the city’s tab. The extension will be part of the TTC’s operation along with the net new operating cost, an unknown amount at this time. A critical issue will be whether the cost estimate overall will hold or increase before final project approval, and how this will affect what actually gets built.
  • The Eglinton Crosstown LRT is now under construction by Metrolinx between Kennedy Station and Mount Dennis (at Weston Road) with a planned 2021 opening, subject to issues about vehicle delivery. This project’s capital cost is funded totally by Ontario, but operating costs will be billed back to Toronto at an anticipated annual net amount of about $40 million in then-current dollars.
  • The Eglinton East LRT extension from Kennedy Station to University of Toronto Scarborough College is part of the Scarborough package approved with much fanfare earlier in 2016. The capital cost is part of the same “pot” as the Scarborough Subway extension, but how much will actually be available after that extension’s scope and price are firmed up remains to be seen. This will be an early test for Council. Does it really believe in a “network”, are councillors willing to accept the extra cost as part of building our city, or is the argument still dominated by an outlook claiming that tax restraint must take precedence. An updated Scarborough report is expected in coming months.
  • The Eglinton West LRT extension from Mount Dennis to the Renforth Gateway (at the western city boundary) and then north to Pearson Airport is part of the SmartTrack package. Funding for the line is still uncertain because city plans depend on contributions from Ottawa (likely as part of the Liberal’s infrastructure program), from Mississauga and the airport authority (GTAA) for the portion outside of Toronto. This extension is now the more expensive portion of “SmartTrack”, and ironically appears to survive mainly because of that branding despite opposition from some Etobicoke councillors.
  • Like the central part of the Crosstown, the two extensions would be operated at the city’s expense even though the lines would be owned by Metrolinx.
  • The Metrolinx GO RER program is provincially funded, although the matter of the municipal contribution to GO’s capital remains a sore point between Queen’s Park and the GTHA. Toronto will pay for six new stations as part of SmartTrack and will also contribute to two stations on the Barrie corridor (Bloor/Lansdowne and Spadina). GO RER’s net operating costs will all be a provincial responsibility, and the amount of service that will actually operate depends on future subsidy levels for Metrolinx. Similarly, the full build-out of RER fleets, electrification and service levels will depend on future provincial budget decisions.
  • The Relief Line remains under study thanks to a provincial infusion of $150 million, and both city and TTC staff emphasize that it is a necessary part of Toronto’s future network. While some relief to Yonge line crowding will come from GO RER and the new SmartTrack stations, this will only blunt but not stop the growth in subway demand. A big problem, as readers have discussed here at length, is the project’s scope and the perception that it is intended for a comparatively small part of the system’s ridership, downtowners. The further north the eastern RL branch goes beyond Danforth (to Eglinton or even to Sheppard), the more it performs a service for the city as a whole, but this benefit is routinely underplayed relative to the cost of a new north-south subway. Major capital spending for the Relief Line would not begin until the mid 2020s, but this will still compete with other city priorities.
  • Waterfront LRT to the west is popular with councillors from southern Etobicoke and has begun to overshadow the shorter eastern LRT line in debates. Both parts of a future waterfront network are under review with the “Reset” study now in progress that has only progressed to the point of developing a moderately long list of options. The strategy appears to be to keep this list as open as possible as long as possible so that political fights over the details are held off at least until there is a better understanding of what will work and what the options might cost. Like the RL, waterfront transit has suffered from being perceived as a “downtown” project despite the scale of development it will have to serve.
  • The Finch West LRT is still on the books, and Metrolinx hopes to begin work in this in 2017. There remains some opposition to the line, and it will be a test of the Wynne government’s resolve to see whether actual work is pushed back beyond the 2018 election.
  • The Sheppard East LRT is also still on the books, although it is no secret that many politicians at City Hall and Queen’s Park would love to see this sacrificed for a Sheppard Subway extension. The LRT would be a provincial project with some federal money. There has not yet been any cost sharing commitment to a subway replacement from any government in part because the cost is unknown. It will almost certainly be greater than the LRT line, and like the extension north from Kennedy, will serve a considerably smaller part of Scarborough than the LRT would have. Any decision on this point is likely to fall to the next provincial government, although it will likely be part of the electioneering to reinforce the “subway champion” brand by all parties if this scheme gains traction at Council.
  • The Richmond Hill extension of the Yonge Subway is a project long-sought by York Region, but the idea is tangled up with network relief from GO RER, the Relief Line and other capacity improvements still pending for the existing subway. Some of these, such as added operating cost for more trains on Line 1 YUS, and capital cost for station capacity impeovements, will fall to Toronto. Whether any of the funding pools now thought to be available for transit projects generally will still be available by the time a decision on Richmond Hill faces council, indeed whether this decision will even be in Toronto Council’s hands, are questions for a future beyond any of the existing governments.
  • Not to be forgotten for its demand on city funding is the surface transit system including the bus and streetcar network. While billions in new projects preoccupy debates, a long-standing problem faces Toronto with population growth, much of it “downtown”, that has not been matched by additional transit. Indeed, transit service today is little changed from twenty years ago largely because the TTC streetcar fleet sits roughly at late 1990s levels, and traffic congestion has been responsible for service cuts to stretch the available fleet. Current operating budget plans at the TTC foresee a major shortfall in 2017 that appears unlikely to be addressed by a supposedly pro-transit council and mayor, and this will almost certainly continue into the 2018 election year. On the capital side, the TTC requires an additional batch of streetcars beyond the 204 now on order from Bombardier. Both the financing and supply of this fleet expansion are on shaky ground. As for the bus fleet, TTC management seems more preoccupied with simply replacing its existing fleet of hybrid buses with diesels rather than actually expanding the level of bus service to Toronto.

In this context, the SmartTrack decision is only a small part, and Council has yet to be presented with a comprehensive view of the effect building a real transit network, rather than a few lines, will have on its budget and future financing requirements.