TTC Board Meeting July 22, 2026

The TTC Board will meet on July 22 at 9:30am in Committee Room 2 at City Hall. The agenda includes several confidential items, and it is not yet clear when they will be considered and what period will be an open public session. As usual, the public portion will be streamed for those not making the trek to City Hall.

Items covered by this article:

  • CEO’s Report
  • Transit Network Expansion Update – Provincial Projects in Delivery
  • New Entrance to Spadina Station
  • New Entrance to Eglinton Station
  • Large Contract Awards
  • A proposed study of speeding up the 506 Carlton streetcar

Items with confidential material include:

  • A update on the Fare Collection System
  • Fitness for Duty Grievance Update

There is also an Accessibility Plan Status Report. I will cover this in a separate article.

This will be the last meeting of the current TTC Board before the municipal election in October.

Continue reading

Metrolinx Board Meeting – June 25, 2026

The Metrolinx Board met on June 25, and as usual for that secretive organization, most of the agenda was discussed in private session. What they do talk about in public is inevitably “good news”, and there is rarely any indication that the Board might have issues with management.

Items included in this article:

  • Write-Down of GO Transit Assets
  • GO Transit Project Status
  • Update on Line 5 and Line 6 LRT Operations
  • Fare Enforcement Bylaw Update
Continue reading

Reviewing TTC Surface Delay Data 2025-2026

This article is a followup to a review of subway delay data published here in early June.

Four sets of data are summarized here:

  • Bus data January 2025 through April 2026
  • Streetcar data January 2025 through May 2026
  • Line 6 Finch data December 2025 through May 2026
  • Line 5 Eglinton data February through May 2026

There is no bus data for May 2026 because the TTC’s June 22, 2026 update on the City’s Open Data site did not include it.

The Open Data files include a key translating delay codes to text. However, many codes used in the logs do not appear in the key, and in those cases I have used “?” in the tables. I have asked TTC for an updated code list, but they have not replied.

Among the information shown in these delay logs:

  • “No Operator Available” is a serious problem related to TTC staffing levels.
  • Diversions account for a large number of delays, notably on the bus network, not just streetcars.
  • Collisions involving buses and streetcars are common.
  • Weather related delays including autos blocking tracks peak in winter months for buses and streetcars.
  • Streetcar delays related to switches are reported under various codes, but there is no code for derailment thereby masking the number of the most serious track-related events.
  • The number and length of delays on 6 Finch have fallen by over 50% since the opening months.
  • A common source of delay on 5 Eglinton relates to guideway intrusion.
Continue reading

Line 5 Eglinton Hours Extended

The hours of service on Line 5 will be extended effective April 5, 2026. Trains will run later into the evening with buses covering the route at other times.

Service now ends just before 11pm inbound from the terminals, but will be extended to 1:20am weekdays and Sundays, 12:30am on Saturdays.

Bus services on Eglinton remain the same:

  • 34 Eglinton provides local bus service every 20 minutes from 6:00am to 1:30am (8:00am start on Sundays).
  • The Line 5 shuttle bus will continue to run between 10:00pm and 1:00am stopping only at Line 5 stops.
  • The 334 Eglinton night bus runs from 1:00am to 5:30am (7:30am on Sundays).

Whether the Line 5 shuttle late night operation will continue beyond the next schedule change remains to be seen as it duplicates the extended LRT service.

34 Eglinton East Bus: Travel Times East of Don Mills

With Line 5 Eglinton entering its second week of operation, comparison of LRT and bus speeds on the surface portion of the route is inevitable, especially among those who would prefer subways everywhere.

This article reviews the actual travel times in December 2025 and January 2026 for the bus service that was replaced by Line 5. This gives a variety of operating conditions including holidays and winter storms, and reflects stopping patterns and dwell times for the level of demand before Line 5 opened for business.

Actual bus travel times only bettered the scheduled LRT from mid-evening onward on weekdays, and were considerably longer in the PM peak. For trips to/from Kennedy Station, the LRT has an advantage of a more direct path into the station avoiding both the traffic signal at Kennedy Road and the roundabout bus route within the terminal.

The section of Eglinton where the LRT runs at the surface is uncongested during much of the day compared to other routes in the city. Some spots have slower bus travel times, but these do not persist. This is a challenge to “better” performance by the LRT unless it has some advantage over buses notably in faster speed during all operating periods, good priority at traffic signals and reliable travel times when the adjacent road is congested.

The potential for faster LRT trips through transit signal priority lies in the 2-4 minute range, an improvement of 10-20%, depending on how aggressively this is implemented. There are 14 traffic signals over the route between Ionview and the DVP, and a variety of locations with nearside, farside or no stops at these points. The Transit Signal Priority strategy should be tuned to the characteristics of each crossing.

This analysis does not include additional access time to LRT vs bus stops. This affects the surface section of Line 5 less than the underground section where both station spacing and vertical access times add to LRT journeys.

Detailed tracking data for Lines 5 and 6 are not available from the TTC although “next train” predictions are in their public data feed. This hampers analysis of the reliability and travel times of the new LRT lines.

Continue reading

Metrolinx Board Meeting: February 12, 2026

The Metrolinx Board met on February 12 with an extensive agenda, but as usual almost none of it was discussed in public. Of particular interest was an explanation of the derailment at Union Station that snarled GO Transit operations for much of the past week. Although a detailed review continues and a full report is promised, Metrolinx was unusually forthcoming with a description of the event.

The public portion of the meeting began with a “safety moment” that focused on problems with pedestrian, cyclist and auto intrusions into the Eglinton and Finch rights-of-way. This was discussed in a tone reminiscent of GO mainline rail corridors which the new LRT lines definitely are not. In the case of Finch, the right-of-way has less physical protection than on Eglinton, and no areas of open track or grass to signal that this is not part of the overall roadway.

The very nature of a surface route, regardless of technology, is that people and vehicles will cross the tracks. They have been doing it for over a century on the streetcar system, and it is odd that Metrolinx finds this an unusual behaviour. It is not clear, other than the presence of two separate P3s on these projects, why the Eglinton and Finch designs are so different. This also contributed to the switching problems on Finch because of inadequate heaters and drainage.

Reviewing the operation of Finch, Metrolinx CEO Michael Lindsay made no mention of equipment reliability, a major problem on that line compared to Eglinton. As revealed in TTC delay logs, at times there were not enough working cars to operate the scheduled service. Delays due to “mechanical problems” continue to appear in Line 6 service alerts. The logs in the City’s Open Data website do not yet include January 2026, but when they do, I will publish a review.

Speaking of Finch, Lindsay spoke of recent improvements. At Metrolinx’ urging, the P3 partner, Mosaic, took steps to improve infrastructure maintenance. The line is now into a stage of “perfection” of operations and maintenance protocols as opposed to building issues. The issue is the readiness of private sector partners to deal with climate effects, and more generally to bring their supposed expertise from other systems to Toronto. Only recently has Mosaic hired someone with expertise in cold weather operations.

Lindsay reported that all 55 switch heaters on Finch have been checked, and drainage at 40 sites is improving. Performance stats are better since the record snowstorm of January 25 with 95% availability, and TTC on time performance is 70-80% over past couple of weeks. This may sound impressive, but any stats are bound to look better as weather improved. As for OTP, TTC standards allow for erratic service as discussed here many times.

In all the celebration of Eglinton’s recent opening, Lindsay made no mention of accessibility issues with several elevators out of service including at key interchanges like Don Valley, Eglinton and Mount Dennis. Further problems include long walks to transfer between routes and less than adequate signage. Metrolinx is supposed to have design standards, but if these lines are any indication, they desperately need review. In many ways, this was the usual Metrolinx “good news” presentation which skated around problems, or presented them as past events no longer of concern.

On the subject of “lessons learned”, Lindsay claimed that private sector partners underestimated complexity, risk, and challenge of the projects, but gave no indication that Metrolinx or Infrastructure Ontario bore responsibility for assuming more expertise within the P3s than might actually have existed. There was a hint that things might have gone better. Lindsay noted that Metrolinx has changed processes, a reference to the shift to an “alliance” model where the P3 are treated as collaborators.

Lindsay hinted at problems with the Metrolinx regime and its confrontational nature saying that all parties need to remain focused on project completion, not commercial claims. They must do the right things for the good of a project even if this compromises legal or commercial strategies. Design review and acceptance must be much more efficient and less bureaucratic in all hands. When unexpected issues such as cavities in the original 1950s Eglinton Station box are encountered, a quick regulatory process to respond is needed.

Lindsay noted that there must be an early and insistent focus on systems integration — bricks and mortar are only one milestone. More important are testing, commissioning and interoperability. This should be no surprise to anyone with transit experience. Construction is a large and impressive part of a project, but without well integrated, reliable systems and vehicles, billions of dollars worth of tunnels are useless.

He remarked on another aspect of P3s that is rarely discussed: procurement must ensure that joint ventures have a collaborative relationship without their own contentious internal issues.

Better public communications on construction, cost estimates and timelines are needed.

These remarks, for those reading between the lines, are not a ringing endorsement of how Metrolinx operated on two major projects. They might have learned lessons from the experience, but the proof will show in how work now underway actually proceeds.

Continue reading

TTC Service Changes Effective February 8, 2026

Updated February 10 at 9:50am: This article was updated in stages. All pending updates are now in place with the most recent being at the end.

Changes:

  • Maps with more detail have been substituted for added clarity.
  • Maps showing bus bay allocations at stations have been added.
  • Changes to routes not affected by Line 5 opening have been added.
  • The list of current construction projects affecting routes has been added.
  • Notes about transfer connections between buses on Don Mills and Don Valley Station.
  • A detailed before-and-after spreadsheet showing operating plans, vehicle and garage assignments, etc.
  • A list of updated destination signs.
  • Construction project list.
  • Vehicle allocation tables.
  • Service budget information.

In addition to Line 5 related changes, there are also updates to:

  • 6 Finch West
  • 7/307 Bathurst
  • 21 Brimley
  • 30 High Park North
  • 31 Greenwood
  • 39 Finch East
  • 80 Queensway
  • 84 Sheppard West
  • 384 Sheppard West Night Bus
  • 101 Downsview Park
  • 106 Sentinel
  • 111 East Mall
  • 116 Morningside
  • 133 Neilson
  • 149 Etobicoke-Bloor
  • 189 Stockyards
  • 927 Highway 27 Express
  • 935 Jane Express
  • 830 Henry Kelsey–Middlefield (new school service)
  • Other routes with school trips.
  • 301/501 Queen
  • 506 Carlton
  • 507 Long Branch

These are described at the end of the article.

Continue reading

How Fast Will Line 5 Be Compared to the 32/34 Bus?

With the imminent opening of Line 5 Eglinton LRT on February 8, the TTC has repeatedly been asked “will it be faster than the bus”. They have said, yes, but with few details.

On February 3, the online schedules (GTFS format) came out for the next period including stop-by-stop travel times for Line 5. This article compares these times with the existing schedules for the 32 Eglinton West and 34 Eglinton East buses. The LRT is almost always faster except late in the evening, and then on only part of the route.

Later in the article are charts of scheduled speeds and stop spacing for the bus and LRT operations.

Continue reading

Will Line 5 Eglinton Open In February?

The TTC has posted an internal notice that the operators’ sign-up for work in the period starting February 8, 2026 has been delayed because of the complexity of changes happening concurrently on the bus network.

The year 2026 is in the memo giving hope that the line may actually open soon.

Thanks to Gamile Anthony King for posting this on Facebook

Metrolinx Hands Line 5 Crosstown to TTC

Ooops! The initial version of this article used Line 6 in the title. I am too focused on the impending Finch opening!

The Ontario Ministry of Transportation has announced that the Line 5 Crosstown project achieved substantial completion today, December 5. The line is now transferred to the TTC for operation.

No start date has been set, and the TTC will have to conduct its own final pre-service testing just as they did on 6 Finch after the provincial hand-off. A likely date would be mid-February which corresponds to a planned schedule change far enough in the future to accommodate both Line 5 testing and the crewing process for concurrent network changes.

The opening of Line 6 on December 7 is a “mid period” change that is not part of the TTC’s regular cycle, but is likely due to a political desire to complete at least one of the lines in 2025.

According to the Ministry, service on Line 5 will ramp up:

Opening Day

  • Operation from 6am to 11pm
  • Peak service every 4’45”

Six-Month Service

  • Operation from 5:30am to 2:30am
  • Peak service every 3’30”

The TTC has not announced what type of supplementary service will operate during the six-month interim period, nor the service to be provided on a parallel 34 Eglinton bus from Kennedy to Mount Dennis Station in the long term.