Street Construction Project Update: July 2021

Although this is high construction season, various projects are moving along more slowly than hoped.

Broadview from Gerrard to Danforth

Work on the watermains in this area was delayed by a shortage of pipe. This has now been solved, and work is in progress north from Hogarth/Montcrest to Danforth (as of July 22). When that is done, the southern section will follow.

Queen Street West from Bay to York Street

The work here includes both watermain and track renewal. As of July 22, saw cutting of the pavement was underway.

As previously reported, the track and watermain work on Queen will occur in stages west from Bay to Spadina, and then east from Fennings to Spadina. There is a supply of new track strings on the north side of Queen in front of City Hall and on the north side of Queen at Trinity-Bellwoods Park.

Queen Street West from University to Spadina

New support poles will be installed here in anticipation of conversion of the overhead for pantograph operation.

King-Queen-Queensway-Roncesvalles

As of July 4, the switches for the yard leads from The Queensway had been installed, but not the connecting tracks across the north sidewalk to the yard. Excavation and some foundation work for Sunnyside Loop was underway.

On the north side of The Queensway from Sunnyside west to Claude (the beginning of the streetcar right-of-way), the curb lane was excavated and a new north curb poured. The situation was identical on July 22.

Looking West on The Queensway at Sunnyside Loop Entrance July 4/21
Looking West on The Queensway from Sunnyside Avenue July 4/21
Looking West on The Queensway at Claude, July 4/21

The photo below shows the south side of Roncesvalles Yard including the forest of poles holding up the overhead.

Looking East on The Queensway toward Roncesvalles July 22/21

On July 22, the connecting switches to a realigned Sunnyside Loop were in place. In the photos above and below note that the existing loop tracks do not align with the new switches. This intersection will be revised with signals for autos and streetcars with, in theory at least, priority for streetcars leaving the loop.

Looking East across Sunnyside Loop July 22/21

Queen/Kingston Road Overhead Replacement July 26 to August 5

Streetcar service on Queen east of Leslie Street will be suspended from July 26 for overhead upgrades and track repairs on Queen from east of Leslie to Woodbine.

501 bus service that now ends at Broadview will be extended east to Neville Loop.

A 503 bus shuttle will operate on Kingston Road between Bingham and Woodbine Loops.

Brown’s Line & Lakeshore Queue Jump Lane

The project to create a queue jump lane on the approach to Long Branch Loop is on hold. I await feedback from the TTC on the status of this project.

Photo credit: All photos are by me.

Service Reliability on 35/935 Jane

This article continues a series reviewing the behaviour of service on routes that are either part of the RapidTO bus lane network or have been proposed for inclusion in future stages of its rollout.

See also:

The 35 Jane and 935 Jane Express buses operate between Jane and Pioneer Village Stations and follow identical routes except for a peak-only 35B Jane branch that operates via Hullmar between York Gate and Steeles.

This article deals with:

  • The change in travel times for the local 35 Jane service between Eglinton and Steeles (the portion of the route proposed for Rapid TO) from pre-pandemic traffic conditions and their evolution through the low point of demand and congestion in 2020 through to June 2021.
  • The difference between local and express services.
  • The reliability of service.
  • The effect of construction of the 6 Finch West LRT.

The High Points

Although much of Toronto’s traffic congestion and transit riding have not returned to pre-pandemic levels, the travel times on the Jane bus are now as high as or greater than values in November 2019, particularly in the PM peak. Southbound travel times were historically longer than northbound, and this pattern continues today.

Construction at Finch produced substantial congestion on the approaches in both directions during the latter weeks of June 2021. However, this was not the only location where traffic congestion, as measured by slower travel speeds, rose later in June.

Headways (the time between buses) are less reliable in the afternoons and evenings on both the local and express services, and this worsened in late June with the combined effect of construction delays and schedule changes. Waits for express buses can be so long that they outweigh the benefit of an “express” trip.

Service can be irregular even on weekends when conditions that disrupt weekday operations are either absent or at a much lower level. This shows a need to better manage service so that disruptions, when they occur, are clearly the product of external conditions, not of laissez-faire operations.

Continue reading