TTC Subway & Streetcar Infrastructure Projects 2023-24 (Updated)

The TTC has published its planned schedule for various streetcar infrastructure inspection and repair projects for 2023, and a look-ahead to 2024.

See: Subway Closure and Streetcar Diversions – 2022 Review and 2023/2024 Forecast

This article was updated on January 19, 2023 at 8:45 pm with additional illustrations from a staff presentation to the TTC Board.

See: Board Report Briefing Subway Closure & Streetcar Diversions – 2022 Review and 2023/2024 Forecast

Subway

The full list of closures begins on p 13 of the report. There is a variety of full weekend, early closing and late opening events (check the legend to the chart).

There are fewer Line 1 closures in 2023 due to ATC (Automatic Train Control) than in 2022 because the main work is complete. However, there is a follow-up phase that will require some weekend closures for testing and implementation. Other work affecting Line 1 includes repair of station finishes on the University subway, elevator installation at Lawrence, various track replacements, and preliminary work at Finch for the Yonge North Subway Extension.

On Line 2, there will be work at Kipling to add a new storage track, preparatory work at Kennedy for Scarborough Subway Extension, preparatory work on the east end of the line for ATC installation, and some track replacement work. As usual there will be several late openings of service on Sundays for beam replacement on the Prince Edward Viaduct.

Many closures involve only an early shutdown of subway service to give a longer overnight maintenance window than would be possible with normal hours of service.

Streetcar

There is a long list of events for the streetcar system, but many of them are short interruptions of overnight/weekend work for inspections or minor repairs.

The major trackwork planned in 2023 is listed both in the report (starting on p 19) and on the TOInview map of City construction projects. The schedule implies that a good chunk of the streetcar system will be shut down at various times during the year. The Ontario Line contributes some of this to the Queen car, but the long-suffering riders on King do not get a break either after years of work at King-Queen-Roncesvalles. Note that Adelaide from York to Victoria is a Metrolinx project and so does not appear in this list.

Some of the dates in the TTC list do not align with info on TOInview. This is very common.

Parts of the schedule simply do not make sense. Some projects have far more time reserved than they should take based on past experience. Some projects will block the routes from carhouses in the east end to the rest of the network either via Queen Street or via Coxwell and Gerrard Streets, and times for these overlap.

Update: The TTC confirms that planned work on Gerrard Street will not occur at the same time as projects on Queen will block access to Leslie Barns and Russell Carhouse. See the map at the end of this section for a graphic view of the planned work.

Details of the Broadview Station Loop expansion are not yet available, nor is it confirmed whether this will actually occur.

I hope to get clarification of what is going on from the TTC.

  • Feb 27-Mar 26: King Street West from Close to Strachan
  • Mar 10-Oct 29: Dufferin Loop
  • Mar 24-Nov 28: Queen Street East from Carlaw to Leslie & Leslie to Greenwood
  • Mar 31-Apr 7: Intersection of King & Church
  • May 1-Nov 29: York from Queen to Adelaide (Ontario Line diversion)
  • May 6-July 8: Intersection of Lower Gerrard & Coxwell
  • May 6-Nov 21: Russell Yard
  • May 14-Nov 8: Broadview from Gerrard to Broadview Station
  • June 18-July 29: Intersection of King & Parliament
  • July 30-Nov 18: Metrolinx work at Queen/Degrassi overpass
  • Sept 3-Oct 2: Broadview Station Loop
  • Sept 7-Oct 29: Queen from Parliament to River & Davies to Broadview
  • Oct 8-Dec 16: Oakwood Loop
  • Oct 16-Feb12: St. Clair West Station Loop

The report does not list specifics for 2024, but info already appears on the TOInview map. It is not clear how some of this work will interact with Metrolinx Ontario Line construction at King & Bathurst. There is a proposed track and lane realignment at Bathurst & Fleet, but it is not clear whether this will actually occur, or if the planned work is simply replacement of existing special work as is. Details of the Spadina Station streetcar loop expansion are not yet available.

  • St. Clair & Yonge
  • St. Clair & Bathurst
  • Queen St. W from O’Hara to Triller
  • King St. W from Strachan to Spadina
  • King & Queen (Don Bridge)
  • Bathurst St. from Queen to Front
  • Bathurst & Queen
  • Bathurst & Fleet
  • College St. from Bay to Yonge
  • Main & Gerrard
  • Russell Yard (continuing from 2023)
  • Expansion of the streetcar platform at Spadina Station Loop

Update: The following map was included in the staff presentation to the Board on January 19, 2023.

This map contains several geographic errors:

  • The project labelled Queen & Yonge points at King & Spadina.
  • The project for St. Clair & Bathurst is shown east of St. Clair West Station rather than west of it.
  • The project for St. Clair & Earlscourt is shown well west of Lansdowne rather than east of it.
  • Carstops on Queen East at Wineva and at Waverley are shown as west of Kingston Road rather than east of it.
  • The project for Queen & Jarvis is shown well west of Yonge.
  • The project for Fleet Loop actually points to Exhibition Loop.

There are a few more, but my point in cataloguing them is that this is sloppy work and it speaks to the quality of information presented to the Board by management.

Pantograph Conversion

Gradually, and several years behind the original target date, the TTC has converted overhead wiring designed for trolley poles first to a hybrid pole/pantograph configuration, and then to pure pantograph style. A map of the current status was included in the staff presentation.

There are some problems with this map which is based off of a track plan that is itself out of date. “Wrong way” track has been removed from the one-way streets downtown, although it still appears here. Also, some work is underway on King West even this is not shown with the orange “in progress” colour. The intersection of King & Shaw had already been converted to Hybrid format when I visited it a month ago. (There are other errors in the map, but please don’t bother commenting with fixes.)

One amusing relic is the legend “Hillsdale Ave” on Lake Shore Blvd West. This was the site of a long-removed wye, the last in the system, and the street is called “Hillside Ave”. “Hillsdale” is in North Toronto.

Again, this is an unfortunate example of how the “official” records of the system are out of sync with actual conditions in the field.

TTC Track Construction Update December 22, 2022

King-Queen-Queensway-Roncesvalles

Updated December 23, 2022: The City has issued an update stating that the work on Roncesvalles will not be finished until at least the end of February, and The Queensway will not be complete until Spring 2023.

  • Stage 3 work on Roncesvalles will be completed by the end of February 2023.
  • Work will continue after this period with the installation of TTC streetcar track platforms and overhead wiring, with only lane restrictions as necessary.

The final major piece of trackwork installation is underway. Once new paving is in place, the overhead can be restored and, at least in theory, streetcars can return to Roncesvalles Avenue. This is likely to be confined initially to carhouse moves to and from Howard Park until TTC schedules catch up. A service restoration date for 504 streetcars has not yet been announced, but the mid-February schedule change would be the first opportunity. (As I write this, the January changes have not yet been announced.)

With the revised completion dates announced by the City, the first schedule change that could restore streetcars to Roncesvalles would come at the end of March or early April. It is possible that bus service on Roncesvalles could be restored as work north of Queen reaches a point where some lanes can be opened.

Meanwhile, although road construction continues on The Queensway between Sunnyside and Parkside, only the span wires and hangers are up at Sunnyside Loop, but no contact wire. There is still no track between Glendale (St. Joseph’s Hospital stop) and Parkside (the first stop on the Queensway right-of-way). Paving of the new curb lane eastbound from Parkside to Roncesvalles was underway on December 22, and the new eastbound Glendale stop platform is now in place.

Dates for restoration of streetcar service to Sunnyside and to Long Branch have not been announced.

The City’s update puts completion of the road work in Spring 2023. Whether this will include restoration of track and overhead remains to be seen.

  • As part of work being completed on The Queensway (Parkside Drive to Roncesvalles Avenue), the contractor has uncovered conflicts with underground utilities that require modifications to the designs.
  • The Stage 2 work is now expected to be complete in Spring 2023. Upon completion, all travel lanes on The Queensway will be restored and northbound access to Sunnyside Avenue from The Queensway will be reinstated.  

Dundas Sinkhole

A major sinkhole on Dundas near Brock caused a service diversion of route 505 Dundas via College and Ossington. This ended in the early evening of December 19. The photo below, provided by reader Raymond Lee, shows the track restoration in progress on December 10.

Reinstalling track over Dundas sinkhole. Photo by Raymond Lee.

King & Shaw

Service was restored to King Street west of Bathurst on December 9, 2022. 504A Distillery cars run to Dufferin Loop. 504B Broadview Station cars run to Bathurst Street.

Adelaide Street

Work is expected to be complete to Charlotte Street by year-end. Work east from York Street to Victoria, and on York Street itself will be done as a separate project in 2023.

College Street

Most work on College Street is complete although 506 Carlton streetcar service remains on diversion. The TTC should be restoring the normal route soon, but has not announced a date yet. As of December 19, the 506C bus shuttle operates along College and Carlton streets rather than diverting along Harbord, Hoskin, Queen’s Park, University and Gerrard.

According to the City’s webpage for this project:

In spring 2023, the City’s contractor will return to complete work on the elevated cycle tracks between Manning Avenue and Spadina Avenue and upgrades to the existing bike lanes between Spadina Avenue and Bay Street.

Wellington Street

Updated: This original text has been removed because it proved to be out of date.

The current status is that undocumented underground conflicts still dog this project, which also was delayed to accommodate local festivals. Work on the north side of Wellington is expected to be largely completed in 2022, but the south side will be finished next Spring.

There is no word on when TTC will reinstall overhead so that 503 cars can return to the Church-Wellington-York loop.

TTC Track Construction Update December 5, 2022

Here is a brief update on various construction projects in progress.

King/Queen/Queensway/Roncesvalles

Excavation continues on Roncesvalles at the north gate of the carhouse while the track panels for the new junction remain on trailers on King Street (see previous update).

Track installation has started south from Harvard Street toward the north gate.

The TTC has not yet announced a date for resumption of through service on Roncesvalles between Howard Park and The Queensway on route 504 King, nor for through streetcar service from downtown to Dundas West Station.

On The Queensway, the eastbound stop at Glendale has finally been taken out of service. Passengers are now directed to use westbound buses to access St. Joseph’s Hospital transferring at Roncesvalles or at Colborne Lodge Drive as appropriate.

The map below was tweeted by @ttchelps. As I write this, neither this map nor the diversion notice for the 504 bus service are linked to the route’s schedule page.

Construction continues on the new eastbound curb lane and the eastbound streetcar stop at Glendale. Work is also in progress on the track between Glendale and Parkside.

Overhead is still not in place at Sunnyside Loop although many span wires and hangers have appeared. The 501 Queen service cannot be extended from Dufferin to Sunnyside until this loop is available.

King & Shaw

According to a City of Toronto construction notice, this intersection will reopen on Friday, December 16. This would allow the 504 King and 63 Ossington services to resume normal operations here.

When the TTC announced their November service changes, this included a temporary option, once King & Shaw reopened, with half of the 504 service turning back at Exhibition Loop (the 504B Broadview cars) and half running through to Dufferin (the 504A Distillery cars). The 504C buses which loop at York Street would shift to a Bathurst turnback.

The TTC has not yet confirmed whether these arrangements will actually happen.

Adelaide Street

Construction has moved swiftly west on Adelaide and is now in the final stretch between Widmer and Charlotte Streets. The section east from York to Victoria will be rebuilt in 2023.

Wellington Street

New overhead has not yet been installed on Wellington Street. The 503 Kingston Road bus is looping via York, Richmond and University from King. Streetcar service should return in the Spring when pantograph-friendly overhead on the downtown loop and on Kingston Road has been installed.

Dundas at Brock Street

A large sinkhole appeared under the streetcar tracks on Dundas at Brock due to a burst 120-year old sewer. The City expects the street to be restored by the end of December, but the TTC will then have to restore the track and overhead. Until that work is finished, tentatively by the end of January 2023, the 505 Dundas service is diverting both ways east of Lansdowne via College and Ossington.

Media coverage is available from CBC and CITY, among other sources.

College Street

The diversion of 506 Carlton streetcars around the College Street reconstruction project is expected to finish by the end of 2022. Streetcars continue to operate both ways via Bay, Dundas and Ossington.

King-Queen-Queensway-Roncesvalles Update: November 26, 2022

The KQQR project is heading into the home stretch with work now underway on the North Gate to Roncesvalles Carhouse, and roadway construction and paving on The Queensway west to Parkside Drive. Alas, there is no announced completion date.

At the North Gate, recently completed utility work allows the area to be excavated in preparation for the new special work. This track has not yet been rebuilt to current standards (a program that will take years to complete as the cycle time is 20-30 years) with a concrete foundation, pre-welded track mounted on panels, and a top layer of concrete that can be removed for repairs without disturbing the two layers below.

The new track panels are sitting on trailers on King Street east of Roncesvalles awaiting installation.

Meanwhile there is some preliminary work on new overhead leading north into this area, but the main installation cannot occur until the new track is in place and overhead trucks can drive under the new wire.

On The Queensway itself, overhead has begun to take shape at Sunnyside Loop, but it is still not operational. This leaves the 501 Queen service turning back at Dufferin Street.

On King Street east from The Queensway, conversion of overhead suspension to pantograph compliance has finally started. This area and Kingston Road are the last two major areas to be converted.

Along the south side of The Queensway, much of the new curb is now in place and concrete for the new curb lane will likely appear soon, weather permitting. At Glendale eastbound (St. Joseph’s Hospital) the bus stop is even more rudimentary than on previous visits. Passengers wait in the temporary crossing area (which is now at least concrete rather than a wooden bridge), and then move across the traffic lane to board a bus when it arrives.

Between Claude and Parkside (the easternmost part of the existing streetcar right-of-way) excavation is in progress to remove old track and wooden ties in anticipation of completing the new trackwork between Glendale and Parkside.

TTC Service Changes Effective November 20, 2022 (Updated)

Updated November 20, 2022: Information regarding diversions for 504 King and 503 Kingston Road has been updated with current details.

The TTC is making a few service changes for the November board period affecting mainly streetcars and the Yonge subway (Line 1).

1 Yonge-University-Spadina

With the complete implementation of Automatic Train Control on Line 1, the full route will switch to one person train operation (aka “OPTO”). Service will be improved during peak periods as well as some off-peak. Some running times will be reduced.

The peak service improvement is achieved through a combination of running time reduction and the conversion of two of the “gap” trains in each peak to regular service trains.

501 Queen

The originally announced service for 501 Queen in October would have seen the route extended to Roncesvalles from Dufferin. This proved impractical, and the route continued as it had been in September. The official schedule now reverts to September’s version for both the streetcar and bus services. There is almost no change to scheduled headways.

503 Kingston Road

The 503 Kingston Road car will be converted to bus operation until March 2023 to allow overhead conversion on Kingston Road. The buses will operate to the “standard” downtown route 503 destination at King & York via Wellington.

Update: The downtown loop of the 503 buses will be via King to York Street, north to Richmond, west to University, south to King and returning east.

504 King

The intersection of King & Shaw is expected to reopen in early December for streetcars and buses. In anticipation, the November schedules are based on the service plan after the reopening.

Update: The TTC has posted a service change notice dated December 1, 2022 stating that the reopening will occur in “early December”. December 1st is a Thursday, and so it is not clear exactly when this change will take place. There is no comparable notice for 63 Ossington which is also diverting around King & Shaw.

Before reopening:

  • All 504 King cars will operate to Exhibition Loop, but they will not serve stops on Bathurst or Fleet Streets.

In practice, much of the 504 King service has not reached Exhibition Loop in recent weeks short turning either at Fleet Loop or at Charlotte Loop (King/Spadina).

After reopening:

  • 504A Distillery cars will operate to Dufferin Loop.
  • 504B Broadview Station cars will operate to Wolseley Loop (at Queen & Bathurst).

This arrangement reduces the number of transit vehicles attempting to use Dufferin Loop while this is still the western terminus for 501 Queen streetcars.

The 504C King shuttle bus was originally scheduled to operate to Exhibition via Strachan, but instead it will run east to Bathurst and King looping via Bathurst, Adelaide and Portland. Additional service will be provided if necessary from the run-as-directed pool.

929 Dufferin Express

All trips will terminate at Dufferin Loop.

Seasonal Changes

  • 86 Scarborough service on Saturdays to the Zoo for Terra Lumina will now end at 9:20 pm to match the planned earlier closing time.
  • 172 Cherry Beach weekday service will be discontinued for the winter (typically until May).

The changes are summarized in the spreadsheet linked below.

Continue reading

TTC Track Construction Update November 3, 2022

Various track construction projects continue into November, but there are signs of progress at some locations.

Updated November 6, 2022 at Noon: Photos of the current state of the King-Queen-Queensway-Roncesvalles project added.

College/Carlton Reconstruction and Diversion

Effective November 2, the intersection of Carlton and Church reopened for streetcars after a long delaty. This had been caused by an unexpected hydro vault under the intersection that conflicted with the new, deeper foundation that is placed under streetcar track.

The 506 Carlton service now operates on the originally planned Dundas Street diversion from Bay to Ossington while College Street is under construction. Here is the updated diversion map from the TTC’s Service Advisory.

The replacement 506C bus continues to operate via Harbord and Hoskin from University to Ossington, and via Gerrard from University to Parliament.

This configuration is expected to last to the end of 2022.

Track reconstruction has shifted east into its second phase between St. George and Bay Streets. Here is a view west on College from University showing the track structure with the old rails removed. The steel ties and attachment points for Pandrol clips are ready to receive new rails.

The City of Toronto’s project webpage contains more information about this status and details of the planned road reconfiguration.

King & Shaw

Construction continues at King and Shaw, but should be finished in time for service restoration on 504 King and 63 Ossington for the next schedule period on November 22. This has not yet been confirmed.

The service alert on the TTC’s website shows the correct routing for 504 services in the west end, but still includes the Queen/Parliament diversion to the east which ended a few weeks ago.

Queen & Carroll

Stop rail replacement on Queen east of the Don Bridge will occur over the weekend of November 4-7. 501 Queen and 504B King/Broadview Station services will divert via Parliament, Dundas and Broadview as shown below.

Although the map does not show this, the 504A King/Distillery service will continue to run on its normal route.

Wellington Street

Installation of new overhead is underway on Wellington, and the 503 Kingston Road car is supposed to resume its loop via Church, Wellington and York with the November 22 schedule changes. This has not yet been confirmed.

Adelaide Street

Track construction has begun on Adelaide Street to restore the link between Spadina and Victoria that has been inactive and unusable for decades. This will provide the eastbound diversion from York to Church for 501 Queen service during Ontario Line construction at Queen & Yonge. The track west to Spadina was included in the project as it will be useful for other diversions including the 504 King car during the film festival which typically closes King Street from Simcoe to west of John.

The construction work will occur in phases as described in the City of Toronto’s project page.

Phase 1A runs east from York to Victoria. This involves the replacement of an old watermain, work that is necessary before the tracks can be rebuilt. This is now in progress.

Phase 1B runs west from York to Simcoe. This is the first phase of track replacement. Initially only the eastbound track area will be excavated. The westbound track will be removed later.

Phase 2 will begin after phase 1B completes. It runs west from Simcoe to Widmer, and is expected to begin on November 7 subject to completion of work further east.

Phase 3 will begin after phase 2 completes. It runs west from Widmer to Charlotte where it will connect with existing track.

Once all of this work is finished, phase 4 will see the pavement marked for a revised configuration with the bicycle track relocated to the north curb lane from Bathurst to Parliament.

In 2023, a separate project will see new southbound track installed on York between Queen and Adelaide, and installation of new track from York to Victoria. The date for this work has not yet been announced.

In the map below, a shared lane is shown on the south side of Adelaide through the construction zone. The lane is actually on the north side of the street, at least as of November 2.

Adelaide Street looking east (on the left) and west (on the right) at University.

Here is a view looking west on Adelaide on July 1, 1967, west of Simcoe. The neighbourhood has changed quite a bit in 55 years.

King/Queen/Queensway/Roncesvalles

Due to persistent fog, I have not visited KQQR but plan to do so soon. I will update this article with the current status and photos in the next few days.

Updated November 6, 2022 at Noon

Here is a gallery showing the current state of the KQQR project.

The watermain reconstruction on Roncesvalles north of Queen completed recently. Concrete around the old track at the north gate has been broken up in preparation for removal of the special work.

At the Glendale stop (St. Joseph’s Hospital) formwork is in place for the new eastbound platform, but buses are still stopping beside an unmaintained dirt area on the south side of the street.

The walkway across the tracks to the eastbound stop has been repaired since my visit a few weeks ago and the handrail is now in place on the full length of both sides.

The new curb along the south side of The Queensway is progressing slowly.

Work at Sunnyside Loop was delayed for construction of a Bell Canada manhole on the south side of The Queensway, but poles required to string the new loop overhead are not yet installed.

According to the most recent construction update from the City, the TTC is considering changing the route of the 504C replacement bus to provide some service on Roncesvalles south of Howard Park, but nothing has been decided yet.

TTC Track Construction Update October 9, 2022

A Word About Diversion Notices

I have often written here and on Twitter about the proliferation of service change cards and posters as the constant changes in streetcar routes occur. Combined with conflicting and out-of-date online information, it is common to find at least two different versions of notices at the same stop, not to mention “stop not in service” notices in locations where streetcars are actually running.

Without question, the constant shifts in the operating plan are challenging to keep up with, but the lack of attention to removal of out of date information, particularly when new notices go up at the same location, does not serve riders well at all. Operating staff, in good faith, give out incorrect info leading passengers astray, and I have rescued a few lost travellers over past weeks.

This is a very serious issue given the amount of construction that will affect TTC routes (and not just the streetcar network) in coming years. Riders have enough challenges with service quality without having to divine whatever route their service might be taking today. There is a clear fragmentation of responsibility for keeping route information up-to-date and consistent within the TTC. Even in a recently announced reorganization, the responsibility for “closures and diversions” is in a separate branch (Operations and Infrastructure) of the TTC from “service delivery” (Transportation and Vehicles).

The phrase “Beware of the leopard”, for those who know the reference, seems particularly apt for some TTC “communications”.

The TTC needs to figure out how communications about service plans and changes can be centrally accessed and administered so that all notices speak with the same voice and contain current, accurate information.

Updated October 9, 2022 at 11:40pm: It turns out that there are four pages within the TTC website where service information might be found. At last count, the list includes:

There is the parent Service Advisories which links three of the four above. Some but not all of the items in the Updates page are also displayed on the main page under “Latest News”.

Although the same topic might be found through different pages, the text is not always the same indicating that multiple versions of the information have been posted. In this situation it is easy for their content to drift thanks to selective updating.

Continue reading

TTC Service Changes Effective September 4, 2022

Updated:

  • The spreadsheet detailing all of the changes has been added at the end of this post.
  • The number of the Mimico GO shuttle has been corrected to 176.
  • Transfer arrangements at Queen & Dufferin for the 501 bus and streetcar services have been clarified.
  • Transfer arrangements at Queen & Roncesvalles for the 501 and 504 bus services have been added.

Updated September 5, 2022:

  • The spreadsheet listing all of the changes has been corrected for route 504 King. The original version included a description of the route carried over from the August version. This has been changed to reflect the September arrangements.

The TTC will make many changes to its scheduled service on September 4, 2022 with restorations of previous service levels on many routes. This will not get the system back to 100% of pre-pandemic levels.

An important distinction is between three values:

  • The amount of service scheduled before Spring 2020
  • The amount of service budgeted for 2022
  • The amount of service scheduled for 2022

The TTC plans to be back to 97% of budgeted service for bus, 84% for streetcar and 92% for subway. The overall numbers are compared below.

Hours/WeekRegularConstructionTotal
January 2020 Scheduled185,8257,068192,893
September 2022 Budgeted186,3796,398192,777
September 2022 Scheduled177,9304,965182,895

In the original 2022 service budget, the TTC planned to be back to roughly the same level of service as in January 2020 by September 2022. However, slower ridership recovery coupled with staffing constraints produced a lower scheduled service expressed as hours/week.

There are further caveats:

  • The distribution of hours by time of day might not be the same in 2022 as in 2020 because of changing demand patterns.
  • Changes in running times to deal with congestion or service reliability can mean that the same service hours are stretched over wider headways. Not all vehicle hours are created equal.

All that said, there are many changes in service levels, and with the bus network being back to 97%, the schedules for September 2022 are often based on old versions before service cuts were implemented. Another change for this month is the reintroduction of school trips on many routes.

Continue reading

Queen West Construction Update: August 14, 2022

Various projects on the west end of the 501 Queen route continue, some faster than others, with one real surprise.

King-Queen-Queensway-Roncesvalles

Little has changed here since my last visit except that the new contact wire is now attached to span wires in places, and some of the frogs (crossing pieces) have been installed.

The new contact wire still ends just east of Sunnyside Loop. Until reconstruction of the south side of The Queensway including bases for new overhead poles has completed, the loop’s overhead suspension system cannot be installed.

Further west at Glendale (St. Joseph’s Hospital), the concrete work now extends to the west side of the intersection, and the beginnings of a new eastbound stop stop are evident.

Lake Shore & Kipling

The TTC is rebuilding both the intersection at Kipling as well as Kipling Loop. To my amazement, they have not only replaced the rarely used east-to-north curve, but have added a new south-to-west. It will now be possible to short turn a Queen car eastbound at Kipling!

This is the same organization that forgets to add much-needed curves during other reconstruction projects or leaves them out on the basis that the budget won’t handle the expense. There is probably a special award for this sort of thing.

In a classic right hand, left hand, situation, note that the new pantograph compliant overhead includes the east-to-north curve, but does not include the south-to-west.

Just east of the intersection, rails have been removed on the approach for replacement. This is a particularly clear example of how the “new” method of track construction adopted in the 1990s pays off with the need to only strip the top layer of concrete and expose existing attachment points to existing ties.

Looking east on Lake Shore east of Kipling

Louisa to Mimico

The track replacement and repaving of Lake Shore from Louisa to Mimico is complete, and only a few traffic cones prevent full use of the roadway.