Tunnels And Track But No Trains

At the TTC Board meeting on June 12, 2023, key reports presented the current and future challenges our transit system faces:

This article reviews the Major Projects Update and more generally the TTC’s Capital Program and funding shortfall. In future articles, I will turn to the Operating Budget, subsidies and the changing environment for transit in 2024 and beyond.

A related report from a past meeting presents the entire Capital Plan, not just the “major projects”, and I have consolidated information from it to provide a complete view.

TTC Capital Plans are presented with three separate timelines:

  • The current year,
  • A ten year window, and
  • Fifteen years and beyond.

The fifteen year view is comparatively recent, but it was a vital addition to the transit outlook. Until this version was introduced, a growing list of needed projects simply did not exist in the published TTC plans nor, more importantly, in the minds of Councillors and financial planners at all three levels of government. Magically, the ten year view always managed to fit within money the City had available from its own revenues or provincial and federal commitments.

That fifteen year view was a huge shock to the City, but it was no secret to anyone who looked through the budget and found gaping holes. This situation was a financial convenience to make future City capital needs appear smaller than they actually were. Funding problems were “fixed” year after year by failing to acknowledge key projects, or by pushing them beyond the City’s ten year capital planning window.

Doug Ford arrived on the scene with his subway plans and billions in provincial spending, but much of this was for projects that were not already part of the City’s plans, or at least not at the scale the City contemplated. The province gave the impression of taking a load off of Toronto, but much of the planned provincial spending was never in Toronto’s plans to start with.

Then came the pandemic and severe doubts about the sustainability of the City’s spending.

For his part, former Mayor Tory’s SmartTrack brand was still on the books, even if it was a shadow of its original plan. Despite going over budget, it lives on as five new GO stations thanks to an infusion of $226 million by the provincial government.

At the TTC, CEO Rick Leary was initially distrustful of Automatic Train Control and the new Line 2 fleet it would require. For a time, the projects to resignal the Bloor-Danforth line, buy a new fleet and build a carhouse at Kipling were put on hold. The TTC would make do through another decade with “life extended” trains which would be at least 40 years old by their retirement. Leary has since changed his tune, but this brought the cost of ATC, new trains and, possibly, the carhouse back onto the table.

The situation is complicated by the Scarborough Subway Extension which would require more trains to provide full peak service to Sheppard than the existing fleet. Half of the peak service would short turn at Kennedy to fit the service within the existing Line 2 fleet.

The already-expensive extension does not include ATC signalling because Metrolinx does not know whether the TTC will have an ATC-capable fleet by the opening date. Only the construction delays due to Ford’s intervention in the project give the TTC enough time, and then only barely, to bring Line 2 up to modern standards.

Another related issue is the emerging demand for Platform Edge Doors (PEDs) for which ATC is a pre-requisite. Without new trains and signals, there will be no PEDs on Line 2.

Toronto is in the unhappy position that we are building miles of tunnels, but may not have trains to run in them when they are finished. The self-contained Ontario Line has a fleet, and the Crosstown has its LRVs, but the subway extensions and planned service improvements are another matter. Moreover, if the Line 2 fleet’s life is pushed out to 40 years, there is no guarantee it will provide reliable service.

Award of the contract for new subway cars has already been delayed into 2024 and costs rise thanks to inflation while we await a funding decision. The Major Projects Report notes that:

  • Delays in securing the required funding for the procurement of new trains will result in declining reliability, longer wait times between trains, increased crowding, and higher maintenance costs. The TTC is actively engaged with its Federal and Provincial partners.
  • The operation of new trains is interdependent with the planned resignalling on Line 2 (ATC). All T1 trains on Line 2 need to be replaced with new subway trains to operationalize ATC on Line 2. As a result, any delay in the funding decision for the procurement of the new trains will have an impact on the ATC requirements as well as the cost and schedule for both projects.
  • Recent increases in escalation will potentially result in an increase in overall cost. The TTC will continue to monitor producer’s price indices, update escalation projections and identify potential offsets to the greatest extent possible.
  • Award Contract in 2024, subject to partner funding. Should the partner funding be delayed or not available, the TTC will commence planning for the T1 Life Extension Overhaul (LEO) program to ensure service continuity.

Meanwhile, on Line 1 Yonge-University, the fleet is in its youth, but more trains are needed to increase service and to provide for the Richmond Hill extension. A new maintenance facility will be required to hold the larger fleet, and it will most likely be built north of the new extension. There has been no word on whether York Region will contribute to any of the cost their subway extension will add to the TTC’s budget woes.

The Major Projects Report notes:

This program includes the accommodation of train storage and maintenance requirements, and other infrastructure enhancements, to expand capacity and improve circulation on Line 1, reduce overcrowding, increase the frequency of trains and reduce travel times, which will result in improved customer service.

[…]

Train Maintenance and Storage Facility (TMSF), which includes:

  • Storage for 34 trains, including a test track, and access track to the site;
  • Carhouse with five Bays for Preventative and Corrective Maintenance to support daily service;
  • Operations and Infrastructure (O&I) facility to support maintenance activities (small shop building, outdoor and indoor storage tracks for work cars, material storage, and staging area);
  • Ancillary facilities (Traction Power Substation (TPSS), Hostler platform).

More service adds to the electrical draw and in turn that will trigger upgrades to the subway’s power distribution system.

Without going into the many details, this illustrates how subway planning is not simply a question of drawing lines on a map and cutting ribbons when the tunnel boring machines arrive.

Continue reading →

TTC Boosts Late Night Subway Service, Restores Beach-to-King Street Service

Effective Monday, May 8, the TTC has restored late night service on Lines 1 Yonge-University-Spadina and 2 Bloor-Danforth to every six minutes, seven days/week. This will be done with extra trains to supplement the scheduled service. The change will be formally scheduled in a future update.

Also, with the disappearance of the 503 Kingston Road car and its temporary replacement by the 505 Dundas, the TTC is now operating a supplementary bus service from Queen & Kingston Road to downtown via Queen and King from 7am to 7pm weekdays.

A direct streetcar service will not be possible until work on the Queen Street Don Bridge finishes sometime this summer, but there is another wrinkle. In the summer, Queen east of Broadview will close for Metrolinx bridge work at the future Riverside Station on the Lake Shore East Rail Corridor forcing all streetcars to operate via Gerrard. In turn that cannot begin until water main and track work at Coxwell & Lower Gerrard completes.

The additional subway service is made possible by an unexpectedly lower absentee rate among operators compared to budget. The TTC made a larger provision for covid-related sickness and finds itself with more available staff.

TTC Board Meeting April 13, 2023

The TTC Board will meet on April 13, and the agenda for their meeting is rather small. Notable by its absence is any reference to the service cuts planned for May 7, 2023.

The big items in the public portion of the agenda are the monthly CEO’s Report and an update on TTC’s finances and major capital projects to the end of 2022.

There are also two reports on collective agreements and non-union salaries. Although the details lie in confidential attachments, the public reports give an overview of the various labour contracts and salary drivers across the organization. I leave perusal of these to interested readers.

Finally there are a few references to the TTC’s eBus program scattered through reports. I will consolidate this info in its own section at the end of the article.

Correction April 18, 2023: It turns out that the size of the bus fleet shown in the graphic below is wrong. There are only 2041 buses, not 2114, in service as of March 2023. The article has been amended to reflect this.

Continue reading →

Osgoode Hall Garden and University Park

Over past months, the Ontario Line’s effect on trees in various locations around Toronto has become something of a cause célèbre. Osgoode Hall was, in a way, the “poster child” for this because of its location and the historic buildings at Queen & University. However, this was far from the only affected location with tree felling on a massive scale elsewhere including Moss Park, Riverside, and now planned for the Don Valley at the Leaside Bridge and the crossing of Walmsley Brook north of Thorncliffe Park.

A common refrain from citizens along the Ontario Line and other corridors is that Metrolinx does not deal in good faith, but rather presents its positions as unchangeable and pressing. They look only for acquiescence so that “consultation” can be claimed for the record. There is no public record of these consultations, and no community is aware of what might be told to others except by information sharing among them.

I have written about the garden at Osgoode Hall before, most recently in a review of the report prepared for the City of Toronto by Parsons looking at various alternative configurations.

On February 23, 2023, Toronto and East York Community Council established a subcommittee composed of Councillors from Wards 10 Spadina-Fort York, 13 Toronto Centre and 14 Toronto-Danforth and “directed the Executive Director Transit Expansion Division to report to the first meeting in March 2023 regarding the current status of the Ontario Line, pedestrian and traffic management plans, and opportunities for City and resident involvement moving forward”.

That meeting will occur on March 22, 2023. The only report on the agenda is from the Executive Director, and a great deal of it is a rehash of information from earlier reports along with a claim that Metrolinx is engaging with communities along the corridor. The actual degree of consultation is a matter for some debate, and one cannot wonder whether the ED is parroting the official line from Metrolinx, hardly an appropriate tactic for a senior City official. I will address that report in more detail after the meeting, but turn here to a proposal for the new entrance to Osgoode Station.

Continue reading →

Bloor-Yonge Station Expansion Update

The TTC has published a Major Projects page for its Bloor-Yonge station expansion with a few renderings of the platform level views.

Many more illustrations were available on the TTC’s bid site, and this article is based on documents there which go into considerably more detail.

There are a lot of images here, and so I will leave most of the article beyond the “more” line.

Project Scope

The project involves the creation of a separate eastbound platform for Line 2 Bloor-Danforth and the reconfiguration of the existing centre platform as westbound only. Circulation space between Line 1 Yonge and Line 2 will be expanded substantially.

At the north end of Bloor Station, both platforms will be extended about one car length to the north (the existing Bloor crossover is located a short distance north of the station) to open up circulation space .

A new main entrance will be built within 2 Bloor Street East.

On the south side, at 81 Bloor East, an entrance will be added within a building whose primary purpose is to house a substation for electrical power to the expanded station. Traction power will continue to be supplied through the TTC’s Asquith Substation.

Four new fan plants will be added to bring the expanded station to modern fire code, and the existing fan plant at the south end of Bloor Station will be refurbished.

The drawings show no provision for Platform Edge Doors.

This will be a Design-Build project with the successful bidder responsible for taking TTC plans now at about 30% completion to a full 100% design, followed by construction. The Request for Proposals is expected to close later in 2023.

Construction is planned to begin in 2024Q2 with the new Line 2 eastbound platform and new areas of Line 1 platforms in service by 2029Q2. This assumes that the Yonge North Subway Extension to York Region will open in 2030. The project would close out in 2031.

Support for the project is in place from all levels of government, but until the bids come in, we will not know whether the full scope of work will fit within available funding of $1.5 billion.

The footprint of the expanded station will be considerable, and the drawing below gives an idea of how much more territory the station will occupy.

Continue reading →

501 Queen Diversions and Shuttles for the Ontario Line

This article is a follow-up to my earlier piece about the TTC’s Rapid Transit Expansion report including the effect of Ontario Line construction on the 501 Queen service.

Updated March 1, 2023:

  • The reason that track installation on Adelaide, which by itself is relatively straightforward, cannot proceed immediately is that nine Toronto Hydro and Bell vaults must be relocated. Metrolinx opted not to do this work, but the City has taken over.
  • Streetcars will remain on 501 Queen but will divert both ways via Broadview, Dundas and McCaul from May 2023 to March 2024. A bus shuttle will operate over the central portion of the route.
  • The list of track construction projects for 2023-24 has been clarified.

Back in December 2021, the City approved a report with a very long list of proposed road closures for Ontario Line construction.

I wrote about this report beginning with this article:

The construction at Queen Station will entail a multi-year diversion of 501 Queen service, and the plan was for streetcars to operate:

  • Eastbound via York, Adelaide and Church
  • Westbound via Church, Richmond and York

Track already exists for the westbound route, but new track is required on York and on Adelaide for the eastbound diversion.

Much of this work was supposed to have been completed in 2022, with the intent that the diversion would be available in May 2023. Various factors combined to foul up this schedule.

  • The contract to install new track on York and on Adelaide east to Victoria was, for some reason, to be a Metrolinx responsibility separate from City work on utility upgrades and relocation. This lengthened the potential timespan with two separate procurements, and inevitable delays as one contractor waited for the the other to finish.
  • Metrolinx was supposed to build the new track on York Street in 2022. This did not happen. According to a recent City report (about which more below), Metrolinx has been preoccupied with the Ontario Line.
  • Construction on Adelaide west from York to Spadina was done by the City to restore track inactive for many decades and to provide more flexibility for downtown diversions. This went quickly through the fall, and was performed by Midome Construction who were also working on utilities east of York.
  • For various reasons, notably discovery of unexpected underground Toronto Hydro and Bell plant, the work east on Adelaide from York did not complete in 2022, although it was substantially finished from York to Bay. Some water main connections were incomplete with pipes blocking the curb lanes, and this complicated traffic and transit diversions around a major sinkhole at King and University.
  • The City proposes to expand the Midome contract to include track replacement from York to Victoria. Work on this can begin immediately where utility construction no longer occupies the eastbound track lane (second counting from the south side). See: Non-competitive Contract with Midome Construction Services Limited for the New Streetcar Tracks on Adelaide Street

Queen Streetcars or Shuttle Buses

Until quite recently, if one ignored the incomplete work on the diversion trackage, it was possible to think that the streetcars would simply divert as planned beginning in May. This is obviously not going to happen, and it must have been clear to the TTC for months that the 501 Queen service would have to be modified.

The first hint of this was buried in the report under discussion at today’s (February 28, 2023) TTC Board Meeting.

Metrolinx has identified that the potential delay to complete the streetcar detour work will result in approximately 20 months of shuttle bus service commencing in early May 2023. The TTC is still working closely with Metrolinx and the City on exploring options to optimize the construction schedule of the Adelaide civil and streetcar track construction work to reduce the duration of shuttle bus service.

TTC Transit Network Expansion Update at p. 14

The words “shuttle bus” will send hapless TTC riders screaming from the room. There is a long history, particularly in recent years, of the TTC’s incompetence in operating construction shuttles including changing routes with little or no notice, conflicting information online and at stops, and erratic service with shuttles running in packs and taking long layovers at terminals. This was compounded by the number of planned and unplanned construction projects and the overlapped periods of construction on what should have been distinct route and road closures.

The grand daddy of them all is the King-Queen-Queensway-Roncesvalles project where all manner of delays including pandemic effects on work, unexpected utility relocations, slow work by affected companies such as Toronto Hydro, Bell and others, pushed the completion date out to, with luck, July 2023.

The idea that Queen would see 20 months of shuttle buses before the streetcar diversion would be ready is a testament to fouled up planning. The work should never have been divided between Metrolinx and the City but consolidated as a single contract with a goal of completion as fast as possible.

We now know, courtesy of the Star’s reporting that the delay will be only ten months instead of twenty thanks to the City’s contract consolidation. That’s an improvement, but it should never have been necessary.

For the TTC’s part, this continues a sad tale of communications and consultation foul-ups. The need for shuttles would clearly have been known months ago. How exactly they will operate is totally unknown because the TTC has issued no guidance on this. Will there be shuttles downtown? Over the entire route? Will the route be split to make it more manageable and give different routing options for eastern and western legs?

This should have been a public discussion months ago even if some details were still to be nailed down rather than a surprise landing on already-suffering riders who have dealt with many disruptions on Queen and other routes.

There are several planned track and road construction projects on Queen and King Street in coming years, and I learned recently that several of these have been deferred to reduce overlaps and conflicts. The revised schedule has not been published, and yet this will be essential to any discussion of transit service through the Ontario Line’s construction period. These include:

  • Scheduled for 2023, but deferred:
    • King West from Close to Strachan.
    • Queen East from Parliament to River.
    • Queen East from Carlaw to Greenwood.
  • Queen at Degrassi. Revision to streetcar power distribution for Ontario Line. 2023, date TBA.
  • Scheduled for 2024:
    • Queen West from O’Hara to Triller. 2024.
    • Queen East from Davies to Carlaw. 2024 (likely during Metrolinx work at Degrassi underpass).
    • King West from Strachan to Spadina. 2024.
  • Bathurst Street from Queen to Front
  • Scheduled for 2024, but deferred:
    • King East at Church (intersection).

The City, TTC and Metrolinx owe everyone an apology for this cock-up, and a commitment to resolve conflicting schedules and publish credible plans as soon as possible.

I will add to this article as the story develops.

TTC Transit Network Expansion: February 2023 Update

At its meeting on February 28, the TTC Board will receive a report summarizing the status of most of the rapid transit plans in Toronto. This article condenses the TTC report and reorders some sections to group related items together.

Dominant among many projects are, of course, the “big four” provincial projects: Ontario Line, Scarborough Subway, Yonge North Subway, and Eglinton West LRT extension.

Project Status Overview

The effect of major projects elbowing everything else aside is clear in the table below. Some projects do not have in service dates because they are not funded, and the timing of that (when and if it occurs) will determine when various lines can open.

Not shown in this table are several major projects that pop up from time to time:

  • Bloor-Yonge Station Expansion
  • Waterfront West LRT from Dufferin to The Queensway
  • Bloor West subway extension
  • New Line 2 fleet and yard at Kipling (Obico yard property)
  • Sheppard East subway extension
  • Platform Edge Doors

Of these, only the Bloor-Yonge project has funding, and some are only a glimmer in various politicians’ eyes.

Continue reading →

Toronto’s Board of Trade Contemplates Transportation

Prologue: When I started to write this story, John Tory was still Mayor of Toronto and the dynamics of City-Province relations assumed he was in charge. The context for these discussions was soon to change.

The Toronto Region Board of Trade holds a yearly “transportation summit”, and on February 8, 2023, this focused on the Greater Toronto Area’s transit, plans for the future, and the aftermath of the covid pandemic.

The TRBoT is no wild-eyed radical institution. The regional economy and businesses are at the heart of causes it advocates.

Both in the introductory remarks and in comments by speakers sprinkled through the day, the economic effect of traffic congestion was a mantra. This sets the framework for the importance of both transit and road projects, depending on who is speaking. The latest factoid describing Toronto’s problems is that we have the third worst congestion in North America and the seventh worst in the world.

CBC: Toronto ranks 3rd most congested city in North America. Here are the city’s worst traffic spots

A problem with this hand-wringing is that there is little acknowledgement that some particularly bad locations are related to major infrastructure projects such as the Gardiner Expressway rebuild and various rapid transit lines. Moreover, goods movement has severe problems in areas that historically have poor transit and show little chance of seeing any in the near future. No single project will solve the problem of many-to-many trips patterns that now depend almost totally on roads and private vehicles.

Continue reading →

Osgoode Station Entrance Review

Metrolinx plans along several of its corridors have provoked community opposition and proposed alternative schemes, but Metrolinx has been quite intransigent about “just getting things built”, the mantra of the Ford government at Queen’s Park. Opposition is not merely steamrolled, but is painted as anti-transit, out of touch, and nimbyist in preventing the wider population from enjoying the benefit of new transit lines.

This does not endear Metrolinx to many groups (and they stretch well into the 905, not just central Toronto), but Metrolinx does not care. For them, it’s all about managing the message. Most communities just roll over and give in to an unstoppable force trying to make the best of a bad situation. “Consultation” amounts to picking the colour of the tiles for a bathroom reno, and hoping that the contractor actually installs the ones you selected.

Several sites along GO corridors and the Ontario Line have been subject to tree clearing either to open construction sites, or to remove trees that will conflict with electrification infrastructure. A small grove at Osgoode Hall, although far from the largest area Metrolinx has cleared, received much publicity because of its location. The northeast corner of Queen and University is a park beside one of Toronto’s oldest buildings, a green space complementing the square at City Hall just to the east and a more recent arrival, Campbell House, to the west.

Although the park was owned by the Law Society of Ontario, the portion Metrolinx requires was expropriated for the Ontario Line. The community around Osgoode Hall (a mix of the legal profession, the local BIA, residents and heritage advocates) convinced Toronto Council to undertake a review of Metrolinx plans in comparison with alternative designs that would preserve the treed parkland.

This report was produced by a consulting firm, Parsons, and was posted on the City’s website on February 4. It exists in two formats:

An interim injunction, in force until February 10, paused the felling of trees at Osgoode Hall for a time. Other locations have not been as lucky, nor have they had groups like the Law Society capable of taking on Metrolinx.

An important distinction for this site is that it also contains a heritage building, and there are concerns for potential damage Osgoode Hall might suffer from the overall construction plans. However, the injunction itself only applies to the trees, and it is not clear whether the wider issue of construction effects will form part of the broader argument when the application is heard.

Among the legal issues will be whether a heritage site with mixed ownership (the Law Society, Metrolinx and Ontario) can be treated as “indivisible” for the purpose of heritage preservation so that one owner, the LSO, can prevent changes on property of another owner, Metrolinx. There is also the question of whether Metrolinx can even be bound by an injunction as it is one of many agencies that are exempt from many provincial regulations.

In Brief

  • An interim injunction pauses work until February 10, with possible extension, pending further review.
  • The Parsons report commissioned by the City was published at the last moment, and was seized upon by Metrolinx to justify commencement of work on the same day as the injunction hearing.
  • Parsons concurs that the Metrolinx proposal is the best of those analyzed, but suggests that an alternative using the Campbell House site should be studied in more detail.
  • The Campbell House option would effectively displace the house from its location, and it is doubtful that it could return in as harmonious a setting as it has today.
  • Parsons does not afford the same treatment to the Osgoode Plaza proposal even though this is the major contender among the alternatives.
  • The City’s inaction on the proposed Osgoode Plaza is an (almost) missed opportunity to make the new station and the intersection into a major site downtown. If this is to be pursued, prompt action by the City is needed so that Metrolinx could adjust their construction plans accordingly.

If City Council, and most importantly Mayor Tory, are serious about an alternative to the Metrolinx plans for Osgoode Station, they should proceed as quickly as possible to endorse the Osgoode Plaza scheme and work with Metrolinx to adjust construction plans for Osgoode Station on the basis of road space on University Avenue that the plaza will free up.

In the presentation accompanying the report, the Osgoode Plaza option is shown first, and it is dismissed for various reasons notably the absence of detailed studies because the City has not yet embraced the proposed reconfiguration of University Avenue. Rather than recommending that the potential of this scheme be examined in greater detail, Parsons rejects it. This effectively prejudices the report to endorse the Metrolinx scheme as the only viable option, with a faint hope alternative that is worse than the original.

Continue reading →

TTC Subway & Streetcar Infrastructure Projects 2023-24 (Updated)

The TTC has published its planned schedule for various streetcar infrastructure inspection and repair projects for 2023, and a look-ahead to 2024.

See: Subway Closure and Streetcar Diversions – 2022 Review and 2023/2024 Forecast

This article was updated on January 19, 2023 at 8:45 pm with additional illustrations from a staff presentation to the TTC Board.

See: Board Report Briefing Subway Closure & Streetcar Diversions – 2022 Review and 2023/2024 Forecast

Subway

The full list of closures begins on p 13 of the report. There is a variety of full weekend, early closing and late opening events (check the legend to the chart).

There are fewer Line 1 closures in 2023 due to ATC (Automatic Train Control) than in 2022 because the main work is complete. However, there is a follow-up phase that will require some weekend closures for testing and implementation. Other work affecting Line 1 includes repair of station finishes on the University subway, elevator installation at Lawrence, various track replacements, and preliminary work at Finch for the Yonge North Subway Extension.

On Line 2, there will be work at Kipling to add a new storage track, preparatory work at Kennedy for Scarborough Subway Extension, preparatory work on the east end of the line for ATC installation, and some track replacement work. As usual there will be several late openings of service on Sundays for beam replacement on the Prince Edward Viaduct.

Many closures involve only an early shutdown of subway service to give a longer overnight maintenance window than would be possible with normal hours of service.

Streetcar

There is a long list of events for the streetcar system, but many of them are short interruptions of overnight/weekend work for inspections or minor repairs.

The major trackwork planned in 2023 is listed both in the report (starting on p 19) and on the TOInview map of City construction projects. The schedule implies that a good chunk of the streetcar system will be shut down at various times during the year. The Ontario Line contributes some of this to the Queen car, but the long-suffering riders on King do not get a break either after years of work at King-Queen-Roncesvalles. Note that Adelaide from York to Victoria is a Metrolinx project and so does not appear in this list.

Some of the dates in the TTC list do not align with info on TOInview. This is very common.

Parts of the schedule simply do not make sense. Some projects have far more time reserved than they should take based on past experience. Some projects will block the routes from carhouses in the east end to the rest of the network either via Queen Street or via Coxwell and Gerrard Streets, and times for these overlap.

Update: The TTC confirms that planned work on Gerrard Street will not occur at the same time as projects on Queen will block access to Leslie Barns and Russell Carhouse. See the map at the end of this section for a graphic view of the planned work.

Details of the Broadview Station Loop expansion are not yet available, nor is it confirmed whether this will actually occur.

I hope to get clarification of what is going on from the TTC.

  • Feb 27-Mar 26: King Street West from Close to Strachan
  • Mar 10-Oct 29: Dufferin Loop
  • Mar 24-Nov 28: Queen Street East from Carlaw to Leslie & Leslie to Greenwood
  • Mar 31-Apr 7: Intersection of King & Church
  • May 1-Nov 29: York from Queen to Adelaide (Ontario Line diversion)
  • May 6-July 8: Intersection of Lower Gerrard & Coxwell
  • May 6-Nov 21: Russell Yard
  • May 14-Nov 8: Broadview from Gerrard to Broadview Station
  • June 18-July 29: Intersection of King & Parliament
  • July 30-Nov 18: Metrolinx work at Queen/Degrassi overpass
  • Sept 3-Oct 2: Broadview Station Loop
  • Sept 7-Oct 29: Queen from Parliament to River & Davies to Broadview
  • Oct 8-Dec 16: Oakwood Loop
  • Oct 16-Feb12: St. Clair West Station Loop

The report does not list specifics for 2024, but info already appears on the TOInview map. It is not clear how some of this work will interact with Metrolinx Ontario Line construction at King & Bathurst. There is a proposed track and lane realignment at Bathurst & Fleet, but it is not clear whether this will actually occur, or if the planned work is simply replacement of existing special work as is. Details of the Spadina Station streetcar loop expansion are not yet available.

  • St. Clair & Yonge
  • St. Clair & Bathurst
  • Queen St. W from O’Hara to Triller
  • King St. W from Strachan to Spadina
  • King & Queen (Don Bridge)
  • Bathurst St. from Queen to Front
  • Bathurst & Queen
  • Bathurst & Fleet
  • College St. from Bay to Yonge
  • Main & Gerrard
  • Russell Yard (continuing from 2023)
  • Expansion of the streetcar platform at Spadina Station Loop

Update: The following map was included in the staff presentation to the Board on January 19, 2023.

This map contains several geographic errors:

  • The project labelled Queen & Yonge points at King & Spadina.
  • The project for St. Clair & Bathurst is shown east of St. Clair West Station rather than west of it.
  • The project for St. Clair & Earlscourt is shown well west of Lansdowne rather than east of it.
  • Carstops on Queen East at Wineva and at Waverley are shown as west of Kingston Road rather than east of it.
  • The project for Queen & Jarvis is shown well west of Yonge.
  • The project for Fleet Loop actually points to Exhibition Loop.

There are a few more, but my point in cataloguing them is that this is sloppy work and it speaks to the quality of information presented to the Board by management.

Pantograph Conversion

Gradually, and several years behind the original target date, the TTC has converted overhead wiring designed for trolley poles first to a hybrid pole/pantograph configuration, and then to pure pantograph style. A map of the current status was included in the staff presentation.

There are some problems with this map which is based off of a track plan that is itself out of date. “Wrong way” track has been removed from the one-way streets downtown, although it still appears here. Also, some work is underway on King West even this is not shown with the orange “in progress” colour. The intersection of King & Shaw had already been converted to Hybrid format when I visited it a month ago. (There are other errors in the map, but please don’t bother commenting with fixes.)

One amusing relic is the legend “Hillsdale Ave” on Lake Shore Blvd West. This was the site of a long-removed wye, the last in the system, and the street is called “Hillside Ave”. “Hillsdale” is in North Toronto.

Again, this is an unfortunate example of how the “official” records of the system are out of sync with actual conditions in the field.