Metrolinx Gives Toronto the Finger, Twice

On the Toronto Executive Committee agenda for July 6, there is a report updating Council on the status of various rapid transit projects in Toronto. Notable by their absence are the Waterfront East LRT (study in progress as previously reported) and the Eglinton East LRT extension.

The truly galling part is found in two letters from Metrolinx, compounded by the abject parroting by City staff of Metrolinx creative writing in the City’s own report.

The documents are linked here:

  • Update on Metrolinx Transit Expansion Projects –Second Quarter 2021
  • Letter from Karla Avis Birch, Chief Planning Officer, Metrolinx, to Derrick Toigo, Executive Director, Transit Expansion Division, City of Toronto re the Ontario Line alignment
  • Letter from Phil Verster, CEO of Metrolinx to Derrick Toigo re the Ontario Line Maintenance and Storage Facility in Thorncliffe Park

The fundamental problem is that Council asked Metrolinx to consider alternatives to their design for the Ontario Line in Riverside (East Harbour to Gerrard Station) and in Thorncliffe Park (the location of the line’s storage yard).

Metrolinx chose to reply with analyses of options that were not those of concern to Council that addressed proposals from the affected communities. What Metrolinx did do was to trot out analyses of previously rejected options as if this somehow validated their position.

To give the impression that Metrolinx has “responded” to the city is a misrepresentation of what has happened, and it suggests that City staff in the Transit Expansion Division are more interested in buttressing Metrolinx’ case than answering Council’s request.

Continue reading