Ontario Line West Segment Update

Updated June 17, 2021 at 5:20 pm:

In the table of station usage counts, I cited the values as “all day” numbers in the original version of this article because Metrolinx own summary article showed the total value as “daily” not as “peak hourly” . I asked Metrolinx about this discrepancy, and they have not yet responded. However, they have changed the article in which “daily” was used to now say “busiest hour”. I have updated this section accordingly. Other questions to Metrolinx have not yet been answered. (Screen captures are included later in the article.)

Meetings for other segments are scheduled on:

  • June 17: Central downtown
  • June 24: Corktown, East Harbour, Riverside, Gerrard
  • June 30: North to Eglinton from Danforth

The introductory article for the meeting is on the Metrolinx blog and the engagement page includes links to the four meetings and resources for them.

All drawings in this article are taken from the Presentation Deck for June 10. Street view photos are from Google Maps.

Project Schedule

A common question during the session was “when will this affect me”. The entire project is complex and will affect areas in different ways as it moves through its stages. The published schedule concentrates on pre-construction activities. In the chart below, related activities share the same colour so that, for example, the Lower Don Bridges are all yellow.

Early works that can occur before major construction include:

  • Exhibition Station reconfiguration and expansion (construction to begin imminently)
  • Lower Don Bridges (construction begins in early 2022)
  • Corktown Station (no start date shown in the plan)

There are four big contracts that will affect neighbourhoods along the route.

  • The Lakeshore East joint GO and Ontario Line corridor between the Don River and Gerrard is an “Early Work” scheduled to begin construction in the second half of 2022. This segment is controversial because of potential effects on affected neighbourhoods, and Metrolinx’ aggressive efforts to counter “myths” and “misinformation” about their project. See Metrolinx v Riverside: Where Does the Truth Lie?
  • In mid-2022 contracts for the south segment structures and for “RSSOM” (Rolling Stock, Systems, Operations and Maintenance) will be awarded with construction to begin in 2023.
  • The north segment structures contract will go to its RFQ stage in early 2022, with RFPs to selected proponents late that year. Contract award will occur in 2024 and construction would begin some time afterward.

For the south segment, the tunnels will be deep underground, typically about 30m down. They will be bored through rock starting from the west end of the line. Spoil removal and materials delivery will occur at the Exhibition with the tunnel portal west of Strachan Avenue and truck access to the Gardiner Expressway at Dufferin Street.

Stations will be built using a “keyhole” method by digging down from future entrance building locations and then mining outward to create station caverns for the concourses and platforms. This is similar to the approach used for a few stations on the Crosstown project to avoid excavating within streets. That is particularly important for locations where there are streetcar lines and many underground utilities.

The first stage of construction will be to tunnel, with station construction to follow once the tunnel is in place. Metrolinx has not published a detailed schedule, but station work would begin in 2024 in the south segment as tunnel work progresses from Exhibition east to the Don River. Metrolinx expects station sites to be under construction for about three years.

The major RSSOM construction in the early years of the project will be the Maintenance and Storage Facility north of Thorncliffe Park. After the tunnels and aboveground structures are complete, the RSSOM contractor will outfit tracks and systems, but this activity would largely be within the completed tunnels and guideways.