Adelaide Street Reconstruction Open House

The City of Toronto will hold an online open house for the Adelaide Street project on Thursday, July 21 from 6:30 to 8:00 pm.

A link to register for this session is on the project page.

Track on Adelaide has been inactive for many years thanks to various cuts for utility projects and the high level of building construction along the street. The TTC contemplated reactivating the track as a bypass for, among other things, the Tiff street fair, but the opportunity did not present itself until now.

The Ontario Line open cut construction at Queen Station will require diversion of streetcar service around Queen and Yonge for several years. Cars will operate westbound via existing track on Church, Richmond and York. Eastbound service will run via York, Adelaide and Church.

This requires reconstruction of the Adelaide Street trackage as well as installation of new tracks southbound on York from Queen to Adelaide. Although only the track east from York is required for the Ontario Line diversion, the TTC will restore the track between Spadina and York making provision for a longer diversion. York will become two-way from Queen to Adelaide.

It is not yet clear which special work will be added at intersections, notably Adelaide and York where a north-to-east curve would be useful, especially if the TTC adds an east-to-north at King and York when this is rebuilt in a pending King Street project. Unfortunately, with the lead time between planning and execution, the TTC has forgotten on occasion (or chosen for budgetary reasons) to include missing curves that would make their operations more flexible notably at Broadview and Gerrard and, this year at Church and Carlton. These opportunities only come along every 25-30 years.

The project also includes water main reconstruction from York to Church, and repaving. Parts of the street are in very bad condition after years of condo construction trucks pounding the pavement.

From Bathurst to Parliament, the bike lane will shift to the north side of the street where there will be less conflict with the streetcars and with vehicles stopped in the eastbound curb lane.

I will update this article with more info after the open house.

Metrolinx! The Musical!

Updated July 15, 2022 with monthly Metrolinx ridership recovery stats.

Metrolinx Board meetings are rather quiet affairs devoid of controversy, not to mention substance. They are pro-forma efforts at public meetings by an organization that does everything it can in private.

The breakdown of the agenda tells the tale. Contrast this with the openness demanded by legislation in municipal proceedings.

This is not new. In the pre-covid era, I would attend the meetings along with a dwindling band of reporters from the City Hall or Queen’s Park press galleries who eventually decided that it was not worth wasting their time unless there was some burning issue where an interview ambush might yield a juicy quote.

For two years, the Board meetings have been online with all of the technical foul-ups we have come to love through Zoom and its relatives. This month, in a grand return, the Board met in person. It was almost like the lights coming back to Broadway.

Metrolinx just loves to tell everyone how wonderful they are, how everything is going so swimmingly well. This time they even had celebratory video.

The meeting video is available for those who just must watch, although as a show it should have died on the out-of-town tryouts.

There are two common themes:

  • The overwhelming emphasis is on marketing and communications with as much “good news” as possible.
  • There is no discussion of policy. Anything substantive, if the Board discussed it at all, was handled in committee or in a private Board session.

I could not help thinking of how “In here life is beautiful” in Cabaret, or “Everything is beautiful at the ballet” in A Chorus Line. Alas, Metrolinx has not (yet) recruited the likes of Kander & Ebb, or Michael Bennett & Marvin Hamlisch to its burgeoning communications team.

Considering the years of debate over regional fare integration and the number of virtual trees felled for reports on the subject, Metrolinx is skipping over the complexities by simply offering a free transfer between GO and 905 area transit systems. Toronto/TTC? No.

It is hard to understand why we have excruciating debates about things like zone boundaries, time-based transfers or differing classes of service when the main agency, GO/Metrolinx, simply gives free transfers and deeper discounts to encourage ridership. If a municipal system tried this, they would be pilloried for wasting precious tax dollars on people who are not motorists.

The debate on all fare schemes is whether the marginal revenue is worth the complexity and the cost of administration, although the latter is much simpler with fare cards rather than conductors and paper transfers.

The related context is that we learn in the Annual Report for 2021-22 that the operating subsidy for GO Transit doubled to almost $1-billion thanks to the combined effect of lost ridership and continued, albeit reduced, scale of operation during the pandemic.

Operating expenses have declined little, despite service cuts, through the pandemic era.

The operating subsidy, however, has grown because of lost fare and other revenues.

The degree of belt-tightening at Metrolinx will be an interesting contrast to what might be forced on municipal agencies as special pandemic financial supports wind down.

There was no public discussion of how this situation can be sustained in coming years depending on the rate of ridership recovery.

The report on community relations was particularly galling because it pitched Metrolinx’ work as listening to communities as a positive contribution to projects. In fact, Metrolinx’ common strategy is to bull through their proposals and then “involve” the community in making the best of a bad situation with things like design competitions for decoration of new, unwanted structures. Even the canard about parks getting bigger thanks to Metrolinx continues to ignore (a) the relatively small amount of land involved, and (b) the much more extensive effect of the associated project on a neighbourhood.

The Board laps this up as if staff are doing such a wonderful job.

Updated: There was some discrepancy between ridership recovery numbers presented in reports and verbally at the meeting. Here are the definitive monthly numbers from Metrolinx.

MonthGO TransitUP Express
January ’2211.8%16.1%
February ’2220.3%22.6%
March ’2232.4%33.3%
April ’2233.5%41.0%
May ’2239.4%47.3%
June ’2249.5%59.5%
Continue reading

TTC Service Changes: July 31, 2022

There will be a small number of changes on July 31 for the schedule period running through to the Labour Day weekend.

Line 2 Service Improvement

Service on Line 2 Bloor-Danforth will be improved during all operating periods, notably off-peak and weekends. This will not fully restore pre-pandemic levels on the route, but should reduce crowding that has become a problem over past weeks.

King & Sumach Track Repairs

The intersection of King and Sumach (the point where the Distillery line branches off) will be rebuilt in an attempt to reduce noise and vibration.

During this work, all 504 King service will operate to Broadview Station via Parliament and Queen Streets. The 503 Kingston Road route will also use this diversion.

A shuttle bus will operate to provide access to the Distllery, and it will also provide coverage for the 506 Carlton line during construction at Church Street (see below).

Church & Carlton Track Repairs

The intersection of Carlton and Church will be rebuilt as part of the regular maintenance program. This work will not include the addition of missing curves in the southeast quadrant.

506 Carlton service will divert around construction via Parliament, Dundas and Bay both ways. A replacement bus service will operate from Spadina Station to the Distillery District. The map below shows a proposed alignment for this service. This is subject to change depending on possible modifications to turn restrictions due to construction at College & Yonge.

Updated July 28, 2022: This diversion has been changed. See Revised 506 Carlton Diversion Effective July 31, 2022.

Other Changes

Running times on 32 Eglinton West will be adjusted to provide for delays due to the Line 5 Crosstown Extension construction, as well as to restore covid-era service cuts.

A planned reconstruction of the terminal at Kipling Station will require consolidation of loading areas and move of some routes to stops outside of the station. This project has been deferred to 2023, but a schedule change to support this work was already in the pipeline for the coming period. The 40 Junction and 49 Bloor West routes will be interlined.

Route 172 Cherry Beach will shift from “Old” Cherry Street to the “New” street across the future path of the Don River between Commissioners Street and the Ship Channel. Buses will use Old Cherry Street north of Commissioners Street, then jog west to New Cherry Street to cross the new river course.

Route 174 Ontario Place weekend and holiday service was dropped in June due to conflicting activities at the CNE and Ontario Place grounds. This change is now officially in the schedules.

Details of the new service levels are in the spreadsheet linked below.

Major Construction at Russell Carhouse

Reconstruction of Russell Carhouse will begin both to make it fully compatible with the Flexity fleet, to improve the quality of yard paving and convert the overhead system for pantograph operation.

In the first phase of this work, the site’s capacity will be reduced to 28 cars including spares. Only the 504 King service will operate from the yard. Here is the new allocation of routes to the three carhouses.

Note that the maximum number of cars in service is well below the fleet of 204. Bus substitutions on portions of 501 Queen, 504 King and 506 Carlton will continue through the balance of 2022.

As the work at Russell progresses, the capacity of the site will change.

TTC 2023 Service Plan Survey

The TTC’s online survey for their 2023 Service Plan is now available.

It contains three sections, and you can submit answers to any or all of them.

  • Lessons learned from the Covid-19 era
  • Route changes associated with the shutdown of Line 3 SRT (November 2023)
  • Route changes associated with the opening of Line 6 Finch West

There may be added route changes proposed in a second consultation round later this year.

This consultation is for 2023 changes. A separate 2024-2028 Service Plan and Ten-Year Outlook is under development.

Note that the route arrangement for Line 5 Eglinton Crosstown’s opening is already settled from previous consultation in the 2022 Service Plan.

The Varying Strength of Ridership Recovery

This article continues and enlarges on information in TTC 2023 Annual Service Plan Preview with additional material from a report on the July TTC Board agenda Advancing the 5-Year Service Plan (2024-2028) & 10-Year Outlook Reset. That is a long report with several components, and I have pulled chunks of it out as they relate directly to information in the earlier article.

Of particular interest in the restoration of service to the transit network is the fact that recovery has been underway in some locations and times much more strongly than others. This corresponds to the difference in areas where work or study-from-home replaced commuting to an office or school. Maps in the previous article showed the top and bottom 20 routes for ridership relative to pre-pandemic levels in Spring 2020 (the point of lowest ridership) and in Fall 2021. For convenience, they are repeated here.

These ranking are by percentage of pre-pandemic ridership with no reference to absolute numbers. The busiest routes by ridership are shown in the maps below. This presentation inevitably displays the long routes which have a large number of boardings. Short routes like 65 Parliament may have recovered a large proportion of their demand, but the base number is necessarily small because of their smaller service territory.

This shows the danger of looking at absolute numbers out of a context such as riders per route kilometre (in effect, the density of demand), not to mention possible variations in the level of demand and boarding patterns along a long route.

Continue reading

The Myth of “No Short Turns” (Revised)

Note: Calculations behind the charts in the original version of this article include a methodology problem. Short turn counts for vehicles crossing two screenlines (such as eastbound on Queen at Coxwell and at Woodbine) were distorted when these events did not occur in the same hour. Other problems included double counting of cars that looped twice at a short turn point (e.g. College Loop), and cars that were entering service via a loop being counted as short turns.

Changes in the text are shown by highlighting of the new version. All charts have been replaced.

My apologies for any confusion, but the charts used here avoid the potential confusion of values shown originally.

One of the many annoyances of trying to use transit service is to discover that your bus or streetcar has been “short turned”, that is to say, will not reach the destination advertised. This might happen before you board so that an arrival prediction turns out to be for a streetcar you can’t use, or as a “surprise” when the operator gets on the PA to announce that Transit Control wants to short turn the car.

This has been a problem for as long as I have been involved in advocacy for better transit service.

TTC Board members and Councillors hear about this problem a lot, and they in turn beat on management to eliminate the practice. This can produce unwanted side effects, notably the padding of schedules so that it is almost impossible, at least in theory, for a car to be late and, therefore, short turns should not be required.

Alas it is not quite that simple. Short turns occur for various reasons including schedule issues, crew change timing, major delays/diversions and “operational problems”, that catch-all phrase covering everything from a stuck door to a plague of locusts. (Some explanations for transit service problems have been with us so long they have taken on an almost Biblical character.)

Meanwhile, the CEO’s Report happily tells us every month that short turns are a thing of the past, that they are so rare that it might not even be worth tracking them as a service metric.

Source: June 2022 CEO’s Report

The big drop in the metric in spring 2019 coincides with a point where a “no short turn” edict was issued by the CEO. This is not really practical as there are many bona fide reasons for short turning vehicles, but the numbers obediently went down and have stayed down.

Regular riders, however, might choose to differ in their day-to-day observations.

Since 2019, we have come through the pandemic era when a great deal of traffic congestion and ridership disappeared. For a time, the type of event that would disrupt service was comparatively rare. However, with “normal” conditions returning, service is no longer insulated by these effects.

In my own travels, I routinely encounter streetcars that are not going to their scheduled destinations. Let me be the first to say that I understand the need for short turns, but am rather amazed that the reported counts stay very close to zero. This simply does not match actual experience. A short turn is a short turn, regardless of why it is required.

The question, then, is how to count these events reasonably easily without standing on street corners clipboard in hand. Vehicle tracking data that I already receive from the TTC’s Vision system (and which drives the many arrival prediction apps) provides a simple mechanism.

In this article I will review several common streetcar short turn locations to see what is actually happening.

If readers have specific bus routes and locations they would like to see, please leave your request in the comments.

Continue reading

The Myth of “No Short Turns”

Note: The charts in this article include a methodology problem. Short turn counts for vehicles crossing two screenlines (such as eastbound on Queen at Coxwell and at Woodbine) are distorted when these events do not occur in the same hour. This article has been replaced with a revised version, but I am leaving the original here for reference.

Continue reading

Service Quality on 26 Dupont: March-April 2022

Service quality and reliability are, as regular readers here know, central to many of my critiques of the TTC.

Whether a route is short or long, busy or not, the TTC seemed incapable of accepting much less addressing service problems. For years, long before the pandemic, riders have complained about long, unpredictable waits and crowded buses, but the answer has always been that things really are not that bad. This is demonstrably not true.

The TTC relies on metrics based on averages, not on individual vehicle behaviour and this masks the wide variation in rider experience. 26 Dupont is an infrequent route with few riders, and it does not figure in the high end of the TTC’s attentions.

We have been through two years where the pandemic and the need to keep something, anything running took precedence. Now, with the hoped-for recovery, the TTC must address long standing problems that predate covid.

Looking ahead to their 2023 Service Plan, the TTC will attempt to deal with this issue as it is essential to improving transit’s attractiveness and luring riders onto the system.

Continue reading

TTC 2023 Annual Service Plan Preview

The TTC began consultations for its 2023 Service Plan on June 29 with a pair of online meetings for community groups, and more will follow. There will be an online survey available starting on July 11.

At this point, the Service Plan is only a collection of proposals. The TTC seeks feedback on them that will lead to a revised version in the fall and a second consultation round before they go to the TTC Board for approval. The round one proposals relate mainly to the SRT shutdown in fall 2023 and the opening of Line 6 Finch West. In the second round, these proposals will be fine-tuned and other possible changes unrelated to the rapid transit plans will be added.

2022 Service Plan Follow-Up

Some service changes proposed in the 2022 plan have been implemented, and others will follow later this year:

  • Seasonal service on the new 172 Cherry Beach route (replacing the former 121 Front-Esplanade bus) was implemented in May, but the planned route through the Distillery District was impossible due to construction on Cherry at Lake Shore.
  • 65 Parliament will be extended to George Brown College’s Waterfront Campus in September. There is no word on an extension of the 365 Parliament Blue Night bus which originally was going to be dropped. The 365 lost its weekend service in 2021, but that was recently restored.
  • The 118 Thistledown extension to Claireport & Albion and the 8 Broadview extension to Coxwell Station will occur later in the fall, date TBA.

With the completion of the Line 1 Automatic Train Control project later this year, the TTC will be able to improve service on the subway. However, just what this means depends on the base against which “improvement” is measured.

  • There is a planned service improvement in September. Current service is not running at pre-pandemic levels, and we do not yet know if September will see a full restoration.
  • ATC will provide two benefits: trains can run closer together, but also travel times can be trimmed to reduce the number of trains needed. The degree that each of these will show up in new schedules remains to be seen. A related problem is that more frequent service can compound with excess running time to worsen terminal approach queues driving up travel time for riders.

Overall system ridership was at 57 per cent of pre-pandemic levels in June 2022 and is expected to rise to 70 percent in the fall. The TTC is finalizing their fall service plan to accommodate some return to in person office travel and post secondary demand. They plan to restore services to post secondary schools that were cut because of online courses. Details TBA.

There is no announced date for the opening of Line 5 Crosstown by Metrolinx, and so the planned route restructuring to support that line will likely not occur in 2022.

Continue reading

College Street Upgrades Consultation

The City of Toronto will hold an online consultation regarding planned work this fall on College Street between Manning and Bay Streets on Monday, June 27 from 6:30 to 8:00 pm.

The work involved includes streetcar tangent (straight) track replacement from east of Bathurst to west of Bay, not including intersections.

Also planned are new protected cycling tracks as well as changes for pedestrians such as improved transit stops.

Further details are on the city’s website linked above.