TTC Board Meeting March 26, 2015 (Update 2)

The TTC Board met on March 26, and considered a meaty agenda that begins to address some important policy issues.

Updated March 29, 2015 at 3:45 pm: The presentation on One Person Train Operation (OPTO) given at the meeting has been added along with comments.

Updated March 24, 2015 at 8:10 am: After this was published, the TTC posted the CEO’s Report.

In a previous article, I wrote about the Spadina subway extension project update. This will undoubtedly be the main attraction both for board members and the media. Other items of interest include:

  • An overhaul of system key performance indicators (KPIs)
  • A door monitoring system for Toronto Rocket trains and one person train crews (Updated March 29)
  • Revision and consolidation of the resignalling contract for the Yonge-University line
  • A study of express bus routes
  • CEO’s Report

Continue reading

How Much Will The Spadina Extension Cost? (III) (Update 3)

Updated April 13, 2015:

The TTC has issued a press release regarding the management of the Spadina subway extension project:

The Toronto Transit Commission has entered into an agreement with Bechtel Canada Co. for project management of the Toronto-York Spadina Subway Extension (TYSSE) for up to $80 million.

The contract value to Bechtel is based on staffing costs, management fees and incentives to open the subway extension by Dec. 31, 2017. Bechtel staff begin work today and will form an integrated team with existing TTC personnel. The Bechtel contract will expire March 31, 2018. Bechtel’s project director will report directly to TTC CEO Andy Byford.

On March 26, the TTC board approved a report from staff that recommended TTC enter into a sole source agreement with a project manager with a proven track record of delivering similar-sized projects on time, and with experience working with multiple contractors, in order to have the TYSSE in service by Dec. 31, 2017.

Toronto City Council subsequently authorized the expenditure of $90 million, while the Regional Municipality of York authorized the expenditure of $60 million, for a total of $150 million (third party contractor, plus in-house project costs), to fully deliver TYSSE by the end of 2017.

The release is silent on the issue of what might be done with the remaining $70m of Toronto/York’s $160m authorization.

Original article of March 29, 2015:

In a previous article, I reviewed information from a media briefing by Andy Byford on the status of the Toronto York Spadina Subway Extension (TYSSE) project. At the TTC Board meeting on March 26, 2015, further information was made public both in Byford’s presentation, and in additional material appended to his report.

Updated March 30, 2015 at 1:30 pm: The slides from Byford’s presentation are now available starting at page 58 of the linked pdf.

Updated March 30, 2015 at 11:30 pm: A new report from the Toronto City Manager to Council advises that the interest earnings on the “Move Ontario Trust” (the repository for provincial contributions to the TYSSE project) have not achieved the target rate of 4% resulting in an $85m shortfall. Oliver Moore reports in the Globe that Ontario has refused to make up this amount as per the original agreement between the funding partners. Toronto and York Region are on the hook for this additional cost estimated at $51m for Toronto and $34m for York Region. This expense is over and above the cost overruns on various contracts, but at least Council cannot blame the TTC because the trust fund is not under TTC control.

Appendix F (beginning at page 33 of the linked PDF), is a presentation given to the Executive Task Force who oversee the project on behalf of the sponsoring governments on July 28, 2014. The presentation was given by Parsons Brinkerhoff who had been retained by the TTC to review the project.

Appendix G (beginning at page 56) is a two-page summary of Bechtel’s work reviewing PB’s original study and a subsequent APTA (American Public Transit Association) peer review. APTA concluded that an earlier completion date would be possible than PB had projected, but only with major changes to the project management structure. Bechtel concurred in these findings.

It is abundantly clear from this material that the TYSSE’s problems were known at the top level of the project in mid-2014 at the latest. At the time, their severity was so great that the project would still be incomplete by the time of the next municipal and provincial election cycles, and that considerable additional cost could be facing the funding partners. This very serious issue did not arise in public discussion until six months later, notably after Toronto’s 2015 budget cycle was complete.

Continue reading

How Much Will The Spadina Extension Cost (II)?

In a previous article, I reviewed the history of the Toronto York Spadina Subway Extension (TYSSE). This project has been widely reported to be both late and over budget, but details only began to emerge on March 20, 2015 when TTC CEO Andy Byford fired two senior members of the engineering staff.

On March 21, 2015, Byford presented a briefing to the media as a preview of a report to be discussed by the TTC Board on March 26, 2015. This report includes both current information on the project and an October 2012 update that was issued when the TYSSE deadline was shifted to fall 2016.

The key points of the briefing were:

  • The earliest possible opening date for the TYSSE to Vaughan is the end of 2017.
  • Relations between TTC project management and the various contractors working on the TYSSE are badly strained, and this cannot be remedied by those now in charge.
  • Byford recommends that the TTC “retain a third party project-management firm as an incentivized project manager” (the terms of the proposed arrangement are confidential pending execution of the agreement).
  • Alternate schemes for continuing the TYSSE project with TTC staff in part or all of this role will extend the period needed to resolve outstanding issues and reach project completion, and will increase total project costs.
  • Additional funding to keep the project active to the end of 2017 of $150-million is required with Toronto paying $90m and York Region paying $60m. Toronto’s share could come from a TTC operating surplus in 2015 (mistakenly cited as “2014” in the report), property sales and/or deferral of projects. There is no word on how York Region might fund its share of the extra costs.
  • The project is subject to many claims by contractors against the TTC, and some counterclaims on the TTC’s part. The eventual value of settling these is unknown, and this is a potential additional cost beyond the $150m. Whether this can be accommodated by the existing project budget remains to be seen.

Continue reading

TTC Service Changes Effective May 10, 2015

The schedule changes for May 10 will bring the first wave of improvements from the recently adopted City of Toronto budget and increased transit subsidy.

  • Many routes will gain service to begin implementation of the “Ten Minute Network” on core routes across the system. This stage mainly affects weekend service. Weekday changes to some of these routes will follow with the June schedules.
    • 192 Airport Rocket
    • 506 Carlton
    • 25 Don Mills
    • 36 Finch West (to Humberwood)
    • 191 Highway 27 Rocket
    • 504 King
    • 44 Kipling South
    • 47 Lansdowne (Queen to St. Clair)
    • 129 McCowan North (to Steeles)
    • 116 Morningside (to Finch)
    • 63 Ossington (to St. Clair)
    • 86 Scarborough (to Sheppard)
    • 24 Victoria Park (to Steeles)
  • The implementation of “All day, every day” service will begin.
    • 108A Downsview to Jane via Grandravine on Sundays late evening.
  • Expansion of express bus services will begin.
    • 196 York U Rocket to Sheppard-Yonge Station on weekends daytime.

The Scarborough RT will now be officially known as “3 Scarborough”.

Branch name changes will continue the move to use of the “A” designation for the primary branch of routes:

  • 6A Bay Dupont to Queens Quay & Sherbourne (formerly 6)
  • 38A Highland Creek to Rouge Hill GO (formerly 38)
  • 24A Victoria Park to Steeles (formerly 24)
  • 165A Weston Road N to Steeles (formerly 165)
  • 165C Weston Road N to Canada’s Wonderland (formerly 165A)

The 102D Markham Road contract service in York Region will be extended to Major Mackenzie Drive.

At the request of York Region Transit, the 102D (Warden Stn-Mount Joy GO Stn) service will be extended to Major Mackenzie Drive via Bur Oak Avenue and Mingay Avenue. Service will be removed on Castlemore Avenue, Anderson Avenue and Bur Oak Avenue, and from Mount Joy GO Station.

Retirement of the 7200-series Nova RTS buses at Arrow Road will continue through the spring. These vehicles have been used on 96 Wilson and 165 Weston Road North, but they will be confined to peak-hour runs if any remain in service for the May schedule period.

Reconstruction of the south ladder track at Russell Carhouse on Eastern Avenue will require significant operational changes. Some runs will be reassigned to Roncesvalles Carhouse, and the use of Exhibition Loop to store cars overnight will increase. Cars remaining at Russell Carhouse will be backed into the yard from the north entrance.

Various seasonal changes reflecting the decline in school-related travel and the increase in demand for recreational trips will be implemented. However, due to the timing of the Pan Am Games and the Indy car race, the seasonal expansion of 29 Dufferin service to the Princes’ Gates will not occur (weekday midday and evening, Saturday late evening, Sunday/Holiday evening).

The split operation of 72 Pape and 172 Cherry was planned to end with the May schedules. However, construction on Front Street at Union Station continues and a date for resumption of the unified route has not been settled. The TTC advises that, except for Pan Am Games, no other changes are planned until at least September.

With the completion of construction at College & Spadina and at Spadina Station, streetcars will return to 510 Spadina. Other changes this triggers include a reduction of service on 509 Harbourfront and resumption of buses for peak extras on 504 King. Two runs on 509 Harbourfront will be scheduled and crewed for LFLRV operation in anticipation of vehicle availability.

Details of individual route changes are in the spreadsheet linked below.

2015.05.10 Service Changes

TTC 2015-2024 Capital Budget: Streetcar Infrastructure

Updated March 15, 2015 at 8:40 pm: An example of a vintage tram adapted for pantograph operation in Munich has been added to the end of this article. Thanks to John F. Bromley for the photo.

The TTC’s Capital Budget includes ongoing programs to replace worn streetcar rail as well as to upgrade the overhead power distribution system for compatibility with the new Flexity LRVs.

Replacement of streetcar track with infrastructure built to new, robust standards is almost complete on the main lines used by all routes. What remains are sections used for diversions and short turns.

Tangent track on Spadina south from College that was installed for the resumption of streetcar service in 1997 is scheduled for replacement in 2018. The table and the map differ on whether this work will end at Queen or at King. In any event, this will be the first major track replacement over a section constructed to new standards, and only the surface layer (track down to the tie attachments) should have to be removed.

Replacement of overhead contact wire with thicker 4/0 gauge is also well underway, as is the replacement of feeder cables, some of which are very old and are shedding their insulating covering. Intersection and yard upgrades will, together with the new tangent wire, make the system 100% pantograph compatible. When the last of the cars using trolley poles has been retired, the overhead can be further adjusted to remove pole-specific hardware and simplify future maintenance.

This article contains lists and maps of the work planned for 2015-2019.

Continue reading

How Much Will The Spadina Subway Extension Cost?

The Toronto York Spadina Subway Extension (TYSSE) to Vaughan has been much in the news lately thanks to its delayed opening and cost overruns. The line was originally expected to open in 2015, even in early rosy estimates before the Pan Am Games, but now will not be in service until 2017. The project was repeatedly cited (as recently as December 2014’s CEO Report) to be on its budget of approximately $2.6-billion. The exact final cost is not known but has been reported to be up to $400-million more.

To date, the TYSSE project is on budget with a total budget of $2,634 Million. The in-service date is targeted for the fall of 2016 however the project is facing a serious schedule challenge. [CEO’s Report for November-December 2014, p. 29]

The “on budget” statement, which had appeared in all previous CEO reports, vanished with the January 2015 report.

A peer review was conducted by an APTA panel in late 2014 largely to assess schedule and budget challenges. A report is expected at the end of January related to schedule and budget challenges and will make recommendations to mitigate these challenges.

Bechtel Ltd., a consulting firm, was also retained at the CEO’s specific direction to conduct a thorough in depth analysis of the project and likewise is expected to present its findings at the end of January. [CEO’s Report for January 2015, p. 30]

The results of these reviews are to be tabled at the March 26, 2015 TTC Board meeting.

There are two issues in play here. First and most obvious is the question of how a major project can suddenly be found to have budget problems, and why these were not discovered and reported sooner. How much oversight did the TTC Board actually have beyond the one-line monthly assurance that the project was “on budget”? Second is the more general question of the tracking of major projects, and why this is not regularly reported to the Board and through them to City Council and other funding governments.

To learn as much as I could from publicly available sources, I culled through TTC meeting reports going back to the early days of design work on the TYSSE. Tracking a project’s history this way can be challenging for various reasons:

  • Some agendas exist only as a PDF file without links to the underlying reports.
  • TTC procurement policy allows contracts of up to $5-million to be approved by management without a report to the TTC Board. (This is in line with the City of Toronto’s policy.)
  • A monthly report listing all expenditures authorized by management in the $1-5m range was discontinued in March 2012.
  • Changes in the total authorized spending on a line item only appear in public when there is an update involving a large contract change.
  • The CEO’s report tracks variations in capital spending, but this is only against the expected amount for the current year, not for a project overall. Because of various delays, the TYSSE tended to underspend versus plans even though the estimated total cost to completion might actually be rising.

Continue reading

City of Toronto Budget Amendments 2015 (Updated)

At its meeting of March 11 and 12, 2015, City Council passed a few budget amendments affecting the Toronto Transit Commission. Some of these reflect a sense that the TTC has not been “minding the store” quite as well as it claims, and a little belt tightening is good for any organization. Others address specific concerns that, quite frankly, should have been on the TTC’s agenda before now, but were buried under the rapid transit debates.

The motions address the following topics:

  • Additional Streetcars
  • Automatic Train Control
  • Waterfront West Transit
  • TTC Staffing and Project Management

Updated March 13, 2015 at 1:50 pm with further information about proposed staffing reductions.

Continue reading

Metrolinx Board Meeting Wrapup: March 3, 2015

The Metrolinx Board met on March 3 for its quarterly gathering. Although there were important issues on the agenda, the debate was as superficial as usual, and the message that “everything is just great” permeated the proceedings.

Things got off to a slow start. The meeting room is relentlessly beige, overlit and unadorned. Windows there are, but when we entered, they were already partly screened and the view, such as it is, simply looks across to rooms and the roof opposite. Not long into proceedings, a further set of screens blocking this view descended lest we be distracted from the worthies sitting at the board table. We might as well have been in the set of an existential play wondering if there actually was a world outside, not a fine, downtown historic building.

The first order of business was a goodbye to retiring director Nicholas Mutton, a genteel fellow who has headed up the Customer Service Committee. Sadly his reports are always pushed to the back of the agenda and are rushed for time, and his presentations rarely get beyond reading a few pages of a short PowerPoint.

Then we had a brief report from Bruce McCuaig, the Metrolinx President & CEO, reiterating events of note since the last board meeting in December. One might forgive the poor directors for being out of touch with recent news given that they meet so rarely and have so little to say. Surely they stay informed on Metrolinx activities and don’t need a recap beyond the most unusual events.

In the remainder of this article, I will discuss:

  • Back-Charging Toronto for Metrolinx Work
  • The Regional Express Rail (RER) Update
  • The Regional Fare Integration Study
  • The Study of the Pearson Airport Area

Continue reading

TTC Confirms Streetcar Service Levels With New Fleet

Toronto’s Budget Committee has asked staff for many briefing notes on details behind various programs. Among these requests was for TTC to detail the level of service that would be operated on all streetcar routes after the 204 new Flexitys have been delivered, and how this would be improved with the addition of a proposed 60 car order.

The TTC has responded with a report that details how the cars would be used.

Long–Term Peak Headway Projections for Streetcar Routes

With the initial 204 car order:

  • Peak headways would widen by varying degrees on all routes except 501 Queen where existing AM peak frequency would be maintained using the larger cars. The biggest change would be on the 502/503 services changing from 12′ to 14’30” on each of the routes which, in theory, provide a blended service.
  • Capacity increases in the AM peak would be greater than in the PM peak.

With the additional 60 cars:

  • Peak headways would return roughly to current levels. Capacity, relative to today’s service, would be considerably higher than today, except anomalously, on 501 Queen.

The report notes that additional cars will be needed for routes to serve the waterfront, but gives no indication of the service levels or fleet requirements for these routes. Because the report shows only headways for existing routes, not vehicle allocations, it is unclear how many of the 60 cars go for service improvement and how many for new routes. The percentage improvements on existing routes are high enough that it is possible that cars have been double-counted for this purpose. I will follow up on that issue with the TTC.

Updated at 12:22 pm: At Budget Committee, Andy Byford confirmed that the only “expansion” covered by the 60 cars is the Cherry Street spur south from King Street.

Updated at 3:00 pm: The TTC has confirmed that all of the 60 additional cars would be allocated to “legacy” routes with none reserved for expansion. As to the spare ratio they would design for:

“Spare ratio of 18%. We expect that that we will be able to reduce that when the fleet is settled in and we have confidence in the performance and reliability but, until then, this is our going-in assumption.” [Email from Mitch Stambler, TTC]

The ratio for the streetcar fleet today is about 25% (not including cars out of service due to cold weather) with roughly 200 of the 247 in the fleet scheduled for the AM peak.

A Few Questions About Scarborough

Toronto Council’s agenda for today, February 10, 2015, contains a series of “Administrative Inquiries” by Councillor Josh Matlow regarding various aspects of transit plans for Scarborough. The City Manager’s response appeared late yesterday, but it was not exactly packed with revelations.

In theory, the inquiry process provides a way for questions to flow directly from a Councillor to City staff bypassing the usual mechanism of committee reports where administration majorities might strangle debate. In practice, the information released might or might not fully address the question.

Mayor Tory’s position is quite clear: the subway debate is over, and Matlow’s questions are simply attempts to reopen the question on matters that are already known and decided. Would that it were so simple. Subway champions should pause in their dismissal of Matlow’s position because the report shows how much we don’t know, or at least are not being told, about the subway project.

Continue reading