How to Build a Subway — Let Me Count the Ways

As everyone knows, the public sector wastes huge amounts of money on overblown, out-of-control projects, or at least that’s the prevailing view in some quarters. One major side-effect of Ottawa’s participation in funding the York subway extension (or TYSSE: Toronto-York Spadina Subway Extension), in an insistence on value-for-money and the maximum participation by the private sector.

Leaving aside that the TTC doesn’t actually build anything itself, and contracts out a vast amount of the design/engineering work, there is a perception that (a) subway construction projects could be better run and (b) there is (even more) opportunity for private sector participation.

A report on this week’s TTC agenda discusses the various options for delivering this project and includes some revealing information about the pros and cons of various approaches. I will leave it to those who are interested to read the full text, but a few things caught my eye.

First off, there are many ways and degrees in which a private sector company or consortium can be involved in large projects like this all the way from complete design, finance, construction and operation down to a basic contractor who bids on a job, builds a box and leaves.

In the review of options, the variants where operation rested with a private entity were rejected outright because the TYSSE is part of an existing, operating, public-sector subway line. Experience elsewhere suggests that private operation tends to occur only when a new, free-standing line is built such as the Canada line in Vancouver.

Financing options are not discussed at length, but this issue always turns on the question of whether a private partner can provide capital at a lower cost than a public agency. This also involves some creative accounting. A privately owned line (and its associated capital debt) does not appear on the public books. This scheme is commonly used to hide debts (think Enron), although generally accepted accounting practices for governments make this more difficult to pull off. Even if a government is not technically exposed to the debt, the last thing any (well almost any) provincial government will do is to let a subway line close because its owner is bankrupt.

We have heard a lot lately about borrowing from large investment pools such as pension funds. Whether this is done on a government basis or by an arm’s length agency, somehow the interest and debt must be paid. Either this is a direct charge against current operations, or it is transferred to a government through a subsidy arrangement (no doubt with an appropriate management fee).

As for construction, the difference between the two main options depends on whether the TTC designs it all and contractors just build it, or if the TTC says “build me a subway station” and the contractors design to a general set of specs and deliver a finished product. A working group from the construction industry reported that their preference is to leave the design to the TTC for contracts under $100-million, or where there will be multiple contractors (possibly including the TTC itself) onsite. This relieves the contractor of having to manage (and assume risk of) portions of the work not under his control.

For large contracts, it may be worth a contractor’s while to bring the design work in house provided that the job is fairly generic and does not require skills in special systems peculiar to transit. For example, building an empty box that will become a subway station or tunnel structure is a fairly straightforward task while design and co-ordination of the many subsystems fitted within the structure are complex and outside of their regular scope of work.

One point not mentioned here is that the industry’s skill base depends strongly on what they do most of the time. An important observation about Madrid in recent studies is that their continuous program of system expansion allows the industry to develop expertise and continuity of staff that would not otherwise be possible. In Toronto, there are only so many subways to go around among the major players, and we don’t build them very often.

Finally, there is a breakdown of the TYSSE’s estimated cost — $2.09-billion in 2006 dollars, or $2.633-billion assuming completion by 2015. This date could slip if various governments spend time squabbling about whether the project passes a private sector sniff test, adding to the cost.

For all you readers who have wanted a subway station of your very own, we see station costs of $73-to-$100-million depending on the complexity. Of particular note is a 26% contingency. This rather generous $400-million slush fund (a cool half-billion with inflation) will allow considerable overruns while keeping the project “on budget”. At this point, I will be generous and hope that this is for “things we haven’t thought of in the preliminary design”, but at some point this needs to be nailed down. I doubt we will ever know how much contingency everyone builds into their estimates (public or private partner) and yet there is probably more money on the table in this one line than in any savings, real or imaginary, from increased private sector participation.

I should mention the rolling stock. The estimate shows 56 cars, although it is physically impossible to buy them in this quantity as they now come in married sets of 6. Even with these cars, the TTC will not have enough “Toronto Rockets” to completely replace the existing fleet on the Yonge-University-Spadina line, and another car order will be needed. Thunder Bay will be churning out cars for years.

The TYSSE will be interesting if, for nothing else, showing us whether there is money to be saved on subway projects with greater private sector know-how at work. Alas, we won’t have an answer to the question for about 7 years, and we will have spent $2.5-billion finding out.

Kingston Road LRT Update

The Environmental Assessment for the proposed Kingston Road LRT will hold three open houses on March 26, 27 and April 2.

The project’s March 2008 Newsletter includes the meeting locations, a map of various proposals and a breakdown of travel in the corridor.

There are two primary options depending on whether the line stays on Kingston Road all the way west to the existing streetcar network at Bingham Loop (Victoria Park & Kingston Rd.), or if it travels west along Danforth Avenue. Sub-options include connections to the subway at Victoria Park or Main Station.

At the risk of prejudging the evaluation, the route north from Kingston Road either to Main or to Victoria Park would be quite difficult. Victoria Park is a narrow, 3-lane residential street south of Gerrard. Main is a narrow, 4-lane residential street, and has a curved alignment (not shown on the map) and a grade down to Kingston Road. I believe that a connection north to either station from Kingston Road is not practical. (Anyone who wants to argue this point is urged to actually visit the neighbourhood or at least look at Google Maps before taking on this issue.)

The Danforth alignment is more straightforward, and also provides a better connection to the rapid transit network. In the origin-destination survey, only about 1/4 of the respondents showed their AM peak trip as going “downtown”.

Planning for the revised Victoria Park Station (warning – 10MB file) does not show a possible streetcar service, but could accommodate it.

Finally, the Walk 21 conference last fall included a paper about redesigning Kingston Road into a strong shopping and pedestrian community in the Cliffside area. This neighbourhood is now dominated by strip commercial and parking lots, but its transformation is supported by the business community with the new LRT line as a catalyst.

This project is in an odd state of existing in theory, but never appearing on maps showing our bold new Transit City network. This very strange situation makes many wonder whether there is any hope of the project actually being funded and built.

Victoria Park Station Re-Design

There is a report up on the TTC’s site showing the plans for renovation of Victoria Park Station. Note that this is a roughly 3.5MB document.

For those of you looking at the URL linked here, yes there is a spelling mistake in the TTC’s filename with “Vcitoria” Park station and terminal “Finsihes”. If they fix this, the link may break, and you will have to go to the general report site to get the document.

Census Updates on Commuting Reported by CBC

The CBC website has a report about the drop in the percentage of people commuting by transit according to the recent census. In this piece, I am erroneously identified as a member of Rocket Riders. Although I have provided suggestions and advice to that group from time to time, I do not speak for them and my comments should not be construed as an official pronouncement by that group.

Here are my remarks. For the complete text, go to the CBC site.

Toronto transit advocate Steve Munro said the 2006 findings are disappointing because they show there is little change in the number of people taking public transit.

“I’m frankly surprised that’s it’s only gone down by a small amount as it has,” said Munro, a member of the Rocket Riders, a citizen advocacy group dedicated to public transit issues in the Greater Toronto Area.

Munro said part of the problem is much of the transit system in Toronto is oriented towards downtown, including GO Transit and the Toronto Transit Commission with its network of subways, buses and streetcars.

He said travel patterns show people are commuting in all different directions these days.

“It’s one of the biggest challenges for transportation planners,” Munro said.

“It’s an everywhere-to-everywhere kind of demand pattern, and that’s very hard to serve without building quite a large network of transit lines to make everywhere-to-everywhere commuting by transit possible.”

Munro said convincing people who live in areas outside the downtown core to get out of their cars will take large investments in transit in the GTA.

“We’re a long way away from having a really strong network in the outer suburbs to really make a change in the way people think about commuting in those areas.”

A stronger network will also reap environmental and economic benefits, he said.

For individual families, if the transit system can serve their needs, the cost of getting to work is lower. For cities, if the transit system moves people around efficiently, there is less stress on the roads, Munro added.

“The road system in the suburbs is full. There is a general economic benefit to having a better transit service. It means families don’t need a car for every member of the family to get around.”

Transit City Update

At the TTC meeting last week, there was a long presentation about the status of the various Transit City projects. The TTC’s website contains only the two page covering report with absolutely no details, but lucky for you, my readers, here is an electronic copy. As and when the TTC actually posts this report on their own site, I will change the link here to point to the “official” copy.

Warning: 7MB download: Transit City February 2008

While there may be individual issues to prompt kvetching in this report, overall I am impressed by what is happening. For the first time in over 30 years, we have not only a unified plan, but a unified set of studies. I may be naïve to expect all of this will actually be built, but we are in far better shape knowing what might be than if only one or two lines were on the table.

Here is an overview of the report along with my comments.

Overall Priorities

Of the various Transit City proposals, three have been selected as the top priority for design, funding and construction: Sheppard East, Etobicoke Finch-West and Eglinton-Crosstown. All lines were scored against various criteria, and those coming out on top overall got the nod. This doesn’t mean work stops on the others, but at least we know the staging.

Projected total ridership is highest for Eglinton, Finch and Jane, with Sheppard East in 5th place. Partly, this is due to the length of the routes and their catchment areas. Note that Waterfront West brings up the rear, unsurprising given the area it draws from.

The lines rank roughly the same way for the number of car trips diverted to transit and the reduction in greenhouse gases. There’s something of a compound effect here as several measures all vary more or less as a function of ridership.

Transit City, again with the exception of Waterfront West, touches the City’s priority neighbourhoods where better transit is needed to increase mobility and economic opportunities for the residents.

What’s Missing

Notable by their absence are the Waterfront East lines (Queen’s Quay, Cherry Street and Port Lands) as well as the Kingston Road line in Scarborough. EAs are aready in progress for these, but they don’t make it onto the overall status report.

This is a shame because we must stop making distinctions between “Transit City” itself, and other related transit projects that will compete for attention and funding. Continue reading →

Service Improvements, Someday

Peter Kuitenbrouwer in the National Post has a series of articles talking about crowding on the TTC.

One more person, and this subway’s gonna explode

If you ignore the smell, the bus is still the better way

A seat on the Queen streetcar? Don’t make me laugh

The February 17 service improvements are a start, but it’s no secret that there’s a long way to go. A few changes are in the wind as described in a TTC report from their February 27 meeting.

We learn that more service will come with the March 30 and May 11 schedule periods to address the backlog of overcrowding, at least on the bus routes.

In the fall, further improvements will change the peak hour loading standard for bus routes. Across the board, the standard will be improved by 10% so that the acceptable average loads, now in the mid-50s depending on vehicle type, will be reduced by 5 or 6. This won’t mean 10% more service on every route because some lines are running below the new standard already and won’t be eligible for more service. (These tend to be short routes where cuts today would have a severe impact raising the average load above the line or making the headway unacceptably wide.)

Also planned for the fall is a return to full hours of service on most routes so that if the subway is open, the routes are operating at least a 30-minute service. 2009 may bring a 20-minute maximum, but that’s a budget issue for next year.

Meanwhile, we see little discussion of streetcar or rapid transit service because both suffer from constraints in fleet size. That may be the situation, though I am skeptical, but what is missing is a projection of what we would need if we made the same changes in loading standards for the rail modes. Continue reading →

Interminable Waits at Kennedy (Update 3)

Updated Feb 27, 6:15 pm:

At today’s TTC meeting, we learned that they expect to have repairs at Kennedy completed by Friday. I will post more information about the derailment and the nature of the damage when I receive an electronic copy of the report on this incident.

Correction Feb 26, 11:00 pm:

This evening, I received the following email from Adam Giambrone, Chair of the TTC. It was addressed jointly to me and to Ed Drass whose column I cite later in this post.

Steve,

I told Ed Drass yesterday that I understood the slow order was to be off by now BUT that I was going to check with Warren Bartram of TTC during a tour of the tunnels with CTV earlier this morning (2am-5am) to confirm. I actually watched the crews doing the repairs and I called him earlier today to confirm that the slow order was still in place and will be for another week or so.

The problem is that many of the bolts (I don’t know their technical name) that bolt the rail to ground were ripped up (some 150) and there is only so much that can be repaired in the 150 minutes they have most days to do the work.

Anyway, I usually qualify a statement of fact if I am not sure and I did so in this situation.

Adam Giambrone

I expect to get more details at the TTC meeting tomorrow and will post that info here.

This post has been revised in light of Adam Giambrone’s email.

Updated Feb 26:

This morning at 8:40 am, the backlog of trains from Kennedy stretched to Victoria Park Station, and the trip from there to the terminal took 21 minutes.

According to Ed Drass’ column in today’s Metro, Adam Giambrone was advised that the slow order on Kennedy crossover was lifted last week. This proved to be incorrect based on his email quoted above.

Original post:

Ever since the Kennedy Station derailment two weeks ago, service at the eastern terminal of the Danforth Subway has been glacial, especially at the end of the peak periods. As an example, I spent more than 15 minutes this morning getting from Victoria Park to Kennedy Station, and this has happened almost every day for the past two weeks. Looking on the bright side, the TTC has figured out how to operate a reasonable headway on the SRT even when it was in “manual” mode and we no longer creep from Kennedy to STC. The combination of these two delays made the term “rapid transit” quite a joke.

The problem at Kennedy arises from the slow order which has been on the crossover. Trains move over it at low speed while TTC staff watch carefully as the trains pick their way through the special work. Riding on trains, I can’t tell whether the roughness of the crossing is due to the very slow speed or the condition of the track. With luck, we will learn more at Wednesday’s Commission meeting when there will be a presentation on the derailment.

Meanwhile, capacity on the BD subway is badly constrained. In two previous posts, I talked about the physical limitations that subway line and terminal layouts place on the frequency of service.

How Often Can Subway Trains Run?

How Frequently Can We Run Subway Trains?

The minimum headway at a terminal controls the level of service on the rest of the line unless additional trains are inserted at short-turn points. Indeed, that is how the TTC plans to fit more trains onto the Yonge line in eight years or so with turnbacks at Finch (following a northerly extension beyond Steeles) and somewhere in Downsview (following the York U extension).

Just to review, here is the sequence of events at a terminal:

  • Signal turns green
  • Train guard initiates door closing and this completes
  • Train moves off from platform and eventually clears the crossover
  • Signal system determines that the crossover is clear and realigns the switches
  • Signal system displays clear for the incoming train
  • Incoming train starts up and crosses into the station
  • Signal system determines that the crossover is clear and realigns the switches

The two longest steps in this sequence are the train movements. Today, I timed trains at Kennedy, and it takes 80 seconds for a train to move from a stationary position either on a platform (departing) or from the last approach signal (arriving) through the crossover to a point where the junction is clear for another movement.

This means that 160 seconds (2 minutes, 40 seconds) are consumed simply for train movements. Add to this about 10 seconds for signal and switch system activity, and we are up to 170 seconds before any delays introduced by the readiness of crews to depart.

However, the scheduled headway on the BD line is 144 seconds (2 minutes, 24 seconds) in the morning peak. Quite clearly, it is impossible to operate this headway given the constraints at Kennedy, and a queue of trains builds up. This affects service on the entire line unless trains are inserted along the way to bring the headway back down to the scheduled level.

The TTC should seriously consider short-turning some trains. This could be done at Warden, provided that these trains crossed over to the westbound platform so that they did not block the eastbound flow. Yes, this would require careful management at Warden, but it would reduce the backlog at Kennedy and allow a reliably frequent service to operate on the rest of the line.

I say this with some trepidation because this scheme could also foul up the line just as badly as the current arrangement if it were not managed to ensure fast in, fast out turnarounds of the short-turning trains.

A further option, applicable only to the am peak, would be to send trains that would run out of service to Greenwood into the yard eastbound.

I write this not just as someone who is personally inconvenienced, but out of concern that a long-standing operational problem affecting service capacity has not been addressed.

After Wednesday’s update at the TTC, I will add to this item as appropriate.

Queen’s Park, Metrolinx & the TTC (Updated)

Late last week must have been slow for real news when both the Star and Globe devoted considerable space to musings at the Pink Palace about a Metrolinx TTC takeover. Furious backpedalling all ’round with denials from Metrolinx’ Rob MacIsacc and cries of “hands off” from Mayor Miller.

Lurking under this sort of scheme are claims that just don’t hold up to scrutiny.

First up is the oft-heard desire for “seamless integration” of transit. Boiled down to its essentials, this means I should be able to ride from anywhere to anywhere for one fare with convenient integrated service wherever a change of route or mode is needed.

Riding on the back of this is a scheme for fare-by-distance charging and smart cards. While this may keep the technology companies and those who value appearance over substance as transit policy, this is totally the wrong end of the “solution”.

If the desire were to give everyone an integrated fare between the TTC and the 905 systems, we could do it tomorrow either with the GTA pass or some area-specific version. The big problems are how to divide up the revenue, what to charge and whether there will actually be any service in the 905 with which a 416 rider can seamlessly connect.

These are organizational and financial issues. As long as each transit system is expected to keep its own books, raise its own revenue, and account for every penny (perish the thought we might needlessly run one more bus than necessary), the rules of the game create agencies that defend their revenue turf.

As long as we maintain artificial distinctions between who gets to pick up riders on which street (again partly a turf war), we will have duplicate services.

As long as we starve transit agencies for funds, the clear goal is not to improve service but to minimize costs. This is totally contrary to any claims that our public goal is to get more people riding transit.

You don’t need a quarter-billion’s worth of high technology to fix these problems which, indeed, will still remain if we don’t fix the underlying way in which revenue is allocated to operators. If the fare barrier at Steeles Avenue is eliminated, somebody is going to have to pick up the difference — the TTC and its riders, York Region or Queen’s Park. Nobody wants that debate, but we can sidestep it so long as we focus on Presto! rather than on how it will be used.

It’s ironic that many cross-border services are now operated by TTC on contract to other agencies and the only “impediment” is the fare at Steeles Avenue. Maybe York Region would opt to pay the TTC more to carry its customers. Maybe a special subsidy could be arranged just as it is for Oakville passengers connecting with GO Transit. Why is it okay to have a special fare arrangement for GO Transit feeder services, but not for 905-to-TTC riders?

The “seamless barrier” is one of those transit myths that get dragged out regularly to avoid discussing the real issues. The line between the 416 and 905 could disappear tomorrow if only someone wanted to pay for it and co-ordinate the overlapping services where they exist.

This brings me to that shining example of Ontario’s contribution to transit, the GO system. Remember that GO is not paid for entirely by Queen’s Park, but levies a tithe against the municipalities. Only last week, a tripartite agreement with Ottawa was finally settled when Toronto agreed to pony up its share of a GO Transit funding request.

Metrolinx has been churning out discussion papers (green ones to solicit comment now, white ones to set policy soon) like sausages, and they hope this will lead to a Regional Transit Plan by “Spring 2008”. Whether they mean March 21 or June 22, I am not sure, but even the later date is very optimistic. Moreover, it is troubling because we recently learned that the RTP is also to stand in for the first two steps of the already shortened Environmental Assessment process.

We risk having a regional plan rammed through with little opportunity for comment or intelligent debate that could commit us to a complex and explicitly laid-out network long before we have a chance to consider how it will all fit together. Moreover, there is no mandatory ongoing review and process for change of the plan making “getting it right” at the outset all the more critical.

While Queen’s Park muses about a TTC takeover, they should look closer to home first. GO Transit has been in the commuter rail business for decades, with small forrays into buses, but with the focus on peak period, downtown oriented services. It does not matter what the agency name might be, there is a need for long-distance capacity around the GTA that does not stop at every lamppost. Riders in Oshawa don’t want a tour of Pickering, Scarborough, North York and Etobicoke on their way to Mississauga where they might arrive just in time to go back again.

GO’s service reliability raises questions about its ability to take on a larger role. Riders are cranky about crowding and unexpected changes in schedules, and there is even an online petition demanding a fare rebate when service runs late.

GO, however, has been at least as constrained for funding as the TTC and thinks only of its core services. Expansion comes in small jumps because they have no firm commitment from any level of government to do more.

I might believe that a Provincial agency could do a passable job with the TTC if the current one were actually looking beyond a narrow mandate as a commuter service. Imagine the example Queen’s Park could show of what their bounty could bring to transit. So far, what we have is unimpressive as a replacement for the TTC.

This is not to say that the TTC couldn’t use some housecleaning. However, any “new broom” had better know what it’s doing, not just come in to sell off the furniture and declare huge but ephemeral savings.

One particularly troubling aspect to some comments in this debate is the political slant. Adam Giambrone is out-and-out NDP, and David Miller certainly is not a Tory. Toronto Council is, if not in the grip of the left wing, at least not quite as right-wing as it was in the Lastman days.

What’s the solution? Take them over? Well we tried that with amalgamation, and after a few years of flailing around, look what we have: a moderately left Council with a moderately left Mayor. The voters have spoken.

If anyone has designs on the TTC or on GTAH transit in general, let the decisions be made for legitimate reasons of management, finance, operations and community involvement, not because some politician wants to score points for a coming election. We have seen decades of Provincial interference in transit both in funding and in technology choices that had much more to do with so-called economic development and pandering to voters than with production of useful transit infrastructure.

Message to Dalton McGuinty: Leave the TTC alone. Let Metrolinx continue with its planning, and don’t force the issue of a final plan so quickly and so permanently that we regret everything and start over in ten years.

Recognize that building and running more transit, getting a bigger share of the travel market, is going to cost a lot of money, and some of that will come from the public purse. Keep your chequebook handy.

Don’t substitute the illusion of action — organization and re-organization — for the real needs of transit systems throughout the GTAH.

Metrolinx Fast Tracks Environmental Assessments

I received the following note from Tony Turritin that fits in with earlier threads about streamlining the Environmental Assessment process:

Just a note to mention that Metrolinx published Statutory Notices in the Toronto Star on January 7 and 9, 2008 regarding their Regional Transportation Plan study.

By my reading of the notice, transit advocates better get on the stick, because if it ain’t in the plan in just the right way, there is no or little hope for any alternative. The Notice states that the RTP will constitute Phases I and II of any future EA that flows from any element of the RTP as it is implemented.

The Notice states:

“Once completed, the RTP will provide the background for any required future Environmental Assessment (EA) studies. It is intended that the recommended RTP will have fulfilled the requirements of Phases 1 and 2 (i.e. problems/
opportunities and evaluation of alternatives to the undertaking/ selection of the preferred transportation system) of all applicable Class EAs and individual EAs that may be required for projects identified in the RTP. The selection of the preferred transportation system will identify the need for the facilities, the recommended network corridors, and possibly the preferred technology for each corridor.”

This is right out of the traditional way that MTO used to do, and still does, highway EAs. First they would do a “needs” study, those straight-line projects that always show increasing traffic, particularly truck traffic. Then when an EA came along, and people objected saying, where was the comparison with the rail alternative (say trucks on trains), the reply always was, the needs study has already been done, and the road is needed. And Oh, by the way, in a needs study there is no obligation to look at other alternatives.

In perspective, it is clear that an EA is a very very poor tool to attempt to rectify any bad road, transit, rail infrastructure adventure that the transport bureaucracy decision-makers come up with.

Metrolinx’ Regional Transportation Plan is more than a plan — it legally constrains future environmental assessments too.

We are on the verge of a situation where a master transportation plan that will affect the GTA for decades to come may act as the de facto planning process for dozens of lines. The MoveOntario2020 plan was itself a grab-bag of every plan that was sitting on a shelf when it was announced, but at least there was a clear statement that the announcement was a first cut, and fine tuning would follow.

We may find that the “fine tuning” comes by way of the Regional Transportation Plan from Metrolinx that could occur without the sort of fine-grained local input people, at least in the 416, are accustomed to.

All the more reason to stay in touch with what is brewing at Metrolinx.