TTC 2027 Network Plan Consultation Round Two

Back in the summer, the TTC conducted the first round of consultations on its 2027 Annual Network Plan. Comments and details can be found here:

There are three major sections of the plan: route changes, express route review and construction projects. Of these, round one covered proposed route changes and the review of express buses. Feedback from the consultation was generally supportive with a few caveats and the TTC proposes no changes from round one.

Round two primarily looks at construction projects that will affect the streetcar network and the TTC’s proposals for service during the disruption. In recent years, track reconstruction projects have grown in complexity because there is a parallel Toronto Water project to replace water main infrastructure that is, in some cases, well over a century old. Typically this leads to closure of the curb lanes of a major street to rebuild the water infrastructure, followed by the centre lanes (and usually one curb lane) to rebuild the track. The exact details and sequencing are site-specific.

There are many sites where construction will interrupt TTC service and general traffic in 2027, and the potential for nearby projects to have overlapping effects. Timing of the work will be critical to ensure that central Toronto is not snarled by the ever-so-common lack of project co-ordination and schedule changes.

In some cases, the TTC proposes alternate schemes for transit service while portions of major routes are under construction.

There is an online survey available until December 8, 2026.

You can take the survey by mail. To request a copy, call 647-370-5676 or email khly@thirdpartypublic.ca.

In person pop-up sessions will be available at:

  • Thursday, November 26, 7 a.m. to 9 a.m.: Ossington Station
  • Tuesday, December 1, 7 a.m. to 9 a.m.: Queen St E & Carlaw Ave
  • Wednesday, December 2, 4 p.m. to 6 p.m.: King Station
  • Thursday, December 3, 4 p.m. to 6 p.m.: Yonge St & Adelaide St W

Construction Projects With Alternative Transit Schemes

King Street West

Several projects will close or restrict King Street West at various times through 2027.

  • Water mains:
    • Dufferin to Close
    • Shaw to Bathurst
    • Portland to Spadina
    • Charlotte to York
    • King & York
  • Track construction:
    • Dufferin to Close
    • Shaw to Bathurst
    • Portland to Spadina
    • Fleet Loop (not on King, but affects King bus service)
    • King & York intersection
Origin: TTC Survey

Phase 1

This phase includes two stretches of water main replacement from Dufferin west to Close (east of Jameson) and from Portland to Spadina. The 504 King diversions are already scheduled but have not yet been fully implemented pending start of work on the western segment.

  • 504 King streetcars operate as a single service from Broadview Station to Dundas West Station diverting to Queen via Shaw (starting November 22), and later via Spadina.
  • 504C King buses operate from the Distillery District to Sunnyside Loop.
  • 503 Kingston Road buses are extended west on King to Dufferin Loop.

In the downtown area there is also a 501B Queen bus which is part of the replacement service associated with the Queen Street East track and sewer project (see below). This bus loops via Church, Richmond, University, King, York, Adelaide to Church.

Phase 2

These phases includes track replacement at three locations: Dufferin to Close, Portland to Spadina and the intersection at King & York. There will also be track construction at Fleet Loop that will affect the 511 Bathurst and 509 Harbourfront services. Water mains will be replaced between Shaw and Bathurst, and at King & York.

Note that all of these projects will not occur concurrently, but they will potentially overlap on a schedule to be announced.

For the construction at Fleet Loop, service on the 511 Bathurst and 509 Harbourfront routes will be combined with Bathurst cars operating to Union Station. There will be no 509 service. A bus service, 504F, will operate from Exhibition Loop via Fleet, Fort York Boulevard, Bathurst and King to Yonge looping via Yonge, Wellington, Bay, Front and Yonge.

For the track construction on King west from Dufferin to Close, the 504C King bus will divert via Shaw and Queen, and there will be no transit service on King between Dufferin and Queen/Roncesvalles.

For the track construction on King between Portland and Spadina, the 504C King, 504F King and 503 Kingston Road buses will divert via Bathurst, Adelaide/Richmond and Peter.

For the intersection replacement at York & King, the 504C, 504F and 503 buses will divert via University, Wellington and Bay both ways. A contraflow lane will be created on Wellington to allow eastbound bus operation. The 504F bus will loop via Bay, Front, Yonge, King and Bay.

Phase 3

This phase includes track reconstruction from Bathurst to Shaw and water main work from Charlotte to York. The City intends to schedule the water main work to avoid conflict with the film festival on King in early September. The service diversion plan for TIFF has not yet been announced, but will be different from prior years thanks to the construction projects.

The 504 streetcar service will return to King west of Shaw, but will divert via Queen between Church and Shaw (using the Richmond/Adelaide diversion between Church and York).

The 504C bus service will run from the Distillery District west via King to Dufferin Loop with two diversions enroute:

  • Via Bay, Wellington and University (continuing the Phase 2 diversion)
  • Via Bathurst, Queen and Shaw

The 503 bus service will follow the same diversion as the 504C west of Yonge, but the route will end at Bathurst running north to Wolseley Loop at Queen Street. The route east of Yonge will be affected by the Queen & Parliament project (see below).

The work east of Shaw also affects the south end of the 63 Ossington bus route which will divert via Duoro Street east to Strachan.

Queen & Parliament

At Queen & Parliament, there will be replacement of the track at the intersection, and water main rebuilding from Parliament east to Trefann (a short distance east of Parliament).

The TTC presents three alternative diversion scenarios for discussion. They vary in the complexity of proposed routes and the number of existing stops that would lose service.

In all three options, the 65 Parliament bus diverts via Dundas, Sherbourne and Richmond/Adelaide.

  • Option 1 minimizes the loss of service by:
    • diverting the 501 Queen streetcars via King between River and Church, and
    • diverting the 503 Kingston Road bus to Queen between River and Church Streets, bypassing the construction zone via Parliament, Richmond/Adelaide and Sherbourne.
  • Option 2 minimizes the diversions, but leaves a wider area without service by:
    • diverting the 501 Queen streetcars via Dundas between Broadview and Church.
  • Option 3 is a variation on option 1, but with simpler diversions:
    • diverting 501 Queen streetcars via King as in option 1, and
    • diverting the 503 buses via River, Dundas, Sherbourne, Queen and Church.

College Street

The TTC will replace track on College from Bathurst to Ossington including the intersection at Ossington. and Toronto Water will replace water mains over the same stretch. The TTC proposes alternative diversion schemes for consultation.

Source: TTC Survey

Phase 1

In this phase, water mains will be replaced. 506 Carlton streetcars will divert via Bathurst, Dundas and Ossington. The 94B Wellesley bus, which normally runs only between Castle Frank and Wellesley Stations, will be extended west as 94C and will loop via south on Bathurst, west on College and north on Ossington.

Phase 2

During intersection replacement at Ossington, 94 Wellesley will revert to its standard route, but full service on the western branch will continue. The 506 Carlton cars will extend their diversion west on Dundas to Lansdowne.

The options TTC presents deal with the 63 Ossington bus.

  • Option 1:
    • Buses divert southbound via Bloor, Dovercourt, College, Dufferin and Dundas; northbound via Dundas, Dufferin and Bloor.
  • Option 2:
    • Buses divert both ways via Bloor, Dufferin and Dundas.

Option 2 creates a larger “transit desert” around the work site, but avoid bus operation on Dovercourt and puts both directions of travel on the same streets.

As a matter of historical interest, there once was streetcar service on Dovercourt, but only as far south as College. The Dovercourt route jogged east to Ossington and then south to Queen. The track between College and Dundas is a remnant of that route.

During track replacement from Ossington to Bathurst, 506 Carlton cars would divert via Bathurst, Dundas and Ossington. The 63 Ossington and 94 Wellesley buses would resume normal operation.

Construction Projects Not Included in the Consultation

Several projects are not included because there is only one option foreseen for the transit diversions.

  • Gunn’s Loop
    • The loop at the west end of 512 St. Clair will be rebuilt concurrently with Metrolinx work at the railway underpass east of Keele Street. The same bus/streetcar diversion plan that was used in 2026 will be repeated with streetcars turning back from Earlscourt Loop.
  • St. Clair Station
    • The streetcar offloading platform will be rebuilt in Q3-Q4 2027.
      • Weekdays: Streetcars will offload on street outside of St. Clair Station. (It is not clear why the TTC does not simply consolidate offloading and loading on the existing loading platform.)
      • Weekends: Buses will run between St. Clair West and St. Clair Stations.
  • Spadina Station
    • Extension of the platform so that it can handle two streetcars at once will occur for a three-week period in Q2 2027. Streetcars will operate between Queen Street and Union Station. Buses will run north to Spadina Station.
  • Queen Street East, Leslie to Vancouver (west end of Russell Carhouse)
    • The track and sewer work now in progress will continue into Q1 2027.
  • Queen Street East, Carlaw to Leslie
    • Metrolinx work to be co-ordinated with TTC. No specifics yet.
  • Ontario Line at Leslieville and Gerrard Stations
    • Planned work has been deferred to 2028. Overhead work between Parliament and Main Station, as well as track replacement will occur in later years (TBA).

Map of Projects

Commentary

The number of track and water main projects to occur in 2027 is quite substantial along with the potential for conflicting effects of road closures and restrictions.

The situation downtown with the combined effect of the ongoing Metrolinx work at Queen & Yonge, plus bus routes looping through a congested area, can easily lead to the type of gridlock we saw a few years ago on King Street. The City should deploy traffic wardens to manage bus and streetcar turns that could severely hamper intersection capacity. This should not be confined to a few peak hours per day.

Detailed timings for these projects have not yet been published. This should occur before work gets underway, and there should be close monitoring to avoid slippage on one project causing chaos when another begins on time. Toronto does not have good experience with keeping to schedule. To be fair, there are unknown conditions underground, but if these affect construction schedules, Toronto should be prepared to re-jig plans quickly.

Also notable by its absence from this plan is a calendar of major events that could add stress to the transit and road networks.

The City is supposed to be co-ordinating projects through a new “Traffic Czar” or Chief Congestion Officer, Andrew Posluns. It is not clear how much effect he had on the preparation of the overall 2027 construction plans, or how diligent he will be in ensuring that conflicts between projects are minimized. Given the scale of planned work, this will require ongoing monitoring and adjustment before problems emerge rather than after the fact.