TTC 2023 Annual Service Plan Preview

The TTC began consultations for its 2023 Service Plan on June 29 with a pair of online meetings for community groups, and more will follow. There will be an online survey available starting on July 11.

At this point, the Service Plan is only a collection of proposals. The TTC seeks feedback on them that will lead to a revised version in the fall and a second consultation round before they go to the TTC Board for approval. The round one proposals relate mainly to the SRT shutdown in fall 2023 and the opening of Line 6 Finch West. In the second round, these proposals will be fine-tuned and other possible changes unrelated to the rapid transit plans will be added.

2022 Service Plan Follow-Up

Some service changes proposed in the 2022 plan have been implemented, and others will follow later this year:

  • Seasonal service on the new 172 Cherry Beach route (replacing the former 121 Front-Esplanade bus) was implemented in May, but the planned route through the Distillery District was impossible due to construction on Cherry at Lake Shore.
  • 65 Parliament will be extended to George Brown College’s Waterfront Campus in September. There is no word on an extension of the 365 Parliament Blue Night bus which originally was going to be dropped. The 365 lost its weekend service in 2021, but that was recently restored.
  • The 118 Thistledown extension to Claireport & Albion and the 8 Broadview extension to Coxwell Station will occur later in the fall, date TBA.

With the completion of the Line 1 Automatic Train Control project later this year, the TTC will be able to improve service on the subway. However, just what this means depends on the base against which “improvement” is measured.

  • There is a planned service improvement in September. Current service is not running at pre-pandemic levels, and we do not yet know if September will see a full restoration.
  • ATC will provide two benefits: trains can run closer together, but also travel times can be trimmed to reduce the number of trains needed. The degree that each of these will show up in new schedules remains to be seen. A related problem is that more frequent service can compound with excess running time to worsen terminal approach queues driving up travel time for riders.

Overall system ridership was at 57 per cent of pre-pandemic levels in June 2022 and is expected to rise to 70 percent in the fall. The TTC is finalizing their fall service plan to accommodate some return to in person office travel and post secondary demand. They plan to restore services to post secondary schools that were cut because of online courses. Details TBA.

There is no announced date for the opening of Line 5 Crosstown by Metrolinx, and so the planned route restructuring to support that line will likely not occur in 2022.

Continue reading