Dundas West Station Reconstruction (Revised)

The TTC will begin work on reconstruction and expansion at Dundas West Station Loop on Monday April 11, and the project is planned to be mainly completed by June 18. The full notice is on the TTC’s website.

The timing of various stages of the work has changed from the original plan discussed in a previous article.

The original plan was to replace the trackwork on Dundas north from Bloor including the special work at the loop entrance first, followed by the track on Edna Avenue (the north side of the loop), and finally within the loop itself including expansion of platform used by 505 Dundas.

In the revised plan, the area within the loop will be done first working from west to east, followed by the track on Dundas Street, and finally the track on Edna Avenue.

The new phasing also changes plans previously announced for diversion of connecting surface routes.

During phase 1 (April 11 to May 7), the loop will be closed and all surface routes will divert:

  • 40 Junction, 168 Symington and 312 St. Clair Night buses will loop on street stopping on Edna Avenue.
  • 504C King shuttle buses will divert via Bloor to High Park Station and will serve Dundas West Station with on street stops a Bloor & Dundas.
  • 505 Dundas and 306 Carlton Night cars will divert to High Park Loop.
  • 402 Parkdale Community bus will divert as required (TBA).

During phase 2 (May 8 to June 18), some of the diversions will change:

  • 505 Dundas, 504C King and 402 Parkdale will continue as in phase 1.
  • 40 Junction and 168 Symington will divert to Lansdowne Station via Dupont and Bloor Streets respectively.
  • 312 St. Clair Night bus will divert to Keele Station.
  • 306 Carlton Night service will be replaced with buses and these will operate to Keele Station similarly to the 504C service.

Effective June 19 most routes will return to normal except for two that must await completion of new overhead wiring at Dundas West Station:

  • 505 Dundas will continue to operate to High Park Loop.
  • 306 Carlton will continue to operate as a bus service, but will terminate at Dundas West Station.

Additional work to be undertaken includes:

  • Emergency track repair on Dundas south of Bloor.
  • Construction of a “bump out” pedestrian area at the eastbound stop on Dundas just east of Roncesvalles.

There is no effect on subway service, and the station will remain open for access to trains.