$33 Billion and Counting

A political tremour ran through the transit world in Toronto recently with the TTC’s release of a 15-year projection of capital spending requirements at $33.5 billion. This does not include funding for most system expansion projects beyond the already-approved Scarborough Subway.

That number is big, but it’s no surprise to those who have been following TTC budgets for years. A major issue has been that “unfunded” or “below the line” projects don’t get the attention they deserve and are deliberately kept off of the books to reduce the apparent size of the City’s financial problems. Common tactics included omitting projects from the overall budget, or projecting their spending in a period just beyond the rolling ten-year horizon of capital planning.

Transit planning in Toronto and at Queen’s Park is reckless when it downplays the backlog of spending and associated subsidies facing public agencies. New spending and the inevitable photo ops for grinning, back-patting politicians are easier to fit into plans when you can ignore the transit system crumbling in the background.

Several budget reports will be before the TTC Board (and later at City Council) at its next meeting on January 24, 2019.

There is far too much material here to review in a single article, and so I will break this up over multiple posts. Some of the details behind individual projects will not be available until I obtain the full version of the Capital Budget known as the “Blue Books” which expand the line items from the “Blue Pages” into project descriptions and schedules.

A vital part of the new reports is a shift to a longer time frame (15 years) and the inclusion of all projects in the Capital Plan whether they have funding or not. The extent of the problem is quite evident in the following chart. The purple hatched area shows the requirements for coming years while the sold areas show known funding amounts in the medium term and hoped-for income thereafter.

The big drop in the City’s funding share in the early 2020s arises from the lack of borrowing headroom in the overall City budget. A big problem here is the crowding by major projects such as the Scarborough Subway Extension and the Gardiner Expressway rebuild within the overall borrowing plan. Current City policy dictates that the average debt servicing cost should not exceed 15% of City tax revenue over a ten year period. Planned spending in the next few years will eliminate the headroom for additional borrowing. This exactly coincides with the bulge in TTC capital requirements beginning in 2022. To put it another way, if funding continued at 2019 levels across the chart, there would still be a shortfall, but against a much higher base.

Even this chart does not tell the full story because the Capital Plan continues to push major projects beyond the ten-year line, and the financial pressures from system expansion are not fully accounted for here. As things stand today, less than 30% of the ten-year program is funded. Beyond 2028, the level of assumed funding is still well below historical levels.

($ billion) 2019-2028 2029-2033 Total 2019-2033
Funded $6.4 $3.4 $9.8
Unfunded $17.5 $6.2 $23.7
Total $23.9 $9.6 $33.5

System expansion projects will add a further $3.8 billion over the first ten years of the plan:

  • Line 2 Extension (formerly known as the SSE): $3.4 billion (subject to revision when an updated cost report is presented to Council in April 2019).
    • “While the 10-Year Capital Plan includes $3.360 billion in funding for this project (between 2019 to 2028), this project has an overall budget of $3.560 billion. This estimate, which includes $132 million to extend the life of the SRT until the Line 2 East Extension commences operation and a further $123 million to decommission and demolish the SRT, was based on 0% design. The project budget and schedule will be re-baselined in Stage Gate 3 report to City Council in April 2019, factoring in delivery strategy and schedule risk analysis.”
  • Relief Line South: $385 million will be spent in 2019-20 to support early works on this project. Some of this is already funded, but $325 million is being advanced into the current ten-year budget. Of this, the City proposes to provide half and looks to other levels of government for a contribution. The actual RL construction project is a separate entity which is not yet in the budget.
    • “The 10-Year Capital Plan includes funding of $385 million to complete current work only, which includes completing the preliminary design and engineering to between 15% and 30% complete, including developing a project budget and schedule.”
  • Waterfront Transit: The ten-year budget includes only $27 million in 2019-21 for design work on the planned extension from Exhibition Loop to the Dufferin Gate. Design work on any other Waterfront projects, let alone any construction, remains beyond the ten-year window.
  • Spadina Vaughan extension: Outstanding work on this project including close-out costs amount to $60 million in 2019, but this will be funded within the existing project.

[Quotations above are from the 15 Year Capital Investment Plan and 2019-2028 Budget, pp 12-13.]

The Relief Line work includes tasks such as property acquisition, utility relocation and design for the tunnel boring equipment. Now that the line has political support, spending sooner rather than later is on the agenda, and about two years can be shaved from the original project schedule by doing the preliminary work now. This is a major change from the position taken by Mayor Tory during the election campaign, and the need to “do something” as soon as possible is now evident.