Front Street Extension: RIP?

On November 13, Toronto’s Planning & Growth Management Committee will consider a report recommending that the Front Street Extension be deleted from the Official Plan, and that an Environmental Assessment be conducted on a local road north of the rail corridor in Liberty Village.

Official Plan Amendments take time, and the formal change would come before the January committee meeting and then go on to Council.

This change is long, long overdue.  For decades, planning for downtown streets was influenced by Front Street’s eventual purpose as a distributor for traffic from the Gardiner.  Streetcars for Toronto’s original scheme for the Harbourfront line was a bidirectional loop line via Front, Bay, Queen’s Quay and Spadina with a surface transfer station directly above the mezzanine of Union Station modelled after the Bloor Station transferway.  This option was rejected specifically because it would interfere with Front Street’s use as part of the expressway network.

(We were also told that the line could not possibly be on the surface under Bay Street because there was no place to shift the pedestrian traffic.  Tell that to all the people streaming through the teamways today enroute to GO trains and the ACC.)

With the FSE removed from the plans, we can examine transit needs in the western waterfront without it getting in the way.  The Waterfront West LRT is itself badly in need of review as a single entity, not as a hodgepodge of separate projects.

Sadly, the WWLRT seems condemned to travel through the Exhibition Grounds via a route under the Gardiner rather than along the south edge of the park where it could serve Ontario Place and any redevelopment on the CNE lands.  The alignment east of Strachan via Bremner Boulevard is fraught with problems of available road space, conflict with pedestrians and road traffic at Skydome and overcommitment of the capacity of the Union Station loop.

So much of our waterfront transit planning is done piecemeal with past studies used as excuses for continuing down the same failed path, a path of compromises and bad choices where transit always comes second.

Killing off the Front Street Extension is only a first step.

Metrolinx Chair Goes Part Time

The following press release came out today:

MacIsaac to become part time Metrolinx chair following release of final report

TORONTO, Nov. 6 /CNW/ –

NEWS

Mohawk College of Applied Arts and Technology in Hamilton has announced that Rob MacIsaac has been selected as its new president starting February 1, 2009.

MacIsaac will continue his work as Metrolinx board chair on a part time basis.

Since 2006, MacIsaac has built a team to get the regional transportation agency up and running, and to develop a Regional Transportation Plan and Investment Strategy for a seamless and convenient transportation network for the Greater Toronto and Hamilton Area. The final plan is expected to be released before the end of the year.

QUOTES

“I would like to thank Rob for the outstanding success he is achieving in establishing Metrolinx. His vision and leadership is instrumental in working with area elected officials to develop the first Regional Transportation Plan for the Greater Toronto and Hamilton Area. I am pleased that Rob will continue to lead a dedicated team that will continue to deliver,” said Transportation Minister Jim Bradley.

My own take on this is that Metrolinx needs full-time leadership from someone who is dedicated to making the process of building our transportation network truly open.

Too much of Metrolinx’ work has been shrouded in secrecy with critical studies kept from public view.  The massive spending required to overcome decades of neglect, the trade-offs and the need for political and public support demand transparency.  Everyone must trust that the spending is wise and appropriate to the task, and that decisions are made on public needs, not on deals between politicians and lobbyists. 

Decisions may be made out of sight with the best of intentions, but without public understanding and trust, they will be vulnerable.  Metrolinx needs to learn how to have full public debates about the merits of various schemes, and keep the “commercially confidential” stuff separate from the basic question of building our regional network.

The November Board meeting, when Metrolinx is expected to approve a final version of the Regional Transportation Plan, will be interesting indeed.

iPhone Schedule Data, But Not From The TTC (Update 2)

Update 2: The Register has a story about Berlin and the Dutch State Railways where the issue of copyright and use of public schedule data by outside application creators has arisen.

The TTC is not alone in fighting against externally built apps.

Original post follows:

There’s a great post and comment thread by Shawn Micallef on the spacing website about yet another non-TTC application to help users get TTC data.  This time, it’s an iPhone app.

Update:  The Torontoist site also has a post on this (sorry David for not picking up on that earlier).

After the initial burst of launching the still-not-bug-free and incomplete TTC website, work on that site seems to have ground to a halt.  At the very least, the TTC should put up a “coming soon” page with a list of committed improvements and dates.  This would allow people to spot the things that are still missing, and give us all a sense that the project isn’t stillborn.

One excuse is the need to make documents fully accessible.  This places the community who needs such services in the position that they appear to be the problem, rather than the TTC’s own inactivity and lack of preparation for this requirement.

An important issue raised by Shawn (and by others in the past) is the way that the TTC jealously guards its internal data on the grounds that it has some commercial value.

Get off your butts, guys.  This is public information and all your sitting on it does is to prevent people from making good use of the data.  Other cities make this type of scheduling info freely available, but Toronto is too busy protecting its “intellectual property”.

Yonge Subway Headway Study 1988 (Part 7)

This section includes the remainder of Chapter 4 covering three alternatives to the centre platform option at Bloor Yonge.

  • A double station with new platforms north of the existing Bloor Station
  • A bi-level station
  • Two versions of a diversionary route with a new southbound or northbound track and station

I commend these to the readers who have been proposing various alternative tunnel and platform arrangements here for a clear view of just where the structures actually lie.  Bear in mind that much has been built since these plans were drawn, and assumptions about available rights-of-way or the acquisition and demolition of buildings are probably no longer valid.

Continue reading

Yonge Subway Headway Study 1988 (Part 6)

I am inserting a little sidebar into the discussion because my archives yielded up an exhibit not included in the TTC’s report.

This is the demand analysis shown in Chapter 2 which establishes the need for additional capacity on the Yonge line, specfically at Bloor-Yonge Station.

This is the companion chart from the Network 2011 study showing the projected demand on the rapid transit network with the addition of lines on Eglinton West, Sheppard, the DRL and the Spadina/Harbourfront line.

 

 

These two charts appear side by side in the Network 2011 study, but only the first one was included in the Improved Headway Study.

The DRL diverts a good chunk of traffic off of the Yonge line below Bloor, although this is partly backfilled by new riding pouring in at the top of the line. (Other studies had different versions of this line including routes that went further north.)

The projected demand on the Spadina line, 7,500 per hour, was rather high considering it was to be a surface operation crossing many streets. Oddly enough, only the Harbourfront portion was built initially, and we waited until 1997 for the Spadina streetcar.

I don’t intend this to be a definitive example of a demand model (I don’t think “definitive” is a word one can use in that context anyhow), but it points out how the importance of the DRL was recognized over 20 years ago. Indeed, in the Network 2011 plan, it was the second priority for construction with 1st place going to a Sheppard line only as far east as Victoria Park.

Yonge Subway Headway Study 1988 (Part 5)

In this section, we begin Chapter 4 of the study with a description of the centre platform option at Bloor-Yonge Station.

Some of the work needed for this scheme was built during construction of 33 Bloor Street East and the Toronto Parking Authority lot between Hayden and Charles Streets.  The TTC took advantage of the subway structure being uncovered to widen the station and replace the centre columns with a roof spanning both platforms and tracks.  As you can see from visiting the station, this work ends at the northern third of the station because this is physically inside the structure of The Bay.

The section on construction feasibility describes what is necessary to continue this layout further north and it involves, among other things, closing the Bay’s concourse during construction.  That entire passage is almost surreal because it details problem after problem with the construction, but forges bravely onward.  There’s also the small matter of closing Bloor-Yonge Station because the existing platforms must be removed before the tracks can be relocated.

Continue reading

Yonge Subway Headway Study 1988 (Part 4)

This installment completes Chapter 3 of the study with the evaluation of alternative signalling strategies.  The recommented alternative is Automatic Train Control, no surprise there, based on the premise that it provides the maximum benefit versus the expenditure.  Underlying this, however, is the goal of a 90-second headway and the increasing challenges to subway operations as the headway drops.  ATC is treated as a means to achieve this dubious goal rather than a worthwhile move in its own right.

Continue reading

Yonge Subway Headway Study 1988 (Part 3)

This section presents considerations for the vehicle fleet and yards required to house these cars.  An important consideration for any decrease in headway is that the number of trains in service goes up.  This generates added capital and operating costs for an expenditure that addresses only peak period demand.

A proper comparison of lines would look at what happens if the fleet is expanded (regardless of the technology) elsewhere so that new off-peak service is available in a corridor that does not now have rapid transit.

As we will see later, the additional vehicles are a substantial portion of the total project cost for peak headway improvements on an existing line.

Continue reading

Yonge Subway Headway Study 1988 (Part 2)

This thread began with an introduction to the “problem” of capacity at Bloor-Yonge Station which dates back to the 1980s, an era when all expansion of capacity for travel from the suburbs to downtown was assumed to be on the subway network.  If you accept that premise, then it follows that massive expansion of subway capacity is absolutely required.  However, as we have recently seen from demand projections by Metrolinx, when there are good alternatives to the existing subway, people may find other ways to get downtown.

In this section, I will present another chunk from the long Chapter 3 in the TTC’s 1988 study.  This part includes descriptions of four ways to achieve shorter headways on the Yonge line through signalling changes.

Continue reading