Cherry Street Track Construction (Update 3)

Updated September 17, 2013 at 4:25pm:

According to earlier plans I had heard through Waterfront Toronto, Cherry Street Loop was not to be completed until after the Pan Am Games because the site is part of a parking lot for buses.  Contrary to this story, the loop is under construction, albeit surrounded by a parking lot.

IMG_4450w

The now-inactive Cherry Street tower that once controlled the eastern approach to Union Station sits at the south end of the loop.  In the left background, behind the trees, is the GO Don Yard.

The terrible irony about this, our possibly newest streetcar line, is that it won’t actually see service until Spring 2016, and the proposed extension under the railway to connect with a Queens Quay East line isn’t even in the current list of projects awaiting funding.

Continue reading

Cycling as a Transit Alternative

A conversation has broken out in the thread originally dedicated to the Scarborough Subway regarding the ability of cycling to reduce demand on the subway if a bike lane were implemented on Bloor-Danforth.

I have moved all of the comments related to this topic here to separate them from discussions of the subway extension.

Transit Technology Choices: A Quote Worth Repeating

Updated September 6, 2013 at 11:10 am:  There is an excellent article by Stephen Wickens on his blog recounting the sorry history of Queen’s Park’s imposition of the ICTS technology on the Scarborough route.

It is worth noting that the ICTS cars cost over $2-million each 30 years ago, an outrageous sum.  The price to Vancouver was much lower, well below $1m each, and the TTC order was used to funnel money from Queen’s Park to offset the development costs of the new technology.  This is what passed for a “transit strategy” in the Davis government.

Updated September 5, 2013 at 11:00 am: My comments about Transportation Minister Glen Murray’s Scarborough subway announcement yesterday are now online at the Torontoist.

The original post follows below.

Continue reading

King Street Update — Fall 2013

Over the opening weekend of the Toronto International Film Festival (TIFF), King Street is closed in the block from Duncan (aka Ed Mirvish Way) to John to provide additional pedestrian space around the major TIFF events in the area.  This will last until Monday, September 9.

IMG_4406w

Of particular note, control of access by the streetcars to the centre lanes is handled not by Toronto Police paid duty officers, but by TIFF security guards and festival volunteers.

Further east, at the Don Bridge, structural problems that have imposed a slow order on the King Street leg will finally be addressed (now that Waterfront Toronto and the City have sorted out a cost sharing agreement).  Starting September 9, all 504 King and 503 Kingston Road cars will divert both ways via Queen and Parliament.  There will be no replacement bus service on King.

IMG_4410w

The diversion is expected to last until sometime in November.

There is no word on the status of the eastern approach to the bridge which also has a slow order on it.

Where Will the Scarborough Subway Go?

The Toronto Star reports that Queen’s Park is contemplating an alternative route to Toronto’s proposed Scarborough subway extension via Eglinton and McCowan to Sheppard East.

The key paragraphs in the article are:

“In the next couple of weeks we should have an announcement on what the routing will be, what the design will be and what the cost will be,” he told reporters on the way into a cabinet meeting Wednesday.

Queen’s Park wants to have the subway run on a similar route to the light rail transit plan to “maximize the impact of this line and get it connected to as many people (as possible),” said [Transportation Minister] Murray.

Murray seeks to find out how much could be built with the $1.4b already committed to a subway project.  Using an existing corridor could reduce the cost compared to the McCowan alignment.

This raises questions debated in other threads here of how the subway would be extended via the existing SRT alignment including the configuration of Kennedy Station and whether a route from Ellesmere Station eastward would be elevated or underground.

Recycling some or all of the existing corridor will require a period of shutdown for the RT with parallel bus service, an issue that weighed heavily against the LRT scheme in recent debates.  Will the promise of a subway quell objections to this shutdown?

Murray will meet with Lisa Raitt, the federal Minister of Transport, to discuss funding, but he is already throwing cold water on hopes for assistance from Ottawa for a  “416” project.  Even if the feds bring money to the table, the next questions will be whether the original McCowan scheme or an SRT alignment for the subway are the best use of available cash, and how either subway would fit into a larger network.

The debate comes back to Toronto Council in October preceded by Murray’s announcement likely in mid-September.  Backers of the subway like TTC Chair Karen Stintz and recently-elected MPP “Subway Champion” Mitzie Hunter have stressed that their support for a Sheppard LRT was for a different line in different circumstances.  A Scarborough subway, wherever it goes, will leave large parts of eastern Toronto far from rapid transit.

The LRT debate is not over.  Will Stintz and Hunter become “LRT champions” for other parts of the network?

Analysis of Route 54 Lawrence East (Part II)

In the previous article of this series, I examined headways on the Lawrence East 54 bus route for the months of November 2011, March 2012 and May 2013.  The data revealed a route where staying close to the scheduled headway is a matter of chance, and happens far less commonly than “reliable” service demands.

If running times are fairly consistent, then the time taken from point “A” to “B” is predictable and headway maintenance should simply be a matter of short holds for the faster operators and encouragement to speed up to the slow ones.  However, the headways are uneven right from the termini of the route and from an intermediate point (Lawrence East Station) where re-spacing service to a regular headway could easily be done.

A related issue with schedule adherence is the question of running times.  Is the underlying problem that operators cannot make the assigned times in the schedules and therefore have no choice but to run at whatever chance headway occurs?  I have looked at this previously on Queen and on Dufferin where schedules are a problem for some, but not all, specific time periods.

Finally, there is always the issue of traffic congestion, the bane of surface operations and a mantra to which the TTC often resorts when people complain about service.

Continue reading

Analysis of Route 54 Lawrence East (Part I)

This is the first of a series of articles to review service on a number of routes both in the suburbs and downtown.  There are three sets of data for November 2011, March 2012 and May 2013.  The first two were selected to show the effect, if any, of service cuts implemented in February 2012.  All three months had fairly benign weather and this would not have much effect on service.  (The winter of 2011-12 was particularly balmy in Toronto.)

Our old friend the Queen car comes in for lots of abuse on this site and elsewhere that transit riders and critics (not necessarily the same group) congregate.  For a change, I thought it would be interesting to review a very long bus route, 54 Lawrence East, to see what its service looked like.

Lawrence East is actually longer than Queen (Long Branch), although it operates at a higher speed overall. The express service has a substantially higher scheduled speed, but does not run on the congested inner section of the route.

54 Lawrence East operates three services:

  • 54 Eglinton Station to Orton Park (between Markham Road and Morningside)
  • 54A Eglinton Station to Starspray
  • 54E Lawrence East Station to Starspray Express (peak only, express west of Markham Road)

Peak hour headways are shorter on Lawrence East than on Queen due in part to the size of the vehicles.  Although Lawrence East has a 3’00” combined AM peak service, this is only actually available at the few stops between Lawrence East Station and Orton Park served by all three branches.  Each of these operates on a 9’00” headway providing an average 4’30” headway over much of the route where only two of them are available.

During off-peak periods, half of the service operates to Orton Park and half to Starspray.

If we are to believe the common wisdom about transit routes, Lawrence East should have more reliable service because it operates in a relatively less constrained environment than the Queen car.  In fact, actual service on Lawrence East suffers many of the same problems of bunching and uneven headways differing substantially from the advertised schedule.

Continue reading

King & Spadina Intersection Reconstruction (Update 6)

King & Spadina is the last of the TTC’s three Grand Unions to be replaced in as many years.  Work began on August 6, and is planned to reach the point by August 20 that streetcar service can resume on 504 King, 508 Lake Shore and 510 Spadina (to King only).

This post will track the progress of the reconstruction.

Updated August 16, 2013

Paving of the track lanes is substantially complete, and work has now moved to the curb lanes and sidewalks.

Concurrently with the reopening on Tuesday, August 20, the TTC will begin operation of the 521 King Exhibition streetcar service between Church Street and Exhibition Loop, although the cars will be signed “504” because the “521” exposures were removed from the roll signs years ago.

Many of the pedestrian bypass routes through the intersection are now via the roadway.

Updated August 14, 2013

The TTC has clarified the arrangements for service through King/Spadina starting Tuesday, August 20.

504 King and 508 Lake Shore will resume their normal King Street routes rather than diverting via Shaw, Queen and Church.

510 Spadina will remain a bus operation until the next schedule period (Sunday, September 1) when streetcars will return.  The bus diversion via Richmond/Adelaide, Peter, etc., will cease on August 20 and buses will operate straight north-south through King/Spadina.  Some buses will short turn via Charlotte Loop.

Updated August 12, 2013

Assembly of the intersection was substantially complete late today with most of the new rail in place.  Work remains on the approaches as well as levelling, connection of grounding cables and other finishing touches before the track can be set in concrete.

Updated August 11, 2013

The east quadrant has been installed and work is in progress on the north quadrant of the intersection.

Updated August 10, 2013

The diamond plus the west and south quadrants of the intersection have been installed, and the foundation is in place for the remaining two quadrants.  Placement of the grounding cables for the new track has begun.

Updated August 8, 2013

A substantial portion of the new foundation slab is now in place, and the track panels for the intersection are spotted nearby ready for installation.

Photos follow the break.

Continue reading

Analysis of TTC Vehicle Monitoring Data: Looking Under the Covers

Over the years, I have published many articles containing analyses of vehicle operations on various routes.  The process by which the raw data turn into charts has been sketched in some of these posts, but now this information is available in one place.

Methodology for Analysis of TTC’s Vehicle Tracking Data

Any changes or expanded descriptions of the methodology will be maintained on that page to avoid sprinkling the information through route and date specific posts.

Comments should be left on that page.

Note that the article is intended for a reader with a detailed interest in the process.