With all the hoopla about yet another new transit plan for Toronto, it’s time to remember that the 50th birthday of the Bloor-Danforth subway is coming up in a week’s time. Depending on which event you consider the “real” birthday, it will either be Thursday, February 25 (the anniversary of the ceremonial opening) or Friday, February 26 (the first day of revenue service).

Over the next week I will post some ephemera from that era when Toronto launched on a major subway building project.

The handout below was a publicity piece for the Bloor-Danforth-University subway project. Among items of interest are:

  • The expected construction time was 9 years broken down as the University Line (3.5), Greenwood to University including Greenwood Yard (4), and the remaining pieces east from Greenwood to Woodbine, and West from St. George to Keele (2.5). Almost all of the line was built cut-and-cover , and the city expropriated a swath of houses along most of the route to the north of Bloor Street and Danforth Avenue. This strip is now home to parking lots, a few parks, subway entrances, and the occasional new building sitting right on top of the subway.
  • The original completion date to the terminals at Woodbine and Keele was planned to be 1969, but work was accelerated thanks to additional funding from the Metropolitan Toronto government and Queen’s Park.
  • The paintings showing what the new stations would look like date from 1956 and 1957, before the project had been approved by Metro Council.
  • The map of the route includes the original names for most of the stations including Vincent, Walmer and Yorkville. By the time this was printed, “Willowvale” Station had already changed to “Christie”, but the park to the west retained its original name.

The station illustrations are by Sigmund Serafin whose work also shows up in samples of the original Yonge line station designs. Of the four stations shown here, none was built exactly as shown. You can see the full set on Transit Toronto. The eight water colours were rescued from a housecleaning binge at the TTC in the late 1960s when much material went into various private collections lest it simply disappear. These paintings are now back with the TTC who plan to issue them as posters later this year, and the originals will go to the City Archives.

Here is Bloor-Yonge Station in all its mid-50s glory, with Gloucester trains, no Hudson’s Bay building and a lot of Bloor-Yonge streetscape that has vanished over the years.

Yonge_Station_Serafin_1957w

For a detailed history of the Bloor subway, visit Transit Toronto.

Reviewing the New Schedules on 501 Queen for January 2016 (Part I)

Effective January 3, 2016, the TTC introduced a major revision in service on the 501 Queen route. The changes included:

  • Substantially more running time was allocated for almost all periods so that cars would not fall late thanks to congestion and heavy demand, and most of the service could reach the terminals.
  • The route was split at Humber Loop (see note below) so that the Humber-Neville service operated independently of the Humber-Long Branch service, the arrangement that had been in place until March 1995. This is supposed to be “temporary” pending the availability of enough cars to operate the full line with the longer ALRVs or new Flexitys. Service to Long Branch operates with CLRVs (the shorter streetcars) except for some runs that are through-routed from the main part of the route.
  • The section of the route west of Humber Loop was added to the “10 minute network” so that it is guaranteed frequent service at all hours (except overnight).

(Note: Due to the condition of the “Long Branch” side of Humber Loop, the service captive to the west end of the line was discontinued for the last week of January, and “Long Branch” cars ran through to Roncesvalles Carhouse as their eastern terminus.)

The “before” and “after” service designs are summarized in the following table.

501_ServiceHistory_201601

In this article, I will review the operation of the 501 Queen route in December 2015 and January 2016 with a focus on headways (the time between cars), reliability (variation in the headways) and the quality of service on outer ends of the line (the compound effect of reliability and short turns). In the second part of this article I will turn to the effect of additional running time in the schedules.

General Observations

Service in January 2016 is much more reliable, especially on the outer ends of the route as the need to short turn cars simply to stay on schedule is much reduced. On the west end of the line, service on Lake Shore is considerably improved both because this is now part of the “10 minute network” and because cars are now dedicated to serving the segment west of Humber.

Short turns still do occur, although for the most part this is now due more to local incidents such as collisions than congestion. In other words, short turns occasionally spike at a specific time and day rather than being chronic throughout all days and hours of service.

Weekend service was particularly bad in December partly because there is less (or no) unscheduled extra service to fill gaps, and partly because line management seems to apply to weekends with the focus being on “on time” performance rather than actual service levels. This problem is reduced but not eliminated in January.

Wide gaps in service and the complementary effect, bunching, were much more prevalent in December than in January, but unreliable headways are still a problem, albeit at a lower level. Combined with the higher likelihood that cars will run through to their advertised destinations, the length of time a rider must await a through car, and the anguish about whether one will ever appear, is improved.

Cars depart inbound from terminals more reliably, generally within the TTC’s goal of a six minute “on time” window. However, this goal still allows for uneven spacing relative to a six minute scheduled headway, and by the time cars reach Yonge Street, the unevenness of terminal departures is magnified. On Lake Shore, headways are uneven at times even with the dedicated local service simply because cars do not leave terminals on a regular spacing. A six minute “on time” window allows most of these to hit the target, but they still contribute to uneven service

The added running time allows more service to reach its scheduled destination, but during some periods it also contributes to noticeably slower operation. If the schedules are padded, then it should be possible to space service midway along the route. From a traffic viewpoint, the question then becomes whether it is better to have streetcars sit killing time at key locations rather than dawdling along the route to burn up excess time in the schedule.

Continue reading

What Would Fare By Distance Mean For Toronto? (Updated)

The Metrolinx Regional Fare Integration Study studiously avoids one of the most important questions any new fare scheme must face: what is the effect for various types of riders?

As a starting point in examining what might happen, this article looks at some of the basics of travel patterns and fares to see what various Metrolinx schemes might imply. Note that this is not a definitive, accurate-to-the-nth-degree exercise, but a general discussion. The detailed work should already have been done by Metrolinx, but if it has, they are not publishing the results.

My apologies to readers in advance as this is an article more technical than political. Some of the calculations are unapologetically “back of the envelope”, and are intended as estimates, illustrations, not definitive results.

Updated Feb. 14, 2016 at 2:00pm: Comparative information about GO Transit fares has been added at the end of the article.

Updated Feb. 14, 2016 at 4:45pm: A further observation on the relatively low fare by distance paid by GO riders has been added at the end.

Continue reading

Metrolinx Fare Integration Background Study: February 2016 Update

Recently, I reported on a staff presentation to the February 10, 2016, Metrolinx Board meeting in which it was quite clear that the provincial agency is moving inexorably toward some form of fare-by-distance not just for its GO Trains, but for all rail modes that operate on their own right-of-way including subways and LRT. Bus Rapid Transit, although a common part of The Big Move as a “solution” in the 905, is not included as “rapid transit” in their proposals.

Metrolinx has now published the background technical paper to this presentation. This is the second installment in the fare integration review. Part 1 came out in September 2015.

For background information, see:

In previous articles, I noted a strong inclination by Metrolinx toward distance or zone-based fares, and this continues into the most recent paper. What is also troubling, however, is the difference between the backgrounders which have some detail about the workings and effects of a new fare structure, and the staff summary reports where this is all treated as a complex issue to be reported on at some future date. “Have patience”, the Board is told by staff, even though answers to some of their questions can be found in the detailed reports.

A chart from the September 2015 report is worth looking at again.

201509_GTHA_Fare_BCE_QA

It is self-evident that any tests of fare effects, of the various sub-markets which might see higher or lower fares, and of revenue distribution models, could not possibly be conducted without an actual model with real numbers of riders and real fares attached to each type of trip they would make. However, even by February 2016, the staff presentation studiously avoids specifics and gives no hint of the degree by which fares might rise or fall. A related issue is that the tests used a “revenue neutral scenario”, one in which any reduction in one part if the revenue pie must be counterbalanced by an increase somewhere else.

This is the “we don’t want to pay more subsidy” view of fare integration where the “winners” are those who now face multiple fares, typically to use the TTC plus any other GTHA system, while those who now pay single fares within a system will be the “losers”. This fact has been hidden from public view throughout the exercise. We hear a lot about “fair” fares, but absent specifics, there is no way to decide which elements of “fairness” are included in the new formula.

An element that emerged from the 2015 study and now forms an important part of the 2016 update is the concept of “service class”. This is a simplistic division of all transit services into three groups and three trip lengths. The groups such as “local” and “rapid” transit are defined by mode (bus or rail), not by the actual quality of service they provide. Indeed one might argue that the higher speed of “rapid” transit can be offset by the severe overcrowding and unreliability of the service. For the purpose of the fare model, only the nominal speed and presumed comfort of rail services counts. This is very much a GO-centric view of transit service.

Even GO is having its problems with comfort and crowding. For some time, the goals for service quality included the idea that 80% of peak period riders would get a seat. GO never attained this and the metric sat at 66% the last time it was reported, September 2015. This goal appears to have quietly fallen off the service targets GO seeks to hit for the obvious reason that it is not attainable without massive expansion of service beyond the point where latent demand always backfills any new capacity GO provides.

The overall fare integration study is expected to stretch into late 2016 according to the chart below. It is hard to ignore the absence of “rider effects” in the topics listed here.

201601_FareStudyStaging

However, a more detailed chart (Fig. 1.4) clearly shows that a “Preferred Option” would be recommended by Spring/Summer with the implication that any chance to debate and influence the choice has a limited window of the next few months. The Metrolinx Board is not scheduled to meet again until June 2016. Will they be faced with a fait accompli where staff have made all the decisions and the Board’s role is merely to nod in agreement? When will local Councils and transit agency boards have their chance to be heard? In the rush to get a new fare structure, will Metrolinx management do an end run around meaningful consultation at both the general public and political levels?

Continue reading

TTC Replies to Fare Zone and Subway Premium Proposals

An obvious question about the Metrolinx Fare Integration Strategy update is whether the TTC has quietly adopted a new fare policy to suit Metrolinx.

I asked:

The Metrolinx Regional Fare Integration report on their board’s agenda for Wednesday clearly leads the way for fare zones at least on the subway within the TTC system.

There have been rumblings of this from management comments at TTC, but nothing definitive. However, the installation of fare gates with tap out capability is a clear preparation for such a change. While this might be part of the TYSSE roll out, the wider application of zoned fares (or some equivalent) within the TTC has never been a matter for public debate or decision as far as I know.

Has this matter been presented to the Commission for discussion, or are there plans to do so in the near future?

What is the TTC’s position on the Metrolinx fare integration proposals?

The TTC’s Deputy CEO, Chris Upfold, replied:

The TTC[s] sit on the various Steering Working groups for regional fare integration and I feel our voice is well heard there.

As per our report to the Board on Fare Policy TTC staff are not undertaking any more work on fare by distance or by zone within the boundaries of Toronto on service operated by the TTC. We do not feel it is an appropriate or useful policy direction in those circumstances but are working with Metrolinx on how it could work from a regional basis.

Our board has passed a number of motions, over just the few years I’ve been here, that any regional integration must not come at the expense of the TTC or our customers.

Faregates are being rolled out at subway stations for a number of reasons but primarily:

  1. The integration with a legacy turnstile with a new reader wasn’t the best technical solution and caused lots of other potential problems.
  2. The legacy turnstile (especially high gates) are nearing the end of their life and we were likely to need a wholesale replacement in the next 10 years or so.
  3. Overall the whole life cost (over 20 years) was much lower for installing new faregates.
  4. New faregates are higher capacity (and far more flexible) and do things like real time fault reporting etc.

Tap in and out functionality is necessary for the TYSSE in order to manage regional integration on how fare policy sits today. Faregates (with readers on both sides) would help to enable any zonal/distance based system.

Now it is up to Metrolinx to explain how their proposal meshes with the TTC’s stated position.

How Will SmartTrack and GO/RER Co-exist?

Metrolinx has published an update on studies of how the proposed SmartTrack service will be integrated with its own GO/RER (Regional Express Rail) offering. This will be considered at their board meeting on February 10.

This covers several issues, and begins to nail down just what SmartTrack might, or might not, resemble that is beyond the scale of postcard election literature. As we already know, major changes are planned to the western leg where the Crosstown West LRT will take over the function proposed for SmartTrack beyond Mt. Dennis. To the east, SmartTrack remains in the GO Stouffville corridor, but the Scarborough Subway Extension (SSE) has been scaled back to a one-stop line serving only the Town Centre, and the Crosstown East LRT will provide service to eastern Scarborough.

What is GO RER?

WhatIsRER

This graphic is amusing for its complete contrast with the way that Metrolinx/GO presented electrification of their services during early days of public consultation. That hit a low point when it was suggested that electric trains might not work in snow.

Note that the official line now is that lots of cities use this type of service, and that electrification is an integral part of the package.

Metrolinx owes us all an apology for their initial foot-dragging and misinformation campaign. Now if only they had been more supportive of LRT during the dark days of Rob Ford.

Continue reading

Metrolinx Fare Integration: Get Ready to Pay More For Subway Trips

One of the great mysteries surrounding the roll out of Presto on the TTC has been the whole debate about “Regional Fare Integration”. Now and then, discussion papers surface at Metrolinx, but folks at the TTC, especially the politicians, are strangely silent on the subject. “Wait and see” is the order of the day.

Well, folks, we have waited and now we are beginning to see the direction Metrolinx is heading in for a consolidated GTHA-wide fare structure. The results will not please folks in suburban Toronto or the inner 905 for whom long subway trips are a routine part of their commutes.

The Metrolinx Board will consider an update on this subject at its meeting on February 10.

The presentation is in a sadly familiar Metrolinx format: lots of wonderful talk about consultation and fairness, and philosophical musings about what a fare system should look like. One big omission is any evaluation of the relative numbers of riders who would be affected by various schemes, and even worse of any sense of calibration of the fares to produce different results.

This comes at a time when we know from SmartTrack demand studies the importance of fare levels in attracting ridership. It is important here to remember that we are not talking the relatively small differences between types of TTC fares, or year-by-year increments, but the much larger deltas between TTC fares and those on GO Transit.

The problem begins with the arbitrary segmentation of the travel market into “local”, “rapid transit” and “regional transit”.

201602_DefiningServiceTypes

This is a wonderful theoretical view of the world that might find a home in a sophomoric academic paper, but it ignores the very real world in which (a) “rapid transit” today only exists within Toronto and (b) Toronto decided over 40 years ago that “local” trips paid one fare regardless of the mode they used. The entire system is designed on this principle, one that has consistently evaded Metrolinx planners.

If only the world were so simple. Why is Bus Rapid Transit omitted from this list? Why is a streetcar (aka LRT) on right of way “rapid transit”, but not a bus? How close must subway or LRT stops be to each other for the service to drop back to a lower tier? Conversely, if someone slaps a “19x” route number on a bus, should it become “rapid transit”?

The basic problem with this world view is that transit modes, especially bus and streetcar/LRT, have a wide range of overlapping implementations.

Continue reading

TTC’s 2016 Customer Charter Reviewed

The TTC has released the 2016 version of its Customer Charter listing a number of areas in which they promise improvements through the year.

First Quarter:

  • Ensure that 510 Spadina is served by fully accessible streetcars: Mostly done already with a few of the high-floor ALRVs still in service but the majority of runs operated with low-floor Flexitys.
  • Apple Pay at collectors’ booths: In progress.
  • Reduce streetcar short-turns by a further 20% over Q1 2015: New schedules on 501 Queen effective January 3 make a big contribution to this coupled with the milder winter weather.
  • Start subway service at 8:00am on Sunday: Done effective January 3.
  • Add service to Line 1 (YUS) during off-peak: Not done yet, but the schedules going into effect at the end of March have not yet been announced. (Note 1)
  • Establish a Local Working Group for Donlands Station second exit project: Done.
  • Add five new express bus services: Planned for late March.

Second Quarter:

  • Wifi at 22 new stations (Note 2).
  • Roll-out of new fare gates with Main Station as a pilot: Work at Main in progress.
  • Improve bike parking at 5 stations.
  • Add 20 bike repair stops at subway stations: Subject to outcome of a pilot.
  • Install notice boards in 12 busy stations to inform passengers about planned/unplanned closures.

Third Quarter:

  • Ensure 509 Harbourfront and 511 Bathurst are served by low-floor streetcars: With delivery of new cars, Harbourfront is already planned to ramp up beyond two assigned Flexitys in mid-February. Delivery rates for new cars are supposed to be up to 1/week by the end of March and this should make conversion of 511 Bathurst an easy task provided Bombardier manages to stay on track.
  • Pilot high capacity bike parking at one station.
  • Replace T1 trains on Line 4 (Sheppard) with 4-car TR sets: The order for these cars is in progress at Bombardier with delivery expected later this year.
  • Improve 28 Bayview South and 101 Downsview Park routes to be part of all-day, every day service. This will bring services to two park-based areas. The Bayview South bus serves the Brick Works from the west (Davisville Station), but service from the east (Broadview Station) will still be operated by a free shuttle bus.
  • Add 3 trains to Line 1 (YUS) to improve AM peak service. It is unclear whether these will be “gap” trains used to supplement service when things go wrong, or an attempt to slightly shorten the average headway over the entire line. Gap trains generally make a bigger difference for situations where holes in service at peak times and direction need to be filled because the extra train is used specifically where it is most needed.
  • Add peak service to 25 busy bus routes.
  • New streetcar service on Cherry Street: (Note 1) This service could most easily be implemented by converting the 504 buses now scheduled from Dufferin to Parliament back to streetcars as a Dufferin to Cherry operation. Peak vehicle requirements would probably go down, but the off peak service on Cherry would be a net addition. This change is related to whatever modifications the TTC will make to the 72 Pape and 172 Cherry bus routes.
  • Begin revamping the east parking lot at Finch Station.

Fourth Quarter:

  • Widen 25 bus stop pads to improve accessibility: Locations TBA
  • Install external route announcement system on all vehicles: Work in progress.
  • Add two new elevators at Ossington Station: Work in progress.
  • Install customer info screens at Union Station mezzanine and platform levels: An overdue follow-up. This work should have been an integral part of the station renovation.
  • Install customer info screens at Dufferin, York Mills and Lawrence stations.
  • Install transit signal priority at 15 intersections: Locations TBA
  • Complete PRESTO roll out to the entire system: Bus fleet conversion in progress; new fare gates will finish PRESTO subway access as they are installed.
  • 10 additional WiFi stations: Locations TBA (Note 2)
  • Lengthen 10 bus pads for compatibility with articulated buses: Locations TBA
  • Start construction on a bus queue jump lane: Location TBA
  • Introduce a new Wheel-Trans qualification process: Details TBA
  • Install new, “more informative” stop markers at over 3,000 surface stops.
  • Review schedules on 32 bus and streetcar routes to improve reliability and travel times.
  • Reduce subway delays by 10% (counted as both incidents and minutes of delay). See What Causes Subway Delays?
  • Consult with riders and other stakeholders to revise service in three neighbourhoods around routes 40 Junction, 54 Lawrence East and 116 Morningside.

Note 1: Some items in the Charter are not yet funded in the City’s budget. Whether they will actually operate depends on the TTC’s ability and desire to squeeze money out of other parts of their operation.

Note 2: The WiFi rollout in the subway is limited to internet access only because the major telcos – Bell, Rogers, Telus – will not provide service over the incumbent provider’s network. Even the internet access has its problems due to login requirements recently introduced that require signon to a sponsoring site such as Twitter. This state of affairs can be traced to a bad system and contract design by the TTC who appear not to have contemplated the difficulties of the “big” players refusing to come onto, and thereby financially support, the network.

I cannot help feeling that a lot of this “Charter” is a shopping list of the low hanging fruit, things the TTC planned to do anyhow, but repackaged in a “look at us” format where green tick marks will gradually fill up the boxes. What is missing, and this is as much a political discussion as a managerial one, is a “what could we be” dimension and aspirational goals that might not be achieved, certainly not in a one-year timeframe.

Of course, when there are members of Council and the TTC Board who would rather count paperclips than address fundamental issues of just what  “good transit” really is, this situation is almost inevitable. Good news, but as cheaply as possible, and so we aim low.