New Streetcars Come To Harbourfront

With the shutdown of the Spadina line for track work, the Flexitys have shifted to the 509 Harbourfront route. Here are a few images of these cars in a new context.

Green trees would make these so much better!

TTC Board Meeting March 26, 2015 (Update 2)

The TTC Board met on March 26, and considered a meaty agenda that begins to address some important policy issues.

Updated March 29, 2015 at 3:45 pm: The presentation on One Person Train Operation (OPTO) given at the meeting has been added along with comments.

Updated March 24, 2015 at 8:10 am: After this was published, the TTC posted the CEO’s Report.

In a previous article, I wrote about the Spadina subway extension project update. This will undoubtedly be the main attraction both for board members and the media. Other items of interest include:

  • An overhaul of system key performance indicators (KPIs)
  • A door monitoring system for Toronto Rocket trains and one person train crews (Updated March 29)
  • Revision and consolidation of the resignalling contract for the Yonge-University line
  • A study of express bus routes
  • CEO’s Report

Continue reading

TTC 2015-2024 Capital Budget: Streetcar Infrastructure

Updated March 15, 2015 at 8:40 pm: An example of a vintage tram adapted for pantograph operation in Munich has been added to the end of this article. Thanks to John F. Bromley for the photo.

The TTC’s Capital Budget includes ongoing programs to replace worn streetcar rail as well as to upgrade the overhead power distribution system for compatibility with the new Flexity LRVs.

Replacement of streetcar track with infrastructure built to new, robust standards is almost complete on the main lines used by all routes. What remains are sections used for diversions and short turns.

Tangent track on Spadina south from College that was installed for the resumption of streetcar service in 1997 is scheduled for replacement in 2018. The table and the map differ on whether this work will end at Queen or at King. In any event, this will be the first major track replacement over a section constructed to new standards, and only the surface layer (track down to the tie attachments) should have to be removed.

Replacement of overhead contact wire with thicker 4/0 gauge is also well underway, as is the replacement of feeder cables, some of which are very old and are shedding their insulating covering. Intersection and yard upgrades will, together with the new tangent wire, make the system 100% pantograph compatible. When the last of the cars using trolley poles has been retired, the overhead can be further adjusted to remove pole-specific hardware and simplify future maintenance.

This article contains lists and maps of the work planned for 2015-2019.

Continue reading

City of Toronto Budget Amendments 2015 (Updated)

At its meeting of March 11 and 12, 2015, City Council passed a few budget amendments affecting the Toronto Transit Commission. Some of these reflect a sense that the TTC has not been “minding the store” quite as well as it claims, and a little belt tightening is good for any organization. Others address specific concerns that, quite frankly, should have been on the TTC’s agenda before now, but were buried under the rapid transit debates.

The motions address the following topics:

  • Additional Streetcars
  • Automatic Train Control
  • Waterfront West Transit
  • TTC Staffing and Project Management

Updated March 13, 2015 at 1:50 pm with further information about proposed staffing reductions.

Continue reading

4405 Arrives On Spadina

Car 4405 made its revenue service debut today, March 2, 2015, on route 510 Spadina joining 4400, 4403 and 4404 already on that line. (4401 and 4402 are prototypes that have yet to be retrofitted for public service.)

I together with all the riders who yearn for improved capacity on the streetcar system look forward to the day that each new car’s delivery is not cause for its own article.

Car 4405 loads northbound at Baldwin Street.

IMG_5478c

Northbound at College Street. The slow order signs for the intersection are due to its delicate condition. The special work will be replaced in April 2015.

IMG_5481c

Cars 4403 (northbound) and 4404 (southbound) at Willcocks Street.

IMG_5484c

TTC 2015-2024 Capital Budget: System Expansion Projects

The TTC’s Capital Budget generates much debate over a few items, but there are many, many projects at the detailed level. Understanding those details puts the debate over transit spending, operations and expansion in a better context. This and following articles will look under the covers of the Capital Budget. I will start with the expansion projects because these have seen so much debate, but will turn to the more mundane parts of the budget that keep the wheels turning.

The projects discussed here include:

  • The Toronto York Spadina Subway Extension (TYSSE) to Vaughan Metropolitan Centre
  • The Scarborough Subway Extension (SSE)
  • Various Waterfront proposals

Neither the Downtown Relief Line (DRL) nor the Yonge extension north to Richmond Hill is included because these are not yet official projects.

Continue reading

TTC 2015 Fleet Plans (Updated)

Updated March 2, 2015 at 9:20 am: This article has been extended with additional illustrations and information from the detailed TTC Capital Budget. The original version was published on January 28, 2015.

Within the TTC’s 2015 Capital Budget, the Fleet Plans give an indication of current thinking on the evolution of TTC service. Now that Toronto appears to have a pro-transit administration at City Hall, the plans are somewhat out of sync with a revived interest beyond “subways, subways, subways”. The details in the plans need review, and this will affect planning in future budgets.

Some policy decisions are evident within the fleet plans, although these have not yet surfaced in public discussions.

Continue reading

TTC Confirms Streetcar Service Levels With New Fleet

Toronto’s Budget Committee has asked staff for many briefing notes on details behind various programs. Among these requests was for TTC to detail the level of service that would be operated on all streetcar routes after the 204 new Flexitys have been delivered, and how this would be improved with the addition of a proposed 60 car order.

The TTC has responded with a report that details how the cars would be used.

Long–Term Peak Headway Projections for Streetcar Routes

With the initial 204 car order:

  • Peak headways would widen by varying degrees on all routes except 501 Queen where existing AM peak frequency would be maintained using the larger cars. The biggest change would be on the 502/503 services changing from 12′ to 14’30” on each of the routes which, in theory, provide a blended service.
  • Capacity increases in the AM peak would be greater than in the PM peak.

With the additional 60 cars:

  • Peak headways would return roughly to current levels. Capacity, relative to today’s service, would be considerably higher than today, except anomalously, on 501 Queen.

The report notes that additional cars will be needed for routes to serve the waterfront, but gives no indication of the service levels or fleet requirements for these routes. Because the report shows only headways for existing routes, not vehicle allocations, it is unclear how many of the 60 cars go for service improvement and how many for new routes. The percentage improvements on existing routes are high enough that it is possible that cars have been double-counted for this purpose. I will follow up on that issue with the TTC.

Updated at 12:22 pm: At Budget Committee, Andy Byford confirmed that the only “expansion” covered by the 60 cars is the Cherry Street spur south from King Street.

Updated at 3:00 pm: The TTC has confirmed that all of the 60 additional cars would be allocated to “legacy” routes with none reserved for expansion. As to the spare ratio they would design for:

“Spare ratio of 18%. We expect that that we will be able to reduce that when the fleet is settled in and we have confidence in the performance and reliability but, until then, this is our going-in assumption.” [Email from Mitch Stambler, TTC]

The ratio for the streetcar fleet today is about 25% (not including cars out of service due to cold weather) with roughly 200 of the 247 in the fleet scheduled for the AM peak.

Will We Ever See Our New Streetcars?

In the Financial Post, Peter Kuitenbrouwer reports on problems at Bombardier’s Thunder Bay plant.

It’s a sad tale of cock-ups with parts that don’t fit and claims that designing for Toronto’s streetcar environment is too challenging. Fortunately for Bombardier, they have not yet had to start producing the Metrolinx cars that should be an off-the-shelf design as a point of comparison.

Sorry, Bombardier, you bid on this contract, and you pass yourselves off as a world-class supplier. Stop complaining and start delivering.

Building the Connection to Leslie Barns (Updated December 8, 2014)

Progress continues, albeit slowly, on the Leslie Street connection. Much of the utility work is now completed, and a finished road, including streetcar track, is starting to appear in some blocks.

December 8, 2014

Continue reading