Queen’s Quay West Construction Schedule Announced

Waterfront Toronto has announced the schedule for reconstruction of Queen’s Quay between Spadina and Bay based on the long-awaited design by West 8 + DTAH.

Stage I: Summer 2012 to Summer 2013

The first stage concentrates on utilities and on the streetcar right-of-way.  Works include:

  • Bell will install new duct banks and cabling during June and July 2012.
  • Toronto Hydro will install new splicing chambers and cabling to replace existing worn-out infrastructure.  This work begins in July 2012 and will run for a year.
  • A new sanitary sewer will be built in three stages (Rees to York, Bay to York, Lower Spadina to HTO West), and new storm sewers will be built in two areas (York to Bay, 350 Queen’s Quay to Rees).  This will replace existing aging sewers.
  • The TTC right-of-way will be completely rebuilt from the portal west of Bay to just east of Spadina.  The new alignment is slightly different from the existing one, and will include wider platforms (2.4m).  Streetcar service will end on July 29, 2012, but demolition of the right-of-way will not start until the fall with the new corridor to be completed by late spring 2013 when the line will be electrified and streetcar service will resume.  The TTC will also be replacing the track in the Bay Street tunnel (new rails are already in place in the tunnel).
  • During construction a replacement bus service will operate for route 509.  The service will run westbound on Queen’s Quay and eastbound on Lake Shore Blvd.  The connection to Union Station will be via north on York, east on Front, south on Yonge.  While Front is impassible due to construction, the route will be via York, Adelaide, Bay and Front to Yonge.
  • Also in 2012 (as previously reported), there will be interim improvements to the pedestrian and cycling infrastructure from Bay to Jarvis to better link the eastern waterfront to the central portion.

Stage II:   Summer 2013 to Early 2014

The second stage concentrates on the north side of Queen’s Quay to reconfigure the roadway, rebuild the sidewalks and install tree pits ready for planting (which will be timed to benefit the trees even if the civil works are ready earlier).

The TTC will rebuild the intersection and loop at Spadina & Queen’s Quay over three weekends (one each for the intersection, the loop exit on Spadina and the loop entry on Queen’s Quay).  Streetcar service will be suspended for these weekends.

During this work, all road traffic will use the south side (existing eastbound) lanes on Queen’s Quay.  When the new north side is ready, traffic will be switched to the new lanes.  A new traffic crossover with signals will be installed west of Spadina so that eastbound cars can get from the existing lanes south of the streetcar right-of-way to the new north-side alignment.  Eventually, when it is time to rebuild the section from Spadina to Bathurst, this crossover will be eliminated because all motor traffic will be north of the streetcar lanes.

Stage III:  Early 2014 to Late 2014

The south side lanes and the sidewalk will be demolished.  They will be replaced with a new expanded promenade and with the Martin Goodman Trail (bike path).  Planting of the new double row of trees planned for this part of the street may be deferred to spring 2015 to ensure that the trees will survive.

General

The cost of this project is about $110-million of which $90m comes from Waterfront Toronto, $10m from the TTC and the balance from various utilities.  Waterfront Toronto will lead the construction work so that all sub-projects are co-ordinated and the disruption to any one part of Queen’s Quay is kept at a minimum.  There has already been extensive consultation with business and residents, and this will continue through the project to head off problems as they arise.

Sidewalks on both sides of Queen’s Quay will be laid with granite cobbles in a two-tone mosaic with a maple-leaf outlined in the pattern.  The total number of cobbles will be about 2.3-million with about 40% on the north side and 60% on the wider south side promenade.  Granite curbs will be used at the sidewalk edges.

Two public meetings will go into this project in more detail.

Wednesday, June 6 at Harbourfront Centre, Brigantine Room, 7-9 pm.  This meeting will include presentations on many projects underway in different parts of the waterfront.

Saturday, June 9 at Waterpark Place Lobby, 20 Bay Street, 10am-2pm.  This meeting will show detailed construction plans for the various phases and is intended for residents and businesses who want to see the final design and ask detailed questions.

Some information and images are available on Waterfront Toronto’s website.  The Fact Sheet contains details additional to the summary above.

Streetcars in the Eastern Waterfront (Well, Track Anyhow) (Update 3)

Updated May 25, 2012:

Port Lands

Waterfront Toronto’s public meeting on May 24 drew an audience of about 300.  The presentation droned on for well over its allotted time, and consisted mainly of reading through a Powerpoint deck without benefit of a working laser pointer to highlight items of interest on the screen.  Oh well.  No marks for Management Presentation 101.

The content was more important than the style, and what came through loud and clear was that planning by bean counters has replaced planning with a vision for a great waterfront.

Council may have stopped the Fords in their tracks last fall, but Waterfront Toronto is clearly working to a penny-pinching agenda.  This shows up in two major ways.

First, although the most recent plan (see page 12 of the presentation, right side is the newest) attempts to create more greenspace on the water’s edge, it has lost the magic of the revitalized mouth of the Don.  The drawing still shows a river meander, but you have to read the text to learn that the outermost part of this, west of Cherry Street, would not actually be built until and only if the Lafarge Concrete plant decides to close up shop.  Until then, the mouth of the Don will be the Lafarge slip.  In the original plan, the river mouth was north of the slip and could be built independently of the plant.

Second, transit seems to have fallen off of the map.  Something will be built, maybe, eventually, although for the near term we must make do with buses, possibly on a right-of-way.  Waterfront Toronto is obsessed with the problems of connecting to Union Station (and associated costs as discussed elsewhere on this site), but seems to forget that an alternate option from the east end of the harbour, certainly from the Port Lands, is to go north via Cherry to King.  Some of the staging of upcoming projects could support this, but bits are missing, and there is little sense that anyone really is looking beyond a bus route here and there.

Neither of these situations went down particularly well with the attendees.  Examples of “transformational initiatives” (for which you absolutely positively must not ever dream they might mean “casino”) from other cities are included (Page 18), but as one speaker remarked, it is the river that is the “transformation”, the jewel of the project.  Indeed, Waterfront Toronto can hardly stop themselves from talking about the international recognition the design received, a design which depends on the river mouth, now relegated to a “phase 5, maybe” status.

Many spoke about the need for good transit to the site.  The staging (Page 25) could support a through LRT service, but only partly in the early years.  Stage 1 includes realignment of Cherry and Queen’s Quay, but it does not include a new Cherry Street bridge over the Don (essential for an LRT line running south to the Keating Channel), nor does it include widening of the Cherry underpass at the rail corridor (essential for connecting north to the Cherry Street streetcar tracks to be installed later this year).

Adrian Morrow in the Globe wrote about the Tiny Perfect Streetcar Line in today’s Globe including the general problem that transit to real development in the waterfront is not on most politicians’ agendas while transit to phantom developments in the suburbs gets no end of attention.  One big problem is that Metrolinx wants nothing to do with waterfront transit and regards this as a local initiative to be paid for on the City’s dime.  I cannot help wondering just how Queen’s Park justifies its investment in many proposals for the 905 that will serve far less development than the waterfront LRT network, but leaves Toronto high and dry.

I may seem unduly harsh on Waterfront Toronto given the pressures they are under from the Monorail Mania at City Hall, but there is too much of a sense of making do, of a loss of emphasis on what will make the eastern waterfront a great place, not just an OK suburb of downtown.  Particularly notable in the presentation was the absence of any explanation of how these lands would relate to nearby existing and future developments, a sense of place in the larger city.  A big problem was that the presenter, a senior Waterfront Toronto exec, didn’t seem really thrilled about what he was showing us, but instead focussed on how the plan saved money, how it addressed the Ford’s desire for more and faster development.  He was playing to the wrong crowd.

The new overall plan for the Port Lands is broken into three stages based on gradual expansion of flood protection that would allow a wider set of land uses in various areas.

Phase 1 (Page 20) creates a spillway parallel to the Don Roadway so that a flood from the river would not inundate lands west of Cherry Street.  This frees up the first set of lands for redevelopment.

Phase 2 (Page 21) raises the Don Roadway itself to create a berm that protects the Film Studio district.

Phase 3 (Page 22) builds the new river mouth and associated parkland/spillway so that land between Cherry and the Don Roadway can be developed.

The presentation notes that the amount of land available for development is larger in the revised plan, but a number of speakers pointed out that by Waterfront Toronto’s own admission, the real estate industry cannot absorb all of the available lands for decades.  Whether there is any value from the “new” land is unclear, although if this falls within, say, Phase 1, it would accelerate revenue from the overall project.

The whole issue was to go to Council imminently, but this has been put off until the fall so that details of how the financing might work can be figured out, and the plan can undergo an external review.  The next public session will likely be in August with the, in effect, final version of the proposal that will go to Council.  If Council approves the new scheme, this will trigger a roughly 18-month process to amend the approved Environmental Assessment.

Central Waterfront

The Waterfront Toronto Board has approved a project to rebuild the sidewalk and bike path (Martin Goodman trail) from Bay to Jarvis Street this summer.  The work will also  include reconstruction of the aging Jarvis Slip’s dock wall and revision of its anchoring system to provide clearance for new telecomm and hydro ductwork that will serve the eastern waterfront.  Some road refinishing will be done to tidy up Queen’s Quay if the budget permits.

The intent is to provide a link to the new developments on Queen’s Quay east that have been isolated from the stylistic changes further west and especially the major redesign of the road to begin this summer.

Governance

The CEO’s Report includes updates on all major projects at Waterfront Toronto (I tend to focus on transit and related issues).  One of the most important notes in this month’s report is:

The province has indicated that it is tracking for a spring/summer approvals process for Waterfront Toronto’s long-standing request for increased operational governance. A scoped consent package has been negotiated with the three orders of government which would provide Waterfront Toronto the ability to borrow, create subsidiaries, receive revenues and encumber its assets. Once provincial approval has been obtained, the federal government will seek its respective approvals likely in the late summer/fall.  (Page 6)

Several projects, including the transit infrastructure for the eastern waterfront, will require new funding sources among which may be new mechanisms within Waterfront Toronto itself.  At the Board meeting, CEO John Campbell was optimistic that senior governments would agree to proposed changes, although he noted that Queen’s Park was particularly sensitive on the matter of creating subsidiaries in the wake of the ORNGE scandal.

Continue reading

The High Cost of Going Underground(?) (Updated)

Updated May 17 at 11:00 pm:  Richard Gilbert has responded to this article.  Rather than leave his remarks and my replies in the comment stream, I have placed them at the end of this article.

Urban consultant and former city Councillor Richard Gilbert has an article on the Globe & Mail’s blog titled “How Toronto’s transit plan takes taxpayers for a ride”.  The article decries the high cost of the Eglinton LRT and in particular the high effective subsidy per rider of the capital cost of burying much of the line.

The basic premise, the questions behind the article are sound, but the methodology is not.  This leads to a substantial overstatement of the per passenger subsidy for the capital construction.

At the outset, I must emphasize that my intent is not to attack Richard Gilbert himself, but rather to comment on the pitfalls involved in making comparisons between different systems, and in the use of generic formulas in planning.  In many of the critiques I have written over the years, the hardest  part has been to delve into the underlying assumptions and methodologies (themselves often hidden away in background papers).  These may “prove” something, if only that an author found the number he wanted to find and looked no further.

Gilbert writes:

According to Metrolinx, the provincial agency charged with implementing the transit improvements, the Eglinton line is to cost $4.9-billion (an amount under review). It is forecast to carry 5,400 passengers per hour in the peak direction in 2031, eleven years after it is scheduled to begin operation.

This peak rate is usually associated with an annual total of some 17 million rides. The annualized capital cost of the line is about $300-million per year ($4.9-billion amortized over 35 years at 5 per cent).

Thus the capital cost per ride will be an extraordinary $17.50 ($300-million divided by 17 million). This will be the effective subsidy per ride if the fares to be paid roughly cover the operating costs.

Central to this calculation is the translation of a peak point/hour demand of 5,400 to an annual ridership of 17-million.  The Eglinton route, like many transit lines in Toronto, is not a commuter line feeding unidirectional demand into one point like a GO train.  It is a route (actually several bus routes) serving an overlapping set of demands.  Many riders on the line do not contribute to the peak point count — a peak measured westbound to Yonge in the AM peak will not include any riders using the west end of the line, nor will it include any counter-peak traffic.  Many riders will not contribute to the peak hour counts — the ratio of off-peak riding on the TTC is much higher than on GO Transit even where all-day service is provided.

Any claim that a single peak point’s ridership can be translated to an annual figure will be inaccurate because it ignores the characteristics of the line as a whole. Continue reading

Service Changes Effective June 18, 2012

The TTC will implement many service changes on June 18, 2012 mostly for seasonal changes in demand.  The lion’s share of these are service cuts, with a few increases.  These are detailed on the first six pages of the document linked below.

Construction will continue in many parts of the city notably affecting the streetcar system.

Waterfront / Spadina

The separate operation of 509 Harbourfront and 510 Spadina will continue into June, but the Spadina streetcar service will be replaced with buses running in mixed traffic to permit construction.  This includes both track repairs and changes to the safety islands in anticipation of the new LFLRVs and the implementation of the Presto fare card.

Service on 511 Bathurst will be increased to absorb some of the traffic that might otherwise attempt to use the 510 Spadina service.

Whether this arrangement, with buses stuck in the often-jammed traffic lanes of Spadina, will work at all remains to be seen.  I cannot help wondering why the work is not staged in such a way that buses could use the right-of-way for at least part of the distance with police assistance at merge points.

Welding of new rail for the reconstruction of track on Queen’s Quay is now in progress in front of the Redpath’s Sugar site.  Tentative plans have streetcar service coming off of the 509 Harbourfront car at the end of July for the beginning of construction.

Queen Street East / McCaul Street

Work will continue on Queen near Russell Carhouse, but the reconstruction of McCaul Street will close McCaul Loop.  During this period, the branch of the 501 operating from Russell to McCaul will be extended to Wolseley Loop at Bathurst Street.  Whether it will actually reach this destination in the time allowed is quite another matter, and I expect to see a lot of cars short-turning.

Dufferin Street

Dufferin Street will be closed to transit between King and Queen for track and water main work.  The branches of 29 Dufferin which normally operate to Dufferin Loop will be short-turned at Queen via Gladstone.  The branches which operate to the Princes’ Gate will divert via Queen, Shaw and King around the construction zone.

2012.06.18 Service Changes

TTC Meeting Wrapup: May 1, 2012

The TTC board met on May 1.  This was a quiet affair without the political drama of the “old” Ford-stacked Commission, and I almost missed the bumbling antics of the old crew.  The agenda was on the thin side, and everything wrapped up in a few hours.

Major items included:

  • a status report on the LRT projects,
  • proposed changes to the Richmond Hill extension of the Yonge Subway,
  • the Framework Agreement with Metrolinx for implementation of the Presto farecard,
  • the Customer Satisfaction Survey, and
  • the CEO’s report.

Continue reading

Where Should We Put the “Downtown Relief” Line?

The Downtown Relief Line has been in the news a lot lately, what with dreams of vast new revenues to pay for transit expansion and, at long last, a recognition that more people want to travel downtown than we have transit capacity to handle.

Back in the 1980s, the Network 2011 plan included a line from Union Station to Don Mills and Eglinton by way of the rail corridor, Eastern Avenue, Pape, a bridge across the Don Valley, and Don Mills Road.  This scheme was turned down in favour of the Sheppard Subway as part of a misguided idea that if we simply stopped building new lines into downtown, growth would stop.  In fact, GO Transit did a fine job of providing extra capacity, and more recently the new downtown condos have raised short commutes by streetcar, cycling and foot to levels nobody expected thirty years ago.

The Yonge subway filled up, for a time,but the pressure fell off thanks to the 1990s recession and the general drop in transit use.  That’s no longer the case, and suddenly everyone wants to “do something” about transit capacity downtown.  The TTC, shamefully, downplayed anything beyond its own mad scheme to stuff thousands more riders onto the Yonge line, a project requiring major changes in signalling, reconstruction of Bloor-Yonge station (and possibly others) for extra capacity, a much larger subway fleet (and yards to hold it) and possibly even the addition of platform doors at all stations.

Council asked the TTC to look at a DRL, and there is even supposed to be a study.  However, its web page is the only sign that anything is going on.

Meanwhile, every would-be transit planner in town is busy drawing maps, to the point where a credible plan can be found simply by dropping a piece of spaghetti on a map of the city and declaring this a route.  (Post-graduate degrees are available to those who can determine the ideal height from which to drop the pasta and cooking time needed to produce the best results.)  What’s missing in a lot of this discussion is a view of how a DRL might fit into a wider network, not to mention a few basics about how a new rapid transit line will, or will not, fit in some of the proposed alignments.

One of the better proposals is on Phil Orr’s DRL Now site.  It’s not perfect (no proposal is, including those I have floated from time to time), but at least this is a place to start with sufficient detail to understand what is going on.  Drawing a swoosh across a map is easy (politicians do it all the time), but designing something that might actually work is a lot harder.

A major challenge with some versions of this line is that proponents try to do too much.  Playing “connect the dots” with a transit route has its limitations, and trying to hit too many of them causes the line to wander out of its way.  This ties back to a fundamental question:  what is a DRL supposed to do?

If we believe some of the simpler plans (notably one in last week’s Star proposed by Councillor Pasternak), the DRL’s sole function is to get people from the Danforth subway to Union Station.  This is far too simplistic and guarantees the line will not be well used except as a peak period relief valve.

Other schemes take the route south of the rail corridor to serve the Port Lands and eastern waterfront.  Aside from the problems of building such a line in landfill beside Lake Ontario, the route would not provide the fine-grained transit access possible with a surface LRT, and would vastly overservice an area whose expected demand is lower than the existing Sheppard subway.  Connection to Union Station from the south would also be a big challenge.

From time to time, I am asked “what would you do”, but to start that discussion, a few first principles:

  • A”DRL” should not exist solely to relieve the Yonge line’s peak traffic problem, but should provide new links within the transit network giving rapid transit to areas of the city that do not have it today.  Indeed, the regional function within the network may well be as important as the “relief” function at Bloor-Yonge.
  • Any proposed route through downtown must respect the actual built form of the streets and buildings.  Diagonal routes through built-up areas should be avoided as they are difficult if not impossible to build.
  • Stations must be located where it is physically possible to build them.  Some routes use rail corridors without considering how either a surface or underground station might fit or be built.
  • A “DRL” is not the complete solution to capacity problems on the subway.  These problems originate north of Steeles Avenue, and a major role in trimming peak demand falls to GO Transit which has several north-south routes that could drain traffic otherwise headed for the Yonge line.

The proposed route on DRL Now (click on “Interactive Map” under the “Station Information” pulldown) includes four phases:

  • Don Mills and Eglinton to City Place
  • City Place to Dundas West
  • Don Mills from Eglinton to Sheppard
  • Dundas West to Pearson Airport

I have concerns with a few details of this plan, but the basics are good.  Another view of the route is available via Google Maps.  This has the advantage of showing the detailed alignment rather than a “route map” graphic.

Continue reading

Metrolinx Resurrects Transit City (Updated)

Updated April 26, 2012 at 1:10pm:  This article has been updated to reflect discussions at the Metrolinx Board meeting of April 25, the press scrum following that meeting, and correspondence between me and Metrolinx to clarify some issues.

Notes from the Board Meeting and Press Scrum:

Chair Rob Prichard asked about the status of unrecoverable losses due to the diversion of Metrolinx effort from the original Transit City plan to the Ford transit Memorandum of Understanding.  Less that $10-million has been spent on preliminary engineering for the Eglinton tunnel east from Laird Station.  Potential extra costs from Bombardier for the vehicle supply contract are not yet known.  If these were simply inflationary increases, then the Metrolinx funding (which includes inflation) should cover this.  However, Bombardier may also claim additional expenses related to the delay.  Prichard urged staff to “negotiate” away as much of such claims as possible.

This issue came up again in the press scrum.  Metrolinx has always said that “others” must bear any extra costs due to the Ford delay, but the identity of this party is unclear.  Elizabeth Church from the Globe noted that Karen Stintz has pointed out that since the Ford MOU was never approved by City Council, the city can hardly be held responsible for the delay.

Both Rob Prichard and CEO Bruce McCuaig dodged around this and other questions related to Metrolinx’ role in pursuing the Ford plan in the absence of Council support, especially considering that Metrolinx hangs its return to LRT on Council’s clear vote for the original Transit City plan as the City’s definitive policy statement.  The Star’s Royson James described Prichard as being good at “ragging the puck”, but never managed to pin him down to an answer.

Prichard hopes that the value of the “extra cost” will be reduced to zero making this a moot point, or at least one small enough to fit under any nearby rug without most people noticing the lump.

Director Lee Parsons asked about the possible funding from P3 Canada and what this might enable.  Bruce McCuaig suggested that it might be possible to add to the scope of work with the additional money available through this federal program, but the dollar value is not large and Metrolinx must still pitch their projects to the P3C board.

Director Richard Koroscil asked what the differences were between the plan proposed here and the previously approved 5-in-10 scheme.

Jack Collins (Vice President, Rapid Transit Implementation) replied that these are mainly the slippage of Sheppard’s completion out to 2018 and the shift of the SRT completion back from 2020 to 2019.  The design team and project manager for the Sheppard project were disbanded when work stopped just over a year ago and a new team must be assembled.  Moreover, the project will now be delivered through Infrastructure Ontario (IO) as an Alternate Finance and Procurement (AFP) scheme, and this adds time for production of the contracts related to managing this process.

In the case of the SRT, the section of the route north of McCowan Station will be built while the existing SRT is still operating and this allows work to start sooner than planned on that line.

Director Rahul Bhardwaj asked about the requirement that the TTC implement the Presto smart card as a precondition of having these projects funded by Queen’s Park.  Bruce McCuaig replied that a proposal from TTC staff for an agreement with Metrolinx and the rollout of Presto will be going to the TTC board at its meeting of May 1.

Director Joe Halstead asked about the roles of three agencies — Metrolinx, the TTC and IO — in these projects.  Metrolinx will be the project owner.  IO will be the procurement agency.  The TTC will provide the design criteria, manage the design consultants and technical details of the projects, and will eventually operate the lines.

Halstead also asked about lessons learned from the St. Clair project.  Collins replied that Metrolinx will maintain a presence in communities to keep them informed as the projects evolve, and noted that the neighbourhood office for the Sheppard LRT that had been closed because of the Ford MOU would have to be reopened.

Director Doug Turnbull asked where Metrolinx stands on the role of subways.  Bruce McCuaig replied that Metrolinx supports subways such as the Spadina extension now under construction, and noted that “The Big Move 2.0” includes both the Richmond Hill extension of the Yonge line and the Downtown Relief Line.  Metrolinx will continue to support subways in this context.  Rob Prichard noted that Toronto Council had asked city planning staff for studies of a Sheppard West connection to Downsview and a Bloor West extension to Sherway.

Turnbull asked whether TBM 2.0 affects any of the four LRT lines up for approval.  Bruce McCuaig replied that the 2.0 document will review progress to date and incorporate new initiatives such as the GO electrification.

During the press scrum, Metrolinx clarified that The Big Move 2.0 will be published at the end of 2012.

Director Stephen Smith asked for a clarification of the AFP bidding process and the meaning of the term “Financial Close” in the project chart.  Jack Collins explained that the procurement would have several stages.  First, bidders would be invited to qualify to bid on the work.  Based on this, three would be chosen, and they would be given funding to prepare a more detailed proposal.  From that work, IO would make its evaluation and select a winner.  At that point, the overall contract and financing details would have to be nailed down, and this would be the “financial close”.  IO will rely on Metrolinx, the TTC and technical consultants for evaluation of the proposals.

Smith asked whether pricing would be affected by the level of activity in the construction market.  Collins replied that preliminary indications from the international market are good because work is drying up overseas.  Also, experienced resources now committed to the Spadina extension will be freed up starting in late 2015.

The report was approved by the Board, and most of us adjourned to the press scrum which was attended by Rob Prichard, Bruce McCuaig, Jack Collins and the usual bevy of Metrolinx communications staff.

After the discussion about “extra costs” noted above, questions turned to the location of the Eglinton tunnel.  It will definitely not go under the Don River because this would involve tunneling through bedrock.  The tunnel boring machines are designed for softer conditions (soil, clay, etc), not for hard rock, and this work would be very expensive.  The line will go under Don Mills Road and will provide for a future connection to a north-south route.

Questions returned to the role of Metrolinx and “the need for a clear and supportive partner” as they put it.  Elizabeth Church asked about the Mayor’s opposition to the LRT scheme.  Bruce McCuaig noted that Council had voted, and had delegated authority to the City Manager to execute contracts for these projects.  Rob Prichard observed that the Mayor and his brother speak for themselves, and that there is a broad consensus for the LRT plan.  Metrolinx won’t stand in the way of debate, but they have lots of room for working with the city.

John Lorinc asked whether Metrolinx is concerned about being “the meat in the sandwich” in the 2014 election?  Prichard replied “no”.  He observed that political actors have strong ideas, and we shouldn’t try to take politics out of transit.  However, we should keep our eyes on the main goal of better transit and less congestion rather than just fixating on four projects.  There will be a contract with the city for these four, and other projects may come.  Metrolinx should be steady in its execution of the projects and although there will be elections along the way, the recommendation is that these projects should be completed.

A few questions on the vehicle contract came up.

Would other cities outside the Metrolinx planning area be able to procure LRVs through the Metrolinx contract?  Jack Collins replied that this decision would be up to the local municipality (e.g. Kitchener-Waterloo or Ottawa).

Given the extended period between vehicle delivery and start of service on the first line (Sheppard), what will Metrolinx do about the warranty that could expire before the cars begin revenue operations?  Bruce McCuaig replied that this would form part of the discussions with Bombardier and final approval of the terms would come from Queen’s Park.  There will be two pilot cars built for Metrolinx but no dates are set yet for their delivery.

Royson James asked about Metrolinx’ role — are they simply following the political path of least resistance, or can we “take their recommendations to the bank”?  Bruce McCuaig replied that Metrolinx would give its best advice regarding regional transportation systems, and that they are the keeper of the long term view.

James asked why Metrolinx keeps changing its mind.  McCuaig replied that there are choices between technologies, and it’s not always a black and white decision.

Rob Prichard chimed in saying that there had also been changes in preference on the City’s side for Eglinton’s technology.  The Ford MOU had tradeoffs — a longer Eglinton tunnel was a gain at the expense of losing the Finch LRT (and the eastern part of a Sheppard line).  Metrolinx need to build projects that make sense, and they are “respecting democracy”.

Elizabeth Church noted that Metrolinx has changed its “expert opinion” especially on Eglinton, and this is frustrating to those who seek technical advice.  Prichard replied that between 2006-08, the original vision for Eglinton was all underground, a faster line attracting more riders.  However, the tradeoffs between costs and benefits led to a subway-surface arrangement.

This exchange led me to write for clarification because at no time did the City of Toronto endorse an all-underground Eglinton line, particularly not once Transit City was announced.  Even before, Eglinton was flagged as a corridor for improved transit and surface priority treatment, but not for a subway.  Prichard is mixing the Metrolinx planners’ fantasies of an all-underground Eglinton with official city and TTC policy decisions, and Metrolinx can hardly claim to be following the City’s changes in policy when in fact the drive for an Eglinton subway came from Metrolinx itself.

I wrote to Metrolinx:

At the media scrum, Rob Prichard talked about the to-and-fro of the city’s position on an Eglinton all-underground line.

It’s worth noting that several reports dating from 2005-6 including the City’s Official Plan and the TTC’s “Building a Transit City” showed Eglinton as a potential transit corridor, but talked much more of surface transit priority than of a subway. ‪

Yes, there was an older proposal for a subway west from Mt. Dennis to Renforth, but the projected demand was quite low and it was not taken seriously.

Therefore to suggest that there was any serious support for an Eglinton line completely underground … is stretching the point.

Metrolinx replied:

As The Big Move was being developed between 2006 and 2008, a variety of transit lines and technologies were modeled and considered in developing the full integrated GTHA system of the future, including Eglinton as a fully-separated rapid transit corridor. The Big Move does not specify whether sections are below ground or above ground.

Also, as Metrolinx worked with the City of Toronto and the Toronto Transit Commission, and a more detailed Benefits Case Analysis was undertaken, Eglinton was confirmed as grade-separated through the central section, and at surface, east of Laird Ave.

It should be noted that the benefits of a totally grade-separated Eglinton were weighed against all other rapid transit projects across the GTHA on a range of issues, including future land use, location of employment, integration with local transit, GHG reductions, the ability to serve communities of higher social need, and travel time.

You can judge for yourself whether there was a city position on the vertical alignment of Eglinton that would support Metrolinx’ claim.

John Lorinc got in a good last word with the question “Will you still support this plan in 2014?”

To assist readers in keeping track of the shifting completion dates for the projects, here is a consolidated chart of the original plans, the revised “5-in-10” plan, and the new 2012 version.

2012.04.25_Project Staging Chart

The original article from April 24 follows below.  Note that some route-specific information has been updated on April 26.

Continue reading

The Challenge of the Eastern Waterfront

Redevelopment of Toronto’s eastern waterfront, notably the “Port Lands” area southeast of Lake Shore and Parliament, was the first of many issues on which the Ford brothers’ vision for our future ran headlong into voters and Councillors.  A fantasy of malls, Ferris wheels and a monorail did not fit with previous schemes for a naturalized river mouth at the Don and a well-designed residential/commercial neighbourhood.  That battle ended with Council voting to send the whole design question off for review, a process now nearing its completion.

Waterfront Toronto has a separate website for the public consultation process behind this review.

From a transit perspective, plans for the eastern waterfront are a mess.

Continue reading

The Sheppard LRT Report (Part IV)

Now we come to what I must call “The Chong Dissent”, the reports prepared under the company “Toronto Transit Infrastructure Limited” (TTIL), a dormant TTC corporation resurrected for the purpose because it had $160k sitting in its bank account.  All this and more was spent to argue the case for a Sheppard Subway.

Council has already opted for an LRT line on Sheppard, but arguments originating from the TTIL reports continue to haunt the debate.  It’s time to expose their threadbare, self-serving nature.

Continue reading