TTC Service Changes Effective Sunday, August 31, 2014 (Update 3)

The August 31 schedules will see a return to fall service across the system as well as several other changes.  At long last (I have been distracted with other events, and there was a lot to do this month) here is the consolidated list of service changes. The list combines all types of change because there are overlapping seasonal, construction and service improvement effects.

The table linked here has been updated to correct errors missed in its creation. Thanks to Timor Urakov for catching these.

2014.08.31_Service_Changes (Revision 2)

Major changes include:

  • Return of streetcars to 510 Spadina
  • A major change of the 504 King schedule to provide added running time
  • Return of 504 King and 505 Dundas streetcars to Broadview Station
  • Route split of 501 Queen for Gardiner Expressway construction at Humber Loop
  • Route split of 116E Morningside Express to 198 UTSC Rocket

Something I have not included here, but will add in a future update, is a list of all of the Standby Buses (and a few streetcars) that are spotted around the city for various reasons. They don’t show up in the route-by-route info, but there is a substantial chunk of the fleet used to provide this service. Due to a bus shortage, the number of standby vehicles scheduled for fall 2014 is lower than originally planned.

510 Spadina

Streetcars will return to Spadina between Bloor and Queens Quay with all service running through to the south end of the line. The route will be scheduled based on CLRV capacity, and new Flexities will take over runs one by one as cars become available. Current plans are for through service to Union and a resumption of streetcar service on 509 Harbourfront in October.

At the end of the AM Peak, 508 Lake Shore trippers operate a westbound trip as 506 Carlton to provide extra capacity to the UofT St. George campus. These trips previously operated back to Roncesvalles Carhouse, but they will be changed so that the cars switch over to 510 Spadina which has more cars during the midday than the AM peak.

Previously, this interlining was done using 503 Kingston Road cars from Russell, but with the move of 510 Spadina to Roncesvalles, trippers from that division will be used.

504 King Running Time Changes

In an attempt to reduce the need to short turn much of the service to keep operators on time, the TTC is changing the round trip times during all periods of service on this route.

King Round Trip Time Changes September 2014

                    Weekdays     Saturday     Sunday
                    Aug   Sept   Aug   Sept   Aug   Sept
AM Peak             104+8 120+8
M-F Midday          100+8 122+5
PM Peak             115+8 135+7

S-S Early Morning                85+5  105+5  78+2  95+4
S-S Late Morning                 97+7  111+6  94+5  109+5
S-S Afternoon                    97+7  111+6  94+8  109+5

Early Evening        95+7 116+6  97+4  111+4  82+8  97+3
Late Evening         85+6  99+4  83+7  100+4  76+4  95+4

In the table above, the “before” times are shown under “Aug” and are taken from the schedules in effect until Aug. 30. The “after” times are shown under “Sept” and are taken from the schedules effective Aug. 31.

The time is given as running time plus recovery time. For example, the AM peak running time of “120+8” means that cars will have 120 minutes of driving time to make a round trip plus 8 minutes of terminal recovery time. Some of the changes increase the total time by 20%, a very substantial increase.

Whether this will translate into a noticeable reduction in short turns remains to be seen. One potential problem will be the accumulation of “early” cars at terminals where it is already possible to find lineups of cars. From my own knowledge of the line, some of these changes appear to be excessive and will probably have to be rolled back.

501 Queen & 508 Lake Shore

From September through December, reconstruction of the Gardiner Expressway at Humber Loop will close off the underpass between the loop and Lake Shore Blvd. The outer end of the Queen route will once again switch to a shuttle bus connecting with the streetcar.

Subway Changes

Yonge subway operations will be changed to base more trains at Davisville Yard. This will give more time for maintenance work as the last service trains will be clear of the line sooner than on current schedules. An early morning non-revenue train that carries Station Collectors to work will be replaced with a shuttle bus.

On the Bloor subway, service will be improved weekday middays and evenings, and on Saturday afternoons to reduce crowding.

Roncesvalles Yard

In anticipation of the arrival of more Flexities, some runs will be shifted to other locations. Exhibition Loop will now be used to store some 511 Bathurst runs as well as 512 St. Clair runs already at that location.

The 510 Spadina route will operate from Roncesvalles where the Flexities will be based, and to make room, all runs on 505 Dundas will operate from Russell.

Broadview Avenue

Streetcar service will return to Broadview Station after a temporary absence in July-August.

Since the re-opening of the Broadview & Queen intersection, carhouse trips from Russell westbound have resumed using the west-to-north curve that was taken out of service for safety concerns in October 2012.

Six Points Project

The reconstruction of the Kipling-Dundas-Bloor interchange begins in September and this will trigger diversions of various routes around Kipling Station.

Metrolinx Board Meeting June 26, 2014 (Corrected)

Correction July 1, 2014: In the original version of this article, I attributed a comment to Metrolinx Chair Rob Prichard regarding the sharing of information between bidders on rapid transit projects, and expresssed my surprise that this did not match the process I was familiar with from my own public sector experience. In fact, the remark was with regard to sharing information about questions to Metrolinx from candidates in the municipal election.

The procurement process does include sharing of information via addenda to Requests for Information issued to all bidders as mentioned in the Rapid Transit Quarterly Report. I regret this error and frankly cannot understand how I scrambled two very different topics together.

However, the process for dealing with candidate questions at Metrolinx is completely different from that followed by the City of Toronto. Where Metrolinx preserves confidentiality about questions a campaign might ask, the City posts responses to any query online so that no candidate has the advantage of professional advice not available to others. The basic premise is that the staff works for Council, not for an individual member or candidate.

As a public agency, Metrolinx should be providing information to everyone. The discussion (which starts at about 21:10 of the meeting video) emphasizes that Metrolinx has no part in the election, and yet the confidentiality of information exchanges could offer an advantage to a campaign that is unknown to other candidates.

Original Article  from June 29, 2014:

The Metrolinx Board met on Thursday, June 26 in a quite celebratory air. With the provincial election out of the way and the return of a pro-transit Liberal majority to Queen’s Park, Metrolinx sees a rosy future for transit expansion. They wasted no time telling anyone who would listen about the great work now at hand.

Among the items of interest were reports on:

Another burning question about the recently announced funding is just how much money is on the table, especially how much is new money as opposed to funds earmarked for specific projects like RER or previously announced/expected for projects in the “Next Wave” of Metrolinx undertakings. It didn’t take the assembled media long to notice that the GO RER scheme would gobble up much of the $15b earmarked for transit in the GTHA. I will return to this in a separate article.

Continue reading

Queens Quay Reopening for Streetcars Delayed Again (Update June 24, 2014)

Updated June 24, 2014 at 11:35 pm with additional info from the TTC. Please scroll down to the end of the article.

Updated June 19, 2014 at 11:15 am: Waterfront Toronto has replied to my query about the status of the Queens Quay project. This has been added to the end of the article.

In what is becoming a distressingly common TTC tactic, the first sign of delays to the Harbourfront streetcar’s return has again appeared buried deep in the monthly CEO’s Report in the TTC Board’s meeting agenda.

The report now shows two separate dates for resumption of service to Queens Quay:

Queens Quay Union Stn to Yo Yo Ma Lane
Jul 29/12 – Oct 11/14
Waterfront Toronto
Queens Quay Reconstruction

Spadina Ave. and Queens Quay including Loop
May 13/13 – Aug 30/14
Platform Upgrades & Track Replacement

[See table on page 21]

I wrote to the TTC’s Brad Ross about this slippage, and also asked whether another factor was the planned opening date for the second platform at Union Station (which provides access to the Union Station Loop). He replied:

QQ may well be ready, but then again it may not. As you can appreciate, we had to schedule service as bus in case it wasn’t ready.

Union second platform is to open this summer. I don’t have a specific date to share yet.

What astounds me here is that the trackwork on Queens Quay is nearly complete, except for the section west of Spadina which is not required for restoration of streetcar service to Union Station.

When I pressed Ross further on the issue of opening east from Spadina, he replied:

Our track and overhead staff do not have a high level of confidence of readiness. We have made clear to WT in the strongest terms possible, our desire to have QQ back.

I will pursue this issue with Waterfront Toronto to get their side of the story.

Updated June 19, 2014:

Waterfront Toronto replies:

We are working collaboratively with TTC to substantially complete the construction of both the Spadina Loop and the streetcar corridor on Queens Quay by the end of June to give TTC crews the time they need to commission the line. To date, we have completed over 90% of the construction and have begun installing TTC poles along the corridor. Unfortunately, due to a collapsed telecommunications duct bank in the roadway west of Spadina (which is now repaired), reconstruction of the streetcar corridor in that block has been delayed by approximately two weeks. While we are working diligently to provide TTC crews the time they need to commission the line in that area, we fully respect their Service Planning process and the decision to have buses available to serve customers on the 509 Harbourfront line through September. We are pleased that the TTC will resume the 510 Spadina streetcar service to the newly rebuilt Spadina Loop as of August 31 and that we are on schedule to deliver the fully revitalized Queens Quay next June.

Updated June 24, 2014 at 11:35 pm:

Today I spoke with TTC CEO Andy Byford who advises that a major problem for the TTC is not the completion of the track, but the availability of poles on which to string the overhead. This is a particular problem at Queens Quay and Spadina where even getting the loop open for August 31 may be a challenge.

From various Waterfront Toronto construction reports, I know that work west of this intersection has been delayed first by the unexpected collapse of a Bell duct, and also while work was put on hold so the area could be used for staging of new track panels. That said, it is difficult to believe that WT cannot get the new poles installed promptly now that the intersection construction is largely complete. I will follow this up with WT for further info.

TTC Service Changes Effective May 11, 2014 (Update 4)

The May 2014 schedules will bring major changes across the system mainly in response to construction projects.  Extra running time will be provided on many routes in response to construction delays.  At some times, the current headway will be maintained, while at others the headway will be stretched.  In two cases (46 Martin Grove and 94 Wellesley), no buses are available to improve PM peak service to compensate for extra running time.

The budget for construction-related service is considerably less than what will actually be required.  Although the total hours operated will be greater than the budget for May, “regular” service will be below budget while “construction” more than compensates.  Some changes in the fleet and in service levels have been deferred until later in 2014.

2014.05.11_Service_Changes

This table is broken into four sections listing miscellaneous minor changes, construction-related changes, one route restructuring and seasonal changes.

Updated May 17, 2014:

Effective Tuesday, May 20, the diversions for the Queen & Victoria track project will be changed.

  • All westbound 501 Queen cars will divert via Church-King-York.
  • 501/502/503 shuttle bus services will terminate at Church Street.

The details are on the TTC service advisory page (scroll down to see the portion effective May 20).

Continue reading

Neptis Reviews Metrolinx: A Critique (I)

In December 2013, the Neptis Foundation published a review of the Metrolinx Big Move plan authored by Michael Schabas. This review received prominent attention in the Toronto Star and is regularly cited in their coverage of transportation issues. Some elements also appear in recent comments by Transportation Minister Glen Murray, and it is reasonable to assume that his view of Metrolinx priorities has been influenced by the Neptis paper.

Since its publication, I have resisted writing a detailed critique in part because of the sheer size of the document and my disappointment with many claims made in it, and a hope that it would quietly fade from view. Recent Ministerial musings suggest that this will not happen.

The stated goals of the report arose from four basic questions posed shortly after The Big Move was released in 2008:

  • What evidence suggests that the projects in the Big Move will double the number of transit riders and significantly reduce congestion in the region, as promised by Metrolinx?
  • Does each project offer good value for money?
  • Do all the projects add up to a substantial regional transit network or is the Big Move just an amalgam of projects put forward by diverse sponsors?
  • How do the projects in the Big Move relate to the Growth Plan for the Greater Golden Horseshoe, its land use equivalent? [Page 2]

The report itself addresses a somewhat different set of questions and notably omits the land use component.

  • Will the Big Move projects achieve the Metrolinx objective of doubling transit ridership?
  • Are these projects consistent with Metrolinx’s own “guiding principles”?
  • Are they well-designed, consistent with international best practice, and integrated with other transport infrastructure?
  • Will they support a shift of inter-regional travel onto transit?
  • Are there alternative, more effective schemes that should be considered?
  • What changes would help Metrolinx produce better results? [Page 14]

Schabas’ work is frustrating because on some points he is cogent, right on the mark.

Metrolinx has bumbled through its existence protected from significant criticism, swaddled in a cocoon of “good news” and the presumed excellence of its work. To be fair, the agency operates in a political environment where independent thought, especially in public, is rare, and years of planning can be overturned by governmental whim and the need to win votes.

That said, Metrolinx is a frustrating, secretive organization conducting much of its business in private, and tightly scripting public events. Schabas rightly exposes inconsistencies in Metrolinx work, although his own analysis and alternatives are, in places, flawed and blinkered.

Continue reading

Neptis Reviews Metrolinx: A Critique (III)

This article is the third section of my critique of the December 2013 review of the Metrolinx Big Move Plan written by Michael Schabas for the Neptis Foundation. It should be read in conjunction with Part I and Part II.

Continue reading

TTC Board Meeting: March 26, 2014

The Toronto Transit Commission Board will meet on March 26, 2014 at 1:00 pm in Council Chambers at City Hall.  The Agenda contains a number of items of interest.

  • An update on the Union Station project (Revised to add info from Metrolinx)
  • The March 2014 CEO’s report
  • Purchase of 10 additional “TR” subway trains for future demand growth
  • A report on Community Bus services
  • A proposed design for Kennedy Station’s interface to the Eglinton LRT line
  • A report on a temporary bus terminal at Islington Station

Continue reading

Streetcar System News: March 2014

On March 11, 2014, photos of car 4401 on training runs appeared in at least two locations:

  • St. Clair & Yonge on Torontoist
  • Spadina south of Adelaide on Twitter (Photo by Kyle Baptista @kylebap)

Delivery of the first production car, 4403, has been delayed until late April according to the TTC’s Brad Ross, but the rate of production can be ramped up by Bombardier.  In any event, 510 Spadina will operate with new cars effective August 31, 2014.

Meanwhile on Queens Quay, construction of the new streetcar right-of-way and the permanent north roadway is expected to begin later in March depending on the weather.  Work will begin west from Lower Simcoe to Rees, a section where utility work is completed and traffic can be shifted to the south side of the road.  West of Rees, installation of sewers is still underway.

Preliminary overhead work has been done at the exit from Queens Quay Loop, and work is also underway at the King/Spadina intersection.  During brief spells of warm weather, track within the loop was set in concrete.

TTC Board Meeting Followup: February 24, 2014

The TTC Board met on Monday, February 24.  In an earlier article, I gave a preview of issues from the agenda.  This post reports on some of the debate and follow-up information from the meeting.

This was the first meeting under new Chair Maria Augimeri, and it was noteworth for the amount of actual discussion that took place.  The four citizen members, who at one point were a majority of Commissioners actually present, participated at some length with pointed questions.  One can only guess the degree to with former Chair, now mayoral hopeful Karen Stintz, ran tightly scripted meetings that were all about good news with little or no dissent or disruption.

Continue reading