Ontario Announces Toronto Subway Plan

On April 10, 2019, Premier Doug Ford announced his government’s intentions to expand transit in Toronto. The plan includes:

  • The “Ontario Line”, a rebranded and extended version of the Relief Line, will run from Don Mills and Eglinton to Ontario Place.
  • The Yonge North Extension from Finch Station to Richmond Hill Centre
  • The three-stop version of the Scarborough Subway Extension from Kennedy Station to Sheppard with stops at Lawrence East and Scarborough Town Centre
  • Extension of the Sheppard Subway east from Don Mills Station to connect with the SSE at McCowan and Sheppard
  • Extension of the Eglinton Crosstown west from Mount Dennis to Pearson Airport

Continue reading

Toronto’s Omnibus Transit Report: Part I

Planning for many transit projects in Toronto has been underway for years, but the public face of this work took a long holiday in 2018 thanks to elections at both the provincial and municipal levels.

In coming weeks, Toronto’s Executive Committee and then Council will consider an omnibus report that provides updates on many transit projects and recommends a path forward.

Today, that path is murky given uncertainty about provincial intentions and the degree to which consultation between the city and province is actually in good faith. Premier Ford’s approach on other portfolios, coupled with the breezy confidence of his Transportation Minister (seen recently on TVO’s The Agenda), do not bode well. With the arrival of Doug Ford at Queen’s Park, the provincial goal on transit is more about settling old scores with Toronto Council and proving that Ford’s transit vision is correct than it is about good planning. Recent correspondence between the province’s special advisor on a proposed subway takeover revealed just how much the province does not know, or chooses to ignore. This was not a good start and the province wounded its credibility on basic technical points, never mind the political context.

But for a moment, let us consider Toronto’s future from the point of view of what the city hopes to do, if only they have the control and the money to pull this off.

The report is long, and to break this article into digestible pieces, I will focus on groups of issues. This article covers overall financing of the transit expansion project and specific details for the Scarborough Subway Extension (SSE), now known as the Line 2 East Extension (L2EE). I will turn to other components of the plan in further articles.

Many reports are available on the City’s website (scroll down to the end for all of the links). The principal reports are:

Financing Transit Expansion

The most challenging part of any transit project, let alone a complex program, is to obtain funding from governments whose priorities do not necessarily align and which may talk at least as much about the sanctity of “taxpayer dollars” as they do about investment in public infrastructure.

In a media briefing, city staff were quite clear that no project can proceed to the stage of contract tendering and awards unless the contribution agreements underpinning a project are in place.

At the federal level, the primary funding source will be the Public Transit Infrastructure Fund (PTIF) which has two phases. An initial phase was time-limited, and was used in Toronto mainly to fund the purchase of hundreds of new buses. The second, longer-lived phase of PTIF will be used for transit construction projects. There is some urgency to nail down PTIF contributions given the fall 2019 election and uncertainty about this program under a new government.

Note that this entire discussion relates only to projects that would be funded in part through PTIF, not to many others such as the Eglinton LRT extensions or the Waterfront LRT.

Federal funding of $4.897 billion will be allocated by the city, assuming government approval, as below [Main Report, p. 2]:

  • $0.660 billion for the Line 2 East Extension project
  • $0.585 billion for the SmartTrack Stations Program
  • $3.151 billion for the Relief Line South
  • $0.500 billion for the Bloor-Yonge Capacity Improvement project

Negotiations with Ontario are ongoing, and the status of projects and associated $4.04 billion in provincial funding is unclear. This could be clarified in the provincial budget to be announced on April 11, 2019. Provincial interest in and plans for the Scarborough extension and the Relief Line will affect both of these projects.

City funding comes from a variety of sources:

  • Development charges
  • The Scarborough Subway levy
  • The City Building Fund levy
  • Interest on accumulated reserves from the levies

Financial projections are also affected by factors that have changed since projections made in past years:

  • Higher growth rates in development
  • Lower interest rates

PTIF2 has an assumed split of 40-33-27% for the federal, provincial and municipal governments respectively. This creates a breakdown of responsibilities as shown below.

The provincial share is supposed to be “new funding” and the amount here does not include prior commitments to Scarborough transit which originally were for the proposed LRT line, later for a subway. Exactly how much Ontario will contribute remains to be seen given discussions about ownership and the scope of the Scarborough subway project. I will return to this in more detail later.

Within the city share, $2.42 billion is unfunded (no revenue sources have been committed to fund/finance the expense), and only $885 million of the SmartTrack Stations Program has city funding. The report recommends that the city’s CFO and Treasurer report prior to the 2020 budget process on strategies for addressing the shortfall.

The project cost estimates for these are broken down below. In the chart, the acronyms are:

  • LTD: Life To Date
  • PDE: Preliminary Design & Engineering

The possible funding arrangements vary for each project, and these are complicated both by past history and by the uncertainty of early “class 5” estimates. A tentative breakdown is shown below, but this must be taken with a grain (or more) of salt due to technical and political uncertainties. For example, the assumed provincial contribution to the Line 2 Scarborough project is based on inflation of a commitment made in 2010 dollars where the city and province do not agree on the appropriate inflation factor.

Two separate numbers have been used for the Relief Line cost estimate: $6.8 billion in Table 2 above, and $7.2 billion in Table 3 below. In the media briefing, TTC staff explained that the change was due to an alignment revision (Carlaw vs Pape) and changes in construction techniques (mining vs cut-and-cover) at some locations. That may be so, but to have two different numbers for the same project so close together within a report makes one wonder about the care taken in other aspects. On top of that is almost $2 billion as a “provision” for the Relief Line to guard against potential cost increase as the estimate is refined from class 5 to class 3.

This sort of uncertainty is not unusual, but the constant variation in quoted “estimates” makes for no end of problems. The converse is seen with the Scarborough project where the “estimate” for the subway’s cost has remained fixed since 2014 despite major changes in project scope.

The report explains the difference between initial class 5 estimates and the class 3 estimates to be used in setting project budgets:

As a project moves through the three phases, project definition becomes more refined and the information used as the basis for developing a cost estimate is more mature.

  • A Class 5 cost estimate is typical when starting the initiation and development phase, where the project is conceptual (0-2% design level). This an order of magnitude estimate to inform the decision of whether or not to continue to study an option.
  • A Class 3 cost estimate is based on PDE work (10-40% design level), and is the estimate class recommended when establishing a project budget for procurement and construction. A Class 3 estimate should be used to inform full funding commitment decisions. [p. 16]

Note that the term “order of magnitude” has considerable leeway, and a change from one order to the next is a factor of 10. Saying that costs “A” and “B” are in “the same order of magnitude” gives huge scope which on projects of this nature is measured in billions of dollars. Too much past debate has assumed that minor swings in estimates might occur as designs are refined, but this is more wishful thinking and the political hope that a project will not get out of hand even before shovels hit the ground.

Overall Project Status

The map below shows the location of all projects in the transit network plan.

Projects will advance from stage to stage on their own timetables which are summarized in the chart below.

Line 2 East Extension (aka Scarborough Subway Extension)

This section reviews the status of the Scarborough extension as it is presented in the city reports. Obviously this is subject to major change given provincial announcements of support for taking ownership of the extension and for building a three-stop subway.

Continue reading

Premier Doug Plays With Toronto’s Train Set

In the continuing circus which is the Ford Family Transit Plan, the provincial government has advised Toronto and the TTC of its priorities for rapid transit construction. The Province is quite firm that since it will be paying for these lines, it will call the shots.

This information broke in two letters dated March 22 and 26, 2019 from Michael Lindsay, Special Advisor to the Cabinet – Transit Upload, and Shelley Tapp, Deputy Minister of Transportation, together with a report from the Toronto City Manager, Chris Murray, dated March 26.

The Province has four priority projects, although some of the information about them is vague:

  • A three-stop Scarborough Subway Extension [SSE]
  • A Downtown Relief Line [DRL] of indefinite scope
  • The Richmond Hill Extension of the Yonge Subway [YNE]
  • Construction of the Eglinton West Crosstown LRT primarily underground rather than at grade

These are the only projects mentioned in the letters. By implication anything else is off of the table as far as provincial funding is concerned except for whatever the subway “upload” still under discussion might entail. More about that later.

The Province refers to “incongruencies between the province and city/TTC with respect to the design and delivery of priority projects”. Most of this should be no surprise given previous statements both by Doug Ford as a candidate, and rumblings from his supporters.

The March 22 letter arose from a March 8 meeting between Provincial, City and TTC representatives. Two things are clear:

  • The Province was not paying attention to, or chose to ignore, information it received or should have been able to access easily through public channels.
  • The City/TTC should have had some idea of what was coming down the pipe over two weeks ago, but there was no public hint of what was in store even with the subway upload on the Executive Committee and Council agendas. This is a classic case of “who knew what and when”, and a troubling question of whether the direction of provincial plans was withheld from public view for political expediency.

The March 22 letter makes statements that were revised on March 26, and which have provoked considerable comment as this story broke. Most astounding among these was:

Per our meeting of March 8, we were informed that the City’s preliminary cost estimates for both the Relief Line South and the Scarborough Subway Extension have significantly increased to nearly double or greater the figures released publicly.

On March 26, the Province wrote:

We acknowledge, in light of the helpful clarification you provided at our Steering Committee meeting [of March 25], that the city’s/TTC’s revised project cost estimates for the Relief Line South and Scarborough Subway Extension projects represent estimates in anticipation of formal work that will reflect greater specificity in design. We accept that the actual budget figures remain to be determined …

This bizarre pair of statements suggests that either:

  • the Province was not really paying attention in the meeting of March 8 which led to the March 22 letter, or
  • they really were, but that their first statement was guaranteed to blow every transit plan to smithereens if it were not retracted.

On March 26, they do not say they were wrong, merely that they were dealing with preliminary estimates.

That is a strange position considering that the SSE is on the verge of reaching a firm design number and budget to be reported in early April to Toronto Executive Committee and Council. The agenda publication date is April 2, and it is hard to believe that a firm estimate for the SSE does not already exist. As for the DRL South, that is in a more preliminary state, but if anything the numbers already published have been rather high.

The Scarborough Subway Extension

For the SSE, there are two conflicting proposals:

  • City: One stop extension terminating at Scarborough Town Centre
  • Province: Three stop extension “with the same terminus point”.

There is no reference to any potential connection with a Sheppard Subway extension. However, the March 26 letter contains this statement:

… we recognize that the city/TTC and province share the intention for a station to be located at Scarborough Centre. However, under the province’s preferred three-stop extension of Line 2, the project would proceed northward from the station at Scarborough Centre.

Given that the TTC’s alignment for STC station is itself on a north-south axis, it is unclear just what this remark refers to especially if STC is to be the terminus of the provincial project.

As I wrote recently in another article, there is an issue of equipment and storage required to allow the SSE to open with full service to STC. One potential source of “additional” cost could well be that works such as a new Line 2 yard at Kipling plus the rebuilding and/or replacement/expansion of the fleet are now counted as part of the overall project cost. This is precisely the sort of hidden cost I warned the Province would face when they started to understand the full scope of the TTC’s infrastructure requirements.

Whether this is the case remains to be seen, but with the Province taking responsibility for delivery of this project and planning to assume the cost of maintenance and expansion of the existing subway, they (or anyone else looking at funding the SSE) will be facing these costs as “add ons”.

One other concern is that there is no mention of capacity expansion for Line 2 either by way of station expansion at critical junction points nor of fleet expansion to allow more service once the line has Automatic Train Control [ATC].

Crosstown LRT Westward Extension

  • City: A substantially at-grade extension from Mount Dennis westward, although there are references from recent public participation to the possibility of some grade separations.
  • Province: A “significant portion of this extension” would be underground, an option “which has not been considered in a material way” as part of the current design.

The March 26 letter revised the characterization of the City’s work to date:

… we recognize that tunnelling options for the project have been considered as part of previous assessment, but that these options are not preferred by the city/TTC.

Again, one must wonder just what the province was doing at the March 8 meeting to have so botched their understanding of the work to date. The work already done is documented on the project’s website. I cannot help wondering how much the original provincial position was a product of political posturing by Etobicoke politicians. Such a gaffe does no credit to Michael Lindsay and his team.

It is no secret that there is strong political pressure from politicians in Etobicoke for the LRT line to be buried as much as possible, and it is no surprise that the Province would embrace this.

Missing, however, is any reference to the portion of the line west of the Toronto-Mississauga boundary and specifically the link into Pearson Airport. Will this be part of the Provincial project?

Relief Line South

The text in this section has provoked speculation in various fora, both the mainstream and social media.

Planning work undertaken by the TTC contemplates utilizing existing technology … the province would propose … a truly unique transit artery spanning the city that is not beholden to the requirements of the technologically-outdated Line 2.

On March 26, the Province changed their tune, a bit:

… we recognize that the city/TTC is contemplating a different technology for the project than that currently deployed for Line 2.

It is hilarious to see Line 2 described as “technologically outdated” when it is this line that the Province plans to extend to STC. At the risk of peering into a murky crystal ball, I will venture an interpretation of what is being said here.

The “outdated technology” is the current fleet of T1 trains which do not have ATC installed. Moreover, TTC plans would not see ATC operation on Line 2 for at least a decade unless the existing fleet is retrofitted.

The TTC has always intended that the DRL would use modern technology, and again I cannot help wonder whether the Provincial reps were paying attention at their March 8 meeting with the TTC. This information is not difficult to obtain. They could even read my blog if they don’t want to spend time wading through official documents, but possibly it is simpler just to slag the municipal agency in a time-honoured Queen’s Park tradition.

The Province wants the DRL to be completely free-standing in that it would not depend on Line 2 and the existing yard at Greenwood, but would be built completely separate from the existing subway network. Moreover, “alternate delivery methods” would be used for this project, a clear indication that this would be a privately designed, built, financed and operated line much as the Crosstown was intended to be before a deal was worked out to let the TTC drive the trains, at least for a time.

The reference to a “transit artery spanning the city” implies something much more extensive than the DRL South from Pape to Osgoode Station, but what exactly this might be is anyone’s guess. It could be a truly different technology, something like Skytrain in Vancouver (which itself has two separate technologies). The construction technique could be changed from the proposed double bore to a single bore line, especially if the vehicle cross-section were smaller. The alignment and station locations could be changed. Any of these and more is possible, but we don’t know. As this is to be an AFP project, a blanket of confidentiality hides everything.

Yonge Northern Extension to Richmond Hill

The primary provincial interest here is in getting the line built as quickly as possible with planning and design work for the YNE and DRL to progress in parallel so that “the in-service date for the extension is fast tracked to the greatest extent possible”.

There is no mention of capacity issues on the existing Line 1 including the need for more trains, nor of the expansion needed at key stations to handle larger volumes of passengers.

Jumping the Gun on Uploading?

The March 26 letter clearly attempts to correct misapprehensions from the March 22 missive. These were presumably communicated privately at or before the March 25 meeting.

The Province is supposed to be engaged, in good faith, in discussions with the City and TTC about how or if it would take control of subway assets and what that control, and associated responsibility for ongoing costs, would entail. One might easily read the March 22 letter as showing that the Province has made up their mind, and all that remains is to “drop the other shoe” with respect to everything beyond the “priority projects”.

On March 26, the Province talks at length about “our priority transit expansion projects”. This has always been the political red meat in that new lines translate into votes, or so the Ford faction hopes. The myriad of details in looking after the existing system do not lend themselves to coverage in a two-page letter, let alone simplistic posturings by politicians eager to show the wisdom of their plans.

The March 26 letter does not discuss any aspect of the existing system including asset transfers or financial commitments. That’s not to say the Province has not considered this, but no details are public yet. That will be a critical issue for Toronto because the degree to which the Province actually plans to pay for the existing subway system will affect future City budgets.

There is a myth that fare revenues will cover off the City’s share, but we don’t actually know which aspects of subway “maintenance” will remain in the City/TTC hands. There are two separate budgets, capital and operating, but there has been no statement of how these will be divided. Although there could be a one-time payment for the capital value of the system, this begs two questions. First, who benefits from appreciation of property value as subway lands are repurposed/redeveloped. Second, what does the City do when the nest egg from selling the subway, assuming they even have anything left over after discharging subway-related debt, is used up.

Another issue to be decided is how the split in ownership and financial responsibility will affect gas tax funding that now flows from both the Provincial and Federal governments, over $300 million in 2018. How much of this will Toronto lose, and what will be offset by costs the Province will assume?

Further System Expansion

The correspondence from the Province is silent on many projects including:

  • Eglinton East LRT
  • Waterfront LRT
  • Finch LRT extension to Pearson Airport
  • Sheppard Subway extension to STC
  • SmartTrack and GO Transit Service Expansion

Eglinton East and Waterfront would, assuming a City/Province divide on surface/subway projects, lie clearly in the City’s court, while any extension of Line 4 Sheppard would be a Provincial project. Oddly, Eglinton East would be a “City” extension of a provincially-owned line, the Crosstown.

The Finch LRT occupies an odd place as a surface line that for historical reasons is being delivered by the Province. Moreover, an airport extension would lie partly outside of Toronto. Who knows what the fate of this will be.

To Be Continued …

The provincial letters have dropped into the Council meeting planned for March 27, and we can expect a great deal of debate, if not clarity, in coming days.

At a minimum, the Province owes Toronto a better explanation of just what they intend with their view of projects. This information should not be “confidential” because we are simply asking “what exactly do you want to do”. This is particularly critical for the Downtown Relief Line whatever the “unique transit artery” it might become.

SmartTrack and GO are important components because they will add to the “local” network within Toronto and could be part of the “relief” efforts that will span multiple projects. SmartTrack is a City project, and we are about to learn just how much it will cost Toronto to put a handful of John Tory branded stations on GO’s Kitchener and Stouffville corridors. SmartTrack also takes us into the tangled net of fare “integration” and the degree to which Toronto riders will pay more so that riders from beyond the City can have cheaper fares.

Finally, there is the question of operating costs. The Ford mythology includes a claim that subways break even, and in the uploading schemes mooted to date, there is an assumption that Toronto will still operate the subway network and pay for its day-to-day costs out of farebox revenue. Even if that were true today, much of the proposed network expansion will not gain revenue to cover its operating cost, and Toronto will face increased outlay. There is still no proposal, let alone an agreement, about the operating costs of the Crosstown and Finch LRT lines from which we might guess at how the combination of three new lines/extensions will affect the subsidy call against Toronto’s tax base.

With clear errors in the March 22 letter, the Province showed that it cannot be trusted to propose policy based on fair and accurate characterization of Toronto’s transit system. One would hope that a “Special Advisor” backed by the boffins at Metrolinx and the Ministry of Transportation might be able to avoid screw-ups. When the Province puts forward a scheme to take over part of the TTC, their rationale should be based on transparent and accurate information. Alas, recent experience in other portfolios shows that this will not happen, and dogma will trump common sense.

$33 Billion and Counting

A political tremour ran through the transit world in Toronto recently with the TTC’s release of a 15-year projection of capital spending requirements at $33.5 billion. This does not include funding for most system expansion projects beyond the already-approved Scarborough Subway.

That number is big, but it’s no surprise to those who have been following TTC budgets for years. A major issue has been that “unfunded” or “below the line” projects don’t get the attention they deserve and are deliberately kept off of the books to reduce the apparent size of the City’s financial problems. Common tactics included omitting projects from the overall budget, or projecting their spending in a period just beyond the rolling ten-year horizon of capital planning.

Transit planning in Toronto and at Queen’s Park is reckless when it downplays the backlog of spending and associated subsidies facing public agencies. New spending and the inevitable photo ops for grinning, back-patting politicians are easier to fit into plans when you can ignore the transit system crumbling in the background.

Several budget reports will be before the TTC Board (and later at City Council) at its next meeting on January 24, 2019.

There is far too much material here to review in a single article, and so I will break this up over multiple posts. Some of the details behind individual projects will not be available until I obtain the full version of the Capital Budget known as the “Blue Books” which expand the line items from the “Blue Pages” into project descriptions and schedules.

A vital part of the new reports is a shift to a longer time frame (15 years) and the inclusion of all projects in the Capital Plan whether they have funding or not. The extent of the problem is quite evident in the following chart. The purple hatched area shows the requirements for coming years while the sold areas show known funding amounts in the medium term and hoped-for income thereafter.

The big drop in the City’s funding share in the early 2020s arises from the lack of borrowing headroom in the overall City budget. A big problem here is the crowding by major projects such as the Scarborough Subway Extension and the Gardiner Expressway rebuild within the overall borrowing plan. Current City policy dictates that the average debt servicing cost should not exceed 15% of City tax revenue over a ten year period. Planned spending in the next few years will eliminate the headroom for additional borrowing. This exactly coincides with the bulge in TTC capital requirements beginning in 2022. To put it another way, if funding continued at 2019 levels across the chart, there would still be a shortfall, but against a much higher base.

Even this chart does not tell the full story because the Capital Plan continues to push major projects beyond the ten-year line, and the financial pressures from system expansion are not fully accounted for here. As things stand today, less than 30% of the ten-year program is funded. Beyond 2028, the level of assumed funding is still well below historical levels.

($ billion) 2019-2028 2029-2033 Total 2019-2033
Funded $6.4 $3.4 $9.8
Unfunded $17.5 $6.2 $23.7
Total $23.9 $9.6 $33.5

System expansion projects will add a further $3.8 billion over the first ten years of the plan:

  • Line 2 Extension (formerly known as the SSE): $3.4 billion (subject to revision when an updated cost report is presented to Council in April 2019).
    • “While the 10-Year Capital Plan includes $3.360 billion in funding for this project (between 2019 to 2028), this project has an overall budget of $3.560 billion. This estimate, which includes $132 million to extend the life of the SRT until the Line 2 East Extension commences operation and a further $123 million to decommission and demolish the SRT, was based on 0% design. The project budget and schedule will be re-baselined in Stage Gate 3 report to City Council in April 2019, factoring in delivery strategy and schedule risk analysis.”
  • Relief Line South: $385 million will be spent in 2019-20 to support early works on this project. Some of this is already funded, but $325 million is being advanced into the current ten-year budget. Of this, the City proposes to provide half and looks to other levels of government for a contribution. The actual RL construction project is a separate entity which is not yet in the budget.
    • “The 10-Year Capital Plan includes funding of $385 million to complete current work only, which includes completing the preliminary design and engineering to between 15% and 30% complete, including developing a project budget and schedule.”
  • Waterfront Transit: The ten-year budget includes only $27 million in 2019-21 for design work on the planned extension from Exhibition Loop to the Dufferin Gate. Design work on any other Waterfront projects, let alone any construction, remains beyond the ten-year window.
  • Spadina Vaughan extension: Outstanding work on this project including close-out costs amount to $60 million in 2019, but this will be funded within the existing project.

[Quotations above are from the 15 Year Capital Investment Plan and 2019-2028 Budget, pp 12-13.]

The Relief Line work includes tasks such as property acquisition, utility relocation and design for the tunnel boring equipment. Now that the line has political support, spending sooner rather than later is on the agenda, and about two years can be shaved from the original project schedule by doing the preliminary work now. This is a major change from the position taken by Mayor Tory during the election campaign, and the need to “do something” as soon as possible is now evident.

Continue reading

PTIF Phase 2: The Lottery Win Is Not As Big As It Seems (Updated)

Updated March 16, 2018 at 5:15 pm: The Fire Ventillation Project which includes second exits from several stations was omitted from the list of major projects in the original version of this post. It has been added.

Updated March 16, 2018 at 3:25 pm: The Ontario Ministry of Infrastructure has clarified that the Ontario funding for the Scarborough Subway is separate from the $4 billion in matching dollars shown in the table below.

On March 14, 2018, the Federal and Provincial governments announced the scale of the second phase of the Public Transit Infrastructure Fund (PTIF) to be spent over the next decade. Some of the details are in a backgrounder.

Funding allocations for the Toronto area are summarized in the table below. The amounts are based on transit ridership, not on population, and so Toronto gets by far the largest share of the pie.

Source: Infrastructure Canada Backgrounder

If one believed the ecstatic response of politicians and some media, one might think that all our transit prayers have been answered.

Not quite.

An additional $9 billion is not exactly small change, but Toronto has a huge appetite for transit spending and a daunting project backlog. The new money will help, but with it comes the requirement that Toronto pony up about $3 billion for projects that are not in the city’s long-term budget.

Capital planning for many years understated the infrastructure deficit by hiding projects “below the line” outside of the budget, and even more by leaving important work off of the list completely. The infrastructure deficit is much larger than the TTC reports and city financial plans indicate.

That, in turn, affects the city’s financial planning, subject of a recent report from the City Manager. Despite assurances from city staff that all known TTC costs have been included in their projections, there is a long history of the TTC leaving significant projects out of funding lists to keep their total “ask” down to a politically acceptable number.

Much needed work is not the sexy, photo-op rich stuff of subway extensions, but the mundane business of buying new equipment to replace old cars and buses, and to increase system capacity.

The new plan is to run for ten years. The money will not all land in Toronto’s hands this year, but will be parceled out as projects are approved and actual spending occurs. There is no guarantee that a future government will stick to any commitments especially if the “funded” projects are not the subject of a binding agreement. Toronto has its share of cancelled projects including the Sheppard Subway, cut back to Don Mills, and the Eglinton West Subway (both victims of Mike Harris), not to mention Transit City and the pliable attitude of various governments to the worth of a subway in Scarborough.

Updated March 16, 2018 at 3:25 pm:

Before we even start into the possible projects to be funded, some money is lopped off the top based on a past commitment.

  • Ottawa will provide “up to $660 million for the Scarborough Subway extension project, pending submission and approval”.
  • It is unclear how much of the provincial commitment to the SSE of nearly $2 billion is included in the $4 billion under the new program.

This brings the available federal funding down to about $4.237 billion.

Whether the total available from Queen’s Park is $6 billion ($4b new plus $2b for the Scarborough Subway), we do no know. I have a question in to the Ontario Ministry of Infrastructure to clarify this. They have acknowledged the question, but have not replied as of 11:45 am, March 16.

Update: The Ministry of Infrastructure has clarified how the previous SSE funding fits with the newly announced program:

Ontario is committed to cost-matching federal funding for municipal projects at 33 percent. This equates to $4 billion from the province to match the City of Toronto’s $4.9 billion federal allocation. No previously committed funding for Toronto projects is included in this allocation.

Ontario’s commitment to match this new federal funding at a 33 per cent share is separate from and above the province’s previous commitment of $1.48 billion in 2010 to the Scarborough Subway. [Email from Alex Benac, Press Secretary to the Minister]

Continue reading

TTC Board Meeting February 15, 2018

The TTC Board will meet on February 15, 2018. Among the items on the agenda are:

Scarborough Subway Extension (SSE)

The SSE itself is not on the agenda, but it has been the subject of much recent debate over when the projected cost and schedule for the extension will be released.

In the November 2017 CEO’s Report, the project scorecard included a schedule showing that 30% design would be complete in the second quarter of 2018, and an RFP [Request for Proposals] would be issued in the third quarter. Even when this report came out, former CEO Andy Byford was hedging his bets about a spring 2018 date saying that more work would be needed to verify and finalize the figures. A key note in this scorecard states:

EFC [Estimated Final Cost] was approved in 2013 based on 0% design. With the alignment/bus terminal now confirmed by City Council, the project budget and schedule will be confirmed as design is developed to the 30% stage, factoring in delivery strategy and risk. The performance scorecard will continue to report relative to the project’s original scope, budget and schedule, as approved by Council in 2013, until the project is rebaselined at the 30% stage in late 2018.

In other words, neither the schedule nor the projected cost reflected the evolving and expanding design of this project.

Jennifer Pagliaro in the Star wrote about the result of a Freedom of Information Request that revealed a briefing to Mayor Tory in September 2017. That briefing included a statement that the cost estimate for a Stage 3, 30% design, would be available in September 2018.

Because Council will not meet until 2019, numbers that might have been available before the election would not be released until after the new Council takes office. After the story appeared, City staff replied:

The cost information referenced in page 9 of the October TTC briefing deck refers to the planned timing for initial cost inputs from TTC engineering staff. These are not the full cost estimates necessary for consideration by Council. Further work will be required to appropriately account for financing, procurement model, market assessment and other critical factors. The final cost estimate, subject to the variability ranges noted below, will include these inputs.

This additional work will be undertaken by various TTC staff as well as city officials from corporate finance, financial planning, city planning and other divisions. [Tweet from Jennifer Pagliaro, February 7, 2018]

I wrote to the TTC’s Brad Ross about this conflicting information, and particularly about the question of how an RFP could be issued in 3Q18 when Council would not be approving that the project pass beyond “stage gate 3” until 2019. He replied:

No RFP will be issued until after Council approval. You will note in the Key Issues and Risks section of the scorecard from November reads, “The performance scorecard will continue to report relative to the project’s original scope, budget and schedule, as approved by Council in 2013, until the project is rebaselined at the 30% stage in late 2018.”

To be consistent with the report to Council in March 2017, only the revenue service date was revised in the scorecard (from Q4 2023 to Q2 2026). The TTC recognizes and acknowledges that this has led to confusion. The TTC will be taking steps to ensure greater clarity in its next CEO Report in March 2018. [Email of February 9, 2018]

The February CEO’s report states:

Work continues to progress design towards Stage Gate 3, expected in fall of 2018. At this time, the project will provide initial cost inputs from the TTC team (includes detailed costs for the Scarborough Centre station, tunnel, Kennedy station, systems, property and utilities). Further work is underway by the new Chief Project Manager with key stakeholders within TTC and the City to define the activities, approval process and timelines to arrive at the final Class 3 Cost Estimate, Level 3 Project Schedule, and associated Risk Analysis.

As requested by City Council, a report will be presented at the first opportunity to the Executive Committee, TTC Board and City Council, which is expected to be Q1 of 2019. [pp 15-16]

The debate, as it now stands, is about releasing whatever material will be available in September 2018 so that it can inform the election debates. Additional costs as cited by the city would sit on top of the September numbers, but at least voters and politicians would know whether the SSE’s cost has gone up just for the basic construction, let alone factors related to financing and procurement that would be added later.

Meanwhile, SSE promoter Councillor Glenn De Baeremaeker speaking on CBC’s Metro Morning said:

I don’t think it matters what the costs are.

This has been taken to read that money is no object, and that well may be the political reality in Scarborough – there is no way the many politicians who have so deeply committed to the subway project can back out. De Baeremaeker continued:

Whether the costs go up or the costs go down, people who have tried to sabotage the subway and stop the subway, will continue to try to sabotage it, they’ll continue to try to stop it, and they will never vote for it. So I would challenge the Councillors who say “I want to see the cost”. My response is and if it’s a reasonable cost, will you support the subway? Well, no. [At 3:26 in the linked clip]

What De Baeremaeker does not address is whether he has an upper limit beyond which even his enthusiasm might be dimmed. Also, on the question of a “reasonable cost”, what has been lost here is the fact that the subway “deal” was sold on the basis that the $3.5 billion included the Eglinton LRT extension to UTSC Campus. What had been a $2 billion-plus subway when it was approved as a compromise by Council, quickly grew to $3 billion-plus, and the LRT extension is left to find alternate funding. One could reasonably ask whether the LRT was ever really part of the deal, or was simply there as a sweetener that pulled in wavering supporters who now see just how gullible they were.

A related issue that has not yet surfaced is the question of whether building the SSE for a 2026 opening will require concurrent changes in timing and/or scope for the planned renewal of the Bloor-Danforth subway including a new signalling system and fleet. A report on the renewal is expected in April 2018, although this date has changed a few times over past months. The TTC/City capital budget and ten year plan do not reflect this project, at least with respect to timing, and probably with respect to total cost.

Continue reading

SmartTrack Update: More Questions Than Answers (October 13 Update)

For the coming three evenings, October 10-12, the City of Toronto, Metrolinx and the TTC will host open houses to present and discuss plans for six new SmartTrack and two new GO Transit stations. Although material for all stations will be part of each event, stations “local” to each site will receive more emphasis than others.

Each meeting will run from 6:30 to 8:30 p.m., with a presentation at 7 p.m.

  • Tuesday, October 10, Scarborough Civic Centre, 150 Borough Dr.
  • Wednesday, October 11, Riverdale Collegiate Institute, 1094 Gerrard St. E.
  • Thursday, October 12, New Horizons Tower, 1140 Bloor St. W. (new location)

Note: The location of the Oct. 12 meeting has been changed and it is now across the street from the originally announced site (which was Bloor Collegiate).

Updated October 11 at 10:30 pm: There continues to be confusion about just what “SmartTrack” service will look like, and this is not helped by the City’s presentation. Details can be found in the June 2016 Metrolinx report. For further info, see the update at the end of this article.

Updated October 13 at noon: Metrolinx has confirmed that the Barrie corridor trains will operate through to Union Station, not terminate at Spadina/Bathurst Station as I had originally thought. However, the operational details have not yet been worked out. For further discussion, scroll down to the section on the Spadina/Bathurst Station.

I attended a media briefing that covered the materials to be presented and the following article is based on that briefing which was conducted by City of Toronto staff. Illustrations here are taken from the deck for the media briefing which is available on the City of Toronto’s site. Resolution of some images is constrained by the quality of data in the deck.

[In the interest of full disclosure: A “Stakeholder Advisory Committee” (or SAC) has already been meeting on this, and I was invited to participate, but declined given my concern with a potential conflict between “advisory” and “journalist/commentator” roles. It is no secret that I believe SmartTrack is a deeply flawed concept. Its implementation is compromised by fitting a poorly-conceived election promise into a workable, operational scheme for the commuter rail network. Any “debate” is skewed by the need to pretend that this is anything beyond campaign literature.]

The intent of these three meetings is to conduct the first detailed conversation about these stations with the general public. Early designs appeared in the “Initial Business Case” for the stations, but these have been revised both for technical and for philosophical reasons. Specifically:

  • The City does not want to build traditional GO stations dominated by parking.
  • The interface between the new stations and the transit network (both rapid transit and surface routes) should be optimized.
  • Strong pedestrian and cycling connections are required.
  • Stations should be close to main streets.
  • Stations should support other City objectives such as the West Toronto Railpath and parallel projects such as the St. Clair/Weston study now in progress.
  • Transit-oriented development should be possible at stations.

This is a list that to a typical GO Transit proposal in the 905 would be unrecognizable. GO Transit’s plan ever since its creation has been to serve auto-based commuting first and foremost with ever larger parking structures that poison the land around stations. Local transit was something GO, and later Metrolinx, simply “didn’t do”, and the idea that Queen’s Park might fund strong local transit as a feeder to GO services has been limited to co-fare arrangements.

The situation within Toronto is very different, and there are connecting routes on the TTC that individually carry a substantial proportion of the daily ridership of the entire GO network. Moreover, if GO (or SmartTrack, whatever it is called) will be a real benefit to TTC riders, then the process of getting people to and from stations must not depend on parking lots that are full before the morning peak is even completed.

The new stations will go into existing built-up areas, not into fields with sites determined primarily by which well-connected developer owns nearby property. Residents will be consulted about how these stations will fit their neighbourhoods, how they will be accessed, and what might eventually become of the community and future development.

A big problem facing those who would present “SmartTrack” to the public beyond City Hall insiders and neighbourhood activists is that almost nobody knows what SmartTrack actually is. This is a direct result of Mayor Tory running on a design that could not be achieved, and which has evolved a great deal since he announced it in May 2014. In brief, it is three GO corridors (Stouffville, Lake Shore East and Kitchener) plus an Eglinton West LRT extension, but this differs greatly from what was promised in the election.

Service levels for SmartTrack are described as every 6-10 minutes peak, with off-peak trains every 15, but this does not necessarily match Metrolinx’ announced service plans for their GO RER network onto which SmartTrack is overlaid. The idea that there would be extra SmartTrack trains added to the GO service was killed off in 2016 in the evaluation of possible operating modes for the corridor.

Fares on “SmartTrack” are supposed to be “TTC fares”, but this is a moving target. Voters understood the term to mean free transfer onto and off of SmartTrack trains as part of their TTC fare, but with all the talk of regional fare integration, it is far from clear just what a “TTC fare” will be by the time SmartTrack is operating.

Even that date appears to be a moving target. City Staff referred to 2025 when GO RER would be fully up and running as the target date for “integration”, but Mayor Tory still speaks of being able to ride SmartTrack by 2021 while he is presumably still in office to cut the ribbon.

At the briefing, many questions arose from the media, and the answer to almost all of them was “we don’t know yet”. It is clear that the Mayor’s plan has not proceeded beyond the half-baked stage, and many important details remain to be sorted out.

  • What is the status of Lawrence East Station and how does it fit with the recently announced review of this (and Kirby) stations by the Auditor General?
  • How will an expanded GO/ST presence at Lawrence East co-exist with the SRT which will operate until at least 2025, if not beyond to whenever the Scarborough Subway opens?
  • What are the arrangements for City/Province cost sharing on the stations, especially since Lawrence East was originally to be a GO station, but its future as such is unknown?
  • What will be the cost of the new stations once design reaches a level where the numbers are credible? The range of $700 million to $1.1 billion has not been updated since the matter was before Council.
  • Will all stations on the SmartTrack corridor honour ST fare arrangements regardless of whether this is a city-built station under the ST banner?
  • Why should GO riders who are not on the SmartTrack corridor pay regular GO fares, while those using the ST route have a “TTC fare” for their journey? The most obvious contrast in this case is between the existing Exhibition Station on the Lake Shore corridor and the proposed Liberty Village Station on the ST/Kitchener corridor, but there are many others.
  • What service levels will be provided, and how will they affect projected demand at the stations? Were previously published estimates based on more ST service than Metrolinx actually plans to  operate? How will constraints at Union affect the ability to through-route service between the Stouffville to the Weston/Kitchener corridors?
  • If the City wants more service than Metrolinx plans (assuming it would even fit on the available trackage), how much would Toronto have to pay Metrolinx to operate it?
  • Where are the residents and jobs that are expected to generate ST demand, and how convenient will access to the service actually be considering walking time, station geometry (stairs, tunnels, bridges, etc) and service frequency?

The stations under consideration are shown on the map below. A common question for all of these locations will be that of available capacity on the GO trains that will originate further out in the corridor. Without knowing the planned service design for “GO” trains and “SmartTrack” trains, it is unclear how often, if at all, there will be short-haul ST trains originating within Toronto as opposed to longer-haul GO trains from the 905. The availability of space on trains could affect the perceived service frequency if people cannot board at stations near Union (just as long-suffering riders of the King car complain about full streetcars).

Updated October 10, 2017 at 10:30 pm

After I posted this article, I realized that there was an important part missing, a commentary on the “consultation” process  itself.

A big problem with many attempts to seek public input is that the wrong question is posed, and factors are taken as given when they should be challenged. In the case of SmartTrack, the basic question is “why do we have SmartTrack at all”.

The original scheme was essentially a real estate ploy to make property in Markham and south of the Airport more valuable by linking both areas with a frequent rail service to downtown. Reverse commuters were a big potential market for this service. In the course of becoming part of the Tory election campaign, the focus turned inward, and SmartTrack became the line that would solve every transit problem. The claims about service frequency, fares and integration with other local and regional service were complete fantasies, but they gave the impression that Tory “had a plan” as distinct from the bumbling proposals of his opponent, Doug Ford, and the lackluster efforts of Olivia Chow. Tory even got professionals to declare his scheme a great idea, one giving it an “A+” on CBC’s Metro Morning, but this was for a version of SmartTrack that was unbuildable.

Now, over three years later, we are still faced with the myth that SmartTrack is a real plan, that it is anything more than what GO Transit would have done in the fullness of time. We are, in effect, being asked about the colour of tiles in stations when we should be asking whether the stations should even be built at all. There is no guarantee that service can be overlaid on GO’s existing plans to provide anywhere near what was promised in the campaign – a “surface subway”. Metrolinx has been quite firm on the subject, and going to the frequencies assumed by ST advocates would be well beyond the infrastructure we are likely to see on GO corridors.

The City will conduct its consultations, but the hard question – Why SmartTrack? – will never be asked.

For the October 11 update, please scroll to the end of the article.

Continue reading

A Contrary View of Ontario’s 2017 Budget

With the release of Ontario’s budget for 2017, City Hall launched into predictable hand-wringing about all the things Toronto didn’t get with the two big-ticket portfolios, transit and housing, taking centre stage. Claims and counterclaims echo between Queen Street and Queen’s Park, and the situation is not helped by the provincial trick of constantly re-announcing money from past budgets while adding comparatively little with new ones.

There was a time when budgets came with projections of three to five years into the future, the life of one government plus some promise of the next mandate, but over time the amounts included within that period simply were not enough to be impressive. Moreover, in a constrained financial environment, much new spending (or at least promises) lies in the “out years” where “commitment” is a difficult thing to pin down, especially if there is a change in government.

Toronto has “out year” problems, but it has even more pressing concerns right now, today and for the next few years. Very little in the provincial budget addresses this beyond the authority to levy a hotel tax, and a gradual doubling of gas tax grants for transit over the next five years. These add tens, not hundreds, of millions to a City budget that runs at $12 billion.

The transit tax credit for seniors will cover eligible public transit costs beginning in July 2017 with a refundable benefit of 15 percent. Whether all seniors actually deserve this credit is a matter for debate, but an important difference from the soon-to-disappear federal credit is that Ontario’s is “refundable”. This means that even if someone does not have enough income to pay tax, they can still receive the credit. The devil is in the details, however, and the degree to which this will be available to casual, as opposed to regular transit users remains to be seen. The term “eligible costs” is key. (The federal credit includes restrictions on eligibility.) In any event, a tax credit does nothing for transit budgets because it adds no revenue either directly to the transit agency or to the City which provides operating subsidies.

There are two major problems with both Ontario’s support for transit and Toronto’s politically-motivated budgets:

  • In both cases, the focus is on capital projects, building and buying infrastructure, with little regard for the cost of operating new and existing assets.
  • Past decisions on transportation spending have locked billions of dollars into a few projects for short-term political benefit at the expense of long-term flexibility.

Toronto perennially assumes that there will be new money somewhere to backfill the shortage in its capital budget. The Trudeau economic stimulus plan was the most recent magical relief Toronto expected, but it came with dual constraints: Toronto gets a fixed amount over the life of the program, and Ottawa will not contribute more than 40% to any individual project. Toronto had hoped that Ontario would chip in, possibly at the 30% or even 40% level, leaving the City with a manageable, if challenging, task of finding money to pay its share for the backlog of projects. The Ontario budget is quite clear – Toronto is already getting lots of provincial money and at least for now, there’s nothing new to spend.

Ontario is hardly innocent in this whole exercise having meddled for years with Toronto’s transit plans, most notoriously in Scarborough where the whole subway extension debate was twisted to suit political aims. After leading Toronto down the garden path on the SSE, Ontario has capped its project funding leaving Toronto to handle the cost of its ever-changing plans.

Queen’s Park loves to tell Toronto how much provincial money is already spent for Toronto, if not in Toronto, and the distinction gets blurry. GO Transit improvements, for example, will bring more service into Toronto benefiting the core area business district, but they will also improve commuting options for people outside of the City itself.

Before the fiscal crash of 2008, when Ontario was running surpluses, the typical way to handle project funding was to hive off surplus funds at year end into a trust account. That is how the provincial share of the TYSSE was handled. By contrast, Ottawa operates on the pay-as-you-play basis, and only turns over subsidies after work has been done. Each approach suits the spending and accounting goals of the respective governments. In a surplus situation, one wants the money “off the books” right away, but in a deficit, the spending is delayed as long as possible. Further accounting legerdemain arises by making the assets provincial to offset the debt raised to pay for them.

To put all of this into context, here is a review of projects proposed or underway in Toronto.

Continue reading

TTC Board Meeting April 20, 2017 (Updated)

The TTC Board will meet on April 20, 2017. Items of interest on the agenda include:

  • The monthly CEO’s Report
  • Repair of SRT Vehicles
  • Disposition of Bay Street Bus Terminal

This article has been updated with a commentary on subway and surface route performance statistics presented at the Board meeting. (Scroll down to the end of the CEO’s Report.)

Continue reading

Scarborough’s New/Old Transit Map

In all the talk about the Scarborough Subway and SmartTrack, there has been much less discussion of how the surface route network will be adjusted around the new lines. In preparation for Council’s upcoming debate on the SSE, the TTC has produced a map of the proposed bus network following the subway opening. Here are the current and proposed maps for comparison (click to expand).

Many of the routes on this map are unchanged from the current network which is already built around the Town Centre and Kennedy stations.

What is quite striking, however, is the complete absence of services dedicated to existing GO and potential future SmartTrack stations that are supposed to be an integral part of a future Scarborough Network. Inclusion of connecting service to those stations would presume, of course, that ST will actually operate as advertised with frequent service and free transfer to and from TTC routes. There is also no Eglinton East LRT to the UTSC campus.

Looking at the map, and the degree to which “all roads lead to STC”, shows the effect of having a major “mobility hub” in the middle of Scarborough. If that’s where you want to go, there is a bus route to take you there. Other travel patterns can be more challenging, especially if the peak service hours are designed for downtown-bound commuters.

Rearranging the network to feed into SmartTrack would require some work, and it is unclear if multiple hubs could actually co-exist. However, SmartTrack is planned to open five years before the SSE, and will trigger its own interim changes. Without really intending to, the TTC has given us a view of Scarborough transit that is uncomfortably closer to what might actually be built than many, certainly Mayor Tory and his circle, would care to admit.

Meanwhile, the SSE does not bring the same degree of change to the surface transit network as might occur in other areas because STC is already a major transit node. Indeed, the TTC could introduce new and revised routes long before the subway opens in 2026.

[The information in this article is taken from a compendium report in the TTC’s upcoming Board Meeting agenda at pp. 129-130. Routes and names shown are, at this point, only proposals and are subject to refinement.]

Proposed Changes
9 Bellamy Warden Stn to STC Unchanged
16 McCowan Warden Stn to STC Unchanged
21 Brimley Kennedy Stn to STC Unchanged
38 Highland Creek Rouge Hill GO to STC Unchanged
39A Finch East Finch Stn to Morningside Hts Branch rerouted and extended
199 Finch Rocket Finch W Stn to STC Unchanged
42 Cummer Finch Stn to Morningside Hts Extended
43B Kennedy via Progress Kennedy Stn to STC Unchanged
53 Steeles East Finch Stn to Morningside Hts East end loop revised
53E Steeles East Express Replaced by 253 Steeles Rocket
253 Steeles Rocket Pioneer Village Stn to STC New route
54 Lawrence East Science Ctr Stn to Starspray Base route unchanged
154 Lawrence East Kennedy Stn to UTSC Orton Pk service replaced and extended
254 Lawrence East Express Science Ctr Stn to Starspray via Kennedy Stn Replaces 54E express. Link to Kennedy Stn added.
57 Midland Kennedy Stn to Steeles Loop at Steeles revised
85 Sheppard East Don Mills Stn to Rouge Hill GO Supplemented by 285 Sheppard E Rocket
285 Sheppard East Rocket Don Mills Stn to UTSC via STC New route
86 Scarborough Kennedy Stn to Zoo Unchanged
93A Ellesmere East STC to Kingston Rd Replaces 95A York Mills east of STC. Route number already in use by 93 Parkview Hills.
93B Ellesmere East STC to Conlins Rd Replaces 95A York Mills east of STC and 116A Morningside Conlins Loop
95 York Mills York Mills Stn to STC Partly replaced by 93 Ellesmere East and 295 York Mills Express
295 York Mills Express York Mills Stn to UTSC via STC New route
102 Markham Rd Warden Stn to Steeles North end loop structure simplified
202 Markham Rocket Warden Stn to Centennial College New route
116 Morningside Kennedy Stn to Steeles Extended to Steeles & Markham Rd. Service via Guildwood replaced by 153.
153 Kennedy Stn to Beechgrove New route replacing 116 Guildwood service
129 McCowan North STC to Steeles Express service provided by 253, 199 and 285 Rockets
130A Middlefield STC to Steeles Route and loop from McNicoll to Steeles revised
130B Middlefield STC to Tapscott Route consolidates existing peak period loops of 42, 53, 102, 134
131 Nugget STC to Old Finch Service to Kennedy Stn replaced by subway
132 Milner STC to Hupfield/McClevin Unchanged
133 Neilson STC to Morningside Hts Unchanged
134A Progress STC to Finchdene Unchanged
134B Progress STC to McNicoll Discontinued, partly replaced by 130B
134C Progress STC to Centennial College Unchanged
169 Huntingwood Don Mills Stn to STC Unchanged