At its meeting on February 28, the TTC Board will receive a report summarizing the status of most of the rapid transit plans in Toronto. This article condenses the TTC report and reorders some sections to group related items together.
Dominant among many projects are, of course, the “big four” provincial projects: Ontario Line, Scarborough Subway, Yonge North Subway, and Eglinton West LRT extension.
Project Status Overview
The effect of major projects elbowing everything else aside is clear in the table below. Some projects do not have in service dates because they are not funded, and the timing of that (when and if it occurs) will determine when various lines can open.
Not shown in this table are several major projects that pop up from time to time:
- Bloor-Yonge Station Expansion
- Waterfront West LRT from Dufferin to The Queensway
- Bloor West subway extension
- New Line 2 fleet and yard at Kipling (Obico yard property)
- Sheppard East subway extension
- Platform Edge Doors
Of these, only the Bloor-Yonge project has funding, and some are only a glimmer in various politicians’ eyes.