Reconstruction of Dundas & Parliament Streets

On Monday, May 15, the TTC began demolition of the intersection of Dundas & Parliament for complete replacement of the special work. By the morning of Saturday, May 20, most of the new track was in place although much of the concrete pour remains to be done as well as installation of the approach tracks connecting the neighbouring tangent rails to the intersection.

Continue reading