Toronto Deserves Better Transit Service Now! Part 4: Streetcar Riders Count Too

Much discussion of improved service has talked about bus riders in the suburbs who have long trips and whose bus routes lost peak service when the crowding standards were rolled back in 2012.

Peak period crowding standards had never been improved for streetcars because there were no spare vehicles, and so there was nothing to roll back. However, over past decades, that shortage of streetcars limited peak service in a way that the bus system didn’t have to deal with.  This was compounded by two factors:

  • The TTC opened a new Spadina-Harbourfront line without increasing the fleet.  This was possible because service cuts on the early 1990s left Toronto with “spare” streetcars.
  • The project to buy new streetcars dragged on for years thanks both to the embrace of 100% low floor technology, and the obstructions posed by Mayor Ford to streetcar and LRT plans in general.

Between 1998 and 2014, the total number of streetcars scheduled for the peak periods has risen only 10%, and there is no headroom for further growth with the existing fleet. Indeed, service quality is compromised by vehicle failures, and the scheduled service may not all get out of the carhouse.

This year, the TTC will finally take delivery of the first “production” vehicles in its new fleet, and claims that service will operate as of August 31, 2014 on 510 Spadina with the new cars.  Whether the line will convert 100% to the new fleet in one go remains to be seen.

The TTC Fleet Plan contains no provision for improving service on any streetcar route beyond the higher capacity that new cars will provide. This will come only as the new fleet rolls out line-by-line and some routes will wait until late this decade to see more capacity (and even then with less frequent service).  Existing cars would be retired at a rate that matches or exceeds the new fleet’s ability to replace service, and would also eliminate any spare capacity for growth on lines running older cars.

This is what passes for responsible planning in an organization that claims a dedication to “customer service”.

This article looks at each streetcar route in turn and at a possible revised fleet plan that would make provision for short term improvements as the new fleet arrives.

Continue reading

Streetcar System News: March 2014

On March 11, 2014, photos of car 4401 on training runs appeared in at least two locations:

  • St. Clair & Yonge on Torontoist
  • Spadina south of Adelaide on Twitter (Photo by Kyle Baptista @kylebap)

Delivery of the first production car, 4403, has been delayed until late April according to the TTC’s Brad Ross, but the rate of production can be ramped up by Bombardier.  In any event, 510 Spadina will operate with new cars effective August 31, 2014.

Meanwhile on Queens Quay, construction of the new streetcar right-of-way and the permanent north roadway is expected to begin later in March depending on the weather.  Work will begin west from Lower Simcoe to Rees, a section where utility work is completed and traffic can be shifted to the south side of the road.  West of Rees, installation of sewers is still underway.

Preliminary overhead work has been done at the exit from Queens Quay Loop, and work is also underway at the King/Spadina intersection.  During brief spells of warm weather, track within the loop was set in concrete.

TTC Board Meeting Followup: February 24, 2014

The TTC Board met on Monday, February 24.  In an earlier article, I gave a preview of issues from the agenda.  This post reports on some of the debate and follow-up information from the meeting.

This was the first meeting under new Chair Maria Augimeri, and it was noteworth for the amount of actual discussion that took place.  The four citizen members, who at one point were a majority of Commissioners actually present, participated at some length with pointed questions.  One can only guess the degree to with former Chair, now mayoral hopeful Karen Stintz, ran tightly scripted meetings that were all about good news with little or no dissent or disruption.

Continue reading

Metrolinx Contemplates Relief (2)

This article is a continuation of a previous commentary on the Metrolinx Yonge Network Relief Strategy.

On February 14, 2014, the Metrolinx Board considered the presentation on the Yonge Network Relief Study, but little information was added in the debate.  One question, from Chair Robert Prichard, went roughly “shouldn’t this have been started two years ago”, but it was left hanging in the air without a response.  Two years, of course, has brought us a new Provincial Premier and a recognition that her predecessor’s timidity on the transit file wasted a great deal of time.

Moreover, there is a long overdue acknowledgement that Metrolinx cannot simply plan one line at a time without understanding network effects including those beyond its own services.

Originally, I planned to leave the next installment in this discussion until public consultation sessions began, but I have now decided to make some brief comments on the various options that will be on the table.  (See Yonge Network Relief Study, page 11.)

Continue reading

Streetcar System News – February 2014 (Updated)

Updated February 11, 2014 at 10:00 am:  Questions & answers related to trackwork plans and new streetcars have been added.

Spadina / Queens Quay Update

To nobody’s great surprise, the restoration of streetcar service south of King Street on Spadina will not occur until June 21 rather than with the schedule change in late May as originally hoped. This is a direct result of the bad weather and poor construction conditions. The TTC’s position is:

Due to the delays in Waterfront Toronto’s work and the need for TTC work to follow in series (i.e. overhead), it is not anticipated that the loop will be available for service for the May Board Period. Once we have greater clarity, we will reflect that online.

Some preliminary work on suspension for the new overhead has already been done, but this cannot be completed until the track is in and overhead vans can drive on the new pavement at the loop.

As plans now stand, service will resume on both the 510 Spadina and 509 Harbourfront routes with the re-opening of new streetcar track on Queens Quay rather than in two stages as originally hoped.

I await detailed info from Waterfront Toronto on updates to their construction plans. Much of the utility work on the south side of Queens Quay is now completed, and traffic is shifting to that side of the road at least as far west as Rees Street. This move will allow work to begin on the new streetcar right-of-way in the middle of Queens Quay and the construction of the new permanent roadway on the north side.

Detailed construction news updated weekly is available on Waterfront Toronto’s Queens Quay project page.

No sooner will streetcar service resume on southern Spadina, but the route will convert to bus operation for two track projects likely in August. The intersection at Dundas will be rebuilt this year (the one at College has been deferred because of scheduling conflicts), and there will also be work at Spadina Station.

When the line reopens on August 31, service will be provided, at least in part, by the new low-floor streetcars.

Updated February 11, 2014:

Q: What work is planned at Spadina Station? Track? Platform – especially provision so that two new cars can be on the platform at once – one loading, one unloading. Only 3 CLRVs fit there today.

A: The TTC has placed two low floor streetcars at Spadina already. They can physically fit inside the station, although the lead module of the lead car would have to be positioned opposite the five pillars with glass curtains, and that the lead door would be on curved track with a wider gap between the vehicle and the platform. We are reviewing operating procedures and possible alterations that are necessary to allow two new cars to be on the platform at the same time if necessary.

This implies that the work to be done in August will be trackwork, not platform changes.

New Streetcars

Recently, I sent questions to the TTC about the status of new car production and the implementation of these vehicles. Here are the replies:

Q: What is the status of the order and when will production deliveries begin?

A: Production deliveries will begin in March.

Q: What will be the rate of deliveries?

A: As always planned, there will be a ramp up to the production rate of 3 per month (36 per year). Once stabilized at this rate there are opportunities to transition to a higher rate and this is currently under investigation.

Q: What effect will this have on planned retirement of the problem ALRVs before the next winter season?

A: ALRVs will begin retirement at the end of this year and throughout 2015 as more new streetcars enter service.

What is still unclear is how the TTC will adjust service on 504 King and 501 Queen as the ALRVs [the existing two-section streetcars] disappear from the fleet and these routes continue operation with the remaining CLRVs [the shorter, single-section cars].

Updated February 11, 2014:

Q: Are there outstanding issues still to be dealt with on the ramps in the new streetcars, or have whatever design tweaks were necessary been incorporated in the production versions we will receive?

A: There are still a number of outstanding issues to be resolved. The production vehicle will have the necessary structural changes made to receive the new ramps. However, there is a transition phase between cars going into revenue service and when the final version of the ramp is delivered. For a number of vehicles that will go into service, an interim ramp will be incorporated to improve on accessibility – with improved transition between the ramp, the door threshold and the interior car floor. The final production version will be lighter in weight, less demanding on the drive mechanism (hence more reliable), and will have faster deployment and retrieval times. Initial production cars that do not have the latest ramp configuration will be retrofitted with the final version as part of the configuration control process.

Capital Budget Cuts

Among the City-imposed cuts in the Capital Budget was a $10-million/year cut in surface track maintenance for 2014 to 2018 with an equal cut to subway track in 2019 to 2023. I asked about the effect of these cuts.

State of good repair, which track replacement is clearly part of, will not be affected. If we need to further cut the capital budget to do track work, we’ll find that money elsewhere.

Queen East Major Track Projects

Two major projects will affect streetcar service on Queen Street East this spring.

At Queen and Leslie, the new sewer line must be tied into existing infrastructure under Queen Street, and then the new special work for the track leading to Leslie Barns must be installed.   Tentative plans are for this work to begin in mid-May and run to the end of June.

While Queen Street is closed, service will operate with bus replacements and streetcar diversions:

  • A 501 Queen bus will run from McCaul Loop to Woodbine Loop (at Kingston Road) diverting around construction via Jones, Dundas and Greenwood.
  • 501 Queen, 502 Downtowner and 503 Kingston Road Tripper streetcars will divert via Broadview, Gerrard and Coxwell.
  • Carhouse trips for 504 King and 505 Dundas that now operate west from Russell Carhouse via Queen will use Coxwell and Gerrard.

Beginning at the end of June and running through July, the special work at Broadview and Queen will be replaced. This intersection is in poor condition with long-standing slow orders and one switch (west to north) permanently out of service due to a danger of derailments.

During this work, service will operate as below:

  • The 501 Queen bus will divert via River, Dundas and Carlaw.
  • 501 Queen, 502 Downtowner and 503 Kingston Road Tripper streetcars will divert via Parliament, Gerrard and Coxwell.
  • 504 King cars will divert via Parliament and Dundas.
  • Carhouse trips to Russell will continue to operate via Coxwell.

Normal service on all routes resumes in August.

King Street Diversion

New February 11, 2013:

Q:  The 504 King diversion around construction at the Don Bridge is now listed as running to August due to additional work in the area.  I understand that the track connection at Sumach to the new Cherry Street line is to go in this year.  Will this be done while the 504 is on diversion (ie before August), or will there be yet another shutdown for this trackwork too?

A:  The Sumach/King connection work is scheduled for March 30.

Transit Priority for Diversions:

Q:  With the extended period of various diversions, why has there been no change to implement transit priority or at least advance greens for left turns at various locations?

A: We continue to work with the City on transit priority signalling. There are no new installations to date; where there, they are in use. Advance greens and the like is a question better put to the City.

I am meeting with Stephen Buckley, Toronto’s General Manager of Transportation Services, on February 12 and will discuss this issue with him.

[TTC comments provided by Brad Ross via email on February 7, 2014.  Updates by email on February 11, 2014.]

Poor Frozen Streetcars

Over the past week, we have heard a lot about streetcars that were stuck in the yard or failed in service because of frozen air lines.

If the air isn’t dry, moisture condenses and freezes, blocking air movement.  Whatever system that air line runs – such as releasing the brakes – stops working, and the streetcar is stuck just as if it were frozen to the rails.  Think of this as sclerosis for streetcars.

Drying the air has been an issue for the streetcar fleet more or less since it was delivered 30 years ago, and the problem is worse on the long ALRVs than on the shorter, and older, CLRVs.  One can only wonder if this is yet another subsystem where the TTC gambled that things would keep running until new cars arrived.

They lost.

Record cold weather meant anything that was borderline temperature sensitive has failed, and riders have seen the effects.

The new cars are over a year late.  If the wait means they work perfectly “out of the box” I will be ecstatic – the Toronto Rocket subway trains have not exactly inspired confidence in Bombardier.

The partial replacement of streetcars by buses led inevitably to musing by Councillor Doug Ford that maybe we should just make this a permanent arrangement.  The Ford family is well known for looking for any excuse to rid Toronto of what they see as a nuisance.

This begs two very important sets of questions for the TTC and its current chair, Karen Stintz.  Will they rise to the streetcars’ defence not just for the short, post-deep-freeze, but for their long-term future?

Continue reading

TTC Capital Budget 2014-2023 Part II: Streetcar Infrastructure

The TTC 2014-2023 Capital Budget contains a great deal of streetcar infrastructure work over coming years.  Broadly, this can be subdivided into three types of project:

  • Catching up with inferior maintenance of past decades to bring the system to a “steady state” condition where each year’s work is commensurate to the scale of the network and industry norms for the lifespan of assets .
  • Changes to support the new low floor LRVs including Leslie Barns, conversion to pantograph power collection, and updating other infrastructure such as power supply and track switching.
  • System expansion.

Although some of this looks ambitious on paper, the plans are threatened by capital availability at a level well below what is needed.  The TTC has other demands on a shrinking capital pool, notably on the subway system.  Combined with the City of Toronto’s self-imposed limits on debt levels and taxes and the expiry of various provincial and federal funding programs, there is insufficient capital to maintain the system.  The streetcar network takes a hit from this, but the details are not yet known.

I will explore the shortfall in capital funding in the next article of this series.  Meanwhile, the plans discussed here should be read in the context that the City Budget, as now written, seeks a reduction in various line items of the TTC’s Capital Budget.  How this will fare at Council remains to be seen.  The two biggest problems are the lack of details of where cuts will fall and their effect, and the abdication of responsibility for advocacy by TTC Board members and senior management.  “We will muddle through somehow” is not an inspiring call to battle.

Continue reading

TTC Capital Budget 2014-23 Part I: Fleet Plans (Or, Where Will We Put The Riders?)

The past two years at TTC and Council have been all about the fight over LRT and subways, and the shifting loyalty to each mode especially when potential votes are to be gained.  While Toronto (and Queen’s Park) flailed about with expensive rapid transit plans, something more important, but more subtle, off the radar, was happening.

Discussion of the future of our transit fleet and service levels later this decade took a back seat in the triumph of ideology over planning.  We are now in a position where all three modes — subway, streetcar and bus — will strain to meet demands placed on them for the foreseeable future.  We will have very clean subway stations, but service and capacity are quite another matter.

The problems for each mode are different.

Continue reading

TTC Board Meeting Wrapup for July 24, 2013

The TTC Board met on July 24, 2013, with a rather threadbare agenda.  The most important item discussed — a proposal for a new Downtown Relief Line on GO corridors — wasn’t even on the agenda.  It was walked in by Chair Karen Stintz, proposed as a report request and voted on with almost no debate near the end of the meeting.

Included in this wrapup:

  • Steeles West Station gets a new name (again)
  • Evaluation of contract bids
  • Bixi and the TTC
  • CEO’s Report
  • Trial Service Changes on 53 Steeles East and 95 York Mills
  • Implementation of New Streetcars (update)

Continue reading