Spadina Reconstruction News (Updated May 15, 2013)

Updated May 15, 2013 at 1:30 pm:

TTC CEO Andy Byford spoke at a meeting of the York Quay Neighbourhood Association yesterday evening and the status of transit service to Queens Quay was a major topic.  There appears to be some confusion among and within agencies about the date when service will return to Queens Quay on the 510 as a through route and as a streetcar.

The TTC Service Planning memo for the schedule period beginning June 23 says that the current operation is expected to last until the end of that period (late July).  However, Waterfront Toronto and Andy Byford himself speak of November or even December dates.  The TTC website has given June 2013 as a date for service resumption for quite some time, although this is to be corrected, presuming someone knows what the information should be.

Part of the confusion may arise from the fact that streetcar service will be suspended for reconstruction of the intersections at King and at Dundas and this will require bus replacement on the route.  Those buses will be able to run through to Queen’s Quay replacing the shuttle and so there will be “through” service, just not with streetcars.

I have asked the TTC for definitive information on the date for resumption of streetcar service to Queens Quay.

The Service Planning  memo also notes that a planned shutdown for reconstruction of the platform at Spadina Station Loop has been deferred to 2014.  One can only hope that this will include changes to allow two LFLRVs to serve the platform simultaneously for unloading and loading.

Continue reading

Downtown Traffic Operations Study

The City of Toronto is studying transportation in the downtown.  The study area is bounded roughly by Lake Shore Boulevard/Harbour Street, Queen Street, Jarvis Street, and Bathurst Street.  The scope extends just north of Dundas between University and Yonge.

The intent is to find short-to-medium term improvements that are possible:

… getting more out of the existing transportation infrastructure, in an attempt to make travel in the downtown less challenging and more efficient for all road users.

There will be an Open House for this study in the rotunda of Metro Hall (John Street south of King) on Wednesday, March 27 from noon to 9:30pm.  The study’s website includes a link to a short survey of travel patterns.

This post will be used as a repository for updates on the study as well as comments from readers.

York Street Construction News

The City of Toronto has issued a preliminary notice regarding the reconstruction of York Street from Wellington to Queen.

This will include pavement and sidewalk reconstruction, water main work, and the installation of new track.  This work includes replacement of the intersection at Queen & York, but not at King & York which is comparatively new.

Only the northbound track will be retained and, as I understand current plans, the special work at Adelaide Street will be removed.  If at a future date, the TTC decides to reactivate Adelaide Street from Charlotte east to Victoria, the York Street intersection will be dealt with at that time.

The City is studying Richmond and Adelaide Streets with a view to installing cycling lanes, and the reconstruction of Adelaide will depend on the design that emerges from this process.  A related issue is the ongoing construction of condos along Adelaide requiring curb lane occupancy and causing  damage to the road from heavy trucks.

Co-ordination with the Spadina & King project during August will be needed to ensure that there is one street clear for King and Queen services through downtown.

Past and Future Streetcar Service Capacity

Now that the first Low Floor Light Rail Vehicle (LFLRV) is rolling through Toronto streets on test runs, the question of service quality and capacity for streetcar routes is once again an issue.

The most recent TTC document setting out their intended use of the new fleet appeared in the 2013 Capital Budget Blue Books.  These are not available online, but I presented the TTC’s fleet plan in an article last fall.  From the numbers of vehicles to be assigned to each route, one can work back to the service frequency and capacity numbers.  In general, peak period headways get a bit wider, but the capacity goes up, in some cases dramatically.

The TTC faces two challenges: one on the budget, and one in operations.

Toronto Council has been extremely stingy with operating subsidies and “flat lined” the TTC over the past two budget cycles.  Hard liners will want the TTC to simply replace service on an equivalent capacity basis and maximize the savings in operator costs.  This would be a disaster for service quality even if the TTC actually ran cars on the headways they advertise.

On the operational side, any increase in headways brings even wider gaps when the service is upset by weather, random delays and short turns.  It is already a matter of record that the largest drop in riding over the past two decades came on the lines where 50-foot long CLRVs (the standard Toronto cars) were replaced by 75-foot long ALRVs (the articulated version) on an equivalent capacity basis.  Falling riding led to reduced service and the familiar downward spiral.  This must not happen when the new fleet rolls out across the system.

Since at least the mid-1990s, the TTC has told us that they cannot improve streetcar service because they have no spare cars.  In part, they are the victims of their own fleet planning.  The TTC originally rebuilt some of its old PCC cars (the fleet preceding the current one) in order to have enough to expand operations on the Harbourfront and Spadina lines.  However, by the mid-1990s, service cuts on many routes thanks to the economic downturn in that decade and the subsidy cuts by the Harris government, reduced the fleet requirements to the point where the PCCs could be retired and the Spadina line opened without buying any new cars.  When riding started to grow again, the TTC had no spare vehicles to improve service, and to make matters worse, the fleet was entering a period of lower reliability thanks, in part, to poor design.

Toronto waited a long time for new cars to be ordered, and this process was delayed both by the decision to go with all low-floor cars, and by political meddling at City Hall.  New residential construction along the streetcar lines pushes up demand, but the TTC cannot respond with better service until they have more cars.

Recent discussions about the new cars have included comments about how we cannot possibly have more streetcars on the road.  What many people forget is that the streetcar services were once much better than today.  In this article, I will look back at service levels once operated in Toronto, and at the service that we might see if the TTC actually operates the new fleet in the manner their Fleet Plan claims.

Continue reading

Looking Back: Services to the CNE

With all the recent talk about Ontario Place, and with Exhibition season almost upon us, I thought this would be a good excuse for photos of streetcar services to the Ex.  Decades ago, the CNE raised much bigger crowds and there was a time it really was a showcase, an “exhibition”.  I remember when the “Better Living Centre” was brand new, and its intent was to give fairgoers a look at all that was new and exciting in household goods.  The Internet didn’t exist yet, and the phenomenon of the shopping mall full of goods manufactured anywhere but here was in its infancy.

The TTC ran many streetcar services into the Ex over the years, and parades of cars would leave the grounds following the evening fireworks.  (Transit Toronto has a short history of the CNE services on its website.)

The photos here have been chosen not just for the fact that cars might be operating on Exhibition routes, but also for interesting details about what is, or is not, still in the city today. Continue reading

King/Bathurst Reconstruction Project (Update 8)

Update 8:  August 10, 2011 at 7:40 am:

Construction of the new safety islands has completed early, and the 511 is back to its normal routing.

Update 7:  July 26, 2011 at 8:00 am:

The TTC has revised dates for resumption of service through the intersection:

  • Wednesday July 27:  504 King and 508 Lake Shore routes return to King Street
  • Saturday July 30:  511 Bathurst route returns temporarily for Caribana
  • Tuesday August 2:  511 Bathurst route resumes diversion via Spadina
  • Monday August 15:  511 Bathurst route diversion ends

Update 6:  July 24, 2011 at 5:00 am:

An excellent overhead view of the completed intersection dated July 17 is available on Flickr.

Service on King Street through the intersection resumes on Monday, July 25.

Continue reading

Roncesvalles Renewed Celebration (Updated)

Updated July 24, 2011 at 11:00 pm:  Links to archival photos of Roncesvalles Avenue from the City Archives have been added to the end of this article.

Apologies to those who expected to find the PCCs running on Ronces.  In turned out that one car had already been hired out for another event, and the second PCC was in the shop for repairs.  Two CLRVs don’t have quite the same effect.

Continue reading

Service Changes in July 2011

In a previous post, I described the diversions that will begin on July 11 around the reconstruction of the King/Bathurst grand union.

Beginning July 18 and continuing until early September, the 506 Carlton diversion around the Gerrard Street bridge, originally announced for June 19, will actually get underway.  Trackwork on the bridge has been in rough shape with slow orders for some time.  The planned date for return of streetcars to Gerrard Street is September 11.

Westbound service will run via Broadview, Dundas and Parliament.  Eastbound service will run via Parliament, Queen and Broadview.  Cars have been added to the schedule to compensate for the added mileage.

Effective July 31:

192 Airport Rocket: On the northbound trip, buses will serve the upper level bus stop at Jetliner first, then the arrival level at Terminal 1 and the arrival level at Terminal 3.  On the southbound trip, buses will exit the Airport via the ramp to southbound Hwy 427.  These changes are intended to free up running time to improve service reliability.

504 King: Streetcar service will return to Roncesvalles Avenue, although King cars will continue their diversion around the track and overhead work in Parkdale via Shaw and Queen.  There are only minor changes to some off-peak headways so that the running times work out.  However, I suspect with the traffic congestion on Queen and the inevitable streetcar short turns, service on Roncesvalles will not be as good as what is now provided by a dedicated bus shuttle.

Runnymede Station: The construction at Runnymede Station is supposed to be officially completed now, and 71 Runnymede, 77 Swansea and 79 Scarlett Road will return to their normal routings.

512 St. Clair: Overhead between St. Clair and St. Clair West stations will be retrofitted for pantograph compatibility.  Buses will replace streetcars on this section of the route after 10:00 pm weekdays, and all day on weekends.  The TTC claims that there will be timed transfers at St. Clair West.  Regular service resumes on September 4.

Streetcars Return to Roncesvalles, Sort Of

Work is now complete on Roncesvalles Avenue, and it is open for streetcar service.

Starting June 25, carhouse trips for the Carlton and Dundas routes will resume via Roncesvalles, but the 504 King bus shuttle will remain until July 30 because that is the next regular change in TTC schedules.  It is possible that some streetcar shuttles may appear, but the TTC’s press release is a bit vague on the details.  The TTC’s route diversion page for King has not been updated to reflect the change.

Roncesvalles Construction Resumes

Completion of the Roncesvalles reconstruction will proceed over the next four months from mid-March to early July.

The City’s Construction Notice explains the staging of the remaining work between Queen and Dundas Streets.

  • March 21 to 30:  Housekeeping work on sidewalks left over from 2010.
  • March 28 to May 16:  Sidewalk work on the east side of Roncesvalles south from Fern to Queen, and on both sides between Dundas and Howard Park.
  • April 4 to 25:  Enbridge Gas will relocate a main between Geoffrey and Howard Park on the west side of Roncesvalles.
  • May 9 to June 13:  Sidewalk work on the west side of Roncesvalles south from Howard Park to Geoffrey.
  • June 20 to July 4:  Road reconstruction on the west side of Roncesvalles from Geoffrey to Howard Park.

From March 27 onward, the 504 King service will revert to the schedule used in fall 2010 with a bus shuttle running from Dundas West Station to Sunnyside Loop.  Southbound service will run via Lansdowne, and northbound service will run via Roncesvalles.  In early May, construction will reach the point where buses can operate southbound diverting via Howard Park, Parkside Drive and High Park Blvd.  Streetcar service will resume in July.

A related project, the reconstruction of track on King from Roncesvalles to Close, is scheduled to begin in late May and continue until mid August.