How Long Will Rebuilding The SRT Take?

When OneCity was announced with much, if short-lived, fanfare back in June, the centrepiece of the scheme was a proposal for a Scarborough Subway.  Toronto could have a full-blown subway to the heart of Scarborough at a small price, and without the disruption associated with a long shutdown of the RT.

  • A subway would be built from Kennedy Station east along Eglinton and then north on Danforth Road and McCowan to Sheppard with stations at Lawrence, Scarborough Centre (shown as McCowan and Ellesmere on the OneCity map) and Sheppard/McCowan. (OneCity presentation at page 15)
  • Once the subway opened, the RT would cease operating.  Users of existing stations would have to access the subway at its new location.
  • The cost of this option compared to the expected cost of the RT conversion to LRT was $484-million.

According to OneCity (at Page 16) an SRT shutdown would take over four years during which service would be provided by a fleet of 43 shuttle buses.

When I wrote about OneCity, I received an email from Jack Collins, Vice-President of Rapid Transit Implementation at Metrolinx in which he said:

Your recent blog posting implies that Metrolinx or the Province has increased the duration of the SRT shutdown period from 3 years to 3 to 4 years.

This is not the case. The first time we heard 3 to 4 years was during the City Council debate on Wednesday concerning the One City Plan.

This duration did not come from a Metrolinx representative and in all our discussions with the TTC staff the shutdown has been three years, and hopefully less if we put our minds to it.

I wanted to assure you and your readers that even with an AFP type contract, the current Metrolinx plan is:

  • SRT will stay in service until after the 2015 Pan Am/ Para Pan games
  • The AFP contract will have a condition that will limit the shutdown period to no more than 3 years
  • As part of the AFP contractor selection process, contractors will be encouraged to come up with plans to reduce the shutdown period to less than 3 years

One might be forgiven for a bit of confusion here.  When Queen’s Park confirmed funding recently for the Toronto projects, the announcement included:

The Scarborough RT replacement and extension to Sheppard Avenue: work will begin in 2014 and be completed by 2020.

[This announcement originally said “2015”, but this was corrected subsequently to “2014” to align with Metrolinx plans.  However, the end date stayed at “2020”.]

When the proposed staging for the rapid transit projects was before the Metrolinx Board on April 25, the report proposed:

… the Scarborough RT replacement and extension to Sheppard Avenue, with a construction start of 2014 and an in-service date of 2019, …

and further:

The previous plan included a construction schedule for the Scarborough RT of 2015-2020. The schedule allows for the SRT to be in service during the Pan Am/Parapan Games in the summer of 2015, after which the service would be shut down for construction. Planning, design and engineering work will be completed prior to construction in order to minimize down time.

The revised plan will move up SRT completion by one year from 2020 to 2019. This would be accomplished by starting work on the extension of the line between McCowan and Sheppard as a first phase, allowing the existing service to continue until after the Pan Am/Parapan Games are completed.

The presentation slides included:

SRT replacement is a priority

The SRT has high, established ridership, it is near the end of its economic life and in need of replacement. Project acceleration has benefits and staging can be done to avoid any disruptions during the Pan Am/Parapan Games period.

It is quite clear from these statements that a four-year shutdown from 2015-2019 was contemplated, and this no doubt led OneCity proponents to quote such a term in their plan.

Metrolinx now claims that the shutdown will be for, at most, three years.  This means either that:

  • The line will close immediately after the Games in 2015 and re-open in 2018, or
  • The line will close sometime after 2015, possibly as late as 2017, in order to reopen “by 2020” as per the Queen’s Park announcement.

Either way, Metrolinx owes the City a clear statement of its intentions given the frequency with which construction schedules for the “Transit City” lines have been adjusted.  The current situation, according to Collins, is:

We are planning one AFP contract for both Eglinton and SRT to optimize procurement time and contractor selection.

As indicated earlier, the contractor will be required to not exceed a 3 year shutdown period for the SRT and hopefully the contractor will be able to improve on the shutdown period.

The overall schedule of work will be determined once we have a contractor on board at financial close. It is premature to set a specific date for the shutdown of the existing RT, the construction of the new LRT and its opening for revenue service until we have a schedule agreed with the contractor.

It is quite clear from this that the start date for construction is not yet settled, but that it is intended to be at most three years whenever it happens.  If this drifts out beyond 2015, this raises a question of the cost of maintenance and reliability of the SRT which is already a delicate flower.

Any discussion of the future of Scarborough’s rapid transit network must proceed on an informed basis.  Queen’s Park is somewhat misleading in saying that work will begin in 2014 and complete by 2020 if the construction schedule has not already been decided.  Even the 2014 date for prebuilding the extension from McCowan Station north to Sheppard is really subject to whatever the prime contractor for the project proposes.  The words “by 2020” do not inspire confidence.

Meanwhile, the OneCity advocates will have to refine their cost proposal for the subway extension.  They claim a subway cost of $2.3b even though an estimate done for Mayor Ford’s transition team by the TTC pegged the cost at $3.3b including vehicles but not including a new or expanded yard facility.  Given that the TTC has more T-1 cars than it needs to serve the existing Bloor-Danforth subway, it may be possible to extend the line without buying more cars (that surplus is a long story in its own right) or building a new yard.

TTC owns 370 T-1 cars.  The BD line requires 43 trains for peak service (258 cars) and Sheppard requires 4 (16 cars) for a total of 274 cars.  Add in spares at 15% and this brings the fleet requirement to 316 at 2011/12 winter service levels.  If all BD trains ran through to Sheppard, this would require roughly 13 more trains plus spares, half that with a turnback at Kennedy.  15 trains would cost at least $240m.

The TTC’s cost estimate for a subway to Scarborough Town Centre is $2.6b including vehicles.  Adjusting for the T-1 surplus would bring this down to $2.3-2.4b, the number claimed by OneCity for a subway extension all the way to Sheppard.

The whole debate between OneCity and Metrolinx, between a Scarborough Subway and the RT/LRT replacement, needs to proceed on a much more informed basis than it has to date.  With luck, staffs of the various organizations will bring credible information to Council in fall 2012 and will not “cook” the comparison of various options to suit political aims at City Hall or Queen’s Park.

The Fate of OneCity (Updated)

Several postmortems have appeared on blogs about the supposed death of OneCity and what might follow:

Updated July 19, 2012 at 7:00 am:

Updated July 16, 2012 at 11:15am:

My own take on OneCity’s fate together with the original article detailing proposals for dealing with transit planning follow the break.

Continue reading

OneCity Plan Reviewed

The OneCity plan has much to recommend it even though in the details it is far from perfect.

The funding scheme requires Queen’s Park to modify the handling of assessment value changes, and they are already cool to this scheme.  Why OneCity proponents could not simply and honestly say “we need a 1.9% tax hike every year for the next four years” (not unlike the ongoing 9% increases to pay for Toronto Water infrastructure upgrades) is baffling.  A discussion about transit is needlessly diverted into debates about arcane ways of implementing a tax increase without quite calling it what it is.

On the bright side, Toronto may leave behind the technology wars and the posturing of one neighbourhood against another to get their own projects built.  Talking about transit as a city-wide good is essential to break the logjam of decades where parochialism ruled.  Couple this with a revenue stream that could actually be depended on, and the plan has a fighting chance.  Ah, there’s the rub — actually finding funding at some level of government to pay for all of this.

Rob Ford’s subway plan depended on the supposed generosity of Metrolinx to redirect committed funding to the Ford Plan (complete with some faulty arithmetic).  Similarly, the OneCity plan depends for its first big project on money already earmarked by Metrolinx to the Scarborough RT to LRT conversion.  If this goes ahead, we would have a new subway funded roughly 80% by Queen’s Park and 20% by Toronto.  Not a bad deal, but not an arrangement we are likely to see for any other line.

On the eastern waterfront, there is already $90m on the table from Waterfront Toronto (itself funded by three levels of government), and OneCity proposes to spend another @200m or so to top up this project.  Whether all $200m would be City money, or would have to wait for other partners to buy in is unclear.

Toronto must make some hard decisions about a “Plan B” if the Ottawa refuses to play while the Tories remain in power.  Even if we saw an NDP (or an NDP/Liberal) government, I wouldn’t hold my breath for money flowing to Toronto (and other Canadian cities) overnight.  A federal presence is a long term strategy, and spending plans in Toronto must be framed with that in mind.

Sitting on our hands waiting for Premier McGuinty or would-be PM Mulcair to engineer two rainbows complete with pots of gold landing in Nathan Phillips Square would be a dead wrong strategy.  Bang the drum all we might for a “one cent solution” or a “National Transit Strategy”, Toronto needs to get on with debating our transit needs whether funding is already in place or not.  Knowing what we need and want makes for a much stronger argument to pull in funding partners.

In some cases, Toronto may be best to go it alone on some of the smaller projects, or be prepared to fund at a higher level than 1/3.  If transit is important, it should not be held hostage by waiting for a funding partner who will never show up.

The briefing package for OneCity is available online.

My comments on the political aspects of OneCity are over at the Torontoist site.

To start the ball rolling on the technical review of the OneCity network, here are my thoughts on each of the proposals in the network. Throughout the discussions that will inevitably follow, it is vital that politicians, advocates, gurus of all flavours not become wedded to the fine details. Many of these lines won’t be built for decades, if ever, and we can discuss the pros and cons without becoming mired in conversations about the colour of station tiles.

Continue reading

“One City” To Serve Them All

Updated June 27 at 5:20pm:  I have written a political analysis of today’s announcement for the Torontoist website that will probably go live tomorrow morning.  A line-by-line review of the plan will go up here later the same day.

TTC Chair Karen Stintz and Vice-Chair Glen De Baeremaeker will formally announce a new plan called “One City” on June 27 at 10:30.

The plan already has coverage on the Star and Globe websites.  Maps:  Globe Star

I will comment in more detail after their press conference, but two points leap off the page at me:

  • The proposed funding scheme for the $30-billion plan presumes 1/3 shares from each of the Provincial and Federal governments.  This money is extremely unlikely to show up, especially Ottawa’s share.  From Queen’s Park, some of the funding is from presumed “commitments” to current projects such as the Scarborough RT/LRT conversion which would be replaced by a subway extension.  The rest is uncertain.
  • The “plan” is little more than a compendium of every scheme for transit within the 416 that has been floated recently in various quarters (including this blog).  What is notable is the fact that glitches in some of the existing ideas (notably the fact that the Waterfront East line ends at Parliament) are not addressed.  The whole package definitely needs some fine tuning lest it fall victim to the dreaded problem of all maps — once you draw them, it’s almost impossible to change them.

For those who keep an eye on political evolution, the brand “One City” surfaced in April 2012 in a speech made by Karen Stintz at the Economic Club of Canada.  This idea of a new, unifying transit brand appears to have been cooking for some time.

TTC v. Metrolinx (Again): Who’s In Charge Here? (Update 2)

Updated June 8, 2012 at 11:00am:  My comments about the Commission’s action appear in an article on the Torontoist website.

Updated June 1, 2012 at 9:15am:  The motions passed at the TTC meeting of May 30 have been added at the end of this article.  The Commission took a much more conciliatory view of their relationship with Metrolinx than the staff report.  I will be writing about this situation in a separate article.

The original May 29 article follows below.

The Supplementary Agenda for the May 30, 2012 TTC meeting includes a report “LRT Projects in Toronto — Project Delivery”.

This report deals with the proposed transfer of responsibility for the Transit City LRT projects on Eglinton, Sheppard, Finch and the SRT replacement from the TTC to Metrolinx and Infrastructure Ontario.

As TTC reports go, this one is rather oddly worded in that it:

  • asks the Commission to “note” a number of factors,
  • requests that provincial agencies respond to various issues,
  • sets an October 31, 2012 deadline for the transfer of project control, and
  • proposes that the TTC’s own staff now dedicated to the LRT projects be redeployed internally.

In effect, the TTC is taking their ball and going home rather than play with the guys from down the block.  This suggests a strained relationship between agencies notwithstanding the soothing words we hear so often, and a sense that a fed up TTC is telling Queen’s Park to get lost.

From a purely political and administrative point of view, Queen’s Park holds all the cards because they are paying almost the entire cost (with a small Ottawa contribution to Sheppard) for these projects.  It’s their money, and they get to say how it will be spent.  Whether it will be spent wisely, and how the projects might fare with the TTC on the sidelines, these are questions that won’t be answered for years until we see the results.

Continue reading

TTC Meeting Wrapup: May 1, 2012

The TTC board met on May 1.  This was a quiet affair without the political drama of the “old” Ford-stacked Commission, and I almost missed the bumbling antics of the old crew.  The agenda was on the thin side, and everything wrapped up in a few hours.

Major items included:

  • a status report on the LRT projects,
  • proposed changes to the Richmond Hill extension of the Yonge Subway,
  • the Framework Agreement with Metrolinx for implementation of the Presto farecard,
  • the Customer Satisfaction Survey, and
  • the CEO’s report.

Continue reading

Where Should We Put the “Downtown Relief” Line?

The Downtown Relief Line has been in the news a lot lately, what with dreams of vast new revenues to pay for transit expansion and, at long last, a recognition that more people want to travel downtown than we have transit capacity to handle.

Back in the 1980s, the Network 2011 plan included a line from Union Station to Don Mills and Eglinton by way of the rail corridor, Eastern Avenue, Pape, a bridge across the Don Valley, and Don Mills Road.  This scheme was turned down in favour of the Sheppard Subway as part of a misguided idea that if we simply stopped building new lines into downtown, growth would stop.  In fact, GO Transit did a fine job of providing extra capacity, and more recently the new downtown condos have raised short commutes by streetcar, cycling and foot to levels nobody expected thirty years ago.

The Yonge subway filled up, for a time,but the pressure fell off thanks to the 1990s recession and the general drop in transit use.  That’s no longer the case, and suddenly everyone wants to “do something” about transit capacity downtown.  The TTC, shamefully, downplayed anything beyond its own mad scheme to stuff thousands more riders onto the Yonge line, a project requiring major changes in signalling, reconstruction of Bloor-Yonge station (and possibly others) for extra capacity, a much larger subway fleet (and yards to hold it) and possibly even the addition of platform doors at all stations.

Council asked the TTC to look at a DRL, and there is even supposed to be a study.  However, its web page is the only sign that anything is going on.

Meanwhile, every would-be transit planner in town is busy drawing maps, to the point where a credible plan can be found simply by dropping a piece of spaghetti on a map of the city and declaring this a route.  (Post-graduate degrees are available to those who can determine the ideal height from which to drop the pasta and cooking time needed to produce the best results.)  What’s missing in a lot of this discussion is a view of how a DRL might fit into a wider network, not to mention a few basics about how a new rapid transit line will, or will not, fit in some of the proposed alignments.

One of the better proposals is on Phil Orr’s DRL Now site.  It’s not perfect (no proposal is, including those I have floated from time to time), but at least this is a place to start with sufficient detail to understand what is going on.  Drawing a swoosh across a map is easy (politicians do it all the time), but designing something that might actually work is a lot harder.

A major challenge with some versions of this line is that proponents try to do too much.  Playing “connect the dots” with a transit route has its limitations, and trying to hit too many of them causes the line to wander out of its way.  This ties back to a fundamental question:  what is a DRL supposed to do?

If we believe some of the simpler plans (notably one in last week’s Star proposed by Councillor Pasternak), the DRL’s sole function is to get people from the Danforth subway to Union Station.  This is far too simplistic and guarantees the line will not be well used except as a peak period relief valve.

Other schemes take the route south of the rail corridor to serve the Port Lands and eastern waterfront.  Aside from the problems of building such a line in landfill beside Lake Ontario, the route would not provide the fine-grained transit access possible with a surface LRT, and would vastly overservice an area whose expected demand is lower than the existing Sheppard subway.  Connection to Union Station from the south would also be a big challenge.

From time to time, I am asked “what would you do”, but to start that discussion, a few first principles:

  • A”DRL” should not exist solely to relieve the Yonge line’s peak traffic problem, but should provide new links within the transit network giving rapid transit to areas of the city that do not have it today.  Indeed, the regional function within the network may well be as important as the “relief” function at Bloor-Yonge.
  • Any proposed route through downtown must respect the actual built form of the streets and buildings.  Diagonal routes through built-up areas should be avoided as they are difficult if not impossible to build.
  • Stations must be located where it is physically possible to build them.  Some routes use rail corridors without considering how either a surface or underground station might fit or be built.
  • A “DRL” is not the complete solution to capacity problems on the subway.  These problems originate north of Steeles Avenue, and a major role in trimming peak demand falls to GO Transit which has several north-south routes that could drain traffic otherwise headed for the Yonge line.

The proposed route on DRL Now (click on “Interactive Map” under the “Station Information” pulldown) includes four phases:

  • Don Mills and Eglinton to City Place
  • City Place to Dundas West
  • Don Mills from Eglinton to Sheppard
  • Dundas West to Pearson Airport

I have concerns with a few details of this plan, but the basics are good.  Another view of the route is available via Google Maps.  This has the advantage of showing the detailed alignment rather than a “route map” graphic.

Continue reading

Metrolinx Resurrects Transit City (Updated)

Updated April 26, 2012 at 1:10pm:  This article has been updated to reflect discussions at the Metrolinx Board meeting of April 25, the press scrum following that meeting, and correspondence between me and Metrolinx to clarify some issues.

Notes from the Board Meeting and Press Scrum:

Chair Rob Prichard asked about the status of unrecoverable losses due to the diversion of Metrolinx effort from the original Transit City plan to the Ford transit Memorandum of Understanding.  Less that $10-million has been spent on preliminary engineering for the Eglinton tunnel east from Laird Station.  Potential extra costs from Bombardier for the vehicle supply contract are not yet known.  If these were simply inflationary increases, then the Metrolinx funding (which includes inflation) should cover this.  However, Bombardier may also claim additional expenses related to the delay.  Prichard urged staff to “negotiate” away as much of such claims as possible.

This issue came up again in the press scrum.  Metrolinx has always said that “others” must bear any extra costs due to the Ford delay, but the identity of this party is unclear.  Elizabeth Church from the Globe noted that Karen Stintz has pointed out that since the Ford MOU was never approved by City Council, the city can hardly be held responsible for the delay.

Both Rob Prichard and CEO Bruce McCuaig dodged around this and other questions related to Metrolinx’ role in pursuing the Ford plan in the absence of Council support, especially considering that Metrolinx hangs its return to LRT on Council’s clear vote for the original Transit City plan as the City’s definitive policy statement.  The Star’s Royson James described Prichard as being good at “ragging the puck”, but never managed to pin him down to an answer.

Prichard hopes that the value of the “extra cost” will be reduced to zero making this a moot point, or at least one small enough to fit under any nearby rug without most people noticing the lump.

Director Lee Parsons asked about the possible funding from P3 Canada and what this might enable.  Bruce McCuaig suggested that it might be possible to add to the scope of work with the additional money available through this federal program, but the dollar value is not large and Metrolinx must still pitch their projects to the P3C board.

Director Richard Koroscil asked what the differences were between the plan proposed here and the previously approved 5-in-10 scheme.

Jack Collins (Vice President, Rapid Transit Implementation) replied that these are mainly the slippage of Sheppard’s completion out to 2018 and the shift of the SRT completion back from 2020 to 2019.  The design team and project manager for the Sheppard project were disbanded when work stopped just over a year ago and a new team must be assembled.  Moreover, the project will now be delivered through Infrastructure Ontario (IO) as an Alternate Finance and Procurement (AFP) scheme, and this adds time for production of the contracts related to managing this process.

In the case of the SRT, the section of the route north of McCowan Station will be built while the existing SRT is still operating and this allows work to start sooner than planned on that line.

Director Rahul Bhardwaj asked about the requirement that the TTC implement the Presto smart card as a precondition of having these projects funded by Queen’s Park.  Bruce McCuaig replied that a proposal from TTC staff for an agreement with Metrolinx and the rollout of Presto will be going to the TTC board at its meeting of May 1.

Director Joe Halstead asked about the roles of three agencies — Metrolinx, the TTC and IO — in these projects.  Metrolinx will be the project owner.  IO will be the procurement agency.  The TTC will provide the design criteria, manage the design consultants and technical details of the projects, and will eventually operate the lines.

Halstead also asked about lessons learned from the St. Clair project.  Collins replied that Metrolinx will maintain a presence in communities to keep them informed as the projects evolve, and noted that the neighbourhood office for the Sheppard LRT that had been closed because of the Ford MOU would have to be reopened.

Director Doug Turnbull asked where Metrolinx stands on the role of subways.  Bruce McCuaig replied that Metrolinx supports subways such as the Spadina extension now under construction, and noted that “The Big Move 2.0” includes both the Richmond Hill extension of the Yonge line and the Downtown Relief Line.  Metrolinx will continue to support subways in this context.  Rob Prichard noted that Toronto Council had asked city planning staff for studies of a Sheppard West connection to Downsview and a Bloor West extension to Sherway.

Turnbull asked whether TBM 2.0 affects any of the four LRT lines up for approval.  Bruce McCuaig replied that the 2.0 document will review progress to date and incorporate new initiatives such as the GO electrification.

During the press scrum, Metrolinx clarified that The Big Move 2.0 will be published at the end of 2012.

Director Stephen Smith asked for a clarification of the AFP bidding process and the meaning of the term “Financial Close” in the project chart.  Jack Collins explained that the procurement would have several stages.  First, bidders would be invited to qualify to bid on the work.  Based on this, three would be chosen, and they would be given funding to prepare a more detailed proposal.  From that work, IO would make its evaluation and select a winner.  At that point, the overall contract and financing details would have to be nailed down, and this would be the “financial close”.  IO will rely on Metrolinx, the TTC and technical consultants for evaluation of the proposals.

Smith asked whether pricing would be affected by the level of activity in the construction market.  Collins replied that preliminary indications from the international market are good because work is drying up overseas.  Also, experienced resources now committed to the Spadina extension will be freed up starting in late 2015.

The report was approved by the Board, and most of us adjourned to the press scrum which was attended by Rob Prichard, Bruce McCuaig, Jack Collins and the usual bevy of Metrolinx communications staff.

After the discussion about “extra costs” noted above, questions turned to the location of the Eglinton tunnel.  It will definitely not go under the Don River because this would involve tunneling through bedrock.  The tunnel boring machines are designed for softer conditions (soil, clay, etc), not for hard rock, and this work would be very expensive.  The line will go under Don Mills Road and will provide for a future connection to a north-south route.

Questions returned to the role of Metrolinx and “the need for a clear and supportive partner” as they put it.  Elizabeth Church asked about the Mayor’s opposition to the LRT scheme.  Bruce McCuaig noted that Council had voted, and had delegated authority to the City Manager to execute contracts for these projects.  Rob Prichard observed that the Mayor and his brother speak for themselves, and that there is a broad consensus for the LRT plan.  Metrolinx won’t stand in the way of debate, but they have lots of room for working with the city.

John Lorinc asked whether Metrolinx is concerned about being “the meat in the sandwich” in the 2014 election?  Prichard replied “no”.  He observed that political actors have strong ideas, and we shouldn’t try to take politics out of transit.  However, we should keep our eyes on the main goal of better transit and less congestion rather than just fixating on four projects.  There will be a contract with the city for these four, and other projects may come.  Metrolinx should be steady in its execution of the projects and although there will be elections along the way, the recommendation is that these projects should be completed.

A few questions on the vehicle contract came up.

Would other cities outside the Metrolinx planning area be able to procure LRVs through the Metrolinx contract?  Jack Collins replied that this decision would be up to the local municipality (e.g. Kitchener-Waterloo or Ottawa).

Given the extended period between vehicle delivery and start of service on the first line (Sheppard), what will Metrolinx do about the warranty that could expire before the cars begin revenue operations?  Bruce McCuaig replied that this would form part of the discussions with Bombardier and final approval of the terms would come from Queen’s Park.  There will be two pilot cars built for Metrolinx but no dates are set yet for their delivery.

Royson James asked about Metrolinx’ role — are they simply following the political path of least resistance, or can we “take their recommendations to the bank”?  Bruce McCuaig replied that Metrolinx would give its best advice regarding regional transportation systems, and that they are the keeper of the long term view.

James asked why Metrolinx keeps changing its mind.  McCuaig replied that there are choices between technologies, and it’s not always a black and white decision.

Rob Prichard chimed in saying that there had also been changes in preference on the City’s side for Eglinton’s technology.  The Ford MOU had tradeoffs — a longer Eglinton tunnel was a gain at the expense of losing the Finch LRT (and the eastern part of a Sheppard line).  Metrolinx need to build projects that make sense, and they are “respecting democracy”.

Elizabeth Church noted that Metrolinx has changed its “expert opinion” especially on Eglinton, and this is frustrating to those who seek technical advice.  Prichard replied that between 2006-08, the original vision for Eglinton was all underground, a faster line attracting more riders.  However, the tradeoffs between costs and benefits led to a subway-surface arrangement.

This exchange led me to write for clarification because at no time did the City of Toronto endorse an all-underground Eglinton line, particularly not once Transit City was announced.  Even before, Eglinton was flagged as a corridor for improved transit and surface priority treatment, but not for a subway.  Prichard is mixing the Metrolinx planners’ fantasies of an all-underground Eglinton with official city and TTC policy decisions, and Metrolinx can hardly claim to be following the City’s changes in policy when in fact the drive for an Eglinton subway came from Metrolinx itself.

I wrote to Metrolinx:

At the media scrum, Rob Prichard talked about the to-and-fro of the city’s position on an Eglinton all-underground line.

It’s worth noting that several reports dating from 2005-6 including the City’s Official Plan and the TTC’s “Building a Transit City” showed Eglinton as a potential transit corridor, but talked much more of surface transit priority than of a subway. ‪

Yes, there was an older proposal for a subway west from Mt. Dennis to Renforth, but the projected demand was quite low and it was not taken seriously.

Therefore to suggest that there was any serious support for an Eglinton line completely underground … is stretching the point.

Metrolinx replied:

As The Big Move was being developed between 2006 and 2008, a variety of transit lines and technologies were modeled and considered in developing the full integrated GTHA system of the future, including Eglinton as a fully-separated rapid transit corridor. The Big Move does not specify whether sections are below ground or above ground.

Also, as Metrolinx worked with the City of Toronto and the Toronto Transit Commission, and a more detailed Benefits Case Analysis was undertaken, Eglinton was confirmed as grade-separated through the central section, and at surface, east of Laird Ave.

It should be noted that the benefits of a totally grade-separated Eglinton were weighed against all other rapid transit projects across the GTHA on a range of issues, including future land use, location of employment, integration with local transit, GHG reductions, the ability to serve communities of higher social need, and travel time.

You can judge for yourself whether there was a city position on the vertical alignment of Eglinton that would support Metrolinx’ claim.

John Lorinc got in a good last word with the question “Will you still support this plan in 2014?”

To assist readers in keeping track of the shifting completion dates for the projects, here is a consolidated chart of the original plans, the revised “5-in-10” plan, and the new 2012 version.

2012.04.25_Project Staging Chart

The original article from April 24 follows below.  Note that some route-specific information has been updated on April 26.

Continue reading

The Sheppard LRT Report (Part IV)

Now we come to what I must call “The Chong Dissent”, the reports prepared under the company “Toronto Transit Infrastructure Limited” (TTIL), a dormant TTC corporation resurrected for the purpose because it had $160k sitting in its bank account.  All this and more was spent to argue the case for a Sheppard Subway.

Council has already opted for an LRT line on Sheppard, but arguments originating from the TTIL reports continue to haunt the debate.  It’s time to expose their threadbare, self-serving nature.

Continue reading