Toronto’s Network Plan 2031: Part I, SmartTrack

For the past months, Toronto Planning, the TTC and Metrolinx have hosted a number of public consultation sessions leading up to two critical meetings on the same day: June 28, 2016.

One will be the Toronto Executive Committee’s consideration of a series of reports on various transit proposals.

The other will be the Metrolinx Board’s first meeting in four months with several related items on the agenda.

Reviewing all of this material will require several article that I hope to finish before the meetings where these issues will be discussed actually occur.

Here I will begin with SmartTrack because of all of the proposals, that has been the most threadbare one throughout the public consultation. It is complicated by being a joint project with Metrolinx who own the tracks over which the trains will operate, and who now quite clearly will also own and operate the trains regardless of what the service is called.

Continue reading

Spinning a Tale in Scarborough

Brad Duguid, Ontario’s Minister of Economic Development & Growth, also the de facto spokesman for the Scarborough Liberal Caucus, was on CBC’s Metro Morning talking about the planned Scarborough Subway Extension (SSE) and its fast-inflating estimated cost.

Duguid had been quoted in the press a few days earlier as saying that downtown elitists have been opposed to the SSE from the start echoing the divisive us-versus-them context for so much of this debate. He likes to sound oh so reasonable, but his message is full of half-truths and puffery designed to support the “we don’t get our share” chorus so common from Scarborough pols and others.

The [subway] project has been on the books for 30 years.

Well, no, it hasn’t. The TTC’s original plan for Scarborough was that an LRT corridor would run northeast all the way to Malvern. (See Once Upon a Time in Scarborough and The Scarborough LRT That Wasn’t). More recently, the Transit City plan included an LRT network for Scarborough, and this received the endorsement of Council. Only when former Mayor Ford chose to use the potential of a subway as bait did Council change its mind.

If anyone has a plan for a subway from Kennedy to STC that has more status than the back of a napkin or a fantasy map, I’ll be happy to see and comment on it.

LRT was put in there as a political decision by the Davis government to promote UTDC globally.

The UTDC was a provincial agency that concocted the RT technology, and they couldn’t get a sale if Toronto wasn’t buying. This technology is most emphatically not LRT, no matter what Duguid and others like to call it, for the simple reason that it requires a completely segregated right-of-way. The true LRT line was already under construction when Queen’s Park pulled the plug, and there are remnants of the LRT design still visible in the RT structures.

Scarborough Town Centre is one of the fastest growing city centres in Canada.

Very little development, compared to the rest of Toronto, is planned for STC according to Toronto Planning’s own numbers. How many times must the following chart be published to drive home this fact?  [Source: How Does the City Grow, June 2015]

More generally, growth is not happening in the so-called centres which between them have less than 10% of the proposed development. The myth that the former “downtowns” of the old cities will become major nodes in their own right is neatly torpedoed here.

ProposedTorontoDevelopment_201506

Everyone is entitled to their views and opinions.

In a classic “yes, but” statement, Duguid tries to undo his slur against those who criticize the SSE project, but goes on to talk of how Scarborough residents have been fighting for a subway for years.

I [Duguid] have been involved in this debate for 30 years. All we’re asking for is that the fastest growing city centre be attached to higher order transit.

Fighting for “higher order rapid transit” (a phrase he uses a few times without recognizing that it actually includes LRT), maybe, but not specifically for a subway. The problem for years has been that subways and the rattletrap SRT are the only points of comparison Scarborough riders have, and it’s a no-brainer to choose one over the other. The LRT option has always been undersold, and then under Rob Ford, denigrated as “streetcars” (said with a pejorative sneer) when in fact the SLRT could be entirely on its own right-of-way.

The price came in over the estimate, but that was done a number of years ago. The price it’s come in at is the price it’s come in at.

No. The estimate was updated in 2016 for Council’s decision to go with the “optimized” Scarborough plan of a 1-stop subway and the LRT from Kennedy Station to UTSC. Does Duguid now claim that Council made a multi-billion dollar decision on a flimsy, unreliable estimate?

When challenged about insulting critics as a tactic to advance the SSE project:

Not everyone who has opposed this is from downtown, but generally critics are people who are less than 10 minutes to a subway station from their homes.

I don’t have the home addresses of the many SSE critics at my disposal, and there is no secret that I live within sight of Broadview Station. The point here is not where I live, but where people in Scarborough live, and most of them will not be within 10 minutes of the one remaining station on the SSE. Indeed, the “optimized” Scarborough plan does well on access not because of the subway, but because the LRT line to UTSC brings so many more people close to a station.

Scarborough people have been paying for the subway system for years. It is important to the entire city. We have to think about more than our ridings.

Duguid is getting too rich for words here implying that he’s not pushing the subway just to get votes even though his own party did just that, going along with Rob Ford’s fictional ideas about transit planning rather than opposing him. Yes, Scarborough has paid taxes for years into the pot, as has every other part of Toronto, including Etobicoke which is not exactly subway-rich. The SSE tax as well as development charges for new transit generally fall overwhelmingly on buildings nowhere near Scarborough, and the subway will be built mainly by funds raised outside Scarborough borders. That may be a fair trade, but not if the pricetag keeps going up and up, and not if other transit projects are cancelled to pay for it.

Yes, Scarborough too must think about more than itself, and stop acting like a brat who only wants the most expensive toy in the shop window.

Scarborough has been paying for years, but the minute something is going to SCC, such a big deal is made out of it. It’s easy for folks with higher order transit to oppose it, but it’s important to the people of Scarborough.

It is a flat out lie to say that people elsewhere in Toronto oppose “something going to SCC”. The problem here is that Duguid wants only a subway and will accept nothing else. We all need and want more and better transit, but we can’t have it when every penny is vacuumed up for one project.

Ridership numbers have to be put in perspective. STC is the first station in the system, and if the line were full here, people wouldn’t be able to get on elsewhere. It will be the 7th busiest station. If we had only looked at [terminal] ridership, we wouldn’t have built any of the subway lines.

Both the Yonge and Bloor subways were built in corridors where surface transit was already carrying thousands more riders than the RT is today, and where there was a concentrated demand to carry people from their homes to jobs downtown and on other parts of the (mainly) streetcar network. The same is not true for Scarborough, especially for transit carrying people to jobs at STC.

The Yonge extension was built to carry the very heavy demand pouring into Eglinton Station on buses from the north. The Spadina line was partly to relieve this, and partly to serve Yorkdale Mall not to mention sanitizing the proposed Spadina Expressway corridor. The extension through York University to Vaughan is well documented as a political creation, not the result of planning that would have independently justifed a line that far north.

This transcends politics.

That claim brought a guffaw from host Matt Galloway. The whole project has always been about politics, about being a “subway champion” for Scarborough and telling people how hard you are fighting for what they have been convinced they need.

The fact is that I’ve been supporting this since before I got into public office, for nearly 30 years. Scarborough residents take it very seriously. The subway will fulfill our full potential, and I fight strongly for it.

Actually, Scarborough has very substantial travel demands that have nothing to do with the Town Centre, and the subway won’t help them one bit. Moreover, most people who work at STC don’t originate from areas served by the subway network (or particularly well by transit) and they drive out of preference or because they have no choice.

Duguid and company have painted themselves into a corner by backing an option that is increasingly beyond the level where mutual back-scratching at Council and a hope for peace in the family will bring approval for the project. They’re now stuck having convinced voters that there is only one option, and that if Scarborough doesn’t get it, this will be the rich, elitist, downtown Toronto blocking their manifest destiny.

One might ask the same of City Councillors and the Mayor who short change transit at every opportunity and may even cut service rather than raise taxes and fares to pay the bills in 2017.

Our government already would have contributed 2/3 of the original cost estimate. We are the major contributor, and are unwavering in support. We will give the city the space to determine what the plans might be for the other part of the project – the line to UTSC – but we’re not in a position to commit more money.

In other words, don’t come to Queen’s Park looking for a handout, and if you have to raid the piggybank for the billion you thought you had for the UTSC LRT, then that’s Toronto’s decision. Needless to say, Duguid does not represent the ridings that the LRT would serve.

The real issue here is why a provincial Minister gets away with making such inflammatory statements about a decision which, in theory, is Toronto’s to make. Queen’s Park will spend the same dollars on Scarborough regardless of what is built, but they gingerly avoid commenting on which plan they prefer.

We’re getting almost an announcement a day from the Wynne government about transit expansion, even for some LRT funding, but Queen’s Park has stayed out of the Scarborough debate until now. When the bill comes due for the extra cost of a one-stop subway, when the hoped-for line to UTSC vanishes from the map, will Duguid or Wynne be anywhere to be found?

The Scarborough Subway Fiasco

For the benefit of out-of-town readers who may not follow the moment-to-moment upheavals in Toronto politics, the lastest news about the Scarborough Subway is that it will cost $900 million more than originally forecast, and the Eglinton East LRT line has gone up by $600 million.

Updated 10:45pm June 17: The increase in the Eglinton LRT line’s cost may only be $100m, not $600m. Awaiting further details to confirm this.

No details of the components of these increases have been published yet, but here are the current (as of 6:45 pm on June 17) media reports:

  • The Star: Mayor John Tory accused of ‘political posturing’ as Scarborough transit plans balloon by $1 billion
  • The Globe & Mail: Scarborough subway cost rises by $900-million
  • Torontoist: The Bad Decision on the Scarborough Subway Extension Gets Worse

Earlier this year, the much-touted “optimized” plan for Scarborough changed the subway scheme from a Kennedy to Sheppard line stopping enroute at Lawrence and Scarborough Town Centre (STC), to a one stop extension whose terminus and only station was to be at STC. Money saved by shortening the subway would be directed to the Eglinton East LRT project linking Kennedy Station to University of Toronto Scarborough Campus. [See Scarborough Transit Planning Update]

At this point, the total project cost remained within the original 3-stop subway project’s estimate of $3.56 billion (as spent dollars including inflation) of which the City of Toronto’s share would be $910 million financed primarily by a 1.6% Scarborough Subway property tax over 30 years. The remainder would come from Queen’s Park and Ottawa, but their contributions are fixed and any overruns are on the City’s dime.

Material from this report reappeared in a March update on the overall transit network [see Developing Toronto’s Transit Network Plan: Phase 1] and in the May-June presentations to various public consultation meetings. At no time was the possibility of a cost overrun for the Scarborough network mentioned.

Meanwhile, ridership estimates for Scarborough were revised downward quite drastically with a projected AM peak hour demand of 7,300 inbound from STC station. About half of this would be existing SRT riders and the rest would be net new to the transit system. The May presentation makes a point of defending the lower numbers, but here is what City Planning staff said only a few months earlier in their March report:

Preliminary ridership forecasts … indicate:

  • The options are capable of capturing significant ridership. Daily users range from 115,000 to 147,000 in 2031. Morning peak hour, peak point, peak direction ridership ranges from 13,700 to 17,700.
  • Assuming the McCowan 3 option, the introduction of SmartTrack would reduce ridership on the subway extension to about 109,800 daily users and 12,600 peak hour, peak point, peak direction riders assuming 15-minute SmartTrack service in 2031. Assuming 5-minute SmartTrack service daily users would be about 88,200 and peak hour, peak direction, peak point ridership would be about 9,800 riders. In either case, the peak point ridership would be comparable or higher than that observed today near the terminal points of existing subway lines, with the exception of the Yonge line in the vicinity of Finch station. [p. 32]

During his election campaign, John Tory trumpeted SmartTrack as the one line that would solve every problem claiming very high peak and all day ridership based on service probably three times better than we will ever see. SmartTrack is now proposed with trains every 15 minutes, not every 5, and this has a huge effect on ridership both on ST and on neighbouring lines as the numbers above show.

Planners have been twisting themselves into pretzels trying to justify building a subway with the lower projected demand saying it wouldn’t really work at the higher level because there would be no capacity further downstream for existing riders (similar to the problem we now see south from Finch Station). That’s all very well, but the same planners sold Council with the subway concept by touting the much higher estimates that “justified” subway construction as ridership would be at the edge of what an LRT line could handle.

These two arguments cannot both be right, and it is quite clear that planning numbers either were gerrymandered or that they were simply the product of unreliable analysis. Either way, all future projections are suspect especially if they change conveniently to suit the political needs of the day.

Throughout all of this, there has been no change, until today, in the cost estimates, the other vital factor in deciding between transit options. To put this in context, other studies have turned on amounts in the low hundreds of millions to justify choice of a “cheaper” option, while other projects languish because they are “not affordable”. $1.5 billion is no small change.

Technical issues have now come to light that render the original cost estimates meaningless. According to the Globe:

An analysis in Scarborough showed that the topography would require deeper tunnels in some places. The stations themselves would have to be 45 to 90 per cent deeper than thought, raising their construction costs immensely. And the high water table of the area would require more concrete than expected.

This is not something that was discovered last week. Mayor Tory attempted to pirouette around the cost problems with the idea that somehow the “private sector and others” could find a better way to do things. However, the TTC’s CEO Andy Byford, in a restrained comment, demured. From the Star:

TTC CEO Andy Byford said a third-party already helped with the engineering estimates to look at creative solutions for tunnelling or station design.

“I welcome the suggestion of having a third party at least review our costs because we want to make sure that we’re being as efficient as possible,” Byford said, adding: “I want to deliver the Scarborough subway for the best possible price.”

But asked if it’s realistic to expect hundreds of millions of dollars could be shaved off the costs, Byford said: “I think that would be a challenge.”

Indeed, Byford is now in a difficult position because his political neutrality on the subway vs LRT question cannot survive. Any new money to build the more-expensive plan will have to come at the expense of something else. Already, the TTC Budget Committee meeting where a preliminary “wish list” of funding requests to Ottawa was to appear (Byford said as much during the announcement at Greenwood Yard of DRL funding) was cancelled, and we have no idea just what projects TTC management, let alone the Board, feel should vie for funds. At some point, Byford may have his “Gary Webster moment” at City Council where he should openly state a professional opinion. (The reference is to Byford’s predecessor who was sacked by Rob Ford for having the temerity to oppose the subway plan.)

Nothing has been published beyond the Mayor’s comments to the media, and if there was a prepared statement, it still is not available on his website.

The tunnelling issue noted above is one part of the cost, but there are likely to be others as I have already discussed on this site. The key point is that the TTC has many interlocking projects that must proceed before the Scarborough Subway can open.

There are five projects in the future on BD which have serious interdependencies:

  • T1 replacement
  • ATC
  • Scarborough extension
  • New storage facility
  • One-person train operation

Some are below the line and some are above the line. However, the dates and order of projects don’t align, so to minimize changes and maximize efficiencies the correct order should be:

  • New storage facility (ready for permanent 6 car consists)
  • New trains (ready for ATC)
  • ATC or OPTO (with ATC and OPTO ready trains)
  • ATC or OPTO
  • Scarborough extension

[Email from Mike Palmer (Deputy Chief Operating Officer, responsible for subway operations)]

The new storage facility will likely be near Kipling Station. It will be designed around the physical requirements of the new 6-car trainsets, and it will provide concurrent storage for the new and old fleets.

ATC (Automatic Train Control) is a prerequisite for the Scarborough extension which would be built using that technology. Conversion of the existing line to ATC would, strictly speaking, not be required before the SSE opens, but no T1 trains (the existing fleet) could operate on the extension without an expensive and short-lived retrofit. Hence the need for a new fleet sooner than might otherwise have occured.

OPTO is one person train operation. This cannot go into effect until the trains all have suitable cab equipment to allow an operator at the front of a train to monitor the entire train without assistance from a guard at the rear end.

That’s quite a shopping list as a pre-requisite to the SSE, and the TTC has yet to incorporate these projects fully in its capital budget “above the line” (ie: as funded projects). It is not clear whether the TTC Board or members of Council are aware in detail of these issues either, or how much they might contribute to the added cost for the extension.

As an historical note, in the days before the TTC contemplated a move to ATC, fleet planning was based on the premise that all cars for both lines were interchangeable. The result has been that because the YUS is now fully operated with TR trains and Sheppard is being converted, there is a surplus of the older T1 equipment whose only remaining use is on the BD line. With conventional signalling, the SSE could have opened using this equipment, but that’s not how it will be built, and the fleet plans are in disarray as a result.

Why the LRT line has grown in cost is a mystery. It is unclear whether this arises from design changes or estimating errors, although the scope for such error is much less with a surface route. Either way, the magnitude of the change is substantial, and as with the subway, threatens the credibility of a plan that was sold to Council only months ago. By extension, any other plan the City might put forward is also suspect.

Through all of the consultation, we have heard very little about SmartTrack beyond the probable location of its stations and the likely service level. What we do not know is how much it will cost to build the surviving chunk of the route from Mount Dennis to Unionville. Indeed, there is reason to question going beyond the Toronto border considering that the GO/RER plan will itself bring frequent service to the same area. What we do know about ST is that it will poach riders from parallel routes, and that service expansion beyond a basic 15-minute level involves expensive reconstruction of the rail corridor to provide more capacity. Contary to what Tory’s “experts” told us, the track is not just sitting there for the taking by his signature service.

Of the original $8-billion, some has been saved by discarding the Eglinton West segment, now proposed to be part of the Crosstown project, but we really do not know how much Toronto will have to pony up to implement the ST service.

If nothing else, this whole fiasco should be an object lesson to professional staff who tailor their plans and professional advice too closely to a political agenda. When that agenda is ill-advised, but pushed forward through sheer pig-headedness, the quality of planning cannot help but be tainted along with the credibility of the planner. This is a dangerous game.

Toronto, somehow, survived the Rob Ford era and there was some hope that a credible transit plan might be cobbled together under the new Tory regime. However, Mayor Tory has proved as intransigent about acknowledging he is wrong, that circumstances do not support his plan, as his predecessor. If Toronto had time and money to spare, we might say “this too shall pass”, but we have neither.

Propping up the egos of various politicians, including the notorious Scarborough crew at Council and Queen’s Park, is getting expensive. This is complicated by the fervour with which they exhort subway supporters to demand what Scarborough “deserves”. That too is a dangerous game as there are crazies out there with less than healthy wishes for those who advocate something other than a subway. It’s Trumpism on a local scale – giving license to treat subway critics as people who don’t matter.

During his election campaign, John Tory dismissed SmartTrack critics as naysayers who simply wanted to oppose things for the sake of it. That was bullshit then, and it is today with his comments about those who question his continued support for the subway plan.

On a personal note, I have been fighting for better rapid transit in Toronto suburbs, yes, with an LRT network, something all of the planners once supported, for over forty years. A lot got in the way including provincial interference in technology choice, and economic or political downturns that snuffed out hopes for good transit funding. A lot of Scarborough was farmland when this process started. They are still waiting.

Scarborough Subway Ridership and Development Charges

The Star’s Jennifer Pagliaro reports that City Council has approved a confidential settlement with BILD, the Building Industry and Land Development Association, to avoid an Ontario Municipal Board hearing that could lead to rejection of the Bylaw implementing the Development Charges intended to pay for the Scarborough Subway. The matter was before Council in confidential session on June 7, 2016.

Staff miscalculations on the ridership of the Scarborough subway will leave taxpayers on the hook for millions more, after city council voted to settle a dispute with developers.

According to a secret report before council on Tuesday, the contents of which were shared with the Star, the city’s lawyers advised councillors to accept a settlement with the group representing developers, the Building Industry and Land Development Association (BILD).

The settlement, which reduces the amount builders will have to pony up to help finance the subway, is expected to cost the city as much as $6 million in lost revenues.

If the settlement is for only $6 million, the City should consider itself lucky because the calculation underlying the DCs is based on flawed ridership estimates and an out of date network design. Moreover, the original authorization appears to double count subway revenue with both a special Scarborough Subway Tax and Development Charges to recover the same costs.

Recent news of a 50% reduction in expected Scarborough Subway ridership from 14,100 to 7,300 passengers in the AM peak hour reignited political debate on the viability of the subway scheme. However, these numbers are not just hypothetical indicators of how the line might perform, they are integral to the calculation of Development Charges (DCs) that would help to fund the City’s share of this project.

See also my previous articles:

The formula to calculate development charges is complex, but at its heart is one key measure: how much of a new transit project will benefit existing properties versus future development. If the primary role of a new subway is to improve the lot of current riders, then only a minority of its cost can be recouped by DCs (and thus from future purchasers of new properties).

Toronto allocates DCs on a city-wide basis rather than assigning each project only to the neighbourhoods it will directly serve. These charges already help pay for many projects as shown in the introduction to the study establishing the level of new charges for the SSE.

The Council of the City of Toronto passed a Development Charges (DC) By-law, By-law 1347-2013 in October 2013, for the recovery of capital costs associated with meeting the increased needs arising from development. The effective date of the Bylaw was November 1, 2013. The recovery of DCs is on a City-wide basis and relates to a wide range of eligible City services:

  • Spadina Subway Extension
  • Transit
  • Roads and Related
  • Water
  • Sanitary Sewer
  • Storm Water Management
  • Parks and Recreation
  • Library
  • Subsidized Housing
  • Police
  • Fire
  • Emergency Medical Services
  • Development-Related Studies
  • Civic Improvements
  • Child Care
  • Health
  • Pedestrian Infrastructure

For commercial property, there is some justification to this because increased mobility makes travel to jobs simpler well beyond the location of any one project. For example, the Scarborough Subway might be held out as a way to stimulate growth at the Town Centre, but it would also reduce commute times to other parts of Toronto, notably downtown.

For residential property, especially for the large proportion of new development downtown, this link is less clear, and DCs on new condos can wind up funding transit projects of little benefit to the new residents.

This split is part of the eternal battle between sharing the cost of public services across the city and charging them locally or by user group.

In the case of the Scarborough Subway Extension (SSE), the split between new and existing beneficiaries was determined by the change in ridership projected with the subway project. The benefit was allocated 61% to new development and 39% to existing riders. The ratio is high because, at the time of the calculation, the projected peak hour ridership for the SSE was estimated at 14,100 compared with a base value of 5,500. Both of these numbers are suspect.

The base value was factored up from actual SRT ridership of 4,000 per hour to 5,500 to represent the load the subway would have had were it to exist in 2015. That value of 4,000 is equivalent to a load of about 240 per train when the peak service was 17.14 trains/hour (3’30” headway) as in 2012. However, by 2013 service had been cut to 13.33 trains/hour (4’30” headway) to reduce equipment requirements on the aging line. That is the service operating today, although a further cut to 12 trains/hour (5’00” headway) is planned for June 20, 2016. Some of the demand that would be on the SRT travels via alternate routes, some is packed into fewer trains, and some has probably been lost to the TTC. What the ridership might be today were the RT not capacity constrained is hard to tell, but it should certainly be higher.

The high value for future subway ridership combines with the low value for presumed current demand to load much of the SSE’s cost onto new development.

The situation is complicated by two competing ridership estimates:

The contexts for the three estimates differ, and this goes some way to explaining why the numbers are so far apart:

  • A line to Sheppard will attract more ridership than one ending at the STC.
  • A subway station at Sheppard, in the absence of improvements to the GO corridor such as RER and SmartTrack, will attract ridership from Markham just as Finch Station does from the Yonge corridor north of Steeles.
  • Removal of the station at Lawrence East, coupled with new GO corridor services, will reduce demand on the subway.

There is no guarantee that the land use, job and population assumptions underlying the three estimates are the same, especially when the highest number was produced in the context of boosting the importance of STC as a growth centre.

What we are left with, however, is the likelihood that the level of DCs allocated for the Scarborough Subway project were based on the most optimistic scenario for new ridership, and a network configuration quite different from what will actually be built. If the calculation had been done on the basis of lower ridership numbers, the DC revenue available to fund the Scarborough Subway would have been considerably lower.

Continue reading

A Cat’s Cradle of Transit Plans (Updated)

Updated June 6, 2016 at 11:30 pm: The chart of the demand profile for the Eglinton East LRT has been updated by City Planning to correct an error in labelling where inbound and outblound values were reversed. The new chart has been placed into this post, and the link to the source pdf has been updated below.

Public consultation sessions are coming to an end on the “motherlode” of transit projects (as they were described earlier this year by Toronto’s Chief Planner, Jennifer Keesmaat). This process will soon bring a consolidated set of reports and recommendations for Council. So far, the presentations have been subdivided between various projects.

A major challenge for politicians, the media and the general public is to sort out all of these schemes and to understand how they all fit together. This is not just a question of how we will finance all of the projects, but of how each project and the choices made for it will affect everything else. Where typical studies in Toronto might have wrestled with whether a new line should go under street “A” or “B”, and where the stations might be located, today’s work requires understanding of how the network will evolve over time and how it will work as a whole in a few decades.

The process is complicated further by having municipal (City Planning & TTC) and provincial (Metrolinx) components, and the secretive nature of Metrolinx studies means that some vital information about its projects is not yet public. The Metrolinx reports are expected to appear on their Board’s agenda for June 28, and this implies public availability sometime in the preceding week.

The consolidated City reports should be available on June 21 when a briefing session is to occur at City Hall a week before the June 28 Executive Committee meeting.

Continue reading

A Boost for the Relief Line

This afternoon, June 1, there was a small miracle at the TTC’s Greenwood Yard. Assorted politicians and transit management gathered for an announcement of transit funding, of new transit funding, and for that perpetual orphan of Toronto’s political scene, the (Downtown) Relief Line.

Steven Del Duca, Ontario’s Minister of Transportation, announced that Metrolinx would be given “more than $150 million” to work with the City and the TTC on advancing planning and design for the Relief Subway Line to bring it to “shovel ready” status.

This is a substantial commitment of financial support, but more importantly of political support. Del Duca was joined by Mayor John Tory in singing the Relief Line’s praises as a necessary part of growing capacity on the transit network building out from earlier improvements through GO/RER and SmartTrack.

According to Chief Planner Jennifer Keesmaat (whose Twitter session is in progress as I write this), study of the RL will focus initially on Phase 1 (Danforth to downtown), but will then shift to the northern and western extensions. The northern extension is of particular importance because, according to Metrolinx demand projections, it will have a major effect in offloading demand from the Yonge Subway and the Bloor-Yonge interchange.

RLUpdateProjectedDemand_P31

[Source: Metrolinx Yonge Relief Network Study p. 31]

With both the Mayor and Queen’s Park supporting the RL, and with provincial funding of the design work, the Toronto City Council gridlock over transit priorities can be “relieved” for at least a few years. The RL will not have to compete with other schemes for City funding, and with Metrolinx holding the purse, Council will not be able to divert the money to pet “relief” lines for suburban Councillors. Indeed, the whole suburbs-vs-downtown argument, which is born in part by a desire to be at the front of the line, need not pollute the RL study.

The Metrolinx role is also important because the RL (aka the “Don Mills Subway” to many on this site) needs time to be presented for what it can do for suburban Toronto were it to run north at least to Sheppard & Don Mills via Thorncliffe Park. Many riders would have a completely new route to downtown comparable to the service now provided by the Spadina Subway, and this would be completely separate from the existing congested system. Capacity released on the Yonge line would be available to riders from the proposed Richmond Hill subway extension, and the reduction of transfer traffic at Bloor-Yonge could eliminate the need for an extremely expensive and complicated expansion of platform and circulation capacity there offsetting some of the Relief Line’s cost.

Del Duca acknowledged the considerable work already done by the City and TTC on this file. Indeed, had it not been for the TTC’s Andy Byford with support from City Planning raising the alarm about the need for a Relief Line, nothing would have happened.

Some comparatively short term improvements will provide “relief” on the Yonge line, but these will be backfilled by pent up demand over the next decade.

RLUpdateCapacityChart_P20

[Source: Metrolinx Yonge Relief Network Study p. 20]

Smart Track may shave another small amount off of this, but notwithstanding the Mayor’s enthusiasm, the City’s own demand projections published as part of the Scarborough studies show that SmartTrack has a very small effect at Bloor-Yonge.

Tory is still somewhat confused about just what Smart Track’s effect will be considering how much it has been scaled back since his election campaign. He was happy to talk about track work now in progress in Scarborough (on the Stouffville corridor) as being part of Smart Track, when in fact it is the double-tracking work for improved GO service that was in the works before he even ran for office. And he still talks of this as if it were an $8 billion project when a great deal has been lopped off of the project’s scope.

Finally, the TTC CEO Andy Byford is happy just to see money coming his way from all three governments on both the capital and operating sides (although, the latter more grudgingly from the City).

As for construction, that’s still some years off, and it will be important to think of the project in phases, not as one megaproject. It will take five to six years to get to “shovel ready” status, and the issue then is how quickly we want to build the line. A lot of transit capital planning lately has been hostage to constrained finances at both the City and at Queen’s Park. By the early 2020s, the Scarborough subway project should be winding down and spending can shift to the Relief Line.

Now in all this excitement, if only someone would treat other orphaned projects like the Waterfront and Sheppard LRTs seriously.

A Messy “Reset” For Waterfront Transit Planning (Updated)

The first of two public meetings on the City of Toronto’s so-called “reset” of transit plans for the waterfront was held on May 25, and a second is to follow tonight (May 26).

The presentation deck from these meetings is now available online.

Updated May 27, 2016 at 5:30 pm: The preliminary evaluation grids for various routing options have been added to this article following the original discussion of each section of the study. This raises an obvious question of how options can be scored before important factors such as demand projections, design and costing are known, and whether the preliminary scores will bias the discussion and evaluations to occur in Phase 2 of the study. Scroll down to the end of each section for the additional material. (Apologies for the resolution. The grids are not available online, and I am limited by the quality of the paper copies distributed at the meeting.)

There is a lot of material to digest here, and the process is not helped by several factors:

  • Council has imposed a very short timeframe, considerably less than would normally be taken for the scope of work.
  • All proposals that have ever been on the table for the past few decades and a few new schemes are up for discussion, including some that should have been discarded quite early in the process. In part this is due to the many incomplete studies of various sections of the route that never got to the point of killing off the unworkable options.
  • The City and consultant staff presenting this material are not intimately familiar with the details of many proposals, nor with the history of how they came to be part of past studies.
  • Conflicting goals of previous studies, not to mention of today’s Councillors and community groups, make a “one size fits all” solution impossible.
  • Beyond identifying a few locations where GO/Metrolinx might add stations in the Lake Shore corridor, there is little discussion of the role GO/RER can and, equally importantly, cannot play in handling travel.
  • There is very limited origin-destination or demand information with which to validate or compare proposals, or to put them in the wider context of competing demands for transit funding.
  • A vital consideration for any network is the effect on travel times. After spending millions (or even billions), how would the speed and capacity of travel have improved?
  • The real meat of any discussion remains for an as-yet unapproved “Phase 2” study that would include [text taken from the presentation]:
    • Feasibility studies (including but not limited to demand forecasting, operational assessments, further developed cost estimates);
    • Potential Environmental Assessment(s) or amendments to existing Environmental Assessment(s);
    • Pursuing the implementation of short term strategic improvements that minimize long term throwaway costs; and
    • Advancing a Business Case and pursue funding opportunities.

As someone who has worked for years in hopes of better transit service to the waterfront, all of this is quite disheartening. So many competing ideas are on the table, so many competing priorities, and so little desire to spend pervades the discussion. We may end up with nothing at all.

Growth in the Waterfront

The need for better transit to many parts of the waterfront is quite obvious to anyone who looks at the forests of new condo towers along the water and neighbourhood close by to the north. Much of the projected population growth in Toronto is located in the southern part of the city (an area considerably bigger than the traditional “downtown”), but transit improvements there always come second (at best) to proposed expansion elsewhere. Where suburban subway boosters take a “build it and they will come” approach to subway advocacy and treat rapid transit as a trigger that will, they hope, bring new population and jobs, the waterfront already has both, and is growing apace without adequate transit support. Improved transit to the eastern and western waterfront rank in the top five performers of the City’s “Feeling Congested” study.

201605_PopEmpGrowthto2041

201605_PopEmpGrowthto2041_Chart

This growth will not all arrive “tomorrow”, but it certainly will build in over coming decades. Already, access by transit across the waterfront is inadequate, and this will only get worse as time goes on.

Continue reading

Why Are Subway Cars on Bloor-Danforth So Dirty?

As a regular traveller on the Bloor-Danforth subway (Line 2), I cannot help noticing how often a car will appear with a very grimy exterior. Although inside the cars look just fine, the exterior can leave much to be desired. The comparison is quite striking with the gleaming trains on Yonge-University-Spadina (Line 1).

It turns out that this problem is caused by a combination of factors including the fact that the BD trains (the T1 sets) are riveted aluminum, while the YUS trains (the newer TR sets) are welded stainless steel.

I asked the TTC about this issue, especially considering how important system cleanliness is in their attempt to present a good face to customers, and they replied:

You’re correct that some of the T1 cars are not as clean as we like.

There are a number of factors in play here.

Trains are not washed regularly through the winter when the ground temperature drops below a certain point. Every winter, it follows that the trains become less clean. We do wash trains mechanically but it is less effective.

Each summer we employ summer students to hand wash the trains using detergent and pressure washers. They can do a train or so a day. They look pretty good, but with the condition of the body and its design –  it takes time.

Chemicals used also make the aluminium more porous and so we have to be careful how much we use, or we potentially make the issue worse over time as the body will attract even more dirt.

The work is made more difficult due to the number of rivets used on the sides of the train. You can see more staining around the doors in general where the normal train wash (think of a car wash for trains) just doesn’t get into these nooks and crannies. On the TR we designed this dirt trap out by the smooth car body.

The students have started work and you’ll see a gradual improvement in the fleet. That said, progress will be slower this year as we are using them to clean also air filters on the trains’ heating system which whilst invisible to customers needs doing across the fleet and is a higher priority.

We will be targeting the worst units first, and working through the fleet on a priority basis.

[Email from Mike Palmer, Deputy Chief Operating Officer, TTC, April 19, 2016]

The T1s will be with us for many years as they are only about 15 years old. TTC has had aluminum bodied cars for decades, and I hope that they can maintain some semblance of cleanliness with this fleet.

Toronto Council Endorses Transit Plan, Seeks Background Details

At its meeting of March 31, 2016, Toronto Council passed several motions relating to the proposed rapid transit plan for the city.These evolved first as a set of staff recommendations, then amendments at the Executive Committee and finally amendments at Council. The changes along the way give a sense of how the attempt at a general approach taken in the new transit plan by staff can be warped into an emphasis on individual projects while losing sight of the overall purpose. This is not new in Toronto’s political theatre, but the city and region are at a crucial time when the “big picture” of the transportation network is essential. The challenge for those who would lead this process is to find a responsible balance between wider priorities and local concerns without making every decision only on political merits.

Many of these motions involve requests for additional reports, and at one point there was some concern about whether city staff could actually handle the workload. One might ask whether the city should be making such important decisions if staff are unable to produce sufficient background material and simply want approval trusting their recommendations. While studying issues to death is a well-known delay tactic, rushing decisions without all the details is a classic method of railroading through decisions the city might regret later. There is certainly nothing wrong with asking for a more thorough study of items that have been omitted, provided that the same requests do not surface over and over again.

If anything, Council has been woefully underinformed on transit options, priorities and tradeoffs, and such an environment “debate” often has little to do with the real world. Will every Councillor read every page of every study? No, but at least the material will be there to answer questions, support the good ideas and counter the dubious schemes. We hear a lot about “evidence based planning”, but this can be a double-edged sword where “evidence” might not support fondly-held proposals.

This article groups Council’s motions by topic so that readers do not have to sort through the relationship of recommendations and amendments.

Continue reading

GO/RER Details Emerge in Business Case Analysis

Metrolinx has published a set of documents containing the “Initial Business Case” for the GO Transit Regional Express Rail (GO/RER) network.

Updated Dec. 13, 2022: Due to a reorganization of Metrolinx’ site, the reports are no longer available there. However, I have archived copies of them. The Summary and Full Report links below are to my site. The Appendices are not yet available as I must break them into chunks small enough that WordPress will allow them to be uploaded.

  • Summary
  • Full Report
  • Appendices A-J
    • A: Corridor Specifications
    • B: Corridor and System Schematics
    • C: Model Assumptions and Results
    • D: Record of Assumptions – Direct Demand Model
    • E: Financial Performance of RER Systems
    • F: Sensitivity Analysis
    • G: Wider Economic Benefits
    • H: Line Speed Analysis
    • I: Environmental Assessment Program
    • J: Fare Structure Issues and Solutions
  • Appendix K:  Station Access Analysis

[Note that except for the Summary, the documents are large PDFs.]

This article begins a review of these documents and of the various RER proposals examined in the Metrolinx studies.

Overview

Work on this review of GO/RER began in April 2014 following the announcement by Queen’s Park of its commitment to the RER concept. Unlike previous reports, this study looks in depth at all of the GO corridors, and reviews the technical issues associated with both increased service and electrification. This is not a final review, and much engineering work remains to be done, but there is a great deal more information now publicly available as the basis for discussions.

These documents were completed sometime in 2015 as is clear from references to future events that will occur later in the year, notably reports from the City of Toronto on SmartTrack. That scheme gets only passing mention, some of it the usual political cover story, because the specifics had yet to be decided. Exactly what the incremental effect of ST will be beyond the proposed GO/RER configuration is not yet known. Preliminary information in City reports implies that ST will amount to considerably less than was foreseen by the Tory election campaign, possibly as little as a few more stations and some sort of TTC/GO fare integration.

Five scenarios were reviewed to compare the effects, benefits, costs and technical issues associated with various possible future networks.

  1. The “Do Minimum” scenario provides only marginal peak period improvements to the existing system in response to projected demand growth, but with no electrification. This is effectively a “business as usual” model for the base case.
  2. The “Two-Way All-Day” scenario expands off peak service, but with diesel operation and no electrification. This is a minimal level of service expansion.
  3. The “10-Year Plan” would provide frequent service on the inner parts of some corridors, but with limited electrification.
  4. The “Full Build” extends beyond the 10-Year Plan to provide frequent service on the inner parts of all corridors, and with full electrification.
  5. The “10-Year Plan Optimized” extends the scope of electrification beyond that contemplated in scenario 3.

This progression implies a certain sequence of events during the study where a full build is impractical and the original 10-year plan was not aggressive enough with electrification, a key component of the announced government direction.

The estimated capital costs rise from $5 billion for scenario 1, through $10b, $12b and $19b for scenarios 2 to 4. The price tag for the latter is well above what Queen’s Park has available, and scenario 5 was developed with a projected cost of $13.5b. All but scenario 4 are said to be achievable by 2024. Given that it is now 2016, and this is a 10 year plan, that date probably requires some adjustment.

Scenario 5 is the 10-Year Plan Optimized, it represents significant progress towards implementing the service levels of Scenario 4. It goes beyond the investments and service included in Scenario 3 (10-Year Plan), with electrification also to Bramalea, Barrie, Stouffville and to Pearson Airport. This scenario and the resulting recommended RER program has been defined to maximize return on investment while mitigating risks. Depending on resolving various challenges, it can be delivered over 10 years for approximately $13.5 billion. It does not preclude, but rather prepares for, services to Milton and Kitchener to be eventually electrified and frequent all-day services introduced when agreement is reached on co-existence of GO and freight on these privately-owned corridors. [p. iv, Full Report]

Annual ridership is expected to go up by a factor of 2.5 over the coming 15 years, but operation costs will not rise at the same rate. The study postulates that an operating profit would be possible, eventually, but that will depend a lot on future fare policies, and on the evolution of trip patterns (length, direction, average fare). The ridership model foresees that “hundreds of thousands” of auto trips would be replaced by GO ridership each weekday comparing scenario 5 to scenario 1. The proportion of trips and its relationship to expected growth is not specified in the Executive Summary. (Possibly in the demand modelling later.)

The rate of demand increase on GO overall is projected at 2.3% which is lower than recent levels, but allows for some leveling off in a more mature service.

One big issue is the problem of getting riders physically to and from the GO trains. Either this will be done with substantially improved local transit services (an option that brings many issues associated with fare integration and cross-system subsidies), or with parking. The cost estimates include $750m for 15,000 new parking spaces, or $50k per space. At that scale, simply paving empty lots is not an option. The study notes the possibility that some of this cost “may not be necessary if service integration and fare integration with local transit services can be improved”. [p. v]

Those 15,000 spaces represent nowhere near the ratio of new parking spaces to existing facilities that the projected ridership growth would entail if everyone arrived by car. Parking charges are listed as a way of raising additional capital for the RER project, and of encouraging a shift to ride sharing and public transit feeder services.

It is amusing to read about the benefits of proven technology, something for which Ontario has not been noted in past endeavours.

Virtually all of the works are within existing rail corridors, so environmental and community impacts are limited mostly to noise and vibration. RER will use proven technology that is working around the world. [p. v]

Descriptions of RER cite similar operations in more than 50 city regions worldwide [page 6], and list a number of factors that simplify implementation [p. 4]. I cannot help thinking of how badly past studies have downplayed the benefits of LRT which bears a family resemblance, but at a local rather than a regional level.

The first electric railway opened in 1883 (the Volks Tourist Railway on the Brighton seafront in the U.K.). Ever since that time, electric traction has increasingly become the default source of power for the world’s more intensively used rail systems. [p. 14]

Finding this statement in a Metrolinx report is quite amusing considering some of the remarks made during community meetings on electrification before Metrolinx and GO “got religion” on the subject. The report skirts that debate by observing that GO is now at the threshold where electrification makes sense:

Until recently, diesel traction has been the appropriate mode of traction for the GO rail operation. However, the service enhancements envisaged in the near future will take GO rail beyond the threshold of service intensity appropriate for electrification. Continued use of diesel traction will become a source of financial and economic inefficiency. [p. 14]

Metrolinx intends to pursue discussions with the railways regarding the upgrades needed on their trackage, and also intends to review “modern, proven technology” with Transport Canada and the railways.

This is an “initial” analysis, and changes are likely depending on the evolution of expectations, changes in provincial funding, and who knows what political meddling that could arise.

A decade is a long time in politics, and the likelihood that the current governing parties or councillors will still be in place at that distant time is minuscule. Moreover, changes could come at any level part way through the project, and only a very strong, unshakeable commitment (i.e. very popular and difficult to derail) is likely to survive. This is not simply a case of showing up for a photo op or two with a gigantic prop cheque, but of supporting the plan for the long haul, including building a constituency that can survive beyond current governments. The arrival of a Ford-equivalent who simply wanted to start over with his own plan would be disastrous.

Continue reading