SRT Busway To Open A Year Early

The express busway linking Kennedy Station to Ellesmere Road along the former Line 3 Scarborough RT corridor will open in late September 2026 rather than in 2027 as originally planned. This was announced jointly by Mayor Chow, TTC Chair Myers and TTC CEO Lali.

The idea of repurposing the SRT corridor was approved well before the premature end of service with a derailment south of Ellesmere Station in July 2023. According to an April 2022 presentation, design work would begin in 2022, and construction to convert the corridor would begin immediately after the RT shutdown scheduled for November 2023, and the busway would open in Q4 2025.

Yes, it should be open already, but delays in funding the project, acquiring property, gaining Metrolinx approval for co-existence of a busway with their rail corridor, among other factors, pushed design completion out to mid-2024, and the target in-service date well into 2027.

A common factor in many delays was a lack of urgency, and the idea that Ontario should pay for this conversion as part of the Scarborough Subway project. Council approved its expected share of funding in February 2024, but time was lost waiting for provincial money that would never arrive. Eventually the City decided to just get on with the work.

Major Projects Update April 2025:

The 100% Detailed Design of the Busway was completed in December 2024, along with the final cost estimates, which remain within the approved budget. The contract for the Busway was tendered in February 2025 and is expected to be awarded in Q2 2025 to commence the construction of the Busway.

Major Projects Update June 2025:

The contract for the Busway was tendered in February 2025 and closed in April 2025. Delegated authority to award the contract was approved at the May 2025 Board meeting along with a motion to report back to the Board in July 2025 on an acceleration plan.

The July report included:

As the contract was awarded on June 5, 2025, and the first kick-off meeting was held with the Contractor on June 13, 2025, staff are anticipating receiving the Contractor’s baseline schedule in the first week of July. We, therefore, expect to start the discussion with the Contractor on the acceleration plan in July 2025. The Contractor will need time to line up their sub-contractors and suppliers to develop a comprehensive acceleration plan that demonstrates ways and means of achieving the acceleration goal. We anticipate finalizing the acceleration plan by end of the summer and reporting back to the Board in September/October 2025.

Major Projects Update September 2025:

The contract for the Busway was tendered in February 2025. The contract for the Busway implementation was awarded in June 2025, and work commenced on July 22, 2025.

[…]

Awaiting an acceleration plan proposal from the contractor. Upon receipt of the proposal, negotiations to finalize the proposed plan will take place immediately over the following two to three weeks. A report will be provided to the Board at the October 2025 meeting.

No report appeared in October or since.

Major Projects Update December 2025:

“The contractor submitted a baseline construction schedule, and an acceleration plan to target an early revenue service is under negotiation.”

In other words, it was possible to get the busway open sooner, but that was not the original scheme nor was an acceleration plan required in the initial tender. No, it was not your imagination that this project could have run faster, it was actually planned to be long. As of a few days ago, a faster schedule was still only a possibility.

Now with political pressure, the Scarborough Bus Corridor project will speed up. However, the basic question is why was this option not on the table from day one especially after the time lost awaiting provincial funding.

TTC Service Changes Effective Sunday, December 21, 2025

The TTC will adjust schedules on December 21 to reflect lower demand over the holiday period.

506/306 Carlton will revert to the normal route between Spadina and Bay following work at McCaul Street. Additional service on the west half of 94 Wellesley will be removed.

306 Carlton night service will be improved from a 20′ to a 15′ headway.

The following routes will get added, unscheduled service using surplus operators:

  • 57 Midland
  • 80 Queensway
  • 89 Weston
  • 123 Sherway
  • 131 Nugget
  • 960 Steeles West Express

Some routes which received unscheduled additions in November will lose it for the holiday period. This will be restored in January.

  • 7 Bathurst
  • 24 Victoria Park
  • 25 Don Mills
  • 29 Dufferin
  • 100 Flemingdon Park
  • 165 Weston Rd North

Service over the period will be adjusted day to day as shown below.

DateService Design
Fri. Dec. 19Regular weekday service
Sat. Dec. 20Regular Saturday service
Sun. Dec. 21Regular Sunday service with minor changes
Mon. Dec. 22 to
Wed. Dec. 24
Adjusted weekday service (school trips removed)
Thu. Dec. 25Holiday service with most routes starting at 8am
Fri. Dec. 26Holiday service with 32 shopping extras between 11am and 10pm
Sat. Dec. 27Regular Saturday service with minor changes
Sun. Dec. 28Regular Sunday service with minor changes
Mon. Dec. 29
Tue. Dec. 30
Adjusted weekday service (school trips removed)
Wed. Dec. 31New Year’s Eve service (see below) (school trips removed)
Thu. Jan. 1Holiday service with most routes starting at 8am
Fri. Jan. 2Adjusted weekday service (school trips removed)
Sat. Jan. 3Regular Saturday service with minor changes
Sun. Jan. 4Regular Sunday service
Mon. Jan. 5Regular weekday service including school trips

New Year’s Eve Service

Service will operate free of charge from 7pm on December 31 to 7am on January 1. Late evening service on most routes will be extended to 3am January 1.

DepartArrive
1 Yonge-University-Spadina
North from Union to Finch2:31 am3:02 am
North from Union to VMC2:27 am3:10 am
South from Finch2:00 am
South from VMC1:50 am
2 Bloor-Danforth
East from Kipling 2:15 am
East from Bloor-Yonge to Kennedy2:40 am3:02 am
West from Kennedy Station2:18 am
West from Bloor-Yonge to Kipling2:39 am3:08 am
4 Sheppard
East from Sheppard-Yonge to Don Mills2:57 am3:05 am
West from Don Mills to Yonge to Sheppard-Yonge3:09 am3:17 am

Contract services on 52 Lawrence West to Westwood and 68 Warden to Major Mackenzie will end at about 3am. 160 Bathurst North, 102 Markham Road and 129 McCowan North will end at their usual times.

Note that the memo detailing these changes was issued before Line 6 Finch opened, and therefore contains no info about that route.

Continue reading