Various track construction projects continue into November, but there are signs of progress at some locations.
Updated November 6, 2022 at Noon: Photos of the current state of the King-Queen-Queensway-Roncesvalles project added.
College/Carlton Reconstruction and Diversion
Effective November 2, the intersection of Carlton and Church reopened for streetcars after a long delaty. This had been caused by an unexpected hydro vault under the intersection that conflicted with the new, deeper foundation that is placed under streetcar track.
The 506 Carlton service now operates on the originally planned Dundas Street diversion from Bay to Ossington while College Street is under construction. Here is the updated diversion map from the TTC’s Service Advisory.
The replacement 506C bus continues to operate via Harbord and Hoskin from University to Ossington, and via Gerrard from University to Parliament.
This configuration is expected to last to the end of 2022.

Track reconstruction has shifted east into its second phase between St. George and Bay Streets. Here is a view west on College from University showing the track structure with the old rails removed. The steel ties and attachment points for Pandrol clips are ready to receive new rails.

The City of Toronto’s project webpage contains more information about this status and details of the planned road reconfiguration.
King & Shaw
Construction continues at King and Shaw, but should be finished in time for service restoration on 504 King and 63 Ossington for the next schedule period on November 22. This has not yet been confirmed.
The service alert on the TTC’s website shows the correct routing for 504 services in the west end, but still includes the Queen/Parliament diversion to the east which ended a few weeks ago.
Queen & Carroll
Stop rail replacement on Queen east of the Don Bridge will occur over the weekend of November 4-7. 501 Queen and 504B King/Broadview Station services will divert via Parliament, Dundas and Broadview as shown below.
Although the map does not show this, the 504A King/Distillery service will continue to run on its normal route.

Wellington Street
Installation of new overhead is underway on Wellington, and the 503 Kingston Road car is supposed to resume its loop via Church, Wellington and York with the November 22 schedule changes. This has not yet been confirmed.
Adelaide Street
Track construction has begun on Adelaide Street to restore the link between Spadina and Victoria that has been inactive and unusable for decades. This will provide the eastbound diversion from York to Church for 501 Queen service during Ontario Line construction at Queen & Yonge. The track west to Spadina was included in the project as it will be useful for other diversions including the 504 King car during the film festival which typically closes King Street from Simcoe to west of John.
The construction work will occur in phases as described in the City of Toronto’s project page.
Phase 1A runs east from York to Victoria. This involves the replacement of an old watermain, work that is necessary before the tracks can be rebuilt. This is now in progress.
Phase 1B runs west from York to Simcoe. This is the first phase of track replacement. Initially only the eastbound track area will be excavated. The westbound track will be removed later.
Phase 2 will begin after phase 1B completes. It runs west from Simcoe to Widmer, and is expected to begin on November 7 subject to completion of work further east.
Phase 3 will begin after phase 2 completes. It runs west from Widmer to Charlotte where it will connect with existing track.
Once all of this work is finished, phase 4 will see the pavement marked for a revised configuration with the bicycle track relocated to the north curb lane from Bathurst to Parliament.
In 2023, a separate project will see new southbound track installed on York between Queen and Adelaide, and installation of new track from York to Victoria. The date for this work has not yet been announced.
In the map below, a shared lane is shown on the south side of Adelaide through the construction zone. The lane is actually on the north side of the street, at least as of November 2.

Adelaide Street looking east (on the left) and west (on the right) at University.


Here is a view looking west on Adelaide on July 1, 1967, west of Simcoe. The neighbourhood has changed quite a bit in 55 years.

King/Queen/Queensway/Roncesvalles
Due to persistent fog, I have not visited KQQR but plan to do so soon. I will update this article with the current status and photos in the next few days.
Updated November 6, 2022 at Noon
Here is a gallery showing the current state of the KQQR project.
The watermain reconstruction on Roncesvalles north of Queen completed recently. Concrete around the old track at the north gate has been broken up in preparation for removal of the special work.
At the Glendale stop (St. Joseph’s Hospital) formwork is in place for the new eastbound platform, but buses are still stopping beside an unmaintained dirt area on the south side of the street.
The walkway across the tracks to the eastbound stop has been repaired since my visit a few weeks ago and the handrail is now in place on the full length of both sides.
The new curb along the south side of The Queensway is progressing slowly.
Work at Sunnyside Loop was delayed for construction of a Bell Canada manhole on the south side of The Queensway, but poles required to string the new loop overhead are not yet installed.
According to the most recent construction update from the City, the TTC is considering changing the route of the 504C replacement bus to provide some service on Roncesvalles south of Howard Park, but nothing has been decided yet.