Updated June 23, 2020 at 1:50 pm: The table of projects has been updated to include anticipated events, notably “financial close” dates, that were included in various project announcements by Infrastructure Ontario. Also Union Station Platform Expansion was described in the original version of this article as closing sooner than originally projected. This has been corrected to show a delay of roughly nine months.
Infrastructure Ontario recently released its Spring 2020 Update for P3 projects under its control including several Metrolinx projects. To date there have been three of these updates:
These updates include information on the project status, the type of procurement model, and the expected progress of each project through the procurement process. This provides “one stop shopping” compared to Metrolinx’ own site. As a convenience to readers, I have consolidated the three updates as they relate to transit projects to allow easy comparison between versions.
Some projects have evolved since the first version, and in particular the delivery dates for a few projects have moved further into the future. The “financial close” dates for some projects, in effect the point at which a contract is signed and real work can begin, has moved beyond the date of the next Provincial election. Whatever government is in power after summer 2022 will have a final say on whether these projects go ahead.
Subway Projects
Ontario Line
The Ontario Line was previously reported as a single project with a price tag of over $10 billion. In the Fall 2019 update, the intent was to have the financial close in Winter/Spring 2022 ahead of the election. In the Winter 2020 update, this changed to Spring 2022.
In the Spring 2020 update, the project has been split into separate parts to reflect industry feedback about the original scope.
- GO Corridor from Don River to Gerrard
- South Tunnels, Civil Works and Stations CNE to Don River
- Rolling Stock, System Operations & Maintenance
- North Tunnels, Civil Works and Stations
The GO corridor work will be done as a conventional procurement by Metrolinx and will be bundled with upgrades to GO Transit trackage.
The financial close for items 2 and 3 above is now Fall 2022, and for item 4 it is Fall 2023.
This means that an actual sign-on-the-dotted-line commitment to the project will not be within the current government’s mandate. Even the so-called “early works” comprising the southern portion of the route from Exhibition to the Don River is not scheduled to close until Fall 2022. The northern portion, from Gerrard to Eglinton will close in Fall 2023. This contract is being held back pending results for the south contract to determine the industry’s appetite for the work.
The southern portion, with a long tunnel through downtown and stations in congested street locations would start first. However, the line cannot actually open without the northern portion because this provides the link to the maintenance facility which is included as part of item 3 above although the actual access connection would be built as part of item 4.
An issue linking all of these projects is the choice of technology which, in turn drives decisions such as tunnel and station sizes, power supply, signalling and maintenance facility design. When the Ontario Line was a single project, Metrolinx could say that this choice was up to the bidders, but now there must be some co-ordination to ensure that what is built can actually be used to operate the selected technology. It is hardly a secret that Metrolinx is promoting a SkyTrain like technology, although which propulsion scheme (LIM vs rotary motors) is not clear. There are well-known problems with LIMs and the power pickup technology used on the SRT, and this would also be a consideration for the outdoor portions of the Ontario Line.
Scarborough Subway Extension
Like the Ontario Line, the Scarborough Extension has been split into two pieces. The first will be the tunnel contract from Kennedy Station to McCowan. This is now in the procurement phase, and financial close is projected for Spring 2021.
The remainder of the project previously had a projected closing date of “Winter/Spring 2023”, but this is now just “2023”. With the tunnel hived off into a separate contract, it is reasonable that the remainder would have a later start date because the tunnel is a key component that must be in place first.
Metrolinx recently published a Preliminary Business Case for this extension. It includes the following text:
Kennedy Station Pocket Track/Transition Section
The Kennedy transition section extends roughly 550 metres from the east side of the GO Transit Stouffville rail corridor to Commonwealth Avenue and will include special track work and a pocket track to enable every second subway train to short turn to suit ridership demand and minimize fleet requirements, as well as lower operating costs. [p 24]
This turnback has been an on-again, off-again part of the project but it is now clearly included as a cost saving measure. With only every second train running to Sheppard/McCowan, the fleet required (as well as storage) would be within the system’s current capacity. This ties in with the timing of the T1 fleet replacement on Line 2 as there are enough T1s to run alternate, but not full service to Sheppard. This would be similar to the arrangement now used on the TYSSE where only half of the AM peak service runs north of Glencairn Station to Vaughan.
Richmond Hill Subway Extension
The Ontario government recently signed an agreement with York Region for the extension of the Yonge line from Finch to Richmond Hill. The status of this project is unchanged with an RFQ to be issued in Fall 2021, an RFP in Spring 2022 and financial close in Fall 2023.
Sheppard East Subway Extension
This project remains in the planning phase.