The City of Toronto launched its 2020 budget process on January 10, 2020 with a presentation by senior management and a short question-and-answer session with some members of Toronto Council. At this point, the material was quite high level, including some management puffery, but the real meat of the budget lies in the departmental and agency Budget Notes to be discussed at meetings on January 15-17. The TTC budget will be discussed on January 17.
Useful links:
- Presentation by the City Manager
- City of Toronto Budget Reports & Presentations for departments and agencies
- Budget Note for the Toronto Transit Commission
- TTC 2020 Operating Budget Report
- TTC 2019 Making Headway Report on Capital spending requirements
Major Issues
Much has been made of the City Building Fund and its rising property tax levy to finance substantial growth in the TTC and Housing capital budgets. The changes to the TTC’s ten year capital plan between its original launch in December 2019 and the version presented in the January 2020 Budget Note are detailed later in this article. Within those changes are two major categories:
- It was only one year ago, that TTC management proposed, and the Board approved, a significant change in the timing of Line 2 Bloor-Danforth renewal pushing out the installation of Automatic Train Control, construction of a new yard and purchase of a new fleet by a decade. The new Capital Plan shifts this work back into the 2020s and better aligns with the timing of the Scarborough Subway Extension. It also removes a reliance on older technology whose longevity was uncertain, notably the signal system.
- The original Capital Plan included no money for new vehicles beyond purchases now in progress. There is a new item for “Vehicles”, but this is not subdivided by mode. Significant spending is budgeted for 2022 and beyond. Expanding any of the fleets also triggers a need for garage/carhouse facilities and there is a substantial increase in the planned spending on facilities.
On the Operating budget, the changes are much more modest because the additional revenue mainly keeps up with inflationary pressures, but does not go beyond for an aggressive expansion of service.
The TTC plans to hire 88 more operators and has budgeted more service hours, but the purpose of this is described differently depending on which part of the budget report and presentation one reads/hears. In December 2019, the Operating Budget and its presentation talked of relieving overcrowding that placed some routes beyond the Service Standards. However, the same addition to the Service Budget is used to handle other factors and the list makes no mention of reduced crowding.
I await clarification from the TTC on this important issue – does the TTC plan to reduce crowding or not? Will they burn up new service hours mainly to pad schedules for better service “resiliency”, or will they actually add service on overcrowded routes?