After leaks to the Star and the Globe, and a private release to the City of Toronto, Metrolinx made public its Initial Business Case for the Ontario Line, Queen Park’s proposed alternative to the Downtown Relief Line.
The entire document reads as if it were drenched in perfume with a rosy comparison of a modern, inexpensive Ontario Line to an expensive DRL complete with outmoded technology. It is as much a sales manual for the Metrolinx proposal as it is an apples-to-apples comparison. Indeed, the DRL comparator is doomed to look worse simply because it is the shorter version of the line. The intent is to convince the reader that no reasonable person would support any other scheme.
The chart below is one of many that inevitably shows the OL as superior for the simple reason that it covers more ground. The question is whether it can all be built for the price quoted and in the projected timeframe. There may be arguments for parts of the OL compared to the DRL, but the Metrolinx comparison goes out of its way to denigrate the DRL wherever possible and in the process reveals some short-sighted “planning” that is more a question of scoring political points than of giving a technical comparison.
Any new rapid transit line, regardless of technology, cannot help but succeed in the DRL/OL corridor given the density of population and jobs along its length. Contrary to the long-established Toronto practice of building rapid transit where politicians and their developer friends hope to spur local centres away from downtown, the DRL/OL corridor is packed with potential demand already. Even more demand will come from provision of an alternate route into the core from the existing crowded subway network.
Travel times from Thorncliffe Park and neighbouring areas to the core are substantially improved by a new line, no surprise at all.
Planning for downtown growth is years behind what is actually happening.
Population and Employment growth in Downtown Toronto has accelerated, and has already exceeded 2031 forecasts. Population growth is also very high in the Downtown; however population density itself is more diffused, with pockets generally along existing subway lines as well as in neighbourhoods with lower average household incomes. [p. 19]
At this point, the OL cost estimate is very preliminary because there is no detailed design for the line. From experience with other Toronto projects, we know that there is a very wide margin for error in cost estimates. Metrolinx flags several potential issues along their route, but gives no indication of how these might affect the design, the cost or the potential construction period. It is simply not practical or reasonable to give a “business case” or a “cost benefit ratio” when there is such a huge potential variation in the estimate.
Moreover, Metrolinx gives a discount to the Ontario line on the dubious pretext that with risk transfer to a private sector partner, the costs incurred will be lower. This depends on a very well-written and managed contract, as well as an owner (the province) willing to hold a loaded gun to the builder’s head if they don’t deliver. The 3P (a purpose created coalition) always has the option of going bankrupt, or asking for an enticement as happened to get the Crosstown project back “on time”.
CEO Phil Verster was filled with optimism speaking on CBC’s Metro Morning, but somewhat more guarded talking to The Star’s Ben Spurr:
On Thursday, Verster gave his clearest acknowledgement yet that it’s possible that date could end up out of reach.
“(The deadline of) 2027 is hugely ambitious,” said Verster, but “this is the time for us to be ambitious.” He asserted that by building much of the line above ground, it can be completed quickly.
But, said Verster, that when Metrolinx starts the procurement process next year, if the bidding companies say “it can’t be done in 2027,” his agency “will declare that immediately.”
That’s all very well, but delivering the full OL two years before the proposed completion of only the DRL South segment from Pape to Osgoode Station is a big selling point, along with the lower pricetag. Get double the line at only a modest extra cost, and get it faster. Who would choose anything else?