The Next Big Move (II): Where Is The Plan?

Two months ago, I wrote about the Regional Transportation Plan that Metrolinx had put out for public comment, and that period for online feedback has now closed. In the interim, I had hoped to see more details in the new plan, more analysis that could inform debate and feedback, but very little has appeared on the website where one might expect to see a wealth of background. Instead, there are three studies:

The last of these drew my attention first both because of its size and because this would be the place one would expect to learn how the draft network came to be, and what the benefits are expected from its components. Alas, that information is not just missing, it is not even hinted at as if it might exist in some deeper background study. Metrolinx provides a very general overview of the anticipated effect of their network, but little sense of the relative value of its components.

The purpose of the regional network study is quite clear:

This will serve as one of several technical background reports that will provide a foundation for the RTP Update.

The purpose of this Phase 1 report is to describe the preliminary recommendations for a 2041 strategic transit network for the RTP Update. This includes the identification, analysis and evaluation of potential transit projects and the development of a regional transit network to effectively meet existing and future transit needs across the region. Together, these activities comprise Phase 1 of the Regional Transit Network Planning Study.

Phase 2 of the study will support the RTP implementation plan, and will include the preparation of refined alternatives, specific recommendations, potential roles for various service providers, and a preliminary phasing strategy for the proposed strategic transit network. [p. 1]

In other words, don’t look for specifics here because they’re still working on the details.

Only one paragraph later comes a vital comment under the heading of “Regionally Significant Transit”:

While the provision of effective transit is dependent upon a fully integrated system with local transit supporting regional routes, this study focuses on transit projects
that are considered regionally significant. The resulting regional network is intended to link seamlessly with municipal transit services that are planned and operated
by GTHA municipalities. [p. 2]

Local municipally-provided services are an integral part of any network, but they are assumed to “be there” and are not the focus of this study. However, the funding and expansion of local transit is essential to the “last mile” problem where most regional network users access it via park-and-ride lots, a mode that is not sustainable for an expanded system. This is particularly important for trips that are not anchored at one end by a major destination node, or very good local transit. There is no point in making a trip through a “regional” station if there is no “local” service to complete the journey.

Continue reading

TTC Service Changes Effective January 7, 2018

There are few changes planned for the January 2018 schedules.

2018.01.07_Service_Changes

14 Glencairn is the latest of many routes to get additional running time compensating for the Crosstown LRT construction. Oddly, the end date shown for this change is December 2022 where all other Crosstown-related end dates are in 2021.

Supplementary service on 32 Eglinton West is being reorganized. There are currently several Service Relief buses operating from Mt. Dennis during most operating periods. These will be replaced by peak-only buses from various garages.

75 Sherbourne trips at the start and end of service are being changed to begin/end at Sherbourne Station rather than at South Drive in Rosedale.

The official route and stopping arrangements for various lines serving Finch West and Pioneer Village Stations have been clarified for periods when these stations are closed.

The TTC has already confirmed through the media that due to the late delivery of Flexitys from Bombardier, there will be bus substitutions on 505 Dundas and 506 Carlton starting with the February 18, 2018 schedules. This is also related to service reorganization to boost capacity on King Street. I will report the details when they are available.

(Bus trippers originally planned for 504 King are now actually operating on 505 Dundas replacing CLRVs that have been redirected to King Street for extra capacity.)

It should be noted that due to track construction on Broadview planned in 2018, there will be effects on the Carlton, Dundas and King routes that will probably last two schedule periods.