Updated Noveber 20, 2015 at 3:00 pm: Track construction at Russell Carhouse is now complete and overhead installation is in progress.
Updated July 28, 2015 at 12:20 pm: Photos of construction work in progress.
Updated July 3, 2015 at 5:40 pm: Photos of construction work in progress.
Updated June 24, 2015 at 5:00 pm: Photos of construction work in progress.
Updated June 6, 2015 at 10:00 am: Photos of Eastern Avenue construction from 1928 provided by John F. Bromley from his collection have been added to this article.
The ladder track at the south end of Russell Carhouse is being completely regraded and replaced in a project that will consume a few months. This is a joint project with the City of Toronto who are replacing a storm sewer that runs along the northern side of Eastern Avenue.
The track will not only be replaced, but it will be separated from a new sidewalk, and the track elevation will be changed to reduce the effect of turning and climbing at the same time into the tracks at the carhouse.
Eastern Avenue will be one lane each way in the new configuration. Because parking is allowed in curb lanes east and west of this area, a two-lane road is all that is needed to handle typical traffic volumes.

[Image from the City of Toronto Construction Notice]
Removal of the existing track is, as of June 2, complete. Carhouse operations are more complex than usual with cars having to back into their storage and maintenance locations. Originally, the TTC would have had Leslie Barns at least partly available for storage, but that site and its access track are still under construction.
-
-
Looking W on Eastern Avenue from Connaught.
-
-
The south entrance to Russell Carhouse.
-
-
Looking NE to the carhouse.
-
-
The west end of Russell Yard looking north.
-
-
Looking E on Eastern Avenue.
The original ladder track on Eastern Avenue was further south. The change is visible in these construction photos from 1928 provided by John F. Bromley from his collection.
-
-
Looking E from Minto St on Eastern Ave
-
-
Looking E on Eastern Ave
-
-
Looking W on Eastern Ave from Connaught
Updated June 24: Construction work in progress
-
-
June 18: Looking W on Eastern from Connaught
-
-
June 18: S entrance of Russell Carhouse
-
-
June 24: S entrance of Russell Carhouse
-
-
June 24: S entrance of Russell Carhouse
-
-
June 24: Looking E on Eastern from Minto
Updated July 3: Construction work in progress
-
-
July 3: Looking W on Eastern from Connaught
-
-
July 3: S entrance to Russell Carhouse from SE
-
-
July 3: S entrance to Russell Carhouse from SW
-
-
July 3: Looking E on Eastern toward Connaught
Updated July 28: Construction work in progress
-
-
July 28/15: Looking NW to Russell Yard from Eastern
-
-
July 28/15: Looking NE to Russell Carhouse from Eastern
-
-
July 28/15: Looking E on Eastern Ave from Minto
Updated November 20: Overhead installation in progress
-
-
Nov 20/15: Looking W on Eastern Ave at Connaught
-
-
Looking W on Eastern Ave, north side, from Connaught
-
-
Nov 20/15: Looking E on Eastern Ave showing new north sidewalk
-
-
Nov 20/15: Looking E on Eastern Ave
-
-
Nov 20/15: West end of Russell Yard