Robert Wightman sent in this update:
Since I retired again on May 31st (I do this every 6 months or so) I have been driving around and have a few observations on GO construction:
The three track section on Lakeshore West from Burlington to Bayview Junction is finished and new signalling has been installed. The signals are no longer searchlight but three (or in some cases two) aspect LED signals. They look quite sharp. The north track only goes up the Dundas sub and the South track only continues into Hamilton whilst the middle track can go to either.
Most of the track on the Barrie extension has been relayed with 115 lb. continuous welded rail. Every level crossing is having crossing gate installed including the one that runs about 200 yds to a farm house. The Station area at Allendale (Barrie) is all fenced off and levelled. There is a concrete foundation for what appears to be a sub station behind BDO Dunwoody. It looks like the parking lot here will be 200 to 300 feet wide and a mile long. Maybe they will have one long loading platform and you can park either beside where you get on or where you get off. All the new stations on this line are architecturally similar to the original stations which have been completely refurbished. The station in Bradford has, it appears, just been refurbished including the pole that held the train order semaphores. This line is supposed to open later this year.
The track work on the Georgetown line from Bramalea to Mt. Pleasant is proceeding as almost all of the bridges have been widened and in some places grading has started for the additional track. CN has started to replace the existing signals with gantries to hold the signals for the extra track and all the heads are 3 aspect LED signals like on Lakeshore.
They are going to have problems at the Brampton Station — is it is effectively one track east of the station and you very seldom get two trains passing there. People have gotten used to running behind the trains as soon as it has cleared Church Street to get to the train. When it is two tracks some one is going to get killed as they get hit by a through freight going the other way. They have had police out telling people that it will soon be two way all the time but it won’t help. It will be interesting to see the platform on the South side as it will be at street level at the West end and elevated at the East end, the Brampton EL, or is it L?
I do not venture out to the East end much so I have no idea what is happening there. The GO trains have disappeared from Guelph Junction so I assume the new storage yard in Milton is built. I have seen work going on at the Lisgar Station and it is supposed to be open in the fall.
If I see anything new I will report.
Robert Wightman