Metrolinx Contemplates Relief (2)

This article is a continuation of a previous commentary on the Metrolinx Yonge Network Relief Strategy.

On February 14, 2014, the Metrolinx Board considered the presentation on the Yonge Network Relief Study, but little information was added in the debate.  One question, from Chair Robert Prichard, went roughly “shouldn’t this have been started two years ago”, but it was left hanging in the air without a response.  Two years, of course, has brought us a new Provincial Premier and a recognition that her predecessor’s timidity on the transit file wasted a great deal of time.

Moreover, there is a long overdue acknowledgement that Metrolinx cannot simply plan one line at a time without understanding network effects including those beyond its own services.

Originally, I planned to leave the next installment in this discussion until public consultation sessions began, but I have now decided to make some brief comments on the various options that will be on the table.  (See Yonge Network Relief Study, page 11.)

Continue reading

Metrolinx Contemplates Relief

At its meeting on February 14, 2014, the Metrolinx Board will receive a presentation on the Yonge Network Relief Study. Despite the need for better regional transit links (and by that I mean links that do not take people to downtown Toronto), the elephant in the room has always been the unstoppable demand for more capacity into the core area. Planning for and debates about catching up with the backlog of transit infrastructure cannot avoid this issue, and it skews the entire discussion because the scale and cost of serving downtown is greater than any other single location in the GTHA.

Conflicting political and professional attitudes across the region colour the view of downtown.  Toronto suburbs, never mind the regions beyond the city boundary, are jealous of downtown’s growth, and for decades have wanted some of the shiny new buildings and jobs for themselves. But the development, such as it was, skipped over the “old” suburbs to new areas in the 905 that could offer lower taxes possible through booming development and the low short-term cost of “new” cities.

Strangling downtown is not a new idea, and politicians decades ago foretold of gleaming suburban centres to redirect growth together with its travel demand. The transit network would force-feed the new centres, and downtown would magically be constrained by not building any new transit capacity to the core.

Someone forgot to tell GO Transit where service and ridership grew over the decades. Downtown Toronto continued to build, and that is now compounded by the shift of residential construction into the older central city.

Thanks to the early 1990s recession, the subway capacity crisis that had built through the 1980s evaporated, and the TTC could talk as if more downtown capacity was unneeded. To the degree it might be required, the marvels of new technology would allow them to stuff more riders on existing lines. A less obvious motive was that this would avoid competition for funding and political support between new downtown capacity with a much-favoured suburban extension into York Region. Whenever they did talk about “downtown relief”, the TTC did so with disdain.

Times have changed. Long commutes are now a burden, not a fast escape to suburban paradise. Every debate starts with “congestion” and the vain hope that there is a simple, take-two-pills-and-call-me-in-the-morning solution. Top that off with an aversion for any taxes that might actually pay for improvements, or sacrifices in convenience until that blissful day when transit arrives at everyone’s doorstep.

Continue reading

Streetcar System News – February 2014 (Updated)

Updated February 11, 2014 at 10:00 am:  Questions & answers related to trackwork plans and new streetcars have been added.

Spadina / Queens Quay Update

To nobody’s great surprise, the restoration of streetcar service south of King Street on Spadina will not occur until June 21 rather than with the schedule change in late May as originally hoped. This is a direct result of the bad weather and poor construction conditions. The TTC’s position is:

Due to the delays in Waterfront Toronto’s work and the need for TTC work to follow in series (i.e. overhead), it is not anticipated that the loop will be available for service for the May Board Period. Once we have greater clarity, we will reflect that online.

Some preliminary work on suspension for the new overhead has already been done, but this cannot be completed until the track is in and overhead vans can drive on the new pavement at the loop.

As plans now stand, service will resume on both the 510 Spadina and 509 Harbourfront routes with the re-opening of new streetcar track on Queens Quay rather than in two stages as originally hoped.

I await detailed info from Waterfront Toronto on updates to their construction plans. Much of the utility work on the south side of Queens Quay is now completed, and traffic is shifting to that side of the road at least as far west as Rees Street. This move will allow work to begin on the new streetcar right-of-way in the middle of Queens Quay and the construction of the new permanent roadway on the north side.

Detailed construction news updated weekly is available on Waterfront Toronto’s Queens Quay project page.

No sooner will streetcar service resume on southern Spadina, but the route will convert to bus operation for two track projects likely in August. The intersection at Dundas will be rebuilt this year (the one at College has been deferred because of scheduling conflicts), and there will also be work at Spadina Station.

When the line reopens on August 31, service will be provided, at least in part, by the new low-floor streetcars.

Updated February 11, 2014:

Q: What work is planned at Spadina Station? Track? Platform – especially provision so that two new cars can be on the platform at once – one loading, one unloading. Only 3 CLRVs fit there today.

A: The TTC has placed two low floor streetcars at Spadina already. They can physically fit inside the station, although the lead module of the lead car would have to be positioned opposite the five pillars with glass curtains, and that the lead door would be on curved track with a wider gap between the vehicle and the platform. We are reviewing operating procedures and possible alterations that are necessary to allow two new cars to be on the platform at the same time if necessary.

This implies that the work to be done in August will be trackwork, not platform changes.

New Streetcars

Recently, I sent questions to the TTC about the status of new car production and the implementation of these vehicles. Here are the replies:

Q: What is the status of the order and when will production deliveries begin?

A: Production deliveries will begin in March.

Q: What will be the rate of deliveries?

A: As always planned, there will be a ramp up to the production rate of 3 per month (36 per year). Once stabilized at this rate there are opportunities to transition to a higher rate and this is currently under investigation.

Q: What effect will this have on planned retirement of the problem ALRVs before the next winter season?

A: ALRVs will begin retirement at the end of this year and throughout 2015 as more new streetcars enter service.

What is still unclear is how the TTC will adjust service on 504 King and 501 Queen as the ALRVs [the existing two-section streetcars] disappear from the fleet and these routes continue operation with the remaining CLRVs [the shorter, single-section cars].

Updated February 11, 2014:

Q: Are there outstanding issues still to be dealt with on the ramps in the new streetcars, or have whatever design tweaks were necessary been incorporated in the production versions we will receive?

A: There are still a number of outstanding issues to be resolved. The production vehicle will have the necessary structural changes made to receive the new ramps. However, there is a transition phase between cars going into revenue service and when the final version of the ramp is delivered. For a number of vehicles that will go into service, an interim ramp will be incorporated to improve on accessibility – with improved transition between the ramp, the door threshold and the interior car floor. The final production version will be lighter in weight, less demanding on the drive mechanism (hence more reliable), and will have faster deployment and retrieval times. Initial production cars that do not have the latest ramp configuration will be retrofitted with the final version as part of the configuration control process.

Capital Budget Cuts

Among the City-imposed cuts in the Capital Budget was a $10-million/year cut in surface track maintenance for 2014 to 2018 with an equal cut to subway track in 2019 to 2023. I asked about the effect of these cuts.

State of good repair, which track replacement is clearly part of, will not be affected. If we need to further cut the capital budget to do track work, we’ll find that money elsewhere.

Queen East Major Track Projects

Two major projects will affect streetcar service on Queen Street East this spring.

At Queen and Leslie, the new sewer line must be tied into existing infrastructure under Queen Street, and then the new special work for the track leading to Leslie Barns must be installed.   Tentative plans are for this work to begin in mid-May and run to the end of June.

While Queen Street is closed, service will operate with bus replacements and streetcar diversions:

  • A 501 Queen bus will run from McCaul Loop to Woodbine Loop (at Kingston Road) diverting around construction via Jones, Dundas and Greenwood.
  • 501 Queen, 502 Downtowner and 503 Kingston Road Tripper streetcars will divert via Broadview, Gerrard and Coxwell.
  • Carhouse trips for 504 King and 505 Dundas that now operate west from Russell Carhouse via Queen will use Coxwell and Gerrard.

Beginning at the end of June and running through July, the special work at Broadview and Queen will be replaced. This intersection is in poor condition with long-standing slow orders and one switch (west to north) permanently out of service due to a danger of derailments.

During this work, service will operate as below:

  • The 501 Queen bus will divert via River, Dundas and Carlaw.
  • 501 Queen, 502 Downtowner and 503 Kingston Road Tripper streetcars will divert via Parliament, Gerrard and Coxwell.
  • 504 King cars will divert via Parliament and Dundas.
  • Carhouse trips to Russell will continue to operate via Coxwell.

Normal service on all routes resumes in August.

King Street Diversion

New February 11, 2013:

Q:  The 504 King diversion around construction at the Don Bridge is now listed as running to August due to additional work in the area.  I understand that the track connection at Sumach to the new Cherry Street line is to go in this year.  Will this be done while the 504 is on diversion (ie before August), or will there be yet another shutdown for this trackwork too?

A:  The Sumach/King connection work is scheduled for March 30.

Transit Priority for Diversions:

Q:  With the extended period of various diversions, why has there been no change to implement transit priority or at least advance greens for left turns at various locations?

A: We continue to work with the City on transit priority signalling. There are no new installations to date; where there, they are in use. Advance greens and the like is a question better put to the City.

I am meeting with Stephen Buckley, Toronto’s General Manager of Transportation Services, on February 12 and will discuss this issue with him.

[TTC comments provided by Brad Ross via email on February 7, 2014.  Updates by email on February 11, 2014.]

TTC Service Changes Effective February 16, 2014

The February 2014 schedules bring only minor changes on the system.

Exhibition Place

A new “walking transfer” will be added between services in the south end of Liberty Village and Exhibition Loop. This will link 63 Ossington at Atlantic and Liberty Streets to the 511 Bathurst, 509 Harbourfront and 29 Dufferin routes at Exhibition Loop.

Walking transfers are a quaint part of the TTC’s fare system where connections are permitted between routes that do not actually meet, but which operate nearby. This practice (and the rules governing where it is allowed) will not be needed as an exception within the overall system if the TTC moves to time-based fares.

A temporary Dufferin Street bridge will allow 29 Dufferin service to resume its operation into the park.  Service will be the same as in March 2013.

York Region Contracted Services

These changes are at York Region’s request.

The last afternoon peak trip of the 17A Birchmount route north of Steeles will be eliminated.  This trip now leaves Steeles northbound at 6:53, and returns from Royal Crest southbound at 7:06.

The last late Sunday evening trip of the 102 Markham Road route north of McNicoll will be eliminated.  This trip now leaves Nashdene & Markham at 11:14 pm and returns from Mount Joy GO Station at 11:42 pm.

An earlier trip will be added to 105B Dufferin North from Major Mackenzie on weekday mornings.  This trip will depart southbound at 6:29 am.

Pearson Airport Night Services

300 Bloor Danforth and 307 Eglinton West will change to use the same sequence of serving terminals as the daytime 192 Airport Rocket and 58 Malton routes. There will be no change in service levels, but scheduled times at stops will be altered by the new routing.

Other Service and Route Changes

142 Downtown Avenue Road Express was changed in late December by the elimination of a trial extension of its downtown loop west to Peter Street. This is now formally implemented in the scheduled route.

Service on 509 Harbourfront will be reduced in response to lower riding, and schedules will be changed to “improve reliability” with additional recovery time.

Service on some routes will be modified by adjustment of running and recovery times to improve reliability. Service levels are not affected, but some trip times will change.

  • 41 Keele will be modified in the evening on weekdays.
  • 30 Lambton will be modified during many periods, and recovery time will be shifted to Kipling Station to reduce bus idling at High Park Station.
  • 73 Royal York will be modified during peak periods.

Service to the Zoo on 86 Scarborough and 85 Sheppard East will be modified to reflect the change in closing time to 6:00 pm effective March 1, 2014.  Last trips will leave the Zoo at about 7:00 pm.

Service on 91 Woodbine will be changed on weekends to improve reliability with headways on both the 91C York Mills and 91A Parkview Hills branches changing from 20 to 24 minutes to provide extra running time.

The Gardiner Expressway and Transit to Downtown

The City and Waterfront Toronto are holding a public meeting to present an update on the future of the eastern section of the Gardiner Expressway.

Bluma Appel Salon
Toronto Public Library, Yonge North of Bloor
Thursday, February 6, 2014 from 6:30 pm to 9:00 pm

A media briefing on February 5 introduced the material, and there is widespread coverage in the mainstream press that I will not duplicate here. My interest lies more in the relationship of the expressway to travel demand generally, and to the importance of transit for the future development of central Toronto.

The media presentation contains information that will be included in the public meeting, and illustrations here are taken from that file.

StudyArea

The section of the Gardiner under study extends east from Jarvis Street to the Don Valley Parkway, plus the ramp down to Lake Shore Blvd. east of the Don River. It is important to remember what is not being changed.

  • From Jarvis Street west, the existing expressway will be rebuilt under a multi-year program stretching to about 2019.
  • The south end of the DVP will be modified only to the extent needed to connect in with whatever new or revised structure might be built.
  • The ramp down to Lake Shore will remain in its current form except if the Gardiner is removed, in which case the ramp will be demolished and a new Lake Shore will cross the Don on a bridge at grade.

The Gardiner’s design capacity was scaled for connection to a future Scarborough Expressway that was never built, and the structure east of Jarvis is wider than is needed for the demand. This section gives the greatest opportunity for reworking, and releases the most land around the expressway in any new configuration.

Continue reading

Will The TTC Board Ever Discuss Policy, or, Good News Is Not Enough (Updated)

Updated January 21, 2014 at 2:20 pm:  The description of the loading standards introduced with the Ridership Growth Strategy has been corrected.

The election season is upon us in Toronto, and transit made an early appearance on the campaign with mayoral candidate David Soknacki’s proposal that Toronto revert to the LRT plan for Scarborough.  I am not going to rehash that debate here, but there is a much larger issue at stake.

The Ford/Stintz era at Council and at the TTC has been notable for its absence of substantive debate on options and alternatives for our transit future.  Yes, we have had the subways*3 mantra, the palace coup to establish Karen Stintz and LRT, for a time, as a more progressive outlook on the TTC Board, and finally the Scarborough debate.

But that’s not all there is to talk about on the transit file.  Do we have a regular flow of policy papers at Board meetings to discuss what transit could be, should be?  No.  Ford’s stooges may have been deposed, but the conservative fiscal agenda remains.  Make do with less.  Make sacrifices for the greater good, whatever that may be.  Show how “efficiency” can protect taxpayer dollars even while riders freeze in the cold wondering when their bus will appear.

Every Board meeting starts with a little recitation by the Chair of good news, of stories about how TTC staffers helped people and the good will this brings to the organization.  There is ever so much pride in improved cleanliness and attractiveness of the system – a worthwhile achievement, but one that should become second nature to maintain.  It should also be a “canary in the coal mine”, a simple, obvious example of what happens when we make do with “good enough”, with year-by-year trimming to just get by.

If the bathrooms are filthy, imagine the condition of the trains, buses and streetcars you are riding.  I’m not talking about loose newspapers blowing around, but of basic maintenance.  From our experience in the 1990s, we know how a long slide can take a once-proud, almost cocky system to disaster, and how hard it is to rebuild.

In a previous article, I wrote about the threat to basic system maintenance posed by underfunding of the Capital Budget, an issue that has not received enough public debate.  Part of the problem is that the crucial maintenance work that must occur year over year is treated the same way as new projects.  Maintenance competes with the glamour projects for funding, and may be treated as something to be deferred, something we don’t need yet.  Couple that with starvation of funds for basics like a new and expanded fleet and garage space, and there’s a recipe for a TTC that will decline even while more and more is expected of public transit.

The budget isn’t the only issue that deserves more detailed examination, and many other  policies should be up for debate.  Within a month, the TTC will have a new Chair as Karen Stintz departs for the mayoralty campaign.  Within a year, Toronto should have a new Mayor, one whose view of transit is not framed by the window of his SUV.  At Queen’s Park we may have a Liberal government with a fresh, if shaky, mandate to raise new revenues for transit construction and operation, or we may have a populist alternative with a four-year supply of magic beans.

In the remaining months, the TTC Board has a duty to lay the ground for the governments to come, especially at City Hall.  The 2015 budget debates should be well informed about the options for transit, if only for planning where Toronto will need to spend and what services the TTC will offer in years to come.  Will the TTC rise to this challenge, or sit on its hands with a caretaker Board until the end of the current term?

Here is a selection of the major policy issues we should be hearing about, if only the TTC would engage in actual debate to inform itself, Council, the media and the voters.

  • Fare structure:  What is the appropriate way to charge fares for transit service?  By time, distance, week, month?  How does smart card technology change the way fares are collected and monitored?  What are the implications for regional travel and integration?
  • Service standards:  What loading standards should be used to drive service improvements?  Should the TTC build in elbow room to encourage riding and to reduce delays due to crowding?  Should there be a core network of routes with guaranteed frequent service?
  • Service management:  What goals should the TTC aim for in managing service?  Do the measures that are reported today accurately reflect the quality of service?  Are bad schedules to blame for erratic service, or does this stem from management indifference or from labour practices that work against reliable service?  What are the tradeoffs in the relative priority of transit and other traffic?  What are the budgetary effects of moves to improve service?
  • Budgets and Subsidies:  Both the Operating and Capital Budgets have been cut below the level recommended by TTC management.  These cuts will affect service and maintenance in the short and long term, but there has been no debate about the effect, especially if these are not quickly reversed in a post-Ford environment.  The Capital Budget faces a huge gap between available funding and requirements.  Over ten years, the shortfall is 30% in available financing versus requirements, and this is back-end loaded so that the shortfall rises to 50% in later years.  The proposed level of City subsidy is barely half what would be needed if Queen’s Park returned to its historical 50% capital funding formula.  Hoped-for money from Ottawa is more likely to finance major projects such as new subway lines, not the “base” budget for capital  maintenance.  The budget, especially capital, is not well understood by the TTC Board or Council in part because of the confusing way in which it is presented.  Toronto cannot begin to discuss subsidy policies if those responsible for decisions cannot understand their own budgets.
  • The Waterfront:  While battles rage over subway and LRT proposals for the suburbs, a major new development on the waterfront is starved for transit thanks to cost escalation, tepid interest by the TTC, and the perception that waterfront transit can be left for another time.  The pace of development may be threatened if good transit does not materialize on Queens Quay, and later to the Port Lands, but meanwhile this project sits on the back burner little understood by most members of the TTC Board and Council.
  • Rapid transit plans:  The artificial distinction between GO and the subway (or even higher-end LRT operations such as the proposed Scarborough line) will disappear as GO becomes a frequent all-day operation.  There will be one network regardless of the colours of the trains.  GO service to the outer parts of the 416 is particularly important as an alternative to subway construction serving long-haul trips to downtown.  Subways, LRT and BRT each has its place in the network, but electoral planning must not leave us with fragments of a network rather than an integrated whole.
  • Accessibility:  The need for accessibility extends all the way from the severely disabled who require door-to-door service, through a large and growing population who have some degree of independence, to those whose only problem may be bad knees or a weak heart.  Neither the TTC nor the City has taken the issues of accessibility particularly seriously in recent years.  There may be good words, but the budget and service policies clearly limit the growth of the parallel Wheel Trans system.  Meanwhile, retrofitting the system for full access is delayed thanks to funding limitations at both the City and Queen’s Park.  What we do not know is the true extent of the need for accessibility on the TTC and what this means for service and infrastructure.

Continue reading

Construction That Never Ends (Update 4)

Updated November 14, 2013 at 6:20 pm:

According to the TTC CEO’s report for November, the date for resumption of streetcar service on Queens Quay has been changed to June 21, 2014.  Brad Ross of the TTC advises that their website will be updated to reflect this new target date.

Updated October 26, 2013 at 4:32 pm:

According to the TTC CEO’s report for October (at page 20), service will not resume on Queens Quay until August 2014, not the end of June as previously reported.  I have asked the TTC to verify this date and explain why completion has slipped yet again.

The TTC memo listing service changes for the November and December schedule periods came out today, and it contains a few startling items:

  • The Yonge Subway tunnel liner program, originally expected to wrap up at the end of 2013, will now run an additional year to the end of 2014.
  • The loop at the foot of Queens Quay will not be available for service as expected in November, and service on the 510 streetcar will not resume until mid-February 2014.
  • The track on Queens Quay itself will not be available for service as expected in December/January, and service on the 509/510 streetcar will not resume until the end of June 2014.

Updated October 2, 2013 at 10:25 am:

Waterfront Toronto has posted a Construction Update for the Queens Quay project.

Updated October 1, 2013 at 6:00 pm:

Yonge Subway Tunnel Liners

I have received a note from Brad Ross at the TTC explaining the current situation.  The work has proven more extensive both in complexity and scope than originally thought.  In reply to one comment in this thread, I gave the opinion that all of the asbestos had been removed from the tunnels, but according to Ross, there is still some present and this adds to the slowness of the work.

The tunnel liner project involves the inspection of some 10,000 tunnel liners. To date, 4,000 liners have been inspected, 950 identified in need of repair, and 850 of them repaired. The process is not a speedy one as many of the liners are covered in material, including asbestos, which needs to be removed before a liner can be inspected. Add to that the time it takes for crews to get to the work location, set up, clean up, and return to the yard. As we examine liners, we’re identifying more and more that need to be repaired, mostly due to water damage. In short, the project timeline increases as the work involved increases. We are now working to determine what a reasonable completion date might look like and what the overall impact to subway service north of Eglinton will be over the next 12-18 months. Once we have that, we’ll communicate it widely.

[Email from Brad Ross, Executive Director, Corporate Communications, TTC, October 1, 2013]

Waterfront Toronto Queens Quay Project

I met with Waterfront Toronto staff to discuss the status of the project.  They have issued a construction update detailing the current situation.

Because the lanes occupied by the TTC right-of-way are essential as extra space into which construction or temporary road lanes can be shifted for utility work, the new trackbed cannot be laid down until all utility work requiring traffic diversions in an area is completed.

This work has been affected by a number of factors notably:

  • A late start by Toronto Hydro who did not receive funding approval for their Capital Program from the Ontario Energy Board in time to meet the original schedule.
  • Ground water conditions that at some locations were more challenging than expected.
  • Subsidence and resulting damage to existing utilities when areas were de-watered for construction access.  This was anticipated, but the extent of the problem is hard to gauge before the work is actually done.

The area around Spadina and Queens Quay has many utilities competing for space and for construction access.  Some planned work has been complicated by new, more stringent provincial labour safety standards for work near live hydro lines.

Most of the splicing chambers for the new track are complete, but one critical one that will feed Queens Quay Loop is inaccessible at present due to competing work in the same area.  This has slowed installation of the grounding cables for the loop which will tie back to that chamber.

The intent is to have the trackwork in the loop finished by yearend.  TTC would then install its overhead in preparation for service at the start of the February 2014 schedule period which will fall in the middle of the month.  The track installation will likely be done mainly in November, and partial shutdowns of the streets around the loop will be required.

There are three sets of special work (loop entrance from Queens Quay, loop exit to Spadina and the Spadina & Queens Quay intersection).  A preliminary plan for this might have broken the work into three stages, but Waterfront Toronto hopes to consolidate this into two.

A further complication will be the partial closing of Lake Shore Blvd. to complete the track connection south from new rails on Spadina.

Waterfront Toronto expects to publish details of the work schedule soon.

As for the tangent track on Queens Quay, the major constraint is that the space cannot be given up until utility work in a section is clear.  The intention is to build the foundation slab in pieces as various sections of the roadway become available.  Track installation would be completed in spring 2014, followed by overhead catenary, with a target date for streetcar service in late June.  (If the schedule periods for 2014 follow the same pattern as in 2013, this would be Sunday, June 22, 2014.)

Waterfront Toronto’s work plan for summer-fall 2014 will concentrate on the area south of the streetcar right-of-way which will contain the new cycling path, an expanded pedestrian area, and many trees.  Some finishing work will occur in early 2015 in advance of the Pan Am Games.

What is frustrating about all of this is that the delay in Hydro’s approval at the OEB was well known a year ago, and Waterfront Toronto has maintained rather hopeful dates for resumption of service that strained credibility as the construction wore on and on and on.

TTC Board Meeting October 23, 2013 (Update 3)

Updated October 26, 2013 at 5:20 pm to reflect discussions at the meeting.

The TTC Board met on October 23.

Update: The 2014 Operating and Capital Budgets are still not public, and they may now  appear in November (this has yet to be confirmed).  This is unusual because under Mayor Ford, the budget process for the City has been moved up so that the overall budget can be finalized early in the new year.  In 2012, the TTC budgets for 2013 were on the September agenda.

Will the TTC roll over again and accept a flat-lined subsidy placing the entire burden of extra costs on riders through fare hikes and compromises on service quality, or will they finally argue for better subsidies and force Council to debate just what transit should be doing – aside from building one subway line – for Toronto?

The CEO’s report (below) offers a hint in this statement:

“… discussions with the City continue regarding the TTC Operating and Capital Budget submissions for 2014-2023.  I am resolute in expecting an increase in subsidy to accommodate and service ever increasing customer numbers.”  [page 5]

Does this represent a strategic position on the TTC’s part, or division among the Commissioners about the direction the organization should take?

The City of Toronto will launch its 2014 budget process formally on December 2, 2013.

New Wayfinding Standards

Recent reports in other media have talked of a proposal to rename the subway lines with numbers to simplify wayfinding information for riders.  The details of this and other schemes to overhaul information will be presented at the meeting.

Updated October 23 at 10:55am:  The presentation is now online linked from the title above.

Updated October 26 at 5:00pm:  This topic will be split off into a separate thread given the volume of comments, and the accumulated comments will be moved to the new thread.

CEO’s Report

The CEO’s report has little new relative to the September edition.  Riding continues to be above 2012 but below budget.  For reporting period 8 (mainly the month of August), riding was up 3.5% over 2012.  On an annualized basis, riding is up 2.8%.  These results are 0.1% below budget for the period, and 0.5% below budget for the year to date.

Total ridership for 2013 is projected to be 527m, 1m below the budget projection.  This shortfall, coupled with higher-than-expected sales of passes versus token/cash fares, will mean revenue will fall $7.6m below budget.  This will be counterbalanced by various swings plus and minus on individual expense lines (details on page 24).

Update:  According to CEO Andy Byford, the lower ridership and revenue numbers for 2013 are mainly attributed to the severe weather and floods earlier in 2013.  Major shutdowns planned for 2014 will definitely affect ridership and this will be built into the budget estimates.

Subway punctuality on the Yonge-University line remains a problem particularly in off-peak hours.  It is unclear how much this is a side-effect of the yardstick of headways within ‡3 minutes of scheduled values.  During peak periods, it is much easier to meet this goal because there are more trains on the line, and entire trips can be missing without headways going beyond the 3-minute rule.

The BD line problems occasionally from the transfer of trains to the Yonge line to “cover shortages”, although this is not explained.  Are there simply not enough working trainsets to operate the Yonge service, or are BD trains poached to fill major service gaps?

Update:  I have asked the TTC to clarify what this section of the report actually means.

As if the wait hasn’t been long enough already, the CEO’s report states that the Harbourfront line will not return to streetcar operation until August 2, 2014.  No reason is given for the further slippage between the July date given by Waterfront Toronto and the TTC’s new August date.

One major issue that the CEO’s report does not address is the fleet availability in Toronto.  Only through the shutdown of substantial chunks of the streetcar system has the TTC managed to field enough cars to cover what remains in operation.  It is in their interest to prolong construction projects until they can get the first of the new fleet on the road.  What was originally touted as a “spring” startup of LFLRV service may now well slip to at least “summer”.

Production deliveries of cars are supposed to start later this fall.  What is the status of this order?

Service reliability is supposed to be reported quarterly for all surface operations, but the third quarter report has not yet appeared (it is expected to show up sometime on October 21).  When it does, I will be reporting separately on comparisons of the numbers over the past three quarters of 2013.

Update:  The quarterly report was published on October 23 and has been discussed elsewhere on this site.

I will follow up on questions raised here with TTC staff at the meeting and will update the article when further info is available.

TTC Fare Policy – Requests For Fare Discounts

This is a compendium report on various proposals/requests the TTC has received for reduced fares for various groups.  The staff position is that any additional subsidies for various classes of riders must be funded through a policy decision at City Council with adequate funding through the subsidy stream to offset the projected revenue losses.

This has been the TTC’s stock position for such requests for years, but at least we now have a consolidated report listing the projected cost for each option.  If Council wants to fund new discounts, the expected cost is known presuming that we accept the TTC’s estimates (some of which are dubious).

  • Extending “Family Pass” (6 people, maximum 2 adults) pricing to the entire week.  This is projected to cost only $2.2-8.6m per year, although I am suspicious of the figure because it is based on existing pass sales.  If the pass is more attractive, then more of them will be sold, but the estimate does not take this into account.
  • Free off-peak trips for seniors.  The cost is estimated to be at least $22m per year based on the number of non-pass trips by students/seniors today (45.2m), subdivided by the proportion of seniors (40%) and then the proportion of off-peak trips (65%).
  • Off-peak only pass for seniors.  The technology to handle time-of-day passes does not exist on turnstiles today, and so this option would best be left until Presto is rolled out across the system.  The estimated annual cost is $1.0-2.1m, but this depends on various assumptions regarding pass pricing, trip counts and conversion rates from the existing all-day passes.
  • Lower age for “senior” passes to 60 from 65.  The estimated cost is $3.3-4.9m, but this includes only the lost revenue from existing Metropass holders switching to the lower-priced pass.  No provision is included for token users for whom the senior’s Metropass would be more attractive than continuing to pay single adult fares.
  • Extend senior/student fare pricing to ODSP and OWP recipients (these are the Ontario Disability Support and the Ontario Works programs).  This is projected to cost $6.3-12.6m, but the mechanism for administering these fares is not discussed.  Of particular note, the calculation is based only on the actual recipient numbers within Toronto, not on their dependents and spouses.

Any special fare regime will be easier to administer once automatic fare collection is in place.  Time-of-day discounts and special fares associated with a rider’s status can be build into the fare structure, and the actual amount of discount provided for each target group can be tracked.  This will be important if special subsidies are involved so that they remain separate budget lines rather than simply merging into the overall TTC revenue stream.

Advisory Committee Activity

An interesting read in recent TTC agendas has been the meeting minutes for the Advisory Committee on Accessible Transit (ACAT).  This is a very active group whose discussion cover a wide range of issues with TTC staff, and the minutes report their activities in detail.

One might wish for the Customer Liaison Panel to be as forthcoming with information on its activities.  It is unclear whether the CLP has done anything since its formation, or what its areas of focus might be.  If the panel is intended to represent “customers” as part of TTC activities, why doesn’t it show the rest of the world what it is doing?

Supplementary Agenda

Yorkdale Fatality of September 14, 2012 – Final Investigation Report

This report contains the detailed findings regarding an accident last year in which a work car struck two employees during overnight maintenance near Yorkdale Station.

[New] York University Station Construction Status

Councillor Perruzza addressed the Board on the issue of York University Station where, as reported in the National Post, the station excavation is a lake, and no work appears to be in progress.

According to TTC staff, the tunnel construction contractor, Obrascón Huarte Lain and FCC Construcción, has handed off the site to the station contractor, Ellis-Don, but this process has taken longer than expected.  Meanwhile, Ellis-Don did not take over pumping of water even though they were now responsible it.  This is to be corrected, and Ellis-Don will begin active work on the site in 2-3 weeks.

Construction at this location was substantially delayed due to a worksite fatality in 2012.

[New] Time-Based Transfers for Eglinton West

Commissioner Colle requested a report from staff on the implementation of a time-based transfer arrangement on Eglinton West during the Crosstown tunnel construction similar to the setup still in use on St. Clair Avenue.  The TTC will ask Metrolinx to contribute to the cost of this if it is implemented.

[New] GO/TTC Fare Integration at Dundas West and Exhibition Stations

Chair Stintz requested that staff report on the provision of a joint TTC/GO fare between Union Station, Dundas West and Exhibition Stations as a way of relieving demand on the system, notably on the 504 King car.  The report should be on the November agenda.

Moving People Downtown: The Gardiner East Is Only The Beginning

On October 16, 2013, the second public meeting in the Gardiner East Environmental Assessment presented additional information and refinement of the options for dealing with the expressway’s segment between the Don River and Jarvis Street.

The purpose of the meeting was to report on the options that would receive further analysis in the next step of the EA and to provide comparative information about costs and benefits of the various schemes.  Broadly, there are four families of options:

  • Maintain the existing expressway with necessary repairs to make it sound for several decades’ more service.
  • Replace the expressway on a new structure either above or below ground.
  • Improve the existing expressway by selective reconstruction to open up space under the road deck.
  • Remove the expressway and create an at-grade boulevard.

Some options have been dropped from further study:

  • An underground alignment 1km long transitioning to/from existing elevated structured at the Don and at Jarvis.
  • An elevated alignment over the rail corridor.
  • A surface alignment on a berm abutting the south side of the rail corridor.

For any tunnel option, an important consideration is that most of the traffic arriving from the DVP and Lake Shore East is bound for the core area rather than as through trips to the western side of Toronto and beyond.  Therefore, access ramps are essential to any option that is not at grade so that traffic can actually get to downtown.  (By contrast, the “Big Dig” in Boston provided a link between the north and south sides of the core area on a route where 80% of the travel is through traffic and does not create demand for local ramp structures.)

The study claims that 80% of inbound trips have downtown destinations and this argues against a tunnel from which access would be difficult.  However, consider the origin-destination charts on page 15 of the presentation:

GE2P15

Of the traffic arriving from the DVP:

  • 40% leaves at Richmond Street
  • 7% exits to Lake Shore
  • 53% continues onto the Gardiner East, subdivided as
    • 10% exits at Jarvis/Sherbourne
    • 25% exits at Spadina/York/Bay
    • 18% travels beyond downtown.

If we were contemplating a tunnel across all of downtown, the argument about ramps and O-D patterns would be valid, but in this case, from the point of view of such a tunnel, most traffic is “through” traffic.  Only 10% of traffic that would enter a tunnel westbound at the Don leaves at Jarvis, and even this would be served if an off-ramp were incorporated in the transition from tunnel to elevated.  Similar arguments apply to the other O-D maps above.

The real problems with a tunnel are its cost and the barrier effect created by ramps linking the tunnel to the elevated structures at the Don and at Jarvis Street.

The schemes involving the rail corridor have both been dropped because they cannot be fitted into the space available.  In the case of an elevated, there is no room for the support structures needed (not to mention access ramps), and in the case of the berm, the area is reserved for future expansion of rail operations.

A far more important issue hinted at by the presentation but not explored in detail is the wider context of transportation into the core area.

Continue reading