TTC Capital Budget: Where Will The Money Come From?

In between many screenings at the Film Festival, I took the opportunity to write up the TTC’s Capital Budget presentation from August 30.  The information here is a combination of the TTC staff presentation, remarks by Ted Tyndorf, Chief Planner for Toronto, and my own opinions.  This is intended mainly as a view of the most recent TTC thoughts on the subject. 

Here are the high points:

  • Expenditures on transit have been deferred over and over again, with most big-ticket attention going to a handful of subway lines.  This is not sustainable.
  • Population and ridership growth is happening faster than predicted, and significant investment in new and improved service is essential.
  • The goals of the Official Plan and Building a Transit City are not worth a penny if we are not going to invest in transit.
  • The TTC budget projections push some projects further into the future than is reasonable if we are going to lead population growth with transit, for example, the Transit First policy for the eastern waterfront. 
  • There is no provision for many new lines including the proposed LRT/BRT network in Scarborough or anything in the Don Mills corridor.

I will take up the issue of where we should go next with transit planning in a future post, likely over the weekend.  Meanwhile, the gory details. Continue reading

Thunder Track and the Wonder of Queen’s Quay

Today’s jaunt to the St. Lawrence Market took me on a small detour to see the revamped Queen’s Quay complete with bicycle lanes, flowers and grass.  There are some great photos by Peter Hud here.

If we believe the prophets of doom who claim to be traffic engineers in these parts, those photos should be full of fire and brimstone as the wrathful traffic gods rain down on the lost roadspace.  At least there should be a lot of cars.  Strangely not.  A few errant tourists managed to drive east along the transit right-of-way while I was there, but otherwise the calm morning was broken only by sounds of people strolling by, bicycles whirring by and, oh yes, streetcars roaring by. Continue reading

A Short Trip to Long Branch

A few days ago, I set out to visit friends in darkest Long Branch (for an East Ender, Long Branch is near the edge of the planet).  My destination, roughly, was Lake Shore and 32nd Street.  I had a few choices of how to get there from home base at Broadview Station:

  1. Subway to Kipling, 44 Kipling South to Lake Shore, 501 Queen to 30th Street
  2. Subway to Islington, 110 Islington South (30th Street branch) to Lake Shore
  3. Subway to Dundas West, 504 King to Sunnyside, 501 Queen to 30th Street

Being a streetcar fan, and trusting on the speedy service available on the broad boulevards of Queensway and Lake Shore, I chose option 3. Continue reading

Waterfront Revitalization Five and Ten Year Plans

A report on the Policy and Finance agenda for July 18 sets out the business plan for various waterfront projects.  Like the Spadina Subway (discussed elsewhere) this work will be funded through a trust to which various governments will contribute.  Much of this report is dry financial stuff where we take money out of one pot, put it in another, shuffle the cards around, and hope it all comes out in the end.

The interesting stuff is in Appendix A which describes the various projects.  Here we learn the current plans for construction of LRT lines to the eastern waterfront.

  • EA studies to complete by the end of 2008.
  • Construction start in the West Donlands in 2008 and the East Bayfront in 2009.
  • West Donlands LRT (the Cherry Street Car) to be completed by 2008/09 or 2010/11 depending on which page of the report you believe. 
  • East Bayfront LRT (the Queen’s Quay Car) to be completed by 2010/11 or 2014/15 depending etc.

Development of the Port Lands (east of the Don River) is not mentioned probably because it lies beyond the 10-year horizon of this plan.

I mention these schemes in the context of the TTC’s fleet planning.  We are developing a huge new part of the city, and it will need transit service.  Decisions about new streetcars cannot be delayed indefinitely if we are serious in the “transit first” commitment to new neighbourhoods.

Spadina Subway Financing

A report on the Policy and Finance Committee’s agenda for Tuesday, July 18 goes into the rather dry business of setting up a trustee for the Move Ontario Trust.  This creature will be used to hold the moneys contributed by various governments to the Spadina Subway project.

The current project cost estimate, all the way to Vaughan Corporate Centre Station, is $2.1-billion (2006).  To date, the Province has contributed $670-million, slightly less than one-third and with no provision for inflation, in the fund.  York Region’s share is yet to be determined, and everyone looks with hope on Ottawa for a matching contribution.  We shall see. Continue reading

Waterfront West and the Front Street Extension

The Environmental Assessment for the western extension of the waterfront line will get underway soon with the usual preparatory phase of creating the Terms of Reference.  This brings to mind a note I received a while ago from Hamish Wilson, long time opponent of the Front Street Extension, and begs the question of whether the transit EA can be used to revisit options for the corridor as a whole much as the EA now in progress for the Airport Link has widened out to a general review of the northwest corridor.  Continue reading

Waterfront East and Scarborough RT Updates

The draft Terms of Reference for the Environmental Assessment of the eastern waterfront transit plans goes to the TTC for approval next Wednesday.

This draft is the product by much work in full public meetings as well as a community consultation group.  I must commend the team who worked on the draft for their openness to changes, expansion in scope and generally inclusive approach.  The stage of building a ToR can be extremely tedious, but it is vital to ensure that all of the alternatives are considered in the EA itself.  This is a refreshing change from the St. Clair project.

Assuming that the TTC approves the draft, it will go to the Ministry of the Environment for review over the next few months.  While that is underway, some preliminary work will continue collecting information needed for the study and also presenting some technical workshops so that the community can better understand the work behind transportation planning and design.

Meanwhile, the Scarborough RT study is not included on this week’s TTC agenda although it was originally planned for a June presentation.  I suspect that recent events at the TTC coupled with the relatively tighter timelines on the Waterfront studies have pushed the SRT report off into the summer.