A Slightly Less Grand Plan

Ontario’s Finance Minister, Dwight Duncan, yesterday announced that the province will run a half-billion dollar deficit thanks to the international financial upheavals and declining economic outlook.  In this context, I spent the day at a Metrolinx “stakeholders’ meeting” where we discussed details of the Draft Regional Transportation Plan and Investment Strategy.  The whole discussion has a surreal air because nobody is quite sure where the billions to pay for this plan will come from.

There is reasonable agreement about the need for better transit, but much suspicion of whether this plan will join its predecessors on library shelves.

In the informal post-meeting chats, I was asked what I would do if the promissed $11.6-billion MoveOntario money didn’t materialize, if we had to cut back the scope of the “top priority” projects to fit a tighter budget.  This is too big an issue for a short chat, and it deserves a post of its own.

Any budgetary cutback discussion must first consider whether to make the “death of 1000 cuts” or to look hard at big ticket items.  If you need to defer or cut spending, there is more money to be found in large projects than small ones, but we may skip reviews of smaller items that really don’t belong at the top of the pile.

A major problem lies in the dearth of information Metrolinx has published about the detailed performance projections and roles of each component in the plan.  We have demand forecasts only for year 2031 where the combined effect of future job and population growth interact with a completed network.  The published data show only peak point counts, not the demands for each network link.  There is no way to understand which links are cost-effective, and there is no data for intermediate states (such as after the “first 15” are built) to show whether they are an appropriate use of whatever resources might be available.

Metrolinx must publish this information as soon as possible.  Meaningful discussions of cutbacks are impossible without it.

This brings me to the “Business Case Analyses” that are in progress already for some of these lines.  These analyses are proceeding in the old, worn-out style of looking at each project individually rather than collections of projects for their combined effect on the network.  From the 2031 projections, we can see that the regional express rail lines and other new major elements have a big impact on demand on the existing network.  Notably, the forecast overload of the subway system doesn’t materialize because there are other high-capacity lines where the demand can flow.

Meanwhile, the TTC’s report on the north Yonge extension to Richmond Hill raises an old, hare-brained scheme to add a third platform at Bloor-Yonge station for increased capacity.  I won’t go into a detailed discussion here beyond saying that this is horrendously complex and expensive, but at least the TTC finally recognizes that subway capacity involves more than new signalling and more trains. 

The real question, however, is whether the money would be better spent on alternate services to divert riding with new options for travel to the core area.  Should some projects — the Richmond Hill regional express and/or the east leg of the Downtown Relief subway — be moved up as alternatives or as key pre-requisites?  That’s the kind of comparative analysis Metrolinx and the TTC are not doing, but should.

Next we come to project phasing.  Do we really need a line all the way to Richmond Hill?  Is there a shorter “phase I” that will have significant benefits without the cost of the full line?  Analysis on an all-or-nothing basis doesn’t give us staging options.

We need to be open about “the untouchables”, the projects with political clout that soak up billions of dollars because someone wants to see them built.  There is no point in talking about fiscal restraint if billions in proposed spending can’t be reviewed.  A related question is how that “top 15” list came into existence in the first place. 

Some time ago, the Metrolinx Board approved this grab-bag as likely top candidates that should be analyzed in more detail.  However, that analysis isn’t even started for many of them, and there is every possibility that the analyses may show that some projects don’t pull their weight, at least in the short term.  I may be splitting hairs, but that “top 15” has gone from candidates for early study to the definitive list of first projects without benefit of formal approval.  If we are to have a spending review, we must stop assuming that this list has the force of detailed review and blessing.

Oddly, it’s almost an afterthought in the Draft RTP — Metrolinx doesn’t even include a map showing the network with only these lines completed.

The subway to Vaughan is a special case.  There is supposed to be a trust fund holding the funding from Queen’s Park, Ottawa, York Region and Toronto.  Is this money really sitting in a bank somewhere?  Does the provincial share come out of the $11.6-billion MoveOntario pot?  Can we step back and ask questions about why this line is so important?  For starters, someone has to reconcile demand projections in York Region’s own EA that would make the Sheppard subway look busy with the impetus to build this line.  Metrolinx does not break out the section north of Steeles as a separate project, and the published demand for the line gives only the peak point value (likely just north of Downsview Station).

The TTC is already studying alternatives to the SRT including LRT conversion of the existing line.  The original recommendation to keep Skytrain technology only made sense for a line that remained at its existing length or had a short extension.  The further north it goes (Markham is a mooted destination), the less practical and more expensive Skytrain is relative to LRT.  Keeping the RT was a bad recommendation skewed by a desire to preserve Bombardier’s showcase technology, and we cannot afford to avoid this debate.

On the Sheppard/Finch corridor, current thinking is headed toward an eastward extension of the Finch LRT to Don Mills (where it would connect to the Don Mills line) and a westward extension of the subway to Downsview.  These may be viable projects in the long term, but we have to consider them separately from the original Transit City proposals.  Indeed, the Don Mills LRT isn’t even in the “top 15”, and there isn’t much point building the Finch line east of Yonge until it has something to connect with.

At Finch Station, there are big problems with the bus terminal and with the design of a future LRT interchange.  What happens if the subway extension gets underway and much of the bus operation shifts north?

On Eglinton, a line whose projected peak ridership is similar to both of the subway extensions, but whose extent provides rapid transit service to a far larger area, we are faced with an expensive central tunneled section that cannot be avoided.  Indeed, the size of this project requires that it be started sooner rather than later so that its benefits as a key part of the overall network can be available.

In the Don Mills corridor, should the DRL end at Danforth or continue north to Eglinton with a major transit hub linking the Eglinton and Don Mills LRT lines to the DRL subway?  This won’t be part of the “top 15” list, but the Don Mills Transit City study would make a lot more sense if the TTC stopped trying to shoehorn an LRT right-of-way into Pape or Broadview.  That scheme (and related alignments) are holdovers from the days when this was a BRT study, and this nonsense has to stop.

On the Weston/Brampton rail corridor, why do we persist with the fantasy of the Toronto Air Rail Link (TARL, formerly called “Blue 22”) that will chew up track space for a premium fare service on the same route as a proposed regional express service to Brampton?  How much does the private sector-proponent of the line hope to make from this service?  Can they be bought off?  Is it cheaper to not build Blue 22 and devote the resources to upgrading GO in the same corridor?

What are the possibilities for the CPR North Toronto Subdivision?  What options do we have for cross-region service via this corridor especially as an alternative way for riders from the north-east to get into the city without using the RT/subway network?  Negotiating with CPR won’t be easy, but doing nothing may condemn us to building rapid transit capacity elsewhere we might not actually require.

If there is a common thread in all of this, it’s a simple message:  Metrolinx started off designing a network, and they must not lose sight of the network view of any solutions.  Look at revisions to the plan as a whole, look at where the benefits are greatest in the short term so that we spend what money is available on projects that will show real improvements for transit.

Toronto has decades of making wrong, expensive choices, and transit suffers a well-deserved reputation as an “also ran” thanks to those decisions.  Provincial belt-tightening is just the opportunity we need to focus on what really works, on what we really need.

A Tale of Two Maps

Two days ago, Toronto’s Planning & Growth Management Committee approved both the Environmental Assessment Report for the Sheppard East LRT and an Official Plan Amendment extending the scope of the transit corridor east on Sheppard to match the LRT line.

Scarborough Councillors popped the Champagne corks, or at least sparkling water, and I got an invitation to talk about the significance of the occasion on Metro Morning.

This should be a big event — approval of the first leg in a suburban LRT network.  Back in 1972, the Streetcars for Toronto Committee fought to save what we now call the “legacy” system as a base for suburban expansion, and I have waited a very, very long time for this day.

Over the decades, a combination of Provincial meddling in transit and local subway megalomania  stymied transit’s ability to keep up with, let alone form suburban growth.  All the planning mantras about leading development with transit from the sixties and seventies are little more than quaint memories.

Finally, early in 2007, the TTC and City announced the Transit City plan for a network of seven new LRT lines.  Work began immediately on detailed studies, and three EAs are already underway with the Sheppard Line’s being the first to come up for approval.  The Don Mills study recently had a round of public meetings, and the Eglinton study will roll out in the fall.  Add to these the non-TC projects in the eastern waterfront and the Kingston Road study, not to mention proposals outside of Toronto, and there’s a lot of LRT on the table. Continue reading

Sheppard LRT EA Final Open Houses (Update 2)

Update 2 (June 18):  The EA report on the Sheppard LRT came before the TTC and it was extremely warmly received by all present.  A few updates worth noting:

  • Property owners at Settlers’ Road (roughly at the ramps to the Atria development) asked that a stop be added at their location because the spacing from Consumers to Victoria Park is longer than the target average for the line.  They have been working with TTC staff to come up with a suitable configuration.
  • The Don Mills Station connection option includes examination of running both services on the same platform with the subway using the north track, and the LRT using the south track.  This has operational issues, but the TTC is looking at this as an alternative to extending the platform far enough east so that there would be competely separate loading zones.
  • There is a strong push for the Consumers Road subway extension option as a way to improve service to this business park and spur development of much vacant (read parking) land there.  Also, it is hoped that this would reverse the area’s drop in employment of about 25% over past years.
  • The projected cost has risen from the original $555-million in the Transit City announcement to $865-million largely due to the cost of the subway connection at Don Mills (originally this was costed as a surface station) and an increased estimate for vehicles. 

The original post follows. Continue reading

Upcoming Transit City Open Houses

The following open houses have been announced for June 2008:

Sheppard LRT

Tuesday, June 3 at Agincourt Collegiate (Midland north of Sheppard)

Wednesday, June 4 at Malvern Community Centre (Sewell’s Road east of Neilson)

Scarborough RT Extension

Wednesday, June 4 at Malvern Community Centre (Sewell’s Road east of Neilson)

Thursday, June 5 at Scarborough Town Centre Station

Don Mills LRT

Tuesday, June 10 at Rosedale Heights School for the Arts (near Castle Frank Station)

Tuesday, June 17 at East York Town Centre

Wednesday, June 18 at Don Mills Station

Details are available on the project websites (linked above).

New Carhouses for New Cars (Updated)

The TTC Supplementary Agenda for May 21 includes a report on the Master Plan for new carhouses.  These will be needed both to house the replacement fleet for the existing downtown network and for the far-flung Transit City system.

In brief, the proposed scheme involves the building of five new carhouses:

  • One in either the Portlands or in New Toronto to house the downtown network’s fleet.  The New Toronto option is mentioned only once in the text  (with “new” in lower case), and the map shows only the Portlands location.  This would be the primary carhouse for the core area routes, but Roncesvalles and Russell would continue to have a role as regional yards for new cars once the CLRV fleet starts to retire.
  • A Sheppard East carhouse would initially operate the Sheppard line, but later take on the Scarborough/Malvern and part of Eglinton once the Malvern link was in place.
  • A Finch West carhouse would serve that line and, eventually, part of the Jane line as well.
  • An Eglinton West carhouse would serve the Eglinton line initially, and later the Jane and, possibly, the St. Clair line.
  • A Don Mills carhouse would serve the Don Mills line and possibly part of Sheppard.  By the time we get this far into the plan, there will no doubt be more Transit City proposals on the table and it’s anyone’s guess what the real carhouse needs will be.

The four Transit City carhouses are estimated at about $770-million (reference year not stated), while the new downtown carhouse is estimated at $330-million due to the larger fleet it must house.    It’s clear that the long-term status of the existing Russell and Roncesvalles buildings is dubious both because they are not suited to house and maintain the new cars, and because of building code issues if they were to undergo major changes.  However, these properties provide a few advantages over a consolidated operation in the Portlands.

  • If they are used as yards with basic servicing facilities, the dead-head time for cars entering and leaving service will be shorter than if everything funnels back to a Portlands carhouse.
  • As riding grows on the existing system, the TTC needs somewhere to store more than the initial 204 low flow cars they plan to order this year.  The existing yards will provide an overflow.  Whether both of them are needed once all of the existing CLRVs and ALRVs are retired is another question, but that’s almost a decade away.

Note that the map used in this report is the original Transit City map and does not reflect any of the optional changes that have cropped up in discussions about some routes.  It also doesn’t show the new Waterfront East lines, nor the Kingston Road project.  With luck, one of these days, the TTC will start using a new base map for all of its surface rail project reports.

Updated May 21:

The dates for new carhouse availability are driven both by the expected arrival of the new fleet for the downtown system and for the opening dates of the Transit City lines.

The demonstration prototype cars are to arrive at the end of 2010, and it is likely they will be temporary stored and serviced at Hillcrest.  The first 20 production cars will arrive by the end of 2012, and they will need a carhouse and shops.  This sets the date for the Portlands carhouse to be available.  The complete replacement fleet arrives by the end of 2017.

There are seven Transit City lines (not to mention other plans such as Waterfront East and Kingston Road).  The startup dates and estimated fleets for each of these lines are:

  • Sheppard East:  2012 / 35
  • Finch West:  2013 /37
  • Eglinton:  2015 /129
  • Waterfront West:  2015 / 23
  • Don Mills:  2016 / 46
  • Jane:  2017: /41
  • Scarborough Malvern:  2018 / 53

At least 90% of this fleet, possibly with the addition of cars for the St. Clair line, will be housed in the four new carhouses all of which should have room to accommodate growth in requirements.

Sheppard East LRT / Scarborough RT EA Meetings in June

The next round of meetings for the Sheppard East LRT and Scarborough RT Extension Environmental Assessments have been announced.

The Sheppard East LRT meetings are on June 3 (Agincourt Collegiate) and June 4 (Malvern Community Centre).  They will include presentation of:

the recommended design for the Sheppard Avenue East LRT, including stop locations, the proposed grade separation of Sheppard Avenue at the Agincourt Go Line and the preferred option for making the LRT/subway connection.

The Scarborough RT Extension meetings are on June 4 (Malvern Community Centre, jointly with the Sheppard EA) and June 5 (Scarborough RT Station).  They will include:

The rationale for selecting the preferred network: an SRT extension to Malvern Town Centre, and SRT alignments to be considered for detailed evaluation.

Sheppard East LRT Preliminary Design

Now that the TTC and City have held the first open houses for the Sheppard East project, it’s time for a few comments on the design so far. 

The presentation materials are available online.

This study is proceeding under the new, accelerated schedule for Environmental Assessments and it will be important to stay on top of what is happening.  Adam Giambrone’s office has advised me that there will be a third iteration of the open house at Scarborough Town Centre (details to be announced).  Following that, the next opportunity for public input into the overall design will come in late May. Continue reading

Sheppard LRT Environmental Assessment Meetings (Updated)

The City and TTC will be holding two EA meetings for the Sheppard LRT line on Tuesday and Thursday, April 15 and 17, 2008.

These will also include discussions of the proposed extension of the Scarborough RT.

The FAQ linked from the EA notice page includes a variety of intriguing items giving an idea of how the project team views what they will implement.  Apropos of discussions in other threads here about stop spacing and vehicle speed, we learn that

there is normally a much greater distance between stops, relative to a typical bus route.

It should be interesting to see how the TTC and City reconcile this statement with the actual layout of streets and stops on the existing bus route, not to mention the Official Plan goals for Avenues with medium density development along transit lines rather than concentrated at major intersections.

Update: The presentation materials from the meeting are now available online.