Will The TTC Board Ever Discuss Policy, or, Good News Is Not Enough (Updated)

Updated January 21, 2014 at 2:20 pm:  The description of the loading standards introduced with the Ridership Growth Strategy has been corrected.

The election season is upon us in Toronto, and transit made an early appearance on the campaign with mayoral candidate David Soknacki’s proposal that Toronto revert to the LRT plan for Scarborough.  I am not going to rehash that debate here, but there is a much larger issue at stake.

The Ford/Stintz era at Council and at the TTC has been notable for its absence of substantive debate on options and alternatives for our transit future.  Yes, we have had the subways*3 mantra, the palace coup to establish Karen Stintz and LRT, for a time, as a more progressive outlook on the TTC Board, and finally the Scarborough debate.

But that’s not all there is to talk about on the transit file.  Do we have a regular flow of policy papers at Board meetings to discuss what transit could be, should be?  No.  Ford’s stooges may have been deposed, but the conservative fiscal agenda remains.  Make do with less.  Make sacrifices for the greater good, whatever that may be.  Show how “efficiency” can protect taxpayer dollars even while riders freeze in the cold wondering when their bus will appear.

Every Board meeting starts with a little recitation by the Chair of good news, of stories about how TTC staffers helped people and the good will this brings to the organization.  There is ever so much pride in improved cleanliness and attractiveness of the system – a worthwhile achievement, but one that should become second nature to maintain.  It should also be a “canary in the coal mine”, a simple, obvious example of what happens when we make do with “good enough”, with year-by-year trimming to just get by.

If the bathrooms are filthy, imagine the condition of the trains, buses and streetcars you are riding.  I’m not talking about loose newspapers blowing around, but of basic maintenance.  From our experience in the 1990s, we know how a long slide can take a once-proud, almost cocky system to disaster, and how hard it is to rebuild.

In a previous article, I wrote about the threat to basic system maintenance posed by underfunding of the Capital Budget, an issue that has not received enough public debate.  Part of the problem is that the crucial maintenance work that must occur year over year is treated the same way as new projects.  Maintenance competes with the glamour projects for funding, and may be treated as something to be deferred, something we don’t need yet.  Couple that with starvation of funds for basics like a new and expanded fleet and garage space, and there’s a recipe for a TTC that will decline even while more and more is expected of public transit.

The budget isn’t the only issue that deserves more detailed examination, and many other  policies should be up for debate.  Within a month, the TTC will have a new Chair as Karen Stintz departs for the mayoralty campaign.  Within a year, Toronto should have a new Mayor, one whose view of transit is not framed by the window of his SUV.  At Queen’s Park we may have a Liberal government with a fresh, if shaky, mandate to raise new revenues for transit construction and operation, or we may have a populist alternative with a four-year supply of magic beans.

In the remaining months, the TTC Board has a duty to lay the ground for the governments to come, especially at City Hall.  The 2015 budget debates should be well informed about the options for transit, if only for planning where Toronto will need to spend and what services the TTC will offer in years to come.  Will the TTC rise to this challenge, or sit on its hands with a caretaker Board until the end of the current term?

Here is a selection of the major policy issues we should be hearing about, if only the TTC would engage in actual debate to inform itself, Council, the media and the voters.

  • Fare structure:  What is the appropriate way to charge fares for transit service?  By time, distance, week, month?  How does smart card technology change the way fares are collected and monitored?  What are the implications for regional travel and integration?
  • Service standards:  What loading standards should be used to drive service improvements?  Should the TTC build in elbow room to encourage riding and to reduce delays due to crowding?  Should there be a core network of routes with guaranteed frequent service?
  • Service management:  What goals should the TTC aim for in managing service?  Do the measures that are reported today accurately reflect the quality of service?  Are bad schedules to blame for erratic service, or does this stem from management indifference or from labour practices that work against reliable service?  What are the tradeoffs in the relative priority of transit and other traffic?  What are the budgetary effects of moves to improve service?
  • Budgets and Subsidies:  Both the Operating and Capital Budgets have been cut below the level recommended by TTC management.  These cuts will affect service and maintenance in the short and long term, but there has been no debate about the effect, especially if these are not quickly reversed in a post-Ford environment.  The Capital Budget faces a huge gap between available funding and requirements.  Over ten years, the shortfall is 30% in available financing versus requirements, and this is back-end loaded so that the shortfall rises to 50% in later years.  The proposed level of City subsidy is barely half what would be needed if Queen’s Park returned to its historical 50% capital funding formula.  Hoped-for money from Ottawa is more likely to finance major projects such as new subway lines, not the “base” budget for capital  maintenance.  The budget, especially capital, is not well understood by the TTC Board or Council in part because of the confusing way in which it is presented.  Toronto cannot begin to discuss subsidy policies if those responsible for decisions cannot understand their own budgets.
  • The Waterfront:  While battles rage over subway and LRT proposals for the suburbs, a major new development on the waterfront is starved for transit thanks to cost escalation, tepid interest by the TTC, and the perception that waterfront transit can be left for another time.  The pace of development may be threatened if good transit does not materialize on Queens Quay, and later to the Port Lands, but meanwhile this project sits on the back burner little understood by most members of the TTC Board and Council.
  • Rapid transit plans:  The artificial distinction between GO and the subway (or even higher-end LRT operations such as the proposed Scarborough line) will disappear as GO becomes a frequent all-day operation.  There will be one network regardless of the colours of the trains.  GO service to the outer parts of the 416 is particularly important as an alternative to subway construction serving long-haul trips to downtown.  Subways, LRT and BRT each has its place in the network, but electoral planning must not leave us with fragments of a network rather than an integrated whole.
  • Accessibility:  The need for accessibility extends all the way from the severely disabled who require door-to-door service, through a large and growing population who have some degree of independence, to those whose only problem may be bad knees or a weak heart.  Neither the TTC nor the City has taken the issues of accessibility particularly seriously in recent years.  There may be good words, but the budget and service policies clearly limit the growth of the parallel Wheel Trans system.  Meanwhile, retrofitting the system for full access is delayed thanks to funding limitations at both the City and Queen’s Park.  What we do not know is the true extent of the need for accessibility on the TTC and what this means for service and infrastructure.

Continue reading

Eglinton Crosstown Update

On December 20, 2013, there was a briefing for media on the Eglinton Crosstown Project at Metrolinx.  Coming the morning after the Press Gallery’s Christmas party, this was a lightly attended event and it received scant coverage.

Tunnel Construction Progress

The tunneling is making better progress than expected.  Originally, the contractor had planned for 12m/day, but they are actually making 20m/day thanks to improved efficiency in removal of spoil with a conveyor system.

At Eglinton West Station, the project faces the problem of getting under the existing Spadina Subway structure.  Original plans called for an extended shutdown of the Allen Road and much of Eglinton Avenue so that the tunnel boring machines (TBMs) could be disassembled, extracted from the west side of the site, lowered into a new access shaft on the east side, and reassembled to continue their journey east to Yonge.

This scheme was not acceptable to the City of Toronto and a new proposal is under consideration.  The access shafts will be longer, but the TBMs will be extracted, moved and lowered back into place in one piece.  The move across the subway structure would be done similarly to rapid bridge replacement projects with a support structure to carry the TBMs (which weigh 420 metric tons) from the west to the east side.   This approach will eliminate the need to disassemble and reassemble the machines.

The eastern tunnel contract includes the launch shaft (between Brentcliffe and the west branch of the Don River), and work will begin there early in 2014.  The eastern tunnels will bore west to Yonge.

The two tunnel contracts – at $283-million for the west side and $177m for the east – are only part of the much larger cost of building an underground transit line.  The tunnels (of which the western section is now under construction) will be provided as empty tubes – physical structures with no installed systems – for the next stage in the project.  Tunneling will complete in 2016.

At each station site, headwalls are built at each end of what will become the station excavation.  As the TBMs reach the headwalls, they bore through and leave behind a completed tunnel that will be partly disassembled when the station construction digs down to them.  Two techniques are used for these walls depending on local conditions:

  • Secant piles require boreholes into which the piles are installed.  These require utility relocations to avoid the boring activity.
  • Jet grouting uses a slurry to form the headwalls without the need to bore.  This approach is being used at Caledonia Station.

The TTC assisted with specifications for the tunnels to ensure that they meet the standard of other Toronto infrastructure.  These will be constructed as empty round tubes that will be transferred to the bidders for the next stage of construction and who will take over the risk for future maintenance.

Continue reading

Crosstown LRT Interchanges with the Yonge-University-Spadina Subway

The TTC meeting agenda for November 18 includes a report on the proposed designs for the connections at Eglinton and at Eglinton West Stations between the existing subway line and the Crosstown LRT now under construction.

Eglinton is a particularly complex station because the location is constrained by nearby buildings, the platform space is already at a premium with four existing links between the subway and mezzanine levels, and this is expected to be a busy transfer location.

Eglinton West is somewhat simpler in part because the existing station is offset from Eglinton Avenue and the link between the two stations will occur at the south end of the existing structure.

Continue reading

Construction That Never Ends (Update 4)

Updated November 14, 2013 at 6:20 pm:

According to the TTC CEO’s report for November, the date for resumption of streetcar service on Queens Quay has been changed to June 21, 2014.  Brad Ross of the TTC advises that their website will be updated to reflect this new target date.

Updated October 26, 2013 at 4:32 pm:

According to the TTC CEO’s report for October (at page 20), service will not resume on Queens Quay until August 2014, not the end of June as previously reported.  I have asked the TTC to verify this date and explain why completion has slipped yet again.

The TTC memo listing service changes for the November and December schedule periods came out today, and it contains a few startling items:

  • The Yonge Subway tunnel liner program, originally expected to wrap up at the end of 2013, will now run an additional year to the end of 2014.
  • The loop at the foot of Queens Quay will not be available for service as expected in November, and service on the 510 streetcar will not resume until mid-February 2014.
  • The track on Queens Quay itself will not be available for service as expected in December/January, and service on the 509/510 streetcar will not resume until the end of June 2014.

Updated October 2, 2013 at 10:25 am:

Waterfront Toronto has posted a Construction Update for the Queens Quay project.

Updated October 1, 2013 at 6:00 pm:

Yonge Subway Tunnel Liners

I have received a note from Brad Ross at the TTC explaining the current situation.  The work has proven more extensive both in complexity and scope than originally thought.  In reply to one comment in this thread, I gave the opinion that all of the asbestos had been removed from the tunnels, but according to Ross, there is still some present and this adds to the slowness of the work.

The tunnel liner project involves the inspection of some 10,000 tunnel liners. To date, 4,000 liners have been inspected, 950 identified in need of repair, and 850 of them repaired. The process is not a speedy one as many of the liners are covered in material, including asbestos, which needs to be removed before a liner can be inspected. Add to that the time it takes for crews to get to the work location, set up, clean up, and return to the yard. As we examine liners, we’re identifying more and more that need to be repaired, mostly due to water damage. In short, the project timeline increases as the work involved increases. We are now working to determine what a reasonable completion date might look like and what the overall impact to subway service north of Eglinton will be over the next 12-18 months. Once we have that, we’ll communicate it widely.

[Email from Brad Ross, Executive Director, Corporate Communications, TTC, October 1, 2013]

Waterfront Toronto Queens Quay Project

I met with Waterfront Toronto staff to discuss the status of the project.  They have issued a construction update detailing the current situation.

Because the lanes occupied by the TTC right-of-way are essential as extra space into which construction or temporary road lanes can be shifted for utility work, the new trackbed cannot be laid down until all utility work requiring traffic diversions in an area is completed.

This work has been affected by a number of factors notably:

  • A late start by Toronto Hydro who did not receive funding approval for their Capital Program from the Ontario Energy Board in time to meet the original schedule.
  • Ground water conditions that at some locations were more challenging than expected.
  • Subsidence and resulting damage to existing utilities when areas were de-watered for construction access.  This was anticipated, but the extent of the problem is hard to gauge before the work is actually done.

The area around Spadina and Queens Quay has many utilities competing for space and for construction access.  Some planned work has been complicated by new, more stringent provincial labour safety standards for work near live hydro lines.

Most of the splicing chambers for the new track are complete, but one critical one that will feed Queens Quay Loop is inaccessible at present due to competing work in the same area.  This has slowed installation of the grounding cables for the loop which will tie back to that chamber.

The intent is to have the trackwork in the loop finished by yearend.  TTC would then install its overhead in preparation for service at the start of the February 2014 schedule period which will fall in the middle of the month.  The track installation will likely be done mainly in November, and partial shutdowns of the streets around the loop will be required.

There are three sets of special work (loop entrance from Queens Quay, loop exit to Spadina and the Spadina & Queens Quay intersection).  A preliminary plan for this might have broken the work into three stages, but Waterfront Toronto hopes to consolidate this into two.

A further complication will be the partial closing of Lake Shore Blvd. to complete the track connection south from new rails on Spadina.

Waterfront Toronto expects to publish details of the work schedule soon.

As for the tangent track on Queens Quay, the major constraint is that the space cannot be given up until utility work in a section is clear.  The intention is to build the foundation slab in pieces as various sections of the roadway become available.  Track installation would be completed in spring 2014, followed by overhead catenary, with a target date for streetcar service in late June.  (If the schedule periods for 2014 follow the same pattern as in 2013, this would be Sunday, June 22, 2014.)

Waterfront Toronto’s work plan for summer-fall 2014 will concentrate on the area south of the streetcar right-of-way which will contain the new cycling path, an expanded pedestrian area, and many trees.  Some finishing work will occur in early 2015 in advance of the Pan Am Games.

What is frustrating about all of this is that the delay in Hydro’s approval at the OEB was well known a year ago, and Waterfront Toronto has maintained rather hopeful dates for resumption of service that strained credibility as the construction wore on and on and on.

TTC Board Meeting October 23, 2013 (Update 3)

Updated October 26, 2013 at 5:20 pm to reflect discussions at the meeting.

The TTC Board met on October 23.

Update: The 2014 Operating and Capital Budgets are still not public, and they may now  appear in November (this has yet to be confirmed).  This is unusual because under Mayor Ford, the budget process for the City has been moved up so that the overall budget can be finalized early in the new year.  In 2012, the TTC budgets for 2013 were on the September agenda.

Will the TTC roll over again and accept a flat-lined subsidy placing the entire burden of extra costs on riders through fare hikes and compromises on service quality, or will they finally argue for better subsidies and force Council to debate just what transit should be doing – aside from building one subway line – for Toronto?

The CEO’s report (below) offers a hint in this statement:

“… discussions with the City continue regarding the TTC Operating and Capital Budget submissions for 2014-2023.  I am resolute in expecting an increase in subsidy to accommodate and service ever increasing customer numbers.”  [page 5]

Does this represent a strategic position on the TTC’s part, or division among the Commissioners about the direction the organization should take?

The City of Toronto will launch its 2014 budget process formally on December 2, 2013.

New Wayfinding Standards

Recent reports in other media have talked of a proposal to rename the subway lines with numbers to simplify wayfinding information for riders.  The details of this and other schemes to overhaul information will be presented at the meeting.

Updated October 23 at 10:55am:  The presentation is now online linked from the title above.

Updated October 26 at 5:00pm:  This topic will be split off into a separate thread given the volume of comments, and the accumulated comments will be moved to the new thread.

CEO’s Report

The CEO’s report has little new relative to the September edition.  Riding continues to be above 2012 but below budget.  For reporting period 8 (mainly the month of August), riding was up 3.5% over 2012.  On an annualized basis, riding is up 2.8%.  These results are 0.1% below budget for the period, and 0.5% below budget for the year to date.

Total ridership for 2013 is projected to be 527m, 1m below the budget projection.  This shortfall, coupled with higher-than-expected sales of passes versus token/cash fares, will mean revenue will fall $7.6m below budget.  This will be counterbalanced by various swings plus and minus on individual expense lines (details on page 24).

Update:  According to CEO Andy Byford, the lower ridership and revenue numbers for 2013 are mainly attributed to the severe weather and floods earlier in 2013.  Major shutdowns planned for 2014 will definitely affect ridership and this will be built into the budget estimates.

Subway punctuality on the Yonge-University line remains a problem particularly in off-peak hours.  It is unclear how much this is a side-effect of the yardstick of headways within ‡3 minutes of scheduled values.  During peak periods, it is much easier to meet this goal because there are more trains on the line, and entire trips can be missing without headways going beyond the 3-minute rule.

The BD line problems occasionally from the transfer of trains to the Yonge line to “cover shortages”, although this is not explained.  Are there simply not enough working trainsets to operate the Yonge service, or are BD trains poached to fill major service gaps?

Update:  I have asked the TTC to clarify what this section of the report actually means.

As if the wait hasn’t been long enough already, the CEO’s report states that the Harbourfront line will not return to streetcar operation until August 2, 2014.  No reason is given for the further slippage between the July date given by Waterfront Toronto and the TTC’s new August date.

One major issue that the CEO’s report does not address is the fleet availability in Toronto.  Only through the shutdown of substantial chunks of the streetcar system has the TTC managed to field enough cars to cover what remains in operation.  It is in their interest to prolong construction projects until they can get the first of the new fleet on the road.  What was originally touted as a “spring” startup of LFLRV service may now well slip to at least “summer”.

Production deliveries of cars are supposed to start later this fall.  What is the status of this order?

Service reliability is supposed to be reported quarterly for all surface operations, but the third quarter report has not yet appeared (it is expected to show up sometime on October 21).  When it does, I will be reporting separately on comparisons of the numbers over the past three quarters of 2013.

Update:  The quarterly report was published on October 23 and has been discussed elsewhere on this site.

I will follow up on questions raised here with TTC staff at the meeting and will update the article when further info is available.

TTC Fare Policy – Requests For Fare Discounts

This is a compendium report on various proposals/requests the TTC has received for reduced fares for various groups.  The staff position is that any additional subsidies for various classes of riders must be funded through a policy decision at City Council with adequate funding through the subsidy stream to offset the projected revenue losses.

This has been the TTC’s stock position for such requests for years, but at least we now have a consolidated report listing the projected cost for each option.  If Council wants to fund new discounts, the expected cost is known presuming that we accept the TTC’s estimates (some of which are dubious).

  • Extending “Family Pass” (6 people, maximum 2 adults) pricing to the entire week.  This is projected to cost only $2.2-8.6m per year, although I am suspicious of the figure because it is based on existing pass sales.  If the pass is more attractive, then more of them will be sold, but the estimate does not take this into account.
  • Free off-peak trips for seniors.  The cost is estimated to be at least $22m per year based on the number of non-pass trips by students/seniors today (45.2m), subdivided by the proportion of seniors (40%) and then the proportion of off-peak trips (65%).
  • Off-peak only pass for seniors.  The technology to handle time-of-day passes does not exist on turnstiles today, and so this option would best be left until Presto is rolled out across the system.  The estimated annual cost is $1.0-2.1m, but this depends on various assumptions regarding pass pricing, trip counts and conversion rates from the existing all-day passes.
  • Lower age for “senior” passes to 60 from 65.  The estimated cost is $3.3-4.9m, but this includes only the lost revenue from existing Metropass holders switching to the lower-priced pass.  No provision is included for token users for whom the senior’s Metropass would be more attractive than continuing to pay single adult fares.
  • Extend senior/student fare pricing to ODSP and OWP recipients (these are the Ontario Disability Support and the Ontario Works programs).  This is projected to cost $6.3-12.6m, but the mechanism for administering these fares is not discussed.  Of particular note, the calculation is based only on the actual recipient numbers within Toronto, not on their dependents and spouses.

Any special fare regime will be easier to administer once automatic fare collection is in place.  Time-of-day discounts and special fares associated with a rider’s status can be build into the fare structure, and the actual amount of discount provided for each target group can be tracked.  This will be important if special subsidies are involved so that they remain separate budget lines rather than simply merging into the overall TTC revenue stream.

Advisory Committee Activity

An interesting read in recent TTC agendas has been the meeting minutes for the Advisory Committee on Accessible Transit (ACAT).  This is a very active group whose discussion cover a wide range of issues with TTC staff, and the minutes report their activities in detail.

One might wish for the Customer Liaison Panel to be as forthcoming with information on its activities.  It is unclear whether the CLP has done anything since its formation, or what its areas of focus might be.  If the panel is intended to represent “customers” as part of TTC activities, why doesn’t it show the rest of the world what it is doing?

Supplementary Agenda

Yorkdale Fatality of September 14, 2012 – Final Investigation Report

This report contains the detailed findings regarding an accident last year in which a work car struck two employees during overnight maintenance near Yorkdale Station.

[New] York University Station Construction Status

Councillor Perruzza addressed the Board on the issue of York University Station where, as reported in the National Post, the station excavation is a lake, and no work appears to be in progress.

According to TTC staff, the tunnel construction contractor, Obrascón Huarte Lain and FCC Construcción, has handed off the site to the station contractor, Ellis-Don, but this process has taken longer than expected.  Meanwhile, Ellis-Don did not take over pumping of water even though they were now responsible it.  This is to be corrected, and Ellis-Don will begin active work on the site in 2-3 weeks.

Construction at this location was substantially delayed due to a worksite fatality in 2012.

[New] Time-Based Transfers for Eglinton West

Commissioner Colle requested a report from staff on the implementation of a time-based transfer arrangement on Eglinton West during the Crosstown tunnel construction similar to the setup still in use on St. Clair Avenue.  The TTC will ask Metrolinx to contribute to the cost of this if it is implemented.

[New] GO/TTC Fare Integration at Dundas West and Exhibition Stations

Chair Stintz requested that staff report on the provision of a joint TTC/GO fare between Union Station, Dundas West and Exhibition Stations as a way of relieving demand on the system, notably on the 504 King car.  The report should be on the November agenda.

Moving People Downtown: The Gardiner East Is Only The Beginning

On October 16, 2013, the second public meeting in the Gardiner East Environmental Assessment presented additional information and refinement of the options for dealing with the expressway’s segment between the Don River and Jarvis Street.

The purpose of the meeting was to report on the options that would receive further analysis in the next step of the EA and to provide comparative information about costs and benefits of the various schemes.  Broadly, there are four families of options:

  • Maintain the existing expressway with necessary repairs to make it sound for several decades’ more service.
  • Replace the expressway on a new structure either above or below ground.
  • Improve the existing expressway by selective reconstruction to open up space under the road deck.
  • Remove the expressway and create an at-grade boulevard.

Some options have been dropped from further study:

  • An underground alignment 1km long transitioning to/from existing elevated structured at the Don and at Jarvis.
  • An elevated alignment over the rail corridor.
  • A surface alignment on a berm abutting the south side of the rail corridor.

For any tunnel option, an important consideration is that most of the traffic arriving from the DVP and Lake Shore East is bound for the core area rather than as through trips to the western side of Toronto and beyond.  Therefore, access ramps are essential to any option that is not at grade so that traffic can actually get to downtown.  (By contrast, the “Big Dig” in Boston provided a link between the north and south sides of the core area on a route where 80% of the travel is through traffic and does not create demand for local ramp structures.)

The study claims that 80% of inbound trips have downtown destinations and this argues against a tunnel from which access would be difficult.  However, consider the origin-destination charts on page 15 of the presentation:

GE2P15

Of the traffic arriving from the DVP:

  • 40% leaves at Richmond Street
  • 7% exits to Lake Shore
  • 53% continues onto the Gardiner East, subdivided as
    • 10% exits at Jarvis/Sherbourne
    • 25% exits at Spadina/York/Bay
    • 18% travels beyond downtown.

If we were contemplating a tunnel across all of downtown, the argument about ramps and O-D patterns would be valid, but in this case, from the point of view of such a tunnel, most traffic is “through” traffic.  Only 10% of traffic that would enter a tunnel westbound at the Don leaves at Jarvis, and even this would be served if an off-ramp were incorporated in the transition from tunnel to elevated.  Similar arguments apply to the other O-D maps above.

The real problems with a tunnel are its cost and the barrier effect created by ramps linking the tunnel to the elevated structures at the Don and at Jarvis Street.

The schemes involving the rail corridor have both been dropped because they cannot be fitted into the space available.  In the case of an elevated, there is no room for the support structures needed (not to mention access ramps), and in the case of the berm, the area is reserved for future expansion of rail operations.

A far more important issue hinted at by the presentation but not explored in detail is the wider context of transportation into the core area.

Continue reading

Cherry Street Track Construction (Update 3)

Updated September 17, 2013 at 4:25pm:

According to earlier plans I had heard through Waterfront Toronto, Cherry Street Loop was not to be completed until after the Pan Am Games because the site is part of a parking lot for buses.  Contrary to this story, the loop is under construction, albeit surrounded by a parking lot.

IMG_4450w

The now-inactive Cherry Street tower that once controlled the eastern approach to Union Station sits at the south end of the loop.  In the left background, behind the trees, is the GO Don Yard.

The terrible irony about this, our possibly newest streetcar line, is that it won’t actually see service until Spring 2016, and the proposed extension under the railway to connect with a Queens Quay East line isn’t even in the current list of projects awaiting funding.

Continue reading

Where Will the Scarborough Subway Go?

The Toronto Star reports that Queen’s Park is contemplating an alternative route to Toronto’s proposed Scarborough subway extension via Eglinton and McCowan to Sheppard East.

The key paragraphs in the article are:

“In the next couple of weeks we should have an announcement on what the routing will be, what the design will be and what the cost will be,” he told reporters on the way into a cabinet meeting Wednesday.

Queen’s Park wants to have the subway run on a similar route to the light rail transit plan to “maximize the impact of this line and get it connected to as many people (as possible),” said [Transportation Minister] Murray.

Murray seeks to find out how much could be built with the $1.4b already committed to a subway project.  Using an existing corridor could reduce the cost compared to the McCowan alignment.

This raises questions debated in other threads here of how the subway would be extended via the existing SRT alignment including the configuration of Kennedy Station and whether a route from Ellesmere Station eastward would be elevated or underground.

Recycling some or all of the existing corridor will require a period of shutdown for the RT with parallel bus service, an issue that weighed heavily against the LRT scheme in recent debates.  Will the promise of a subway quell objections to this shutdown?

Murray will meet with Lisa Raitt, the federal Minister of Transport, to discuss funding, but he is already throwing cold water on hopes for assistance from Ottawa for a  “416” project.  Even if the feds bring money to the table, the next questions will be whether the original McCowan scheme or an SRT alignment for the subway are the best use of available cash, and how either subway would fit into a larger network.

The debate comes back to Toronto Council in October preceded by Murray’s announcement likely in mid-September.  Backers of the subway like TTC Chair Karen Stintz and recently-elected MPP “Subway Champion” Mitzie Hunter have stressed that their support for a Sheppard LRT was for a different line in different circumstances.  A Scarborough subway, wherever it goes, will leave large parts of eastern Toronto far from rapid transit.

The LRT debate is not over.  Will Stintz and Hunter become “LRT champions” for other parts of the network?

Memo to Glen Murray & Karen Stintz: Are You Really Serious About Transit in Scarborough?

With all the upheaval of transit plans for Scarborough, politicians fall over each other to tell Scarborough residents how downtrodden and ignored they have been, how they always get the short end of the transit stick.  How will we fix this?  Build them a subway!

Mind you, that subway won’t open for 10 years, and riders on the Scarborough RT will have to endure more cold winters and overcrowded service, not to mention bus routes that run occasionally and unreliably.

We should remember what Scarborough was originally promised with the Transit City scheme announced years ago by then-Mayor Miller and now-Candidate Adam Giambrone:

  • An LRT line from an underground station at Don Mills & Sheppard with a direct connection to the Sheppard subway running east to Morningside and beyond.
  • An LRT line from Kennedy Station east and north via Eglinton, Kingston Road and Morningside to Sheppard serving the University of Toronto Scarborough Campus (UTSC).
  • An upgraded and extended Scarborough RT using LRT to reach east and north to Malvern Centre.

The Sheppard LRT is “funded” by Queen’s Park, but actual construction is a moving target with completion now planned for 2021.

The Eglinton/Morningside line (aka “Scarborough-Malvern”) drifts in limbo not even a part of the Metrolinx “Next Wave” implying completion at best by the late 2020s.

The Scarborough LRT has been replaced by the Scarborough Subway.  Although Council attached many conditions to the financing for that line, you can bet that no politician in Toronto is willing to pull the plug, to return to the LRT scheme, with provincial and municipal election fortunes in play.  One way or another, even by the simple expedient of giving Ottawa more time to pony up “their fair share” (whatever that means), the subway scheme will stay alive, and the Scarborough LRT will start to resemble Monty Python’s “dead parrot”.  It will be “sleeping” only in the minds of its most ardent advocates.

Politicians love to tell us how much they support better transit in Scarborough, and they could start by talking about something more than the subway.

Continue reading