Eglinton LRT Design (Part 1: Introduction & Western Segment)

My apologies to regular readers for the delay in posting news and comment on the last round of Eglinton LRT designs.  Over the next few days, I hope to catch up on this and other topics.

June 2009 brought a major round of public meetings for the Eglinton LRT complete with a detailed look at how the line would be implemented.  The display panels for the current proposals are available on the project website.

The Eglinton line is a huge project, and if it’s done right, will show off the capabilities of LRT versus other modes.  The line will be partly on the surface, partly grade separated (mainly underground), and will be a real test of fitting infrastructure appropriate to demand levels across much of the city.

The comments below follow the display panels in the order presented by the TTC to save readers from jumping back and forth to locate various topics. Continue reading

Eglinton LRT Update

Planning for the Eglinton LRT continues as described in a report at the May 28 Commission meeting.  Major points in this report include:

  • Surface operation west from Keele and east from Brentcliffe with a tunnel between these two points.  The exact location of the tunnel entrance, particularly at the west end, is still under study.
  • Centre of the road alignment for the surface sections.  This arrangement is substantially cheaper than an alternative trench arrangement (similar to that used on the Yonge Subway north of Rosedale) along the north side of Eglinton in the land reserved for the Richview Expressway.
  • The carhouse will be somewhere near Black Creek.  Although not explicitly named in the report, the Kodak lands in Weston have been rumoured as a site.
  • The airport alignment and stations are the subject of an area study to deal with special considerations including two highway crossings and a future link with other regional services.
  • Future work in this project will also include connections with existing and future TTC subway and LRT services.

The next round of public consultation including updated designs will occur in June.  There will be six open houses between June 15 and 25 from 6:30 to 9:00 pm:

  • June 15: William Lea Room, 1073 Millwood Rd
  • June 17: Eglinton Public School, 223 Eglinton Avenue East
  • June 18: Richview Collegiate, 1738 Islington Avenue
  • June 23: York Memorial Collegiate, 2690 Eglinton Avenue West (at Keele Street)
  • June 24: Beth Sholom Synagogue, 1445 Eglinton Avenue West (at Allen Road)
  • June 25: Don Montgomery Community Recreation Centre (formerly Mid Scarb. CC), 2467 Eglinton Ave East

How Much Should the Eglinton Line Cost? (Update 1)

Update 1, April 15, 2009:  Although the original Transit City report gave Pearson Airport as the western terminus of the Eglinton line, the cost estimate only covered the portion to Renforth.  Approximately 3 km of additional construction are required to bring the line right into the airport, and the cost of this was not included in the 2007 estimate.

The underground section of the line was originally planned to lie between Keele and Laird Drive, but this may be expanded west to Jane and east to Don Mills (except for the river crossing).  This additional tunnelling is included in the recently announced cost estimate.

Original article:

Today’s Globe & Mail contains an article by Jeff Gray about the constantly escalating estimates for the Eglinton “LRT” line.  Gray cites the original estimate of $2.2-billion in 2007 compared with $4.6-billion figure included in the recent McGuinty funding announcement.  Nobody quite seems to know why the cost has doubled in two years. Continue reading

Ontario Funds Three Transit City Routes

Today, Queen’s Park announced that it would fund three of the Transit City projects — Eglinton, Finch and the Scarborough RT rehab/extension — as well as upgrading of York VIVA BRT corridors with dedicated lanes.

The announcement is fascinating in places for what it does not say, or leaves for future decisions.  Despite much of the build-it-yesterday rhetoric accompanying the GO/Metrolinx merger, the design and EA processes now under way will run their course.  Indeed, the Transit City projects have been proceeding apace thanks to funding at the municipal level to complete this work without waiting for agencies like Metrolinx to get on board.

The estimated cost for the York VIVA project is $1.4-billion with completion in stages from 2011 to 2013.  Lines that will connect with VIVA include the Spadina and Yonge subway extensions although full funding for the latter is not yet in place.

The Scarborough RT will undergo vehicle replacement, infrastructure upgrades and extension to Malvern Town Centre or to Markham Road.  This project will cost $1.4-billion “depending on the technology choice”, and construction will run from 2010 to 2015.  Connecting lines include “the proposed Sheppard East LRT”.

The Eglinton Crosstown line will run from Pearson Airport to Kennedy with a future extension to Malvern (this is the Scarborough-Malvern TC line).  The line will be tunneled between Keele and Leslie, and the total pricetag is $4.6-billion.  Constuction will run from 2010 to 2016.

The Finch LRT will run from Humber College to Don Mills, and then south to Don Mills Station where it will connect with the “proposed Sheppard Avenue East LRT”.  The project will cost $1.2-billion with construction running from 2010 to 2013.

An obvious question in response to this impressive list is “where’s Sheppard East”?  First off, as I noted above, some lines mentioned in the announcement don’t have funding yet, and the Sheppard LRT is mentioned twice.  Finch is explicitly listed as an LRT project, and the technology choice for the RT is still up in the air (no pun intended).  That choice depends on Metrolinx’ own Benefits Case Analysis (BCA) for Eglinton expected to be available, at least in private session, to the Metrolinx Board this month.  We know that the Scarborough RT BCA looked favourably on the LRT option.

There isn’t much point in building one lonely LRT line up on Finch if it wouldn’t be connecting with a larger network, and I think this suggests a larger LRT network is in our future.

Although the source of funding for Sheppard isn’t announced yet, Mayor Miller speaks of construction starting this year on Transit City.  The only place that is possible is on Sheppard.  Also coming up will be the new streetcar order for the “city” network, yet another opportunity for substantial provincial funding.  I suspect there are more rabbits waiting to pop out of one or more hats.

Finally, lest our friends to the west think I have ignored them in my haste to talk about Transit City, Queen’s Park will also fund rapid transit studies in Hamilton.  No technology is mentioned.  There is strong political support for LRT in Hamilton, but will Queen’s Park and Metrolinx let them build anything more than BRT.  A lot depends on what the studies will reveal about demand and development impacts.

Transit City Status Update

This month’s TTC agenda includes a long update on the status of the Transit City plans.  I will not attempt to précis this report, but will touch on points of particular interest.

Funding is in place to allow continued work on Environmental Assessments [sic] and other engineering work, but the real challenge comes later this year when construction is slated to begin on Sheppard.  The fog may clear a bit once the provincial budget is announced and we know just how much money will flow to Metrolinx and to transit in general.

A related problem, of course, is the question of new LRVs for the existing and future streetcar/LRT networks.  By the time the budget is out, the TTC should know what the bids for new cars look like, and Queen’s Park will have to decide whether they are serious about paying for them. Continue reading

Transit City — The Movie

Today’s TTC meeting brought us an update on the various parts of the Transit City plan.  You can read the full report yourself, and there is a quick review of the status of various lines and studies below.

Meanwhile, the TTC is starting a media campaign to tell people about Transit City and about LRT.  You can watch the video on the TTC’s website.  Although it is a breath of fresh air to see the TTC promoting LRT after all these years, there are a few oddities in this piece (the timings where they occur are included below).

  • (0:39) “Work on Transiy City is already well underway.”  Hmmm … a few traffic barriers does not make a construction project.  I wonder why they don’t show the upheaval on St. Clair?  Shortly later we see a new car mockup superimposed on the westbound stop at Yonge Street.
  • (0:55)  “What is Light Rail Transit?”  We learn that LRT is used around the world including, wait for it, in Vancouver!  Er, ah, there’s a heritage streetcar line running with a former BC Electric interurban car, but no LRT.  This is a howling error.  Other cities shown on the world map are many fewer than the actual inventory.
  • (1:15)  “LRT can operate in a street, but has the flexibility to operate underground like a subway.”  LRT advocates will be amused to hear that their chosen mode has the “flexibility” to be just like a subway, when the real issue is the inflexibility and cost of 100% grade separated modes.
  • (1:50) Light rail is bigger than standard streetcars, and allows level boarding from platforms.  It’s nice to hear how LRT is a streetcar, but not a streetcar.
  • (2:10) LRT cars don’t need loops!  Amazing what you can do with modern technology.  See also Kennedy Station Loop.
  • (2:20) All door loading … but wait .. it’s a subway car!
  • (2:38) LRT will be separated from the effects of traffic congestion, not to mention pesky “transit priority” signals if the animation can be believed.
  • (3:32) Streetscaping.  Aside from the gigantic, fast-growing trees (maybe they’re from Vancouver too), note the typical suburban layout with wide setbacks of buildings from the street.  Contrast this with later illustrations of dense suburban redevelopment.
  • (4:05) Transit will be an even better travel alternative.  With a new subway train?  What’s that doing here?

The map of projects reflects the original Transit City announcement because many possible changes are still under study by both TTC and Metrolinx.

Transit City project updates follow the break.

Continue reading

A Slightly Less Grand Plan

Ontario’s Finance Minister, Dwight Duncan, yesterday announced that the province will run a half-billion dollar deficit thanks to the international financial upheavals and declining economic outlook.  In this context, I spent the day at a Metrolinx “stakeholders’ meeting” where we discussed details of the Draft Regional Transportation Plan and Investment Strategy.  The whole discussion has a surreal air because nobody is quite sure where the billions to pay for this plan will come from.

There is reasonable agreement about the need for better transit, but much suspicion of whether this plan will join its predecessors on library shelves.

In the informal post-meeting chats, I was asked what I would do if the promissed $11.6-billion MoveOntario money didn’t materialize, if we had to cut back the scope of the “top priority” projects to fit a tighter budget.  This is too big an issue for a short chat, and it deserves a post of its own.

Any budgetary cutback discussion must first consider whether to make the “death of 1000 cuts” or to look hard at big ticket items.  If you need to defer or cut spending, there is more money to be found in large projects than small ones, but we may skip reviews of smaller items that really don’t belong at the top of the pile.

A major problem lies in the dearth of information Metrolinx has published about the detailed performance projections and roles of each component in the plan.  We have demand forecasts only for year 2031 where the combined effect of future job and population growth interact with a completed network.  The published data show only peak point counts, not the demands for each network link.  There is no way to understand which links are cost-effective, and there is no data for intermediate states (such as after the “first 15” are built) to show whether they are an appropriate use of whatever resources might be available.

Metrolinx must publish this information as soon as possible.  Meaningful discussions of cutbacks are impossible without it.

This brings me to the “Business Case Analyses” that are in progress already for some of these lines.  These analyses are proceeding in the old, worn-out style of looking at each project individually rather than collections of projects for their combined effect on the network.  From the 2031 projections, we can see that the regional express rail lines and other new major elements have a big impact on demand on the existing network.  Notably, the forecast overload of the subway system doesn’t materialize because there are other high-capacity lines where the demand can flow.

Meanwhile, the TTC’s report on the north Yonge extension to Richmond Hill raises an old, hare-brained scheme to add a third platform at Bloor-Yonge station for increased capacity.  I won’t go into a detailed discussion here beyond saying that this is horrendously complex and expensive, but at least the TTC finally recognizes that subway capacity involves more than new signalling and more trains. 

The real question, however, is whether the money would be better spent on alternate services to divert riding with new options for travel to the core area.  Should some projects — the Richmond Hill regional express and/or the east leg of the Downtown Relief subway — be moved up as alternatives or as key pre-requisites?  That’s the kind of comparative analysis Metrolinx and the TTC are not doing, but should.

Next we come to project phasing.  Do we really need a line all the way to Richmond Hill?  Is there a shorter “phase I” that will have significant benefits without the cost of the full line?  Analysis on an all-or-nothing basis doesn’t give us staging options.

We need to be open about “the untouchables”, the projects with political clout that soak up billions of dollars because someone wants to see them built.  There is no point in talking about fiscal restraint if billions in proposed spending can’t be reviewed.  A related question is how that “top 15” list came into existence in the first place. 

Some time ago, the Metrolinx Board approved this grab-bag as likely top candidates that should be analyzed in more detail.  However, that analysis isn’t even started for many of them, and there is every possibility that the analyses may show that some projects don’t pull their weight, at least in the short term.  I may be splitting hairs, but that “top 15” has gone from candidates for early study to the definitive list of first projects without benefit of formal approval.  If we are to have a spending review, we must stop assuming that this list has the force of detailed review and blessing.

Oddly, it’s almost an afterthought in the Draft RTP — Metrolinx doesn’t even include a map showing the network with only these lines completed.

The subway to Vaughan is a special case.  There is supposed to be a trust fund holding the funding from Queen’s Park, Ottawa, York Region and Toronto.  Is this money really sitting in a bank somewhere?  Does the provincial share come out of the $11.6-billion MoveOntario pot?  Can we step back and ask questions about why this line is so important?  For starters, someone has to reconcile demand projections in York Region’s own EA that would make the Sheppard subway look busy with the impetus to build this line.  Metrolinx does not break out the section north of Steeles as a separate project, and the published demand for the line gives only the peak point value (likely just north of Downsview Station).

The TTC is already studying alternatives to the SRT including LRT conversion of the existing line.  The original recommendation to keep Skytrain technology only made sense for a line that remained at its existing length or had a short extension.  The further north it goes (Markham is a mooted destination), the less practical and more expensive Skytrain is relative to LRT.  Keeping the RT was a bad recommendation skewed by a desire to preserve Bombardier’s showcase technology, and we cannot afford to avoid this debate.

On the Sheppard/Finch corridor, current thinking is headed toward an eastward extension of the Finch LRT to Don Mills (where it would connect to the Don Mills line) and a westward extension of the subway to Downsview.  These may be viable projects in the long term, but we have to consider them separately from the original Transit City proposals.  Indeed, the Don Mills LRT isn’t even in the “top 15”, and there isn’t much point building the Finch line east of Yonge until it has something to connect with.

At Finch Station, there are big problems with the bus terminal and with the design of a future LRT interchange.  What happens if the subway extension gets underway and much of the bus operation shifts north?

On Eglinton, a line whose projected peak ridership is similar to both of the subway extensions, but whose extent provides rapid transit service to a far larger area, we are faced with an expensive central tunneled section that cannot be avoided.  Indeed, the size of this project requires that it be started sooner rather than later so that its benefits as a key part of the overall network can be available.

In the Don Mills corridor, should the DRL end at Danforth or continue north to Eglinton with a major transit hub linking the Eglinton and Don Mills LRT lines to the DRL subway?  This won’t be part of the “top 15” list, but the Don Mills Transit City study would make a lot more sense if the TTC stopped trying to shoehorn an LRT right-of-way into Pape or Broadview.  That scheme (and related alignments) are holdovers from the days when this was a BRT study, and this nonsense has to stop.

On the Weston/Brampton rail corridor, why do we persist with the fantasy of the Toronto Air Rail Link (TARL, formerly called “Blue 22”) that will chew up track space for a premium fare service on the same route as a proposed regional express service to Brampton?  How much does the private sector-proponent of the line hope to make from this service?  Can they be bought off?  Is it cheaper to not build Blue 22 and devote the resources to upgrading GO in the same corridor?

What are the possibilities for the CPR North Toronto Subdivision?  What options do we have for cross-region service via this corridor especially as an alternative way for riders from the north-east to get into the city without using the RT/subway network?  Negotiating with CPR won’t be easy, but doing nothing may condemn us to building rapid transit capacity elsewhere we might not actually require.

If there is a common thread in all of this, it’s a simple message:  Metrolinx started off designing a network, and they must not lose sight of the network view of any solutions.  Look at revisions to the plan as a whole, look at where the benefits are greatest in the short term so that we spend what money is available on projects that will show real improvements for transit.

Toronto has decades of making wrong, expensive choices, and transit suffers a well-deserved reputation as an “also ran” thanks to those decisions.  Provincial belt-tightening is just the opportunity we need to focus on what really works, on what we really need.

Jane/Eglinton LRT Open House

Lately I have been distracted by other events, and neglected to post information about the Jane LRT Environmental Assessment.  The display panels from the open houses can be found on the project website.  Note that three linked “display drawings” showing the detailed route layout on an aerial view of the line are quite large with the fine details visible only if they are viewed at 100% size.

There will be a joint presentation of the Jane and Eglinton LRT:

Monday September 22
6:30pm to 9:00pm
Centennial Recreation Centre West, gymnasium
2694 Eglinton Ave West
(just east of the York Civic Centre and adjacent to York Memorial Collegiate Institute)

The Jane LRT design is, putting it mildly, challenging because of the narrow right-of-way available for the south end of the route.  Alternatives including underground construction or reduction in the number of road lanes are being considered.  These will be a harder sell in the Jane corridor than on other Transit City routes because of the lower projected demand relative to the community impact and the cost of an underground option.  This would place the line underground south of Wilson Avenue, but would result in much wider average station spacing (1km if underground, 500m if on the surface).

Oddly, the same language about running LRV trains because of the difficulty of managing close headways is carried over from other EA materials.  This gives us the absurb claim that it is difficult to manage a headway of 3’30” of single cars, and a 7’00” headway of trains would be operated for reliability.  Contrast this with the Eglinton LRT EA where the proposed headways are 3-4 minutes.

At York University, there are three proposed routes to link the Jane LRT with Steeles West Station.  One stays completely on Jane and Steeles, one skirts the campus on the west side via Murray Ross Parkway, and one goes through the campus.

Two Metrolinx proposals (shown on the map published by the Star) include a northern extension of the Jane line to meet up with east-west service in York Region, and truncation of the south end at Eglinton where it would connect to whatever is built in the Eglinton corridor.  Also omitted, thanks to the ever-present Blue 22 line, is any mention of a service via the Weston rail corridor to Union Station.  Both of these schemes for the south end of the line would leave the Jane LRT serving only the portion of the route north of Eglinton with bus service remaining south to Bloor.  These options should be examined if only to determine their impact on peak service demand and the origin-destination pattern of riders in the Jane corridor.

The refined proposals for the Jane route will come back to a second series of open house meetings later in 2008.

Eglinton LRT Open House Presentation

[I decided to start a new thread now that the presentation materials are available online as there were already 50 comments on the post announcing the open house sessions.]

The Eglinton line is a long and complex project, no matter what technology will be used, and tonight’s meeting at Leaside Arena had a good turnout right from the start.  I didn’t hang around, but do know that there’s a lot of interest along the central part of the line in many design and service issues.  Some of these cannot really be addressed until we see a detailed design at the next round of meetings, but the general shape of the line is evident.

This commentary highlights items in the presentation that I found interesting. Continue reading

Eglinton LRT Public Meetings Announced (Update 4)

The City of Toronto has announced the open houses for the first round of consultation for the Eglinton line. 

Update 1:  A fifth meeting has been added to the list below.

Update 2:  The Star contains an article about preliminary response to the information to be presented at public meetings.  Concerns focus on the space between stops on the underground LRT as compared with the current surface bus operations.  The real question is what, if any, residual bus service will be operated over this portion of the route.

Update 3:  The FAQ for this project is now available online.

Update 4:  The presentation materials for this round of public meetings is now available online.

The Open Houses are planned as follows:

Thursday, August 14
6:30pm to 9:00pm
Forest Hill Memorial Arena, 340 Chaplin Cres.

Tuesday, August 19
6:30pm to 9:00pm
Leaside Arena, 1073 Millwood Rd.

Monday, August 25
6:30pm to 9:00pm
Humber Valley United Church, 76 Anglesey Blvd.

Wednesday, August 27
6:30pm to 9:00pm
Don Montgomery Community Recreation Centre
(Formerly the Mid Scarborough Community Centre)
2467 Eglinton Ave  East

(Added) Richview Baptist Church
1548 Kipling Ave (just north of Eglinton)

The project website is now online.

Note:  If you want to contribute to the thread about technology choices for the line, please do that in the post where that discussion is already underway.