OneCity Plan Reviewed

The OneCity plan has much to recommend it even though in the details it is far from perfect.

The funding scheme requires Queen’s Park to modify the handling of assessment value changes, and they are already cool to this scheme.  Why OneCity proponents could not simply and honestly say “we need a 1.9% tax hike every year for the next four years” (not unlike the ongoing 9% increases to pay for Toronto Water infrastructure upgrades) is baffling.  A discussion about transit is needlessly diverted into debates about arcane ways of implementing a tax increase without quite calling it what it is.

On the bright side, Toronto may leave behind the technology wars and the posturing of one neighbourhood against another to get their own projects built.  Talking about transit as a city-wide good is essential to break the logjam of decades where parochialism ruled.  Couple this with a revenue stream that could actually be depended on, and the plan has a fighting chance.  Ah, there’s the rub — actually finding funding at some level of government to pay for all of this.

Rob Ford’s subway plan depended on the supposed generosity of Metrolinx to redirect committed funding to the Ford Plan (complete with some faulty arithmetic).  Similarly, the OneCity plan depends for its first big project on money already earmarked by Metrolinx to the Scarborough RT to LRT conversion.  If this goes ahead, we would have a new subway funded roughly 80% by Queen’s Park and 20% by Toronto.  Not a bad deal, but not an arrangement we are likely to see for any other line.

On the eastern waterfront, there is already $90m on the table from Waterfront Toronto (itself funded by three levels of government), and OneCity proposes to spend another @200m or so to top up this project.  Whether all $200m would be City money, or would have to wait for other partners to buy in is unclear.

Toronto must make some hard decisions about a “Plan B” if the Ottawa refuses to play while the Tories remain in power.  Even if we saw an NDP (or an NDP/Liberal) government, I wouldn’t hold my breath for money flowing to Toronto (and other Canadian cities) overnight.  A federal presence is a long term strategy, and spending plans in Toronto must be framed with that in mind.

Sitting on our hands waiting for Premier McGuinty or would-be PM Mulcair to engineer two rainbows complete with pots of gold landing in Nathan Phillips Square would be a dead wrong strategy.  Bang the drum all we might for a “one cent solution” or a “National Transit Strategy”, Toronto needs to get on with debating our transit needs whether funding is already in place or not.  Knowing what we need and want makes for a much stronger argument to pull in funding partners.

In some cases, Toronto may be best to go it alone on some of the smaller projects, or be prepared to fund at a higher level than 1/3.  If transit is important, it should not be held hostage by waiting for a funding partner who will never show up.

The briefing package for OneCity is available online.

My comments on the political aspects of OneCity are over at the Torontoist site.

To start the ball rolling on the technical review of the OneCity network, here are my thoughts on each of the proposals in the network. Throughout the discussions that will inevitably follow, it is vital that politicians, advocates, gurus of all flavours not become wedded to the fine details. Many of these lines won’t be built for decades, if ever, and we can discuss the pros and cons without becoming mired in conversations about the colour of station tiles.

Continue reading

Metrolinx Board Meeting, June 2012

The Metrolinx Board met on June 21 with a full agenda.  As is unfortunately the case with this quasi-public board, the fatter the agenda, the less time is spent on actual discussion of the material in it, at least in public.  Presentations were rushed, and there were few questions from the Board to staff.  Many issues on the public agenda have counterparts in the private session where, one might hope, there is more robust debate.

[This article has been in the hopper a bit longer than I had hoped while I chased some details from Metrolinx.] Continue reading

“One City” To Serve Them All

Updated June 27 at 5:20pm:  I have written a political analysis of today’s announcement for the Torontoist website that will probably go live tomorrow morning.  A line-by-line review of the plan will go up here later the same day.

TTC Chair Karen Stintz and Vice-Chair Glen De Baeremaeker will formally announce a new plan called “One City” on June 27 at 10:30.

The plan already has coverage on the Star and Globe websites.  Maps:  Globe Star

I will comment in more detail after their press conference, but two points leap off the page at me:

  • The proposed funding scheme for the $30-billion plan presumes 1/3 shares from each of the Provincial and Federal governments.  This money is extremely unlikely to show up, especially Ottawa’s share.  From Queen’s Park, some of the funding is from presumed “commitments” to current projects such as the Scarborough RT/LRT conversion which would be replaced by a subway extension.  The rest is uncertain.
  • The “plan” is little more than a compendium of every scheme for transit within the 416 that has been floated recently in various quarters (including this blog).  What is notable is the fact that glitches in some of the existing ideas (notably the fact that the Waterfront East line ends at Parliament) are not addressed.  The whole package definitely needs some fine tuning lest it fall victim to the dreaded problem of all maps — once you draw them, it’s almost impossible to change them.

For those who keep an eye on political evolution, the brand “One City” surfaced in April 2012 in a speech made by Karen Stintz at the Economic Club of Canada.  This idea of a new, unifying transit brand appears to have been cooking for some time.

TTC v. Metrolinx (Again): Who’s In Charge Here? (Update 2)

Updated June 8, 2012 at 11:00am:  My comments about the Commission’s action appear in an article on the Torontoist website.

Updated June 1, 2012 at 9:15am:  The motions passed at the TTC meeting of May 30 have been added at the end of this article.  The Commission took a much more conciliatory view of their relationship with Metrolinx than the staff report.  I will be writing about this situation in a separate article.

The original May 29 article follows below.

The Supplementary Agenda for the May 30, 2012 TTC meeting includes a report “LRT Projects in Toronto — Project Delivery”.

This report deals with the proposed transfer of responsibility for the Transit City LRT projects on Eglinton, Sheppard, Finch and the SRT replacement from the TTC to Metrolinx and Infrastructure Ontario.

As TTC reports go, this one is rather oddly worded in that it:

  • asks the Commission to “note” a number of factors,
  • requests that provincial agencies respond to various issues,
  • sets an October 31, 2012 deadline for the transfer of project control, and
  • proposes that the TTC’s own staff now dedicated to the LRT projects be redeployed internally.

In effect, the TTC is taking their ball and going home rather than play with the guys from down the block.  This suggests a strained relationship between agencies notwithstanding the soothing words we hear so often, and a sense that a fed up TTC is telling Queen’s Park to get lost.

From a purely political and administrative point of view, Queen’s Park holds all the cards because they are paying almost the entire cost (with a small Ottawa contribution to Sheppard) for these projects.  It’s their money, and they get to say how it will be spent.  Whether it will be spent wisely, and how the projects might fare with the TTC on the sidelines, these are questions that won’t be answered for years until we see the results.

Continue reading

TTC Meeting Preview: May 30, 2012

The Toronto Transit Commission will meet on May 30, 2012.

CEO’s Report

The scoreboard which begins the CEO’s Report includes the Key Performance Indicators (KPIs) about which I have written elsewhere.  Subway performance continues to be monitored against schedule ±3 minutes 96% of the time.  It remains unclear how a systemic delay — where many trains are one or more headways out of place but service is otherwise well-spaced — affects this metric.  Surface routes aim to be within 3 minutes of the scheduled headway 65% of the time for buses and 70% of the time for streetcars.  Considering the headway on which all major routes operate, 3 minutes represents close to if not more than one headway, and much service will easily hit that target even though the rider sees disorganized bunching service with many short turns.  I will address this problem in separate articles looking in detail at specific routes’ behaviour.

Riding is up relative both to actual results in 2011 and to budget in 2012 (see following section on additional service to handle growth), and the offpeak increase is running ahead of peak as it has for some years.

The top source of complaints continues to be “Other” with “Surface Delays” and “Discourtesy” coming next in that order.  The TTC has initiated a rolling survey of customer satisfaction, but it has not yet accumulated enough data to produce a metric that shows a trend over time.  One big challenge of “customer service” is that some initiatives have an effect at limited points — clean and well-maintained washrooms may be appreciated by those who use them, but they don’t make any difference to overall service for most riders.  Pervasive changes — more frequent and regularly spaced buses, improved station cleaning and escalator/elevator maintenance — require changes in how the system thinks about its operation as a whole, not in discrete chunks that are easily targeted. Continue reading

The High Cost of Going Underground(?) (Updated)

Updated May 17 at 11:00 pm:  Richard Gilbert has responded to this article.  Rather than leave his remarks and my replies in the comment stream, I have placed them at the end of this article.

Urban consultant and former city Councillor Richard Gilbert has an article on the Globe & Mail’s blog titled “How Toronto’s transit plan takes taxpayers for a ride”.  The article decries the high cost of the Eglinton LRT and in particular the high effective subsidy per rider of the capital cost of burying much of the line.

The basic premise, the questions behind the article are sound, but the methodology is not.  This leads to a substantial overstatement of the per passenger subsidy for the capital construction.

At the outset, I must emphasize that my intent is not to attack Richard Gilbert himself, but rather to comment on the pitfalls involved in making comparisons between different systems, and in the use of generic formulas in planning.  In many of the critiques I have written over the years, the hardest  part has been to delve into the underlying assumptions and methodologies (themselves often hidden away in background papers).  These may “prove” something, if only that an author found the number he wanted to find and looked no further.

Gilbert writes:

According to Metrolinx, the provincial agency charged with implementing the transit improvements, the Eglinton line is to cost $4.9-billion (an amount under review). It is forecast to carry 5,400 passengers per hour in the peak direction in 2031, eleven years after it is scheduled to begin operation.

This peak rate is usually associated with an annual total of some 17 million rides. The annualized capital cost of the line is about $300-million per year ($4.9-billion amortized over 35 years at 5 per cent).

Thus the capital cost per ride will be an extraordinary $17.50 ($300-million divided by 17 million). This will be the effective subsidy per ride if the fares to be paid roughly cover the operating costs.

Central to this calculation is the translation of a peak point/hour demand of 5,400 to an annual ridership of 17-million.  The Eglinton route, like many transit lines in Toronto, is not a commuter line feeding unidirectional demand into one point like a GO train.  It is a route (actually several bus routes) serving an overlapping set of demands.  Many riders on the line do not contribute to the peak point count — a peak measured westbound to Yonge in the AM peak will not include any riders using the west end of the line, nor will it include any counter-peak traffic.  Many riders will not contribute to the peak hour counts — the ratio of off-peak riding on the TTC is much higher than on GO Transit even where all-day service is provided.

Any claim that a single peak point’s ridership can be translated to an annual figure will be inaccurate because it ignores the characteristics of the line as a whole. Continue reading

Good News Far Too Much of the Time

The TTC has now launched a public-facing version of an internal campaign pitching its new organization and attitude to serving riders under the rubric Modernizing the TTC.  The same information appeared in a poster recently issued throughout the organization.

From a service delivery point of view, the key pages are the 25 Key Performance Indicators and the Daily Customer Service Report.

The “KPIs” are intended to give ongoing information about ridership, service quality and station conditions including availability of escalators and elevators.

Strangely enough, the daily report is not available to the public, only a snapshot from March 19 on which — surprise! — everything is just fine, thank you very much.  This is precisely what has been wrong with the TTC for so many years — they are addicted to hearing good news.

Three changes are badly needed.

1.  Put real time data online

It’s all very well to know service ran so well two months ago, but I want to know how these indices are tracking today and over recent weeks.  Riders who waited while full buses zoomed past their stops, or were thrown off of short-turning streetcars, need to see what’s happening now and whether the TTC’s stats reflect their actual experience.

2.  Put more detail online

While the system as a whole may meet its targets, that does not reflect actual rider experience at a route-by-route level or at various times of the day.  The public information should be subdivided by route so that riders (and members of Council) can check against their local services rather than system averages, and the stats should be subdivided by time of day to distinguish busy peak periods from quiet evenings or weekends.

3.  Collect meaningful statistics

The statistics and targets now reported by the TTC have been with us in one form or another in places like the Chief General Manager’s Report (now the CEO’s Report) for some time.  Everything looks rosy until one thinks about what data drives the KPIs and whether it is really meaningful.

Subway and surface operations are measured by the proportion of trips that operate within three minutes of the scheduled headway.  It’s good to see the TTC moving away from “on time” as a measure of service quality because in most cases customers only care that vehicles/trains are regularly and reliably spaced.  They couldn’t care less if they are “on time” except in cases of wide headways.

However, if a service is scheduled to run every 4 minutes, this means that any headway from 1 minute to 7 minutes is acceptable for the statistics.  Even worse, a parade of vehicles each 1 minute apart meets the target except for the first in the queue where, presumably, there is a large gap.  A parade of 10 cars would be 90% “on time” because 9 of the 10 would be within 3 minutes of their scheduled headway.

With uneven headways more passengers accumulate in the wider gaps.  What most riders see is the train, bus or streetcar that arrives with a heavy load after a long wait, and they may not even be able to board.

The KPI needs to be revised so that vehicle bunching cannot produce statistics showing an acceptable quality of service.  As things stand, it would be easy to achieve a target of 2/3 of trips within an acceptable headway and still have quite ragged service especially on “frequent” routes.

Where headways are wider (some off-peak services and especially those with branches), on time performance is much more important.  Riders would like to plan their travel based on when a bus is supposed to appear rather than having to face waits of 20 minutes or more.

At a route level, an index is required to track service quality not  just at the route’s peak point, but at termini and common short-turn points.  Some routes have multiple peak points, and reporting only on one of them can misrepresent what many riders actually experience.

A sad commentary on the reliability of the SRT is that its service target is to operate 80% of scheduled trips.  Whether this will happen in a snowy winter remains to be seen.

Elevators and escalators are supposed to be 97% available.  However, I understand that this status is of about 9am and does not reflect whatever outages may occur through the day.  Moreover, devices that are out of service for maintenance don’t count against the target.  Unfortunately, a rider who cannot use stairs only cares that they cannot use their station.

As of May 16, 2012, there are seven escalators listed as out of service by the TTC not including devices at Union Station affected by the second platform project.  From a rider’s point of view, these are just as unavailable as a bus or streetcar that shows up after a long gap or hopelessly late.  They are a service that is expected but not available.

Outages for planned maintenance should be included in the stats, even if as a separate category.  Availability stats should be based on all-day operations, not once-a-day surveys.  (Note that it is not necessary to physically visit every station, but simply to log trouble calls that come in.)

When I spoke with the TTC about the fundamental problems in their statistics and goals, they freely admit that these just are not good enough.  However, management and Commissioners are now trumpeting a scorecard of success just at a time when they really need to set the standards higher.  All those green checkmarks will change at least to yellow if not red when the bar is raised.  TTC management and staff must be ready to accept the need for improvement against goals and measurements that reflect what passengers actually see day-to-day.

Service Changes Effective June 18, 2012

The TTC will implement many service changes on June 18, 2012 mostly for seasonal changes in demand.  The lion’s share of these are service cuts, with a few increases.  These are detailed on the first six pages of the document linked below.

Construction will continue in many parts of the city notably affecting the streetcar system.

Waterfront / Spadina

The separate operation of 509 Harbourfront and 510 Spadina will continue into June, but the Spadina streetcar service will be replaced with buses running in mixed traffic to permit construction.  This includes both track repairs and changes to the safety islands in anticipation of the new LFLRVs and the implementation of the Presto fare card.

Service on 511 Bathurst will be increased to absorb some of the traffic that might otherwise attempt to use the 510 Spadina service.

Whether this arrangement, with buses stuck in the often-jammed traffic lanes of Spadina, will work at all remains to be seen.  I cannot help wondering why the work is not staged in such a way that buses could use the right-of-way for at least part of the distance with police assistance at merge points.

Welding of new rail for the reconstruction of track on Queen’s Quay is now in progress in front of the Redpath’s Sugar site.  Tentative plans have streetcar service coming off of the 509 Harbourfront car at the end of July for the beginning of construction.

Queen Street East / McCaul Street

Work will continue on Queen near Russell Carhouse, but the reconstruction of McCaul Street will close McCaul Loop.  During this period, the branch of the 501 operating from Russell to McCaul will be extended to Wolseley Loop at Bathurst Street.  Whether it will actually reach this destination in the time allowed is quite another matter, and I expect to see a lot of cars short-turning.

Dufferin Street

Dufferin Street will be closed to transit between King and Queen for track and water main work.  The branches of 29 Dufferin which normally operate to Dufferin Loop will be short-turned at Queen via Gladstone.  The branches which operate to the Princes’ Gate will divert via Queen, Shaw and King around the construction zone.

2012.06.18 Service Changes

TTC Meeting Wrapup: May 1, 2012

The TTC board met on May 1.  This was a quiet affair without the political drama of the “old” Ford-stacked Commission, and I almost missed the bumbling antics of the old crew.  The agenda was on the thin side, and everything wrapped up in a few hours.

Major items included:

  • a status report on the LRT projects,
  • proposed changes to the Richmond Hill extension of the Yonge Subway,
  • the Framework Agreement with Metrolinx for implementation of the Presto farecard,
  • the Customer Satisfaction Survey, and
  • the CEO’s report.

Continue reading

Where Should We Put the “Downtown Relief” Line?

The Downtown Relief Line has been in the news a lot lately, what with dreams of vast new revenues to pay for transit expansion and, at long last, a recognition that more people want to travel downtown than we have transit capacity to handle.

Back in the 1980s, the Network 2011 plan included a line from Union Station to Don Mills and Eglinton by way of the rail corridor, Eastern Avenue, Pape, a bridge across the Don Valley, and Don Mills Road.  This scheme was turned down in favour of the Sheppard Subway as part of a misguided idea that if we simply stopped building new lines into downtown, growth would stop.  In fact, GO Transit did a fine job of providing extra capacity, and more recently the new downtown condos have raised short commutes by streetcar, cycling and foot to levels nobody expected thirty years ago.

The Yonge subway filled up, for a time,but the pressure fell off thanks to the 1990s recession and the general drop in transit use.  That’s no longer the case, and suddenly everyone wants to “do something” about transit capacity downtown.  The TTC, shamefully, downplayed anything beyond its own mad scheme to stuff thousands more riders onto the Yonge line, a project requiring major changes in signalling, reconstruction of Bloor-Yonge station (and possibly others) for extra capacity, a much larger subway fleet (and yards to hold it) and possibly even the addition of platform doors at all stations.

Council asked the TTC to look at a DRL, and there is even supposed to be a study.  However, its web page is the only sign that anything is going on.

Meanwhile, every would-be transit planner in town is busy drawing maps, to the point where a credible plan can be found simply by dropping a piece of spaghetti on a map of the city and declaring this a route.  (Post-graduate degrees are available to those who can determine the ideal height from which to drop the pasta and cooking time needed to produce the best results.)  What’s missing in a lot of this discussion is a view of how a DRL might fit into a wider network, not to mention a few basics about how a new rapid transit line will, or will not, fit in some of the proposed alignments.

One of the better proposals is on Phil Orr’s DRL Now site.  It’s not perfect (no proposal is, including those I have floated from time to time), but at least this is a place to start with sufficient detail to understand what is going on.  Drawing a swoosh across a map is easy (politicians do it all the time), but designing something that might actually work is a lot harder.

A major challenge with some versions of this line is that proponents try to do too much.  Playing “connect the dots” with a transit route has its limitations, and trying to hit too many of them causes the line to wander out of its way.  This ties back to a fundamental question:  what is a DRL supposed to do?

If we believe some of the simpler plans (notably one in last week’s Star proposed by Councillor Pasternak), the DRL’s sole function is to get people from the Danforth subway to Union Station.  This is far too simplistic and guarantees the line will not be well used except as a peak period relief valve.

Other schemes take the route south of the rail corridor to serve the Port Lands and eastern waterfront.  Aside from the problems of building such a line in landfill beside Lake Ontario, the route would not provide the fine-grained transit access possible with a surface LRT, and would vastly overservice an area whose expected demand is lower than the existing Sheppard subway.  Connection to Union Station from the south would also be a big challenge.

From time to time, I am asked “what would you do”, but to start that discussion, a few first principles:

  • A”DRL” should not exist solely to relieve the Yonge line’s peak traffic problem, but should provide new links within the transit network giving rapid transit to areas of the city that do not have it today.  Indeed, the regional function within the network may well be as important as the “relief” function at Bloor-Yonge.
  • Any proposed route through downtown must respect the actual built form of the streets and buildings.  Diagonal routes through built-up areas should be avoided as they are difficult if not impossible to build.
  • Stations must be located where it is physically possible to build them.  Some routes use rail corridors without considering how either a surface or underground station might fit or be built.
  • A “DRL” is not the complete solution to capacity problems on the subway.  These problems originate north of Steeles Avenue, and a major role in trimming peak demand falls to GO Transit which has several north-south routes that could drain traffic otherwise headed for the Yonge line.

The proposed route on DRL Now (click on “Interactive Map” under the “Station Information” pulldown) includes four phases:

  • Don Mills and Eglinton to City Place
  • City Place to Dundas West
  • Don Mills from Eglinton to Sheppard
  • Dundas West to Pearson Airport

I have concerns with a few details of this plan, but the basics are good.  Another view of the route is available via Google Maps.  This has the advantage of showing the detailed alignment rather than a “route map” graphic.

Continue reading