Metrolinx Continues Its Pursuit of Hydrogen Trains

Metrolinx has released a long study about the feasibility of using electricity generated from hydrogen fuel cells as an alternative to conventional railway electrification with overhead wires. The “Hydrail” project page contains links to both a quicky “fact sheet” and to a 353-page report. The report itself contains a 13-page Executive Summary giving a high level view of the proposals and recommendations without much of the technical detail.

It is impractical here for me to review the entire document, and indeed this is not really needed because a great deal of the content is a tutorial on hydrogen technology. The report is clearly written by people with more of a background in hydrogen technology and marketing than in railway planning and operations.

Fascinating though this is, the report does not address the most crucial issue of all – what are the implementation scenarios for hydrogen propulsion depending both on technical maturity and on policy decisions still to be made about the evolution of the GO Regional Express Rail (RER) system.

A great deal of confusion lies in the process Metrolinx is following to provision RER. Their intent is to farm the entire thing out to a private consortium:

Design-Build-Finance-Operate-Maintain (DBFOM) Procurement Process

Metrolinx is intending to engage a contractor to upgrade the GO network using a Design-Build-Finance-Operate-Maintain (DBFOM) model. As part of the tender process, bidders will be able to propose both hydrail and overhead wire technology to electrify the GO network. The benefit of this DBFOM approach is it allows one single party to manage all the interrelated decisions necessary and oversee each phase of the process from design to maintenance. This ensures optimal performance is achieved for the entire system, which can create efficiencies. [Website]

However, as the industry now stands, the information needed to allow an informed assessment of technical maturity, feasibility and risk for hydrogen trains at the scale of a GO/RER implementation does not exist. There is a lot of speculation, but it is based on much, much smaller and simpler implementations of various aspects of the technology.

The intent of the proposed study is to acquire as much information and experience as possible so that bidders can bid intelligently. The real challenge will be for this to happen before the Request for Proposals is issued at the end of 2018.

There is a subtle change in the text above to statements by Metrolinx CEO Phil Verster in 2017 when he said that it would be up to bidders to decide which technology they would choose to offer. Instead, the description above states that bidders can propose either technology and it would be up to Metrolinx and the Government of Ontario to decide which version to implement. It is quite likely that for the riskier new technology, bidders will be less willing to accept broad technical risk, and they will charge a premium for this. Whether the government of the day will see any extra costs as worth the investment remains to be seen.

Indeed, although the report states that the Cost:Benefit ratios for conventional and hydrogen options are similar, there is no mention of the risk premium a bidder might place on one option over the other. Moreover, the actual calculation of the ratio is not explained, nor are the total costs given. This raises the question of whether a higher cost is offset by a higher assumed benefit so that the ratios come out similarly, even if the magnitudes of investment differ.

At a recent Board of Trade appearance, Verster was asked about electrification, and replied with praise for Ontario’s “hydrogen economy”. It is quite clear that he drank the Kool-Aid and the government’s usual fascination with technology is getting in the way of his proper role as CEO. Immediately afterward, he reverted to the position that it is up to the would-be builders/operators of the RER network to propose technologies and the risk they are willing to assume.

Later the same day, when asked at a Metrolinx Town Hall about the possibility that hydrogen efforts would delay electrification, Verster replied with the standard response that the vendors will decide. However, the timelines for investigation of hydrogen and the contract award date suggest that a lot of work will be jammed into a very short period, and that Metrolinx’ own technical investigations will overlap the bid process.

A fundamental problem with Metrolinx “benefit cases analysis” (also misleadingly termed “business case analysis”) lies in the calculation of presumed benefits which are built up from a variety of factors. These include not just direct spending, but also the imputed value of effects such as reduced travel times, reduction of congestion and the value of environmental improvements. This side of the analysis is not present in the report, and so it is difficult to ascertain the “benefits” against which each scheme is measured. As for costs, so many elements of the hydrogen train proposal are little more than assumptions about the scalability of existing technology, it is hard to believe that the cost estimate is much beyond the back-of-an-envelope stage.

The capital and operating cost estimates presume a level of certainty about the hydrogen option which simply cannot exist at this point. Indeed, a major purpose of the planned work is to provide the technical basis on which a bidder might construct a proposal. Some capital costs included for conventional electrification are not included in the hydrogen scenario, and there is a wide variation in the range of projected operating costs.

With a planned launch of RER by 2025, the timelines are quite tight because major decisions on the infrastucture needed for either alternative must be made soon so that RER is “ready to roll” when planned.

Notable by their absence are key pieces of information:

  • What is the relationship between the timelines of the proposed hydrogen investigations and prototyping, and the timespan of the DBFOM procurement through all of its phases from initial tender up to revenue service? Can the research phase be completed in time to inform bids from potential builders/operators of the GO/RER network?
  • If the DBFOM bidders depend on investigative work done by Metrolinx or others on its behalf, what liability will Metrolinx have for non-performance if their work turns out to be incomplete or faulty, and therefore prevents the successful execution of the contract?
  • What is or will be the position of the railways, CN and CP, to the presence of hydrogen trains on their systems? Their dislike of electrical distribution and overhead structure in their territory is cited as a benefit of the hydrogen alternative, but one must ask how the railways will view the risks of a new propulsion technology co-existing with their operations.

This brings us to a fundamental question about RER and electrification, regardless of the technology. At the risk of being accused of environmental insensitivity, it must be said that electrification is not a prerequisite for RER implementation at the service levels now planned. Indeed, electrification makes the system design more complex especially where GO services operate over other railways’ territory. The tradeoffs are between many issues including the increased intrusion of more frequent GO service in corridors now hemmed in by residential development rather than by industry. This brings noise and pollution from frequent service with diesel locomotives. Even electric trains are not silent.

Reading between the lines, one might well think that full electrification is now contemplated as something for the future, in the mid 2040s, not in the 2020s. This is fundamentally tied up with questions of implementation and roll out, none of which is addressed in the report because it assumes this is a matter for future study.

Although much discussion reads as if RER will appear overnight in January 2025, Metrolinx plans to begin building up service levels from current to the RER proposal on an incremental basis as infrastructure improvements are completed. This means that a substantial portion of “RER” based on existing technology would exist before electrification, by whatever scheme, actually is “turned on”.

An important part of any implementation plan will include the mechanism by which a DBFOM bidder will take over existing assets, and this necessarily must be spelled out as part of the tender process. This will lead to two huge transitions occurring in parallel: the move from direct Metrolinx capital and operating responsibility for the GO system to a separate provider, and the technology transition from diesel to electric on some or all of the network. Whether Metrolinx has the capability to manage something on this scale, or will simply dump the responsibility in the provider’s lap and hope for the best, remains to be seen.

There is also the fantasy that the “risk” will be transferred from the government to the provider, but that risk comes at a price, and what is effectively “risk insurance” usually has a cap. Examples of capped liabilities, or even of providers walking away from their responsibilities, are not hard to find. Of course there could be problems with conventional electrification too, but they are less likely with a mature technology.

In this article, I will review the recommendations so that readers who want the “short version” can get my opinion without reading all the way to the end. In a separate future article, I will turn to specifics in the detailed report.

Continue reading

New SmartTrack/GO Station Designs

In two recent articles, I wrote about new stations that are proposed on some of the GO corridors, and their recently updated evaluations and designs:

The reports did not include any illustrations of the proposed designs, but these are starting to appear through the SmartTrack station consultation meetings. As they become available, I will post excerpts in this article.

The March 1 meeting dealt with four stations on the west side of the old City of Toronto. The presentation materials are not yet online, but I have included excerpts from them here.

Among the issues discussed in an earlier round of meetings were:

  • Noise during the construction period, and later from trains including the bells which sound as they enter and leave stations.
  • The service plan – what will be the frequency of service through and at each station?
  • Fare integration – what will the fare be for a combined TTC/GO trip?

A Metrolinx representative was somewhat evasive on the issue of noise on two counts. First, there is the question of how long it will be before the majority of service will be electrified. If one believes the original electrification plan (cited by the Metrolinx rep), some trains will always be diesel on some lines because they will run into territory owned by other railways where electrification will not occur. Conversely, if one believes the optimistic claims of the hydrogen train study, all GO trains will convert to hydrogen-electric operation, although on exactly what timetable is unclear.

The noise of the bells raises two concerns. First is the question of whether there can be an exemption so that neighbours are not constantly annoyed by the bells of passing trains. The other is the methodology by which an “environmental assessment” treats transient noises like this. Past EAs have dismissed transient noises because they average out with lots of quiet time between trains, but this does not address the problem of occasional noises such as roaring engines or ringing bells. Moreover, with the planned increases in service levels, these noises will be present more frequently.

SmartTrack was described broadly in the following slide:

A pressing issue for most stations is the recently revised service plan that Metrolinx announced in its updated stations report.

Express (non-stop) and tiered service patterns typically have trains serving outer stations. They typically run non-stop past inner stations which are served for by other trains. Such tiered service patterns impact business case assessment in the following key ways:

  • Reduces the number of upstream riders that need to travel through the station. Upstream users that are travelling through may now choose to use a faster express train to reach their destination. This reduces upstream delays and the number of riders that switch to other modes. This will have a positive impact on station performance.
  • Reduced train frequency at stations without express service (i.e. trains that previously stopped at the station can now skip some stations). Riders may also divert to stations with express services resulting in a negative impact on station performance.

As the GO RER service plan is still evolving, a conceptual service plan has been developed for modelling purposes only, which considers the following express or tiered inner/outer service concepts on the Lakeshore West, Barrie and Stouffville corridors.

  • Lakeshore West corridor: Alternating trains with bi-directional 15 minutes service on the corridor with stops at Mimico and Park Lawn stations. Mimico and Park Lawn stations would therefore receive 30 minutes service inbound and outbound all day.
  • Barrie corridor: Outer service stopping at all stations between Allandale Waterfront and Aurora; trains will also stop at Downsview Park and Spadina stations, otherwise, express to Union Station. Inner services will serve all stations between Union Station and Aurora.
  • Stouffville corridor: All-stop peak direction outer service between Lincolnville and Unionville stations; trains will also stop at Kennedy and East Harbour stations, otherwise, express to Union Station. “Inner” services will stop at all stations between Unionville and Union Station.

This does not match the service plan adopted for RER in June 2016 where all trains would serve all stations, although that appears to be the plan staff at the March 1 meeting were working from.

The claim of “all-day two-way service, with more frequent trains during peak periods and every 15 minutes during off-peak periods” can be read to mean quarter-hourly service all day with even better peak service, or it can be read as “better service than you have today” during peak periods, but not necessarily every 15 minutes, let alone 10 minutes or below. As things now stand, the difference between Metrolinx’ updated service plan and the claims of SmartTrack service levels border on misrepresentation.

Continue reading

Metrolinx New Stations Report: The Details

In a previous post, I reviewed the updated evaluation of proposed new stations on the GO/RER/SmartTrack network. In brief, the situation for some locations is not as dire as in mid-2016 because Metrolinx has changed some of the operating rules and plans for it services. Whether the newly proposed services can actually be operated remains to be seen and is, as usual, a subject for further study.

This article is a station-by-station review of the primary issues at each proposed new stop. The stations are ordered here by corridor for ease of reference by geographical grouping, whereas in the Metrolinx report they are in alphabetical sequence.

(There will doubtless be a small industry in pushing for reviews of stops that are not in the Metrolinx list. That is not the purpose of this piece which reviews the updated evaluations as presented by Metrolinx.)

My apologies in advance for a long, text-only read. There were no illustrations beyond general maps in the Metrolinx report, and so there are none here either.

There is a series of planned public meetings about SmartTrack stations, and it is possible that these will include more details of current designs. If so, I will update this article to include them.

THURSDAY MARCH 1, 2018
Lithuanian House
1573 Bloor Street West
6:30 pm – 8:30 pm
Presentation begins at 7:00 pm

TUESDAY MARCH 6, 2018
Scarborough Civic Centre,
Council Chamber
150 Borough Drive
6:30 pm – 8:30 pm
Presentation begins at 7:00 pm

WEDNESDAY MARCH 21, 2018
Queen Alexandra Middle School,
Small Gym
181 Broadview Avenue
6:15 pm – 9:00 pm
Presentation begins at 7:30 pm

A total of 17 stations are reviewed in this study. Of these, 5 were not recommended in the initial report in 2016. Of these, only Park Lawn has been resurrected to go forward for reasons discussed later. One of the 12 in the approved list, Mulock, has negative benefits and might fall off of the table if Metrolinx cannot find a way to make a better case for it.

General issues that are either not addressed by or not detailed in the report include:

  • There are no detailed design drawings of the stations, only very general location maps.
  • Details of the service plan(s) used to model demand. There are some specific references with respect to express and local operations at certain stations, but not for existing stations or the network as a whole. This affects demand modelling.
  • Modelled demand at all stations, not just the new ones, and of the cumulative on-train loads. This is important to ascertain whether the planned service can actually support the projected demand.
  • Details of the boardings and alightings at stations. Combined values are shown, and the descriptive text indicates which is the predominant flow, but not the proportions.
  • Differentiation of new riders attracted to GO service by the station as opposed to existing riders diverted from nearby stations (i.e. net new ridership).
  • The degree to which, if at all, performance improvements through electrification (whether by conventional power of hydrogen fuel cells) will offset the time penalty associated with new stations.
  • Additional infrastructure required for express and local operations to co-exist on each corridor. Some of this is mentioned, but not in a comprehensive way.
  • Details of train operations including use of express and local tracks, and track assignment on corridors with multiple services. Any requirement for individual services to cross each other affects capacity along the route and at Union Station.
  • Details of the implications for freight operations both with respect to existing spur lines and to clearance issues with new structures.
  • The anticipated volume and operational interference of freight operations on GO’s passenger service.

For the original station designs which, in some cases, have now been modified, please refer to the Metrolinx mid-2016 reports. Go to the Metrolinx New Stations page, scroll down to and open the Initial Business Cases bullet.

A consistent problem through all of these studies is the reliance on the imputed value of time savings to travellers. This is not “real money” in the sense that it can be recouped to pay for the transit investment, but a social benefit that transit confers. There is nothing wrong with this outlook, but readers are cautioned that when Metrolinx speaks of benefits exceeding costs, this does not mean that profits will roll in the doors at stations. Moreover, the model is very sensitive to the imputed effect of delays caused by new stations.

In their attempt to address the negative effect of adding stations to the corridors on riders making long trips, Metrolinx has changed their service design to include express and local trains. This fixes one problem, but adds others in terms of the resulting frequency at local stations, and the capacity of local trains to handle the projected demand.

All demand numbers cited here are for the 2031 projection which assumes the current fare structure with GO/TTC co-fares, but no “regional integration” beyond what is already in place:

The PDBC analysis assumes:

  • introduction of Presto on all TTC services across the City of Toronto;
  • the current discounted double fare agreement between the City of Toronto and Metrolinx – a $1.50 discount is applied when an adult Presto user’s journey includes both a TTC and GO segment;
  • the planned TTC 2-hour transfer to make the TTC more aligned with 905 transfer policy, planned for implementation in August 2018; and
  • progress by all transit agencies on addressing removal of fare barriers and improved service integration.

As a starting point, the base fare structure as of December 2017 is assumed for the PDBC analysis. [p 12]

Mayor Tory has trumpeted this report as showing a strong support for his SmartTrack project with 60-year benefits of $4.59 billion greatly exceeding the capital costs of $1.195 billion (2022$). However almost all of the benefit comes from two stations – East Harbour and King-Liberty.

East Harbour provides 55% of the demand and 84% of the imputed benefits from the six SmartTrack stations. King-Liberty adds a further 16% of the demand and 9% of the benefits. These stations stand on their own as worthwhile additions completely separate from SmartTrack.

Continue reading

Metrolinx Updates News Stations Business Cases

In anticipation of its board meeting on March 8, 2018, Metrolinx has released a report updating its analyses of various proposed new GO stations, some of which are intended to serve John Tory’s SmartTrack scheme.

The whole question of new stations has been under a cloud recently thanks to reporting by the Star’s Ben Spurr who has documented political interference in the evaluation process. Metrolinx is very sensitive to this and tries to dodge questions both by characterizing such reporting as “conspiracy theories” and by saying that they want to go forward rather then looking back on how we reached the current situation. It’s water under the bridge, dirt swept under the carpet, pay-no-attention-to-that-man-behind-the-curtain territory. And if you don’t buy that, well, politicians make decisions all the time, and the staff’s job is only to provide advice. That the advice might be tailored to fit a desired conclusion is simply beyond discussion.

In a set of analyses conducted in mid-2016, Metrolinx reviewed several stations and found some of them wanting in the contribution they might make to the network. Notable among these was Kirby Station on the Barrie line which was not originally recommended. Magically, the numbers changed after Ministerial intervention. We have no way of knowing how many other Metrolinx staff recommendations have been perverted in this manner, but the problem will not go away. Already the newly minted Minister is musing about stations in her political territory, the Milton corridor.

The new report seeks to justify continued spending on many stations, but with the focus on individual station analyses, important details are buried or simply not included in the published information. We are supposed to read the summary and look no further.

The status of stations still actively under review is presented in one chart.

In a marvellous piece of newspeak, Metrolinx refers to stations where “Benefits are Positive but Less Than Costs”. In other words, the costs outweigh the benefits, but this is presented as if it were a positive state of affairs.

One would generally expect that the presence of new stations would be positive, and the only case where this does not apply depends on the presumed effect of adding a stop on the attractiveness of service to existing and potential riders. A large proportion of the “benefit” in Metrolinx analyses arises from the imputed value of reduced travel times and diversion of trips from auto to transit. The model is very sensitive to changes in travel time, and so the addition of stops tends to hurt ridership whose trips are lengthened by adding stations.

Back in June 2016, Metrolinx evaluated four models for future service on its network including the new stations to be added by SmartTrack. The service plan at the time was quite clearly to provide a 15 minute or better service on most of the network except some outer sections which would receive a lower level of service, possibly peak only. With respect to service inside the City of Toronto, the report observed:

All seven GO corridors run through the City of Toronto, stopping at 19 stations, and meeting at Union Station. … the GO corridors largely run through Etobicoke and Scarborough, providing downtown access opportunities to neighbourhoods located at a distance from the subway. By bringing fifteen minute or better two-way service to five of the GO corridors, … GO RER will bring more flexible travel options for residents and jobs within the City and to the broader region. [pp 18-19]

This information is echoed on the “How Will You Benefit” pages such as the Stouffville Corridor page where it is quite clear the intent is for all trains to stop at all stations.

This echoes the conclusion of the June 2016 report in which four possible service plans were considered:

• Option A: Increased frequencies, 5 new stations
• Option B: Express and local service, 8 new stations
• Option C: Committed GO RER frequencies, 7-8 new stations
• Option D: Committed GO RER frequencies, 4-5 new stations

The first two options, notably the one including express service, were dropped because of the infrastructure needed to provide for SmartTrack and GO/RER co-existence.

GO RER is expected to utilize the available and planned track and corridor capacity. In this light, integrated GO RER-SmartTrack options were screened to determine the extent of additional infrastructure that they would require over and above that which is required for GO RER. Through this analysis, it was determined that Options A and B would each require extensive additional track infrastructure, resulting in the need for corridor widening, extensive property acquisition, consequent community impacts, and other deliverability challenges. In light of these findings, Options A and B were screened out and detailed analysis focused on Options C and D. [p 19]

Option D makes the cut because with fewer new stations, it creates less delay for riders on the outer ends of the corridors and hence less imputed value from lost time and potential lost ridership.

In summary, based on business case analysis, Option D is the stronger performing option for integration of SmartTrack with GO RER, striking the optimal balance between advancing local access within Toronto while preserving service quality for medium and longer distance passengers. Consistent with the findings of the new stations analysis, this report recommends six new stations for GO RER-SmartTrack integration: St. Clair West, Liberty Village, Don Yard/Unilever, Gerrard, Lawrence East, and Finch with an estimated cost of $0.7 to 1.1 B ($2014, costs do not include escalation, financing costs, lifecycle and operating and maintenance). [p 20]

Times have changed at Metrolinx, and they now regard a mix of express and local services as best service design.

An all-stop service (as in the IBC) means that the upstream riders are delayed at every new station, which is a negative economic benefit. This negative benefit is compared to the positive economic benefit from the new riders joining at the station and the time savings they will make from using GO. It is much more optimal to have an express service (rather than all-stop) that selectively stops at those stations and at those intervals when the new riders joining would be substantial enough to justify the stop. This is best practice in service planning in all jurisdictions. [p 2 Staff Report]

CEO Phil Verster was quite adamant on this point during a media briefing and was quite dismissive of the idea of stopping trains for comparatively few passengers. There is only one small problem – it is precisely this type of stopping pattern and service level at every stop that was used to “sell” SmartTrack as part of GO/RER. No amount of managerial swagger can undo the very real position taken by Metrolinx and by municipal supporters of SmartTrack less than two years ago. A train every 20 minutes is not what riders in Scarborough and elsewhere along the ST corridor expected in place of their existing transit service, especially when SmartTrack is touted as a substitute for stations on the Scarborough Subway Extension.

Stops that would be affected by the new service design include: Bloor-Lansdowne, Kirby, Park Lawn, Mimico, Finch-Kennedy, Lawrence-Kennedy, Gerrard-Carlaw, St. Clair-Old Weston. This list may not include all affected locations as only those in or directly related to the new station analysis are mentioned in the report.

(As an aside, one cannot help wondering what the Toronto subway network would look like if subjected to the Metrolinx outlook. Many stations would close for much of the day, if not permanently, because there simply is no justification to keep them open for very low demand.)

By reversing course and reinstating express trains in the service plan, Metrolinx avoids the travel time penalty of adding new stations, but with the offsetting effect that these stations get much less service. The problem is so acute for the SmartTrack corridor that Metrolinx is now trying to figure out how to squeeze more trains onto the line, and even talks of a separate “relief” function for a U-shaped Unionville to Bramalea service. The infrastructure to support this does not exist, and the scheme is a far cry from the idea that “SmartTrack” could simply be implemented using existing infrastructure. A further problem lies in the Union Station Rail Corridor (USRC) where track, signalling and platform configurations combine to dictate how many trains/hour can operate there without substantial upgrades.

In a media scrum at the Board of Trade, CEO Verster stressed that service was the most important factor, the one with the biggest effect on ridership. GO Transit and Metrolinx have planned within the limitations of their corridors including the USRC, but there may now be a recognition that what is planned simply is inadequate to address region-wide needs.

Two other factors were touted as improvements to GO operations and travel speeds:

By the same logic of minimizing the time of every stop at every station, implementing level boarding (as opposed to low platforms and a delay from stepping up/down and positioning the train) reduces the negative impact of the station on the economic benefits of the upstream riders.

The business cases now assume that all fare barriers have been removed with an integrated fare system in place. The economic benefits of fare integration is estimated to exceed the cost by a factor of 12 (ie a BCR or Benefit Cost Ratio of 12).

There is no question that level boarding will speed things up at GO stations, but this is a matter of reducing the time spent at all stations, including any added ones. Not mentioned at all were the travel time savings possible with electrification. In earlier studies, these were counted as an offset to the extra delay of added stations.

The question of fare barriers is rather odd because it is unclear whether the barrier is physical (a turnstile or limited access streams past Presto readers) or psychological (a double fare). The technical report notes:

As a starting point, the base fare structure as of December 2017 is assumed for the PDBC analysis. A future looking full fare integration scenario was also tested to examine impacts on ridership and the overall economic case for each station where no fare barriers exist. [p 10]

Elimination of physical barriers or congestion points at platform access will only speed travel for riders who show up at the last minute and could face a missed trip if their path from parking space or connecting bus were longer than a “crow fly” distance, or delayed by queueing at fare machines. Otherwise, fare validation occurs during the wait time before a train arrives. From a demand modelling perspective, there is also a “barrier” inherent in extra fares for each stage of a journey. Metrolinx has long talked of the need for “regional fare integration” without getting into the specifics especially as they might affect riders of local transit systems. If the analysis mentioned above shows a benefit cost ratio of 12, or extremely high, this must be based on some specific mix of tariff and subsidy changes.

A major failing of the New Stations report is the omission of much detail such as the derivation of claimed demand at the various stations, notably a split of new and existing riders, a breakdown of boarding and alighting passengers, the effect on conditions at nearby stations, and the specifics of the modelled service plan. Some of this information was included in the initial round of evaluations in 2016, but only summary values are published in 2018.

The chart above shows numbers for AM Peak and All Day boardings and alightings, but there are large differences in the behaviour which are mentioned in the individual station analyses. During the AM peak:

  • Some stations are primarily “boarding” locations either from local transit or from parking. Indeed, it might be argued that in a few cases, the primary function of a new station is to host a new parking garage that might not fit at an existing site.
  • Some stations are primarily “alighting” locations in that they are destinations, not origins, of trips. This is strikingly true for the Liberty Village and East Harbour stations who primary function is to bring people to work in the immediate vicinity, not as an origin point for “in town” travel.
  • Demand at stations could be new GO riders, or it could be from trips that are more conveniently served from the new station. For example, a new station might shorten the access trip to GO by car or transit, and this translates to an imputed benefit from time saving.

For the SmartTrack stations, the 60-year benefits are shown as outweighing the capital costs by a factor of almost 4:1. However, almost all of those benefits are the notional value of time saving, and to a lesser extent, reduced auto travel. Operating costs, including that of any additional local transit service or of fare integration subsidies is not included in the analysis.

Of the six SmartTrack stations, East Harbour, the site of a proposed massive commercial development east of the Don River, is by far the major contributor to the positive comparison for SmartTrack. It accounts for 84% of the travel time savings and 55% of the passenger activity at the six stations. The analysis did not include the presence of the Relief Line, and the service plan assumes that Lake Shore East trains do not stop at East Harbour.

Because the individual station cost estimates are not broken out, it is impossible to know the performance of the StartTrack stations, but we know from the summary that only East Harbour and Liberty Village have benefits which outweigh their costs.

This is an almost meaningless analysis.

Metrolinx claims that it will produce an updated analysis and recommendations by the end of 2018 in time for an RFP for the implementation and operation of GO RER and SmartTrack. At this point, a huge amount of detail is missing, especially the degree to which the original GO service plan from 2016, on which a great deal of infrastructure work now in progress is based, must now be revised. It is quite clear that Metrolinx is struggling to come up with credible plans, and they are quite defensive about the changes they are now making.

All is not sweetness and light, and the unseen hand of political interference to justify many of these stations is clearly at work.

In a future article, I will turn to the individual stations and discuss the issues affecting them.

Toronto’s Transit Capacity Crisis

In recent days, Mayor Tory has announced, twice, a ten point program to address crowding on the TTC. The effectiveness of this program is limited by years of bad political decisions, and the hole Toronto has dug itself into is not one from which it will quickly escape.

This article is a compendium of information about the three major portions of the “conventional” (non-Wheel-Trans) system: subway, bus and streetcar. Some of this material has appeared in other articles, but the intent here is to pull current information for the entire system together.

Amendment February 15, 2018 at 5:30 pm: This article has been modified in respect to SmartTrack costs to reflect the fact that over half of the cost shown as “SmartTrack” in the City Manager’s budget presentation is actually due to the Eglinton West LRT extension which replaced the proposed ST service to the commercial district south of the airport. A report on SmartTrack station costs will come to City Council in April 2018. Eglinton LRT costs will take a bit longer because Council has asked staff to look at other options for this route, notably undergrounding some or all of it.

Continue reading

Metrolinx Board Meeting and Town Hall: December 2017

Metrolinx held a Board meeting on December 7, followed on December 12 by a Town Hall.

Public questions to the Town Hall were submitted in advance and in real time during the Town Hall online, and in person by attendees. Metrolinx plans to put answers to all questions, including those that could not be handled during the Town Hall itself online in coming weeks. That record is now available at MetrolinxEngage.

My interest in both events was as much to see how the new CEO Phil Verster would handle himself especially during an open Q&A session which has not, to be kind, been part of the corporate culture at Metrolinx.

Continue reading

Metrolinx Board Meeting Followup: October 26, 2017

Updated Nov. 2, 2017 at 2:50 pm: Typos corrected, notably “DBFOM”.

The Metrolinx Board met on October 26 with an agenda that was largely discussed in private. This article is a follow-up to the preview published before the meeting.

A major item on the confidential agenda concerned “Benefits Management and Realization”. Why this was handled at such great length in private is a mystery, and I attempted without success to clarify the topic of discussion with Metrolinx.

I asked:

Is this the issue of identifying, encouraging and capturing some of the benefits of transit expansion?

In a thoroughly opaque reply, Metrolinx stated:

Benefits management is a process to help us maximize project value as Metrolinx plans, builds, operates and connects transit projects in order to provide benefits to the region. [Email of Oct. 23 from Scott Money in Metrolinx Communications]

A major problem for Metrolinx and for the Regional Plan in general is the propensity to build stations surrounded by parking lots and structures (GO) or free-standing architectural sculptures that make integration with future development quite difficult. On a smaller scale, Metrolinx will have to get used to thinking smaller, in the sense that stops on BRT and LRT lines should not be planned around massive growth but depend on medium density locally plus intersecting feeder routes.

Metrolinx has committed to publishing information about its private sessions in the future, and it will be interesting to see how much we actually learn about evolving thoughts on this issue. After all, this meeting was billed as a “strategy session”.

The New CEO Introduces Himself

Metrolinx’ new CEO, Phil Verster, made a few remarks most of which were predictable as so much at Metrolinx meetings can be.

His focus since joining the agency has been on talking to customers and front line staff, especially those who do the invisible tasks that keep the system running. He has also been consulting with Metrolinx staff and management about the importance of positioning the agency to get the most out of the investment in the RER (Regional Express Rail) program over the coming years.

Among many projects, Verster spoke of the Kipling mobility hub (recently announced with a media event by sundry politicians), a project that has been brewing for over a decade.

Fare integration was another topic Verster focused on with the recently announced GO-TTC co-fare arrangement being the first step to region-wide integration. This will affect business case analyses, travel behaviours and patterns. New travel, of course, will depend not only on fares, but also on service, a topic on which Verster was silent.

In a telling comment, Verster observed that while Metrolinx has a lot of capital improvements underway, it is important to remember “the soft stuff” of organizational improvement, transparency to the community, and becoming an organization that represents transit in an objective and positive manner.

Being “objective” is a topic that returned in other discussions as the meeting went on.

Regional Transportation Plan Update

Antoine Belaieff presented an overview of the RTP consultations to date. He reported that reception to the draft plan as been generally positive, but that there is continued impatience for system improvements. Riders want seamless fares and service, have diverse opinions on parking and station access, and are interested in seeing how the plan will be staged and implemented. At the municipal level there were few surprises because local planners have been involved in developing the draft, although there is some interest in adding projects to the plan. Stakeholders want clarity about the first/last mile problem and how the growth in travel with RER will affect station access. There is continued interest in long and short haul goods movement by truck and rail.

There have been “fairly technical” discussions about roles and responsibilities for Metrolinx vs the provincial government, especially with respect to the provincial Growth Plan, and a desire for “crisp and concrete” language.

Phil Verster observed that the plan should not be “final” but should be open to changes. It should not be an “event” but an ongoing process.

Board member Upkar Arora asked whether people have been flagging omissions in the plan, have concerns about the environment and sustainability, or are split between an urban/suburban view of the plan.

Belaieff replied that, if anything, people are having to digest a “rich” plan that has a great deal to absorb. Feedback on environment issues has been supportive because of the plan’s “call to action”. Suburban areas tend to focus on how the plan will support growth both through new stations and with expansion that is timely relative to development.

Board member Rahul Bhardwaj asked whether “we hearing from the right people” or just those who are usually engaged, and using an unfortunate phrase, referred to the “silent majority”. Belaieff replied that he was pleased to see audiences not just of his planning friends, but that there was genuine input from “everyday” people. Getting attendees to meetings is hard, and Metrolinx is counting on local networks to help with this, but both “planning intellectuals” and “real people” were present. Leslie Woo, Chief Planning Officer, noted the need to reach marginalized communities.

Woo advised that there will be a report in December on the feedback Metrolinx has received and how it will affect the next version of the document. In parallel staff are working on economic information and will propose “a way forward” with the plan and its implementation. She proposed that the plan not be considered as finite, but as a generator of more specific studies.

One statement caught my ear, namely that this is a plan for ten years, after which there will be a new plan. That is technically correct, in that there is a legal mandate to review the plan every decade (the current review is triggered by that), but the RTP is intended to look forward a quarter century and given the lead time for the most complex projects, a ten year outlook simply won’t do.

As for the comments about “real people” at meetings, this cuts two ways. On one hand, it is vital that the plan be shaped by genuine public opinion as opposed to the “usual suspects” be they those of us who always comment on anything, or politicians who warp transit plans to suit their electoral goals. On the other hand, public opinion can be skewed by biased presentations, and some of the activism so familiar in transit circles arises directly from the need to provide contrary views to the official versions. Being “engaged” should not disqualify one from providing input to a vital plan, and engagement does not necessarily translate to agreement.

The finality of a plan, or its openness to change, is always a tug of war at the planning and political levels. Plans that are open to constant change can leave us with a situation where changing priorities and limited funding guarantee that nothing actually happens. On the other hand, the lack of published details behind many parts of the plan, specifically ridership projections, land use assumptions, project costs and priorities leave us with a full network for 2041 but no sense of how we will get there, or how subsets of the plan would perform.

Hydrogen Trains

Phil Verster introduced this report as an examination of an alternative “green” way to implement non-diesel propulsion for GO saying that there will be a very important feasibility study of the technology this fall. Mark Ciavarro, VP of RER Implementation, took the Board through the presentation (linked above) together with Peter Zuk, Chief Capital Officer.

Ciavarro noted that interest in hydrogen as a fuel goes back to 2012 when it was still a relatively new technology and, at the time, not worth further pursuit. In September 2016, Alstom unveiled a pilot and the vehicle is now in testing, although in a different, much smaller form than trains GO would use. The test train reaches a maximum speed of 140 km/h, and 60 trains are on order. Chief Operating Officer Greg Percy noted that GO’s top speed now is 90m/h or 150km/h. Greg Verster stated that speeds of 180-200km/h and up lie in High Speed Rail territory.

Chair Rob Prichard noted that there is a terminology issue in that all locomotives are electric, but the question is where the energy comes from. [Diesel locos generate their power on board while “electric” locos obtain power from an overhead wire. In both cases the actual propulsion is provided by an electric motor. However, truly electric trains give the option of powering all cars, not just the locomotive, and this changes a train’s performance.]

Zuk stated that GO is electrifying its network and the question is how this would be done. They are doing a feasibility study of hydrogen and other potential technologies. In Germany, commercial uses of hydrogen goes back to 2002, but there is a question here of the scale and applicability to large commuter rail operations.

Verster observed that the application of hydrogen trains in Germany would be to rural lines where electrification infrastructure is not cost effective. The train is small, and the issue is whether the technology can be scaled up. There will be challenges and that is why Metrolinx is conducting the feasibility study. There are hydrogen fuel cell applications in LRT and buses, but this is the first train. Surplus electricity can be used to create hydrogen, and that first stage is always expensive. This is a key part of the study.

Board member Carl Zehr asked whether the study will look at the transition to and integration of hydrogen technology. Verster replied only the technical feasibility is  being studied in the immediate future. His main objective is to deliver RER at the best cost and time. With respect to using the technology on track that GO does not own [portions of some corridors are owned by CN and CP which operate freight traffic over them], hydrogen trains could avoid the need for overhead contact systems (OCS) on non-GO trackage but there is no regulatory framework for this yet in Canada.

Zuk noted that each component of hydrogen fuel cell technology has been around for years. What is new is their integration into a rail system. Metrolinx needs to determine if and how fuel delivery will work, and how the technology would fit into EMU (electric multiple unit) trains.

There will be a symposium to assess the state of the technology on November 16, 2017 (see p. 13 in the presentation deck) and this will be open to outside parties. Whether this means media and the general public is as yet uncertain.

Rob Prichard wondered whether GO Transit would be the last system to build an overhead based system. The obvious rejoinder is that the whole world is building these systems. Verster replied that Metrolinx should not engage in delivering a program that is dependent on research and development.

The study will likely be done by the end of 2017 with a report for the February 2018 Board meeting.

During the press scrum after the meeting, the Star’s Ben Spurr asked Chair Prichard and CEO Phil Verster what made them think hydrogen technology is even possible. Verster replied unambiguously that there are significant community ridership benefits in RER, and Metrolinx will not jeopardize this based on a technology that is not ready to market. He observed that the study will affect RER procurement – under a DBFOM scheme (where a bidder does everything from designing to operating and maintaining the system) there is a question of what technologies a provide might bid.

Spurr also asked about Metrolinx attempting to position Ontario as a global leader, and whether this is a transit agency’s role. Verster replied that Metrolinx should “scan the horizon” to know what is available.

The DBFOM reference raises the question of whether Metrolinx is planning to outsource its RER operations completely on a turnkey basis. I attempted to obtain clarification of this from Metrolinx later on (the scrum ran out of time), but replies yielded no information at all. As for hydrogen itself, it is clear that there is a tension between the basic action of getting an update on the technology, and a political stance that would provide Ontario (and its politicians) with yet another chance to show off advanced technology. Our experience in that regard is less than stellar.

GO/TTC Discounted Double Fare

This report is substantially the same as the one presented at the recent TTC Board meeting. It deals with the proposed agreement between Metrolinx and the City of Toronto/TTC to implement the first stage in a planned four-stage evolution of regional fares:

a) Discounts on double fares (GO-TTC)
b) Discounts on double fares (905-TTC)
c) Adjustments to GO’s fare structure
d) Fare Policy Harmonization

Leslie Woo expects to report to the December Board meeting on all of these.

During the scrum, Rob Prichard observed that although the GO-TTC co-fare is a three year agreement, he feels that unwinding it is unlikely because it is so clearly the right policy direction. If anything, it will be rolled into a more extensive set of integrated fares.

We can only hope that Metrolinx has moved beyond regarding the matter of time-based fares (the two-hour transfer) as a matter of local policy rather than as a potential key part of regional integration for non-GO services. All systems outside of Toronto now use this scheme, and York Region recently eliminated its zone fares. Only the TTC remains as an exception, and there will be a proposal in the coming Ridership Growth Strategy that Toronto move to the two-hour transfer.

This could leave Metrolinx in the position of trying to foist fare by distance, their long-favoured scheme, on local systems that have already standardized on a flat, time-based fare.

Governance

The agenda included a private session item on governance which will be public at the December meeting. This may deal with the issue of which items and reports are dealt with in private session, and which are made public, especially before rather than after they are massaged to fit political reaction.

Rob Prichard, after much prodding in the media scrum, allowed that the controversy over Kirby and Lawrence East Stations was a “catalyst for discussion”. Phil Verster took a shot at the issue by saying that there are four phases to the benefits case process and the station review is at stage 1. There will be more information later in the cycle. Ben Spurr challenged him on the sequence of a Ministerial announcement that appears to seal the decision. Verster replied that communities should get a sense of direction, but that Metrolinx has a long way to go in the maturity of how they work with benefits cases. These are not an absolute science but have strategic overlays leading to a policy decision.

The Globe’s Oliver Moore asked if the Ministerial intervention was appropriate. Verster replied that he cannot comment, but wants to look forward. Metrolinx will give informed advice and options, but it is up to the politicians to make decisions.

These statements dip and dive around the issue, and the comments about the uncertain nature of benefits cases beg the question of the value of the degree to which Metrolinx has relied on these in the past as definitive studies. Either they can hide behind studies as the work of “experts”, or they can recognize them as works in progress that might not be “mature”.

Metrolinx Mulls Strategy (Largely in Private)

Correction: The original version of this article claimed that the Board was meeting in private today to discuss matters that will be on the agenda tomorrow. The Tweet from Metrolinx about today’s is a Stakeholder meeting, not a Board meeting. Thanks to Ben Spurr at the Star for catching this.

The Metrolinx Board will gather on Thursday, October 26 for what is described in the media release as its “annual strategy meeting”. Much of the agenda will be discussed in camera, and if the agency has a strategy, we won’t learn much about how the board members feel on the subject.

The meeting announcement tells us that the Board will discuss “transit expansion progress”. Maybe, but that hardly sounds like “strategy” with the Draft Regional Transit Plan already out to the public for comment. The draft ignores many issues, and the plan does not improve the regional modal split for transit beyond current levels. Moreover, the transit growth is disproportionately focused on Toronto’s core, but transit loses ground (not that it has much to start with) the further from the centre one gets.

Hard discussions about how road space will be used – transit, multi-occupancy vehicles, freight, cycling, pedestrians – need to happen at the regional level, not just on a few “transit streets” downtown. This is a debate both for the 905 and for Toronto’s suburbs where the combination of built form and transit density work against a strong transit market share.

In any event, the public agenda item is a small update on consultation, not a review of any significant policy issues, and it is scheduled for only 15 minutes.

About a month ago, I published a review of the draft plan, and plan to return to the subject in another article soon. My intent had been to make a “deep dive” into the draft, beyond its introductory chapter, but I quickly found how little of substance is actually there.

Other items on the Metrolinx agenda include:

In Private

Benefits Management and Realization (90 minutes)

The title might suggest a discussion of the knotty problem of actually capturing some of the value created by transit investments. I asked Metrolinx to explain just what this was about, and they replied:

Benefits management is a process to help us maximize project value as Metrolinx plans, builds, operates and connects transit projects in order to provide benefits to the region. [Email from Scott Money at Metrolinx, Oct. 23, 2017]

Why, exactly, this should be a matter of confidential discussion is a mystery. This is quite clearly an important part of transit network building, but it has been sidelined when political considerations take precedence over planning issues and “mobility hubs” are little more than enormous parking lots.

Board Governance (15 minutes)

Given recent discussions about political interference in transit decision-making, I cannot help wondering if the Board is aware of its irrelevance, real or perceived. The rare public meetings, the superficial level of debate, and the blizzard of press releases and photo ops from the Minister of Transportation’s office don’t help the situation one bit.

Much of the real debate appears to take place in committee meetings which are so private they are not even advertised and there are is no public record of them.

Metrolinx’ new CEO, Phil Verster, has spoken of the need for “transparency” at Metrolinx, but the problem begins above his level at the Board itself.

Regional Express Rail (60 minutes)

This includes two items: the procurement of a new network operator, and an update on the capital program. Metrolinx has disqualified the current operator, Bombardier, from bidding, a strange move that might raise more eyebrows if Bombardier were not so late on its LRV deliveries. As for the capital programs generally, the only part of this that belongs in a private session would be information on contract issues.

A preliminary discussion of risk issues (30 minutes)

Risk management is an important topic for any Board, and some aspects rightly belong in a private session. That this is “preliminary” and is included in a “strategy” meeting begs the question of what new risks the organization faces, including political fallout from the coming election.

2018/19 Budget Submission (30 minutes)

Unlike budgets at the City of Toronto and TTC, provincial budgets are dark secrets until the moment they are unveiled in the legislature. This puts the public debate of “strategy” for Metrolinx in a difficult position because any spending proposals could embarrass the government by showing what could be if funding were available, or if projects face financial difficulties that could upset spending or delivery plans. The budget could also include new revenue generating strategies including mandated contributions from so-called “municipal partners” or changes to fare schemes.

These are important issues, but we will never hear about them from Metrolinx because of the way Provincial budgets work.

In Public

I will update these sections if there is anything substantive presented at the meeting.

Regional Transportation Plan Update (15 minutes)

This is superficial review of public engagement and has nothing to do with actual content.

Hydrogen Fuel Technology Analysis/Evaluation (30 minutes)

The Minister of Transportation is hot to trot on hydrogen as an alternative fuel, and so of course, Metrolinx must be as well. This report is a review of the current status of the Hydrail project in Germany and an overview of the study work needed to assess its implications for Ontario and GO/RER.

GO/TTC Fare Discount (15 minutes)

This is simply a repeat of the information in the report about the planned co-fare with TTC that has already been dealt with at that agency and is now working its way to City Council.

TTC Board Meeting October 16, 2017 (Updated)

The TTC Board will meet on October 16. Among items of interest on the agenda are:

Continue reading

SmartTrack Update: More Questions Than Answers (October 13 Update)

For the coming three evenings, October 10-12, the City of Toronto, Metrolinx and the TTC will host open houses to present and discuss plans for six new SmartTrack and two new GO Transit stations. Although material for all stations will be part of each event, stations “local” to each site will receive more emphasis than others.

Each meeting will run from 6:30 to 8:30 p.m., with a presentation at 7 p.m.

  • Tuesday, October 10, Scarborough Civic Centre, 150 Borough Dr.
  • Wednesday, October 11, Riverdale Collegiate Institute, 1094 Gerrard St. E.
  • Thursday, October 12, New Horizons Tower, 1140 Bloor St. W. (new location)

Note: The location of the Oct. 12 meeting has been changed and it is now across the street from the originally announced site (which was Bloor Collegiate).

Updated October 11 at 10:30 pm: There continues to be confusion about just what “SmartTrack” service will look like, and this is not helped by the City’s presentation. Details can be found in the June 2016 Metrolinx report. For further info, see the update at the end of this article.

Updated October 13 at noon: Metrolinx has confirmed that the Barrie corridor trains will operate through to Union Station, not terminate at Spadina/Bathurst Station as I had originally thought. However, the operational details have not yet been worked out. For further discussion, scroll down to the section on the Spadina/Bathurst Station.

I attended a media briefing that covered the materials to be presented and the following article is based on that briefing which was conducted by City of Toronto staff. Illustrations here are taken from the deck for the media briefing which is available on the City of Toronto’s site. Resolution of some images is constrained by the quality of data in the deck.

[In the interest of full disclosure: A “Stakeholder Advisory Committee” (or SAC) has already been meeting on this, and I was invited to participate, but declined given my concern with a potential conflict between “advisory” and “journalist/commentator” roles. It is no secret that I believe SmartTrack is a deeply flawed concept. Its implementation is compromised by fitting a poorly-conceived election promise into a workable, operational scheme for the commuter rail network. Any “debate” is skewed by the need to pretend that this is anything beyond campaign literature.]

The intent of these three meetings is to conduct the first detailed conversation about these stations with the general public. Early designs appeared in the “Initial Business Case” for the stations, but these have been revised both for technical and for philosophical reasons. Specifically:

  • The City does not want to build traditional GO stations dominated by parking.
  • The interface between the new stations and the transit network (both rapid transit and surface routes) should be optimized.
  • Strong pedestrian and cycling connections are required.
  • Stations should be close to main streets.
  • Stations should support other City objectives such as the West Toronto Railpath and parallel projects such as the St. Clair/Weston study now in progress.
  • Transit-oriented development should be possible at stations.

This is a list that to a typical GO Transit proposal in the 905 would be unrecognizable. GO Transit’s plan ever since its creation has been to serve auto-based commuting first and foremost with ever larger parking structures that poison the land around stations. Local transit was something GO, and later Metrolinx, simply “didn’t do”, and the idea that Queen’s Park might fund strong local transit as a feeder to GO services has been limited to co-fare arrangements.

The situation within Toronto is very different, and there are connecting routes on the TTC that individually carry a substantial proportion of the daily ridership of the entire GO network. Moreover, if GO (or SmartTrack, whatever it is called) will be a real benefit to TTC riders, then the process of getting people to and from stations must not depend on parking lots that are full before the morning peak is even completed.

The new stations will go into existing built-up areas, not into fields with sites determined primarily by which well-connected developer owns nearby property. Residents will be consulted about how these stations will fit their neighbourhoods, how they will be accessed, and what might eventually become of the community and future development.

A big problem facing those who would present “SmartTrack” to the public beyond City Hall insiders and neighbourhood activists is that almost nobody knows what SmartTrack actually is. This is a direct result of Mayor Tory running on a design that could not be achieved, and which has evolved a great deal since he announced it in May 2014. In brief, it is three GO corridors (Stouffville, Lake Shore East and Kitchener) plus an Eglinton West LRT extension, but this differs greatly from what was promised in the election.

Service levels for SmartTrack are described as every 6-10 minutes peak, with off-peak trains every 15, but this does not necessarily match Metrolinx’ announced service plans for their GO RER network onto which SmartTrack is overlaid. The idea that there would be extra SmartTrack trains added to the GO service was killed off in 2016 in the evaluation of possible operating modes for the corridor.

Fares on “SmartTrack” are supposed to be “TTC fares”, but this is a moving target. Voters understood the term to mean free transfer onto and off of SmartTrack trains as part of their TTC fare, but with all the talk of regional fare integration, it is far from clear just what a “TTC fare” will be by the time SmartTrack is operating.

Even that date appears to be a moving target. City Staff referred to 2025 when GO RER would be fully up and running as the target date for “integration”, but Mayor Tory still speaks of being able to ride SmartTrack by 2021 while he is presumably still in office to cut the ribbon.

At the briefing, many questions arose from the media, and the answer to almost all of them was “we don’t know yet”. It is clear that the Mayor’s plan has not proceeded beyond the half-baked stage, and many important details remain to be sorted out.

  • What is the status of Lawrence East Station and how does it fit with the recently announced review of this (and Kirby) stations by the Auditor General?
  • How will an expanded GO/ST presence at Lawrence East co-exist with the SRT which will operate until at least 2025, if not beyond to whenever the Scarborough Subway opens?
  • What are the arrangements for City/Province cost sharing on the stations, especially since Lawrence East was originally to be a GO station, but its future as such is unknown?
  • What will be the cost of the new stations once design reaches a level where the numbers are credible? The range of $700 million to $1.1 billion has not been updated since the matter was before Council.
  • Will all stations on the SmartTrack corridor honour ST fare arrangements regardless of whether this is a city-built station under the ST banner?
  • Why should GO riders who are not on the SmartTrack corridor pay regular GO fares, while those using the ST route have a “TTC fare” for their journey? The most obvious contrast in this case is between the existing Exhibition Station on the Lake Shore corridor and the proposed Liberty Village Station on the ST/Kitchener corridor, but there are many others.
  • What service levels will be provided, and how will they affect projected demand at the stations? Were previously published estimates based on more ST service than Metrolinx actually plans to  operate? How will constraints at Union affect the ability to through-route service between the Stouffville to the Weston/Kitchener corridors?
  • If the City wants more service than Metrolinx plans (assuming it would even fit on the available trackage), how much would Toronto have to pay Metrolinx to operate it?
  • Where are the residents and jobs that are expected to generate ST demand, and how convenient will access to the service actually be considering walking time, station geometry (stairs, tunnels, bridges, etc) and service frequency?

The stations under consideration are shown on the map below. A common question for all of these locations will be that of available capacity on the GO trains that will originate further out in the corridor. Without knowing the planned service design for “GO” trains and “SmartTrack” trains, it is unclear how often, if at all, there will be short-haul ST trains originating within Toronto as opposed to longer-haul GO trains from the 905. The availability of space on trains could affect the perceived service frequency if people cannot board at stations near Union (just as long-suffering riders of the King car complain about full streetcars).

Updated October 10, 2017 at 10:30 pm

After I posted this article, I realized that there was an important part missing, a commentary on the “consultation” process  itself.

A big problem with many attempts to seek public input is that the wrong question is posed, and factors are taken as given when they should be challenged. In the case of SmartTrack, the basic question is “why do we have SmartTrack at all”.

The original scheme was essentially a real estate ploy to make property in Markham and south of the Airport more valuable by linking both areas with a frequent rail service to downtown. Reverse commuters were a big potential market for this service. In the course of becoming part of the Tory election campaign, the focus turned inward, and SmartTrack became the line that would solve every transit problem. The claims about service frequency, fares and integration with other local and regional service were complete fantasies, but they gave the impression that Tory “had a plan” as distinct from the bumbling proposals of his opponent, Doug Ford, and the lackluster efforts of Olivia Chow. Tory even got professionals to declare his scheme a great idea, one giving it an “A+” on CBC’s Metro Morning, but this was for a version of SmartTrack that was unbuildable.

Now, over three years later, we are still faced with the myth that SmartTrack is a real plan, that it is anything more than what GO Transit would have done in the fullness of time. We are, in effect, being asked about the colour of tiles in stations when we should be asking whether the stations should even be built at all. There is no guarantee that service can be overlaid on GO’s existing plans to provide anywhere near what was promised in the campaign – a “surface subway”. Metrolinx has been quite firm on the subject, and going to the frequencies assumed by ST advocates would be well beyond the infrastructure we are likely to see on GO corridors.

The City will conduct its consultations, but the hard question – Why SmartTrack? – will never be asked.

For the October 11 update, please scroll to the end of the article.

Continue reading