Metrolinx Meeting for February 2012 (Updated)

Updated February 17, 2012 at noon:  The original article from February 13 has been updated to include additional information and comment at the Board Meeting.

The Metrolinx Board will meet on Thursday, February 16.  Among items on the agenda is a “Toronto Update”, but there is no published report.  Given recent events, I suspect this report won’t get beyond the draft stage much before the meeting.

Updated:  The Toronto report and discussion on it are covered in a separate article.

Other items include:

GO Transit Update

This report begins with a review of 2011 operations and updates on ridership to the end of November.

  • On the rail system, weekday riding is up by almost 6%.
  • On the bus system, weekday riding is up by over 6%, and weekend riding is up by 18%.
  • Total weekday ridership is now 243,600, up 13,600 from November 2010.

Looking ahead, GO expects rail ridership to grow by 22% over the next five years while bus riding will go up by 30%.

Although the presentation does not say this explicitly, one constraint on rail growth is the limit on peak capacity GO can provide.  This shows up in GO’s continuing inability to meet its target for passenger comfort with 80% or more of rush hour passengers getting seats on trains.  The number today is 64%, and there is little hope of this improving with demand growing faster than GO can provide capacity.

Updated:  Director Lee Parsons asked where there were capacity constraints in the network.  GO President Gary McNeil replied that demand was high on all corridors, but that Barrie has the strongest growth.  Milton is running at 110-120% of capacity.  GO will put additional trains wherever there is an opening in network schedules because there is strong demand everywhere.

Director Richard Koroscil asked what problems are at the top of GO’s “worry list”.  McNeil replied that the greatest need is for Federal and Provincial support for infrastructure.  Demand for GO service is there whether governments provide funding or not.  Planning where to spend is complicated by the need to keep activity going in many areas at the same time lest riders feel that their part of the network is being ignored.

Director Rahul Bhardwaj worried that people might feel that transit growth has stalled, and asked how GO could get more positive stories out.  McNeil replied that the magnitude of the Toronto debate has overshadowed GO even though they have good news in the 905.  Chair Rob Prichard noted that Metrolinx has to make the same progress in Toronto as they do elsewhere in the GTHA.

I could not help thinking back to the departing remarks of just-retired Director Paul Bedford who, among other parting comments, noted the relative size of the TTC and GO’s operations.  What is big news in the 905 and for GO itself would be small change on the scale of the TTC because GO is, comparatively, such a small operation.  Simply publishing sunny press releases (something GO is very good at) will not make up for the lower presence and mode share that transit generally has in the 905 compared to the 416.

Changes to Ticket Cancelling on the GO System

The title of this report is somewhat misleading as this is actually a report on the phase-out of paper 10-ride and 2-ride tickets and completion of the system’s conversion to Presto.

After May 31, 2012, the 10-ride and 2-ride tickets will no longer be sold.  Those remaining in circulation will be valid up to July 31, 2012 after which they will be refunded or converted to Presto.

Monthly, daily and group passes are not affected by this change.

Presto Update

Presto continues to gain users with a 22% growth in the number of cards issued over the November-December 2011 period.  About $14.4-million in fares were paid using the fare cards during the same period.  What has not been reported is how this lines up against overall fare revenue on GO and on participating regional transit systems.

A major new market for Presto will arrive in June 2012 with the rollout in Ottawa with the “Presto Next Generation” (or “PNG”) card.  PNG will become available in the GTHA in late fall 2012.

Concurrent with the rollout of PNG, the Presto website will be revised with added functionality and an improved layout, according to the report.

Meanwhile on the TTC, Metrolinx expects the Commission to grant authority for a contract with Presto at its March meeting.  Notable among the features to be included will be “Open Payments” allowing cards other than Presto and mobile devices to be used.  However, the exact details are not explained and it is unclear whether this will simply provide the ability to pay a fare with a credit card, or whether that card can be used as an alternative to Presto and receive discounts such as multi-trip incentives or equivalent-to-pass functionality.

A long section originally this article related to questions about Presto arising from the January Board Meeting.  This has been moved to a separate article.

Updated:  Director Rahul Bhardwaj asked how many “free rides” are taken thanks to the discounting system of Presto.  Staff pointed out that there are “free” rides on passes by design, but they are not counted or reported as there is no mechanism to capture pass use comparable to the Presto readers.

Director Lee Parsons noted that a commuter line in New York City saw a jump in counterpeak and weekend demand when it moved to all day service, and a fare tariff that allows for extra trips at little or no cost helps drive this demand. 

A view of transit riding as “free” and somehow undesirable is troubling because it implies that encouraging use through lower “frequent flyer” fares may not be a good idea.  This is the basic philosophical problem of fare structures:  do we purport to charge people for what they use, or do we encourage higher utilization through fares that reward frequent travel.  Is transit a service we wish to make as attractive as possible through the perception that it has a low marginal cost just as autos are thought to be “cheap” until one pulls into a gas station or receives an insurance bill.

After the meeting, I sent questions to Metrolinx asking how the two generations of Presto cards and supporting systems will interoperate.  For example, what will happen if an Ottawa user with a “PNG” card comes to Toronto and attempts to ride GO Transit?  I await answers to my questions.

Metrolinx Plans a Fare Increase

The Metrolinx board will meet on Monday, January 9 to formally approve new, higher fares across the system effective February 18, 2012.  Unlike the previous fare hike of March 20, 2010 which was a flat $0.25 bump in all fares, this round uses tiered increases so that short-distance fares are not as disproportionately penalized.

  • Fares which are now between $4.20 and $5.50 would rise by $0.30 (5.5 to 7.1%)
  • Fares which are now between $5.51 and $7.00 would rise by $0.35 (5.0 to 6.4%)
  • Fares which are now at $7.01 or more would rise by $0.40 (at most 5.7%)

Considering that many GO fares are well above $7 (a one way from Kitchener-Waterloo to Union costs $14.60), that maximum increase amounts to only 2.7%.  Oddly enough, the presentation on the agenda notes that:

A flat increase disproportionately impacts shorter trips and will make any potential future fare integration arrangement with the TTC more difficult to achieve.

The 2012 increase is still disproportionately high for those who might make short journeys.  The idea that this somehow supports future fare integration with the TTC is hard to swallow.

The average GO fare is $6.55 and the average increase, allowing for the effects of discounts, will be about $0.31 (4.7%) .  If this were applied to the KW-Union fare, the increase would be about $0.70.

A chart of page 3 of the presentation makes interesting reading.  It shows various GO cost factors and their rates of increase over the past decade.  By far the highest are diesel fuel and electric power.

Concurrent with the fare increase, GO will change the discount plan for adults and students to encourage their shift from paper passes to Presto.  The discounts of 17.5% and 35% now offered to adult and student passholders respectively will stay in place for Presto fares, but the discounts for a paper pass will drop to 15% and 30%.

Like the TTC, GO faces the dilemma that adding service, even if they carry more riders, drives up costs because on average all services recover only about 80% from the farebox.  Stronger ridership with little service improvement is financially beneficial, but service improvements add to the operating costs.

With constraints on funding from Queen’s Park, passengers will have to dig a little deeper.  This is a major issue for future GO planning as they move to services that will not have as robust a cost recovery rate (two way, all day rail service).  The farebox cannot pay for GO’s evolution from a system that cherry-picks the cheapest of riders to one that provides service as a basic policy for the GTAH.

Metrolinx Board Report

Metrolinx Board Presentation

Union Station & Rail Corridor Capacity

At the recent Metrolinx Board meeting, staff presented an overview of planning now underway for the future of Union Station.  One background report addressed the future levels of GO, VIA and other services at Union and the surrounding rail corridors.  This report makes interesting, if unsurprising, reading because it confirms what anyone with even a modest understanding of railway operations already knows:  there are severe capacity constraints at Union as it is now configured and operated.  Too much discussion focuses on a bright future of frequent service without considering how we will fit all the trains and passengers through the hub of the network.

The full report is not online at Metrolinx, but I have obtained a copy.  Due to its size, I will not link the entire document here.  If you just want the highlights, read the Executive Summary.  For more details including a description of the evolving simulations of various levels of service, read the main report.

USRC Track Study Executive Summary

USRC Track Study Main Report

The study considered various scenarios corresponding to stages in the growth of GO and other services over coming decades:

  • Base Case:  The existing service at Union, including a reservation of two tracks out of service for the reconstruction project.  This was used to calibrate the model.
  • 2015:  Construction at the train shed is completed giving two more tracks for service.  The only new peak hour service beyond the base case would be a few VIA trains and the Air Rail Link.
  • Electrification study base case:  This configuration was used as a starting point for the recent electrification study, and it assumes two-way service on all corridors.  Three variants of this were tested to refine operations and remove constraints triggered by service at a much higher level than today.
  • Maximum capacity:  This configuration attempted to maximise service on all corridors.

The study concludes that significant changes will be required both in the physical plant (track, signals) and in train operations which will have to be managed considerably more tightly than today.

Continue reading

GO Kitchener Rail Service Starts December 19, 2011

As previously rumoured in comments, the Kitchener rail service begins on December 19.  GO will implement this with two trains a day.

In the morning, the existing 6:47 Georgetown trip will originate in Kitchener at 5:52.   A new train will be added leaving Kitchener at 7:10 and arriving at Union at 9:08.

In the afternoon, two existing Georgetown trips leaving Union at 4:45 and 5:45 pm will be extended to Kitchener arriving there at 6:42 and 7:42.

The line will be renamed the “Kitchener” line.

GO Schedule Changes Page

Kitchener Timetable

Metrolinx Board Meeting November 23, 2011 (Part I)

The agenda for November 23rd’s meeting of the Metrolinx Board is now online and it includes several reports of interest.  Here I will deal with GO transit performance and capacity issues.  In a future article, I will turn to Presto (and the proposed TTC implementation which is also on the TTC’s agenda for November 23), the Air Rail Link, and planning issues at “Mobility Hubs”.

Continue reading

No, We’re Not There Yet

Many recent reports and proposals talk about the problems of long commuting trips, of the futility of attempting to move quickly around our increasingly congested city.

Back on August 24, Statistics Canada published their commuting study based on 2010 data.  The study reviews not only comparative commuting times by mode, but also the attitudes of motorists to the transit alternative.

The average commuting time for all of Canada was 26 minutes, but this rises to 30 minutes for CMAs (“Census Metropolitan Areas” which are generally larger than actual municipalities) of 1-million or more population.  Toronto and Montreal average 33 and 31 minutes, but this doesn’t tell the entire story as any Toronto commuter will tell.  27% of Toronto commutes take over 45 minutes, and 29% are caught in traffic jams.

When the data are subdivided by car and transit, the transit trips take longer, and this difference is heightened in lower density areas.  That’s no surprise because low density areas tend to have poor transit service as a direct result of lower demand.  Waiting times are an important part of transit trips when service is poor, and this is compounded by any need to change between routes that may not directly serve all travel patterns.  The average transit commute in large CMAs is 44 minutes while the average car trip is 27 minutes.  The figures are even worse for Toronto.  Missing from this is any discussion of the length of the trip or the differences caused by trip location and density of demand.

Neither transit nor car users like traffic congestion, but the presence of rapid transit  networks means that some trips are congestion-free (even though they may be subject to transit delays that were not part of this study).  The proportion of commuters who were satisfied with their commute times is understandably high where these times are short and congestion is comparatively rare.  Transit riders put up with longer commute times better than car drivers, but those with short trips tended to be less happy with transit than motorists were with their cars.  This is easy to understand when one considers that a short transit trip is more likely to have a relatively large proportion of wait time, while at least some of the longer trips (notably commuter rail) allow the commuter to relax enroute.

The vast majority of motorists view public transit unfavourably, but this statistic is not broken down by region, let alone by sub-region where variations might be seen due to the availability and quality of the public transit option.

Media reaction to this report was quite predictable with stories about how bad Toronto’s commuting times are.  Less clear is the question of what, if anything, can be done about the situation.  Indeed, the most simplistic analysis might suggest that car trips are inherently faster and “better” than transit trips based on their average length.  This would completely mask the effect of averaging together trips over a wide variety of roads and transit lines and the cost, broadly speaking, of increasing capacity for either mode.

Continue reading

How Many Trains Will Fit Through Union Station?

During the Metrolinx Electrification Study, those of us who attended various workshops became aware that there was a parallel study of capacity issues at Union Station.  The electrification plans are, among other things, in support of operating better service on GO generally, but if that service won’t physically fit through Union Station and its approach corridors, there’s a big problem.

That problem is independent of electrification per se because The Big Move from Metrolinx depends on substantially improved commuter rail service.  No capacity, no additional service.

At the recent Metrolinx Board meeting, GO’s President, Gary McNeil, presented an update on GO operations and construction activity.

GO President’s Report & Presentation Deck

The report includes a reference to Union Station capacity:

… Retaining wall construction is well underway to allow for an additional track in this corridor. The Union Station capacity study has been completed, with the result that in the near term, there is capacity at this station to meet needs. With the start of design of double berthing and new south platform, this will provide access required for service expansions. This work is anticipated to be completed in the next five years.  [Page 8]

After the meeting, I requested a copy of the study to learn what conclusions it might have reached. Various working papers from the study had been leaked, but they were neither definitive nor entirely coherent on how to deal with the problem.

Metrolinx has now replied that:

At this time, a detailed public component of the Union Station study is premature as we are undertaking on-going research. Specific information will most likely be available for the public when future potential projects develop from this study.

The purpose of the study is to assess the Union Station Rail Corridor (USRC) train capacity at four time points:

  • existing;
  • completion of planned infrastructure in 2015 and implementation for service improvements, including the ARL;
  • Electrification Reference Case (ERC);
  • and 2031 (Big Move planning document).

In doing so, we hope to identify opportunities to increase capacity by making more effective use of existing and planned infrastructure.  We also hope to identify the infrastructure needed to address any capacity shortfalls.  This study provided only a technical analysis, and Metrolinx will consider its opportunities after further assessment.

However, there is a good deal of material to get started on.

Continue reading

Finally! A Dundas West GO Connection (Updated)

Updated March 24 at 9:00 pm: Metrolinx has published the materials from the Open House.  Of particular interest is the presentation which shows the proposed changes to the area around Bloor GO Station and Dundas West TTC Station.

In the first phase, the north sidewalk of Bloor Street would be redesigned to widen and otherwise beautify the access to the GO level from the sidewalk in the underpass.  Also, a connection from Dundas West Station would be added at the east end of the platform.  (Page 33 of the presentation shows details of the subway to GO link.)

In later phases, the streetcar loop at Dundas West would be redesigned so that all access was from Edna Avenue with traffic signals.  This could be a mixed blessing given the level of transit service at this location.

Original post below:

Metrolinx has announced an open house for the Dundas West-Bloor Mobility Hub Study.

Date: Wednesday, March 23, 2011
Time: 6 p.m. to 8:30 p.m.
Venue: Lithuanian House
1573 Bloor Street West

Further background can be found in The Star.

Dundas West Station was built before GO existed, much less had service on the Weston corridor, but a connection could be built from the east end of the platform to what is now Bloor Station on the rail line.  However, a major development, the Crossways, was not on top of the subway when it opened in 1966, and any connection must deal with this building.

Liberty Village Planning Studies

The City of Toronto has three planning studies underway that will affect Liberty Village, and they will hold a combined open house on March 1 for the next stage of the public consultation.

Dufferin Street Bridges

The south end of Dufferin Street has two bridges — one over the rail corridor, and one over the Gardiner Expressway.  Both are in need of replacement, and future plans require a new design.  This project had its first meeting last year, and now the City is back to discuss alternative schemes.

Projects related to this include expansion of the GO Lake Shore corridor, provision of clearance for electrification and connection of the streetcar system from Exhibition (East) Loop west to Dufferin.  The streetcar extension is part of the proposed Waterfront West LRT line, although it is far from clear whether any of the alignments shown on the drawings for the bridge project would actually be built.  The WWLRT is not exactly at the top of anyone’s list of transit projects, but whatever is decided for the new Dufferin bridges may preclude some of the WWLRT options.

New King-Liberty Pedestrian/Cyclist Link

The Georgetown rail corridor creates a long barrier between Strachan Avenue and the west end of the King Street underpass at Atlantic Avenue.  With the redevelopment of lands to the north, current and future plans for lands to the south, this barrier isolates the two neighbourhoods from each other.  Some crossings are now made illegally, but plans to increase the number of active tracks and the frequency of GO service will make this much more dangerous.

At the first open house last year, various alternatives were presented, and two of these were carried forward for detailed study.  The results will presented at the March 1 open house.

Liberty Village New Street

A new street is proposed along the south edge of Liberty Village from just west of Strachan Avenue to Dufferin Street.  This road would occupy what was originally planned to be the Front Street Extension, but as a purely local street.

The March 1 meeting will launch this project for comment.