Will Scarborough Get Its Subway? (Updated: Probably)

Updated October 9, 2013 at 1:20am:

Toronto Council, by a vote of 24-20, has approved proceeding with the Scarborough Subway project including a three-stage property tax increase totalling 1.6% to finance the City of Toronto’s share of the budget.

There is little new to add at this point on the technical issues all of which were covered on this site before.

My personal reaction is disappointment, but more strongly, disgust at the behaviour of some Councillors and a few City Officials.  The outright hatred and slander against “downtowners” and their motives in “pushing” LRT does not bode well for cordial relations on Council, not to mention sowing equivalent feelings among the electorate.  There are arguments to be made for the subway option (many of them have appeared here in the comment threads), but this should be done in a civil manner relatively free of distortion.

Instead, we got warped versions of the truth about both the subway and LRT options, and not a few outright lies.  TTC CEO Andy Byford, one who trotted out the “100 year subway” myth was forced to backtrack on two counts by questions at Council.  He admitted that the tunnels last for 100 years, but much of what is in them does not.  Meanwhile, he talked about LRT lasting 50 years, not the 30 year figure that has been bandied around of late.  The obvious issue is that a tunnel may very well last 100 years, but if you don’t have to build one in the first place, and can save the expense, what does it matter?

We will have to wait a decade to see whether the suddenly much rosier projections of demand for a rapid transit line in Scarborough come from the same well-cooked land-use and population assumptions that brought us the vastly overstated estimates for the Sheppard Subway (and for growth at Scarborough Town Centre).

In any event, the vote is taken, and barring a discovery of a major extra cost for the City appearing during detailed design, the decision is as final as we can expect to see from this Council and the provincial government.

How the rest of the LRT network will fare really depends on the 2014 municipal and provincial elections.  Mayor Ford has already declared that subways on Sheppard and Finch are goals for his next term.

The half-hearted advocacy for LRT from Metrolinx and Queen’s Park plays a big part in this situation, but I never thought their hearts were in it going right back to the early days of Metrolinx when I was persona non grata for asking their newly-minted Chair if they would consider this mode as an option in their grand plan.

How many more ridings will the Liberals feel the need to buy off with a subway promise?

The original article from October 4 follows the break.

Continue reading

Scarborough Subway (via SRT) Feasibility Study (Update 7)

Updated October 2, 2013 at 12:30 pm:

Metrolinx has released a transcript of a press conference held earlier today regarding their letter to the City Manager about the Scarborough subway.

In related news, Metrolinx advises (through a separate email) that they are “approximately 3 months away from making [a] formal recommendation on Sheppard and Finch” LRT lines, and the possible acceleration of these projects.

Also, regarding Eglinton-Yonge Station, they “hope to have a final concept that Metrolinx, City and TTC agree on in the coming weeks and will present in the public session of the Metrolinx December Board meeting”.

Updated October 2, 2013 at 10:30 am:

Metrolinx has sent a letter to Toronto’s City Manager regarding the proposed Scarborough subway.  Unlike some pronouncements from Queen’s Park, this takes a more conciliatory tone for discussions between Ontario and the City of Toronto.  Notable points include:

  • Metrolinx continues to believe that LRT “would provide an effective rapid transit solution to the transportation challenges in this area” within the available funding, but bows to the desire by all three levels of government to build a subway.
  • Metrolinx is not dictating that a specific route be chosen, but wants a proper alternatives analysis as part of the Environmental Assessment.  This contradicts earlier statements by the government implying that only one route was to be funded.  It also implies that the shorter “Transit Project Assessment” process (which does not include the potentially embarrassing need to review alternatives) will not be used.
  • The Province is sticking with a figure of $1.48-billion in available funding, from which must be deducted the $85m in sunk costs for the Scarborough LRT project and unspecified costs of scaling down the LRT car order from Bombardier.
  • Although the $320m reserved for the Kennedy Station reconstruction with both the Eglinton and Scarborough LRT lines may not all be required, additional costs are expected at the Yonge-Eglinton interchange beyond the current project budget.  Savings from Kennedy may be redirected to Yonge-Eglinton.  If there is anything left of the $320m between the two projects, then it could be directed to the Scarborough subway.
  • The Scarborough subway will be entirely a City/TTC project contrary to previous schemes for the LRT that would have seen provincial ownership and a PPP arrangement similar to that proposed for the Eglinton line.  This begs a question regarding the accounting for the provincial funding contribution: if you don’t own the line, you can’t book the asset as an offset to the money spent on it.  Does this mark a shift away from the creative accounting used to justify taking Toronto’s transit projects away from the TTC in the first place?
  • Provincial funding will begin to flow in the 2018/19 fiscal year implying that no serious construction will be underway until then.  The City and/or Federal government will have to front end the project with funding for the EA and preliminary engineering.  All risk for project cost overruns will be to the City’s account.
  • Infrastructure Ontario remains available to participate in this project, but this is no longer a requirement of the Province for funding.  The decision on whether to use IO or to proceed with a conventional procurement (as on the Spadina extension) is up to the City of Toronto.

Not included in the letter, but reported through Twitter by John Michael McGrath, is a comment from Metrolinx that they are reviewing the timing of the Sheppard and Finch LRT projects.

This letter provides a more balanced response to Scarborough subway issue than some recent statements by Ontario Transportation Minister Glen Murray, and it is good to see Metrolinx acting as a reasonable broker rather than simply as a rubber stamp for ministerial musings.  The next major step will be Council’s discussion of the matter at the October 8-9 meeting.

Continue reading

Metrolinx Benefits Case Analysis for the Richmond Hill Subway

Metrolinx has published a study of the proposed subway extension to Richmond Hill updating a Benefits Case Analysis done in 2009.  The new report is dated May 2013, but it has only recently been publicly released.

Background information in the study gives an indication of the demand challenges facing the transit network in coming decades.  The study itself shows many of the shortcomings of Metrolinx analyses in the selective use of information and limited scope of alternatives comparison.

The study looks at four options for the Richmond Hill line:

  • A Base Case assuming substantial additions to existing subway capacity, leaving things as they are with buses serving the existing terminal at Finch Station.
  • Option 1: Full subway extension to Richmond Hill Centre close to the existing GO station.
  • Option 2: A two-stop subway extension to Steeles with buses serving the area beyond.
  • Option 2A: A Steeles subway extension accompanied by improved GO service on the Richmond Hill corridor.

Notable by its absence is an option of both a full subway line to Richmond Hill and improved GO service or any analysis of how demand would divide between the two routes.

The study notes that the Metrolinx Board, in response to earlier analyses, requested additional information:

  • Possible adjustments in project scope, timing or phasing;
  • Consideration of the extent to which improved service levels on the parallel GO Richmond Hill rail corridor off-loads some of the demand on the Yonge Street subway; and
  • The cost impacts of the various options on the subway yards strategy, Yonge-Bloor subway station improvements, and a future Downtown Relief Line to bypass the Yonge-Bloor congestion pinch point.  [Par. 1.12, page 3]

The 2013 report does not address these requests because it does not include any option where both the subway and improved GO service operate to Richmond Hill.  Although parallel studies (such as the TTC’s own subway yards needs analysis) do look at some aspects of the third point above, this information is not integrated into the analysis, nor is there any review of configurations that could avoid some of the cost of increased subway capacity.  This should follow in the Metrolinx study now underway of the Relief Line and associated alternatives, but that sort of network-based review is years overdue.

Continue reading

TTC Service Changes Effective October 13, 2013 (Updated)

Updated September 24, 2013 at 11:20pm

Information has been added regarding the replacement of streetcars by buses on Lake Shore Blvd. in Etobicoke starting mid October.

Original article:

Several service changes will take effect on October 13, 2013.

Service improvements are almost exclusively in the off-peak period.

2013.10.13_Service_Changes

Night Service Improvements

  • 310 Bathurst service will be improve on Saturday nights / Sunday mornings between 1:00 and 3:00 am, and between 6:00 and 9:00 am.
  • 320 Yonge service will be improved by the elimination of the York Mills short turn.  All trips will operate to Steeles Avenue.  Service on Sunday morning between 1:30 and 3:30 am will be improved.

Construction Diversions

Many construction diversions now in place will continue, and two more will be added.

Continuing to mid-November 2013

  • Construction at Lawrence West Station causing extension of 58 Malton and 59 Maple Leaf routes to Lawrence Station.
  • 510 Spadina streetcars replaced by buses between Queens Quay and King.  Schedules on 504 King will be adjusted to provide additional running time to compensate for congestion at King & Spadina.
  • Track work on Ossington affecting the 63 Ossington route.
  • Water main and platform work on Bathurst requiring buses on 511 Bathurst and changes to mid-day service level on 512 St. Clair.
  • Road construction on Dufferin requiring a northbound diversion of 29 Dufferin from Queen to Dundas.
  • (New) Reconstruction on the Dundas bridge at Sterling Road requiring cutback of streetcar service to Lansdowne on Dundas and Carlton routes with shuttle buses beyond.

Continuing to mid-December 2013

  • Road and track construction on Kingston Road affecting 502/503 streetcar routes, 22A Coxwell, 64 Main and 92 Woodbine South.
  • Road construction on Kingston Road affecting 12 Kingston Road and 69 Warden South routes.
  • York Region bridge and road construction affecting the 68 Warden route.
  • (New) Reconstruction of streetcar platforms on Lake Shore requiring replacement of 501 Queen and 508 Lake Shore services west of Humber Loop with buses.

Updated September 24, 2013:

I asked the TTC why such a long shutdown was required for work on the safety islands on Lake Shore.  Here is their response:

There are 16 platforms needing either lengthening, widening or both, plus shelter installation. In short, a large scope of work. Contractors indicated to us when this was tendered that they’d need more time if they were to bid, so we amended the tender based on that feedback.

Brad Ross

Continuing to end of 2013

  • Yonge subway early shutdown for tunnel liner replacement north of Eglinton.

Continuing to at least the end of 2013

  • Additional buses and running time on many routes for Spadina subway extension project.

Continuing into 2014

  • 509/510 Harbourfront/Spadina services replaced by buses pending completion of track work on Queens Quay and construction at Union Station Loop.
  • 72 Pape diversion for Union Station Second Platform project.
  • Additional buses and running time on many routes for Metrolinx Weston Road bridge project.
  • 83 Jones diversion for utility reconstruction and track work on Leslie Street.

Continuing into 2015

  • Metrolinx LRT construction on Eglinton affecting 32 Eglinton West route.
  • 29/329 Dufferin and 316 Ossington buses turned back due to structural problems with the Dufferin bridge over the rail corridor.

TIFF Reviews 2013: Part I

The Toronto International Film Festival was underway once again in early September, and transit matters on this site went into eclipse for a week or so.  Here is a capsule view of the films I saw during the first half of the fest:

  • Only Lovers Left Alive
  • Southcliffe
  • Watermark
  • Triptych
  • Le Week-End
  • Philomena
  • Fading Gigolo
  • The Unknown Known
  • The Selfish Giant
  • The Lunchbox
  • The Double
  • The Invisible Woman

Continue reading

Cherry Street Track Construction (Update 3)

Updated September 17, 2013 at 4:25pm:

According to earlier plans I had heard through Waterfront Toronto, Cherry Street Loop was not to be completed until after the Pan Am Games because the site is part of a parking lot for buses.  Contrary to this story, the loop is under construction, albeit surrounded by a parking lot.

IMG_4450w

The now-inactive Cherry Street tower that once controlled the eastern approach to Union Station sits at the south end of the loop.  In the left background, behind the trees, is the GO Don Yard.

The terrible irony about this, our possibly newest streetcar line, is that it won’t actually see service until Spring 2016, and the proposed extension under the railway to connect with a Queens Quay East line isn’t even in the current list of projects awaiting funding.

Continue reading

Cycling as a Transit Alternative

A conversation has broken out in the thread originally dedicated to the Scarborough Subway regarding the ability of cycling to reduce demand on the subway if a bike lane were implemented on Bloor-Danforth.

I have moved all of the comments related to this topic here to separate them from discussions of the subway extension.

Transit Technology Choices: A Quote Worth Repeating

Updated September 6, 2013 at 11:10 am:  There is an excellent article by Stephen Wickens on his blog recounting the sorry history of Queen’s Park’s imposition of the ICTS technology on the Scarborough route.

It is worth noting that the ICTS cars cost over $2-million each 30 years ago, an outrageous sum.  The price to Vancouver was much lower, well below $1m each, and the TTC order was used to funnel money from Queen’s Park to offset the development costs of the new technology.  This is what passed for a “transit strategy” in the Davis government.

Updated September 5, 2013 at 11:00 am: My comments about Transportation Minister Glen Murray’s Scarborough subway announcement yesterday are now online at the Torontoist.

The original post follows below.

Continue reading

King Street Update — Fall 2013

Over the opening weekend of the Toronto International Film Festival (TIFF), King Street is closed in the block from Duncan (aka Ed Mirvish Way) to John to provide additional pedestrian space around the major TIFF events in the area.  This will last until Monday, September 9.

IMG_4406w

Of particular note, control of access by the streetcars to the centre lanes is handled not by Toronto Police paid duty officers, but by TIFF security guards and festival volunteers.

Further east, at the Don Bridge, structural problems that have imposed a slow order on the King Street leg will finally be addressed (now that Waterfront Toronto and the City have sorted out a cost sharing agreement).  Starting September 9, all 504 King and 503 Kingston Road cars will divert both ways via Queen and Parliament.  There will be no replacement bus service on King.

IMG_4410w

The diversion is expected to last until sometime in November.

There is no word on the status of the eastern approach to the bridge which also has a slow order on it.

Where Will the Scarborough Subway Go?

The Toronto Star reports that Queen’s Park is contemplating an alternative route to Toronto’s proposed Scarborough subway extension via Eglinton and McCowan to Sheppard East.

The key paragraphs in the article are:

“In the next couple of weeks we should have an announcement on what the routing will be, what the design will be and what the cost will be,” he told reporters on the way into a cabinet meeting Wednesday.

Queen’s Park wants to have the subway run on a similar route to the light rail transit plan to “maximize the impact of this line and get it connected to as many people (as possible),” said [Transportation Minister] Murray.

Murray seeks to find out how much could be built with the $1.4b already committed to a subway project.  Using an existing corridor could reduce the cost compared to the McCowan alignment.

This raises questions debated in other threads here of how the subway would be extended via the existing SRT alignment including the configuration of Kennedy Station and whether a route from Ellesmere Station eastward would be elevated or underground.

Recycling some or all of the existing corridor will require a period of shutdown for the RT with parallel bus service, an issue that weighed heavily against the LRT scheme in recent debates.  Will the promise of a subway quell objections to this shutdown?

Murray will meet with Lisa Raitt, the federal Minister of Transport, to discuss funding, but he is already throwing cold water on hopes for assistance from Ottawa for a  “416” project.  Even if the feds bring money to the table, the next questions will be whether the original McCowan scheme or an SRT alignment for the subway are the best use of available cash, and how either subway would fit into a larger network.

The debate comes back to Toronto Council in October preceded by Murray’s announcement likely in mid-September.  Backers of the subway like TTC Chair Karen Stintz and recently-elected MPP “Subway Champion” Mitzie Hunter have stressed that their support for a Sheppard LRT was for a different line in different circumstances.  A Scarborough subway, wherever it goes, will leave large parts of eastern Toronto far from rapid transit.

The LRT debate is not over.  Will Stintz and Hunter become “LRT champions” for other parts of the network?